Road permeable pavement structure
By introducing permeation pipes, liquid pumps and liquid level sensors into the Reuters permeable pavement structure, the problem of water accumulation on the road when the rainfall is high is solved, and better permeable drainage effect is achieved, and stability is improved through the paving and fixing plate structure. Sex and aesthetics.
Patent Information
- Application Number
- CN202323430337.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-15
- Publication Date
- 2024-12-03
- Estimated Expiration
- 2033-12-15
AI Technical Summary
The existing road structure is prone to water accumulation when the rainfall is high, resulting in poor water permeability and poor drainage effect.
A reciprocal pavement structure including base layer, sand and gravel layer, gravel layer, permeable concrete layer, permeable pipe, diversion pipe, sink, liquid pump and liquid level sensor was designed. The permeability pipe is installed inside the permeable concrete layer and the water tank is inside. Set up a liquid pump and liquid level sensor to assist drainage through a liquid pump to ensure that rainwater flows into the sink quickly and is pumped out in time, improving the permeable drainage effect.
When there is a lot of rainwater, the permeable concrete layer permeable concrete layer assists the infiltration of rainwater. The sink pumps water in time through the liquid pump to avoid water accumulation on the road, significantly improving the permeable drainage effect, and improving stability and aesthetics through the paving and fixing plate structure.
Smart Images

Figure CN222100534U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of municipal roads, in particular to a water-permeable road pavement structure. Background Art
[0002] With the development of urbanization, many areas in China have paved roads. The pavement structure of general roads uses cement, asphalt, concrete and other materials to seal the surface and replace the original soil. Sealing the surface can improve road traffic conditions and beautify the environment, but sealing the surface will make it difficult for water to penetrate, which often causes serious water accumulation in the city after heavy rain. Therefore, people have developed permeable pavement, which can prevent water accumulation on the road surface and allow rainwater to quickly penetrate into the ground without accumulating on the road surface.
[0003] The prior art has the following problems:
[0004] The general road structure design is simple. When the rainfall is heavy, water is likely to accumulate on the surface of the road structure. The rainwater inside the road is condensed, resulting in poor permeability and poor drainage effect. Utility Model Content
[0005] In view of the deficiencies in the prior art, the utility model provides a permeable road pavement structure, which solves the problem that water is easily accumulated on the surface of the road structure when the rainfall is heavy, and rainwater is collated inside the road, resulting in poor permeability and poor drainage effect.
[0006] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: a permeable road pavement structure, comprising a base layer, a sand and gravel layer is arranged on the upper end of the base layer, a crushed stone layer is arranged on the upper end of the sand and gravel layer, a permeable concrete layer is arranged on the upper end of the crushed stone layer, a paving brick layer is arranged on the upper end of the permeable concrete layer, a permeable pipe is arranged inside the permeable concrete layer, a guide pipe is connected to the lower end of the permeable pipe, a partition is arranged on the side of the crushed stone layer, a water trough is arranged on one side of the partition, a drainage pipe is arranged on one side of the water trough, a liquid pump is arranged inside the water trough, and a water outlet pipe is arranged on the upper end of the liquid pump.
[0007] As a preferred technical solution of the utility model, the paving brick layer includes a plurality of paving bricks, the upper ends of the paving bricks are connected with protrusions, a guide plate is arranged in the middle of adjacent protrusions, drainage holes are provided on the sides of the paving bricks, one end of the paving bricks is connected with a first fixed plate, the lower end of the first fixed plate is connected with a clamp, the other end of the paving bricks is connected with a second fixed plate, and a clamping groove is provided on the surface of the second fixed plate.
[0008] As a preferred technical solution of the utility model, the shape of the card slot is triangular and there are several of them, and the number of the card members is several and they are evenly distributed at the lower end of the first fixing plate.
[0009] As a preferred technical solution of the utility model, the internal size of the slot matches the size of the clamping piece, and the first fixed plate and the second fixed plate corresponding to the adjacent paving bricks are clamped together through the clamping piece and the slot.
[0010] As a preferred technical solution of the utility model, the guide plates are in the shape of an inclined surface, and a drainage hole is provided at both ends of each group of guide plates.
[0011] As a preferred technical solution of the utility model, the number of the permeable pipes is several and they are evenly distributed inside the permeable concrete layer and are connected to the water trough on the side through the guide pipe.
[0012] As a preferred technical solution of the utility model, a liquid level sensor is connected to the inner wall of the water tank, and the liquid level sensor is electrically connected to a liquid pump at a corresponding position through a controller.
[0013] Compared with the prior art, the utility model provides a road permeable pavement structure, which has the following beneficial effects:
[0014] 1. This kind of road permeable pavement structure is equipped with a permeable concrete layer, a permeable pipe, a guide pipe, a water tank, a liquid pump, a water outlet pipe and a liquid level sensor. The structure can ensure the rationality of the structure during normal permeable drainage operations. When there is a lot of rain on the road surface, the internal permeable pipe can assist rainwater infiltration, making it convenient for rainwater to quickly flow into the corresponding water tank. When there is a lot of rainwater accumulated in the water tank, the water can be pumped out in time through the action of the liquid pump to avoid water accumulation on the road, thereby greatly improving the permeable drainage effect of the structure.
[0015] 2. This kind of road permeable pavement structure is provided with paving bricks, guide plates, drainage holes, a first fixed plate, clips, a second fixed plate and slots. During the paving bricks at the top of the permeable pavement structure, adjacent paving bricks are laid alternately with each other, and the clips corresponding to one paving brick are stuck in the slots corresponding to the other two paving bricks, which greatly improves the stability of the permeable pavement structure, makes it less likely for the paving bricks to shift or warp, and has good aesthetics. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Figure 1 It is a schematic diagram of the cross section of the road permeable pavement structure;
[0017] Figure 2 This is a schematic diagram of the road permeable pavement structure;
[0018] Figure 3 This is a schematic diagram of the brick paving structure.
[0019] In the figure: 1, base layer; 2, sand and gravel layer; 3, crushed stone layer; 4, permeable concrete layer; 5, brick paving layer; 6, infiltration pipe; 7, guide pipe; 8, partition; 9, sink; 10, drain pipe; 11, liquid pump; 12, outlet pipe; 13, liquid level sensor; 14, brick paving; 15, protrusion; 16, guide plate; 17, drain hole; 18, first fixed plate; 19, clamp; 20, second fixed plate; 21, clamping groove. Implementation
[0020] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0021] See also Figure 1-3 In this embodiment: a permeable road pavement structure includes a base layer 1, a gravel layer 2 is arranged on the upper end of the base layer 1, a crushed stone layer 3 is arranged on the upper end of the gravel layer 2, a permeable concrete layer 4 is arranged on the upper end of the crushed stone layer 3, a brick layer 5 is arranged on the upper end of the permeable concrete layer 4, a permeable pipe 6 is arranged inside the permeable concrete layer 4, and a guide pipe 7 is connected to the lower end of the permeable pipe 6, a partition 8 is arranged on the side of the crushed stone layer 3, a water trough 9 is arranged on one side of the partition 8, a drainage pipe 10 is arranged on one side of the water trough 9, a liquid pump 11 is arranged inside the water trough 9, and a water outlet pipe 12 is arranged on the upper end of the liquid pump 11.
[0022] In this embodiment, the paving brick layer 5 includes a plurality of paving bricks 14, the upper end of the paving brick 14 is connected with a protrusion 15, a guide plate 16 is arranged in the middle of adjacent protrusions 15, a drainage hole 17 is provided on the side of the paving brick 14, one end of the paving brick 14 is connected with a first fixing plate 18, the lower end of the first fixing plate 18 is connected with a clamp 19, the other end of the paving brick 14 is connected with a second fixing plate 20, and a clamping groove 21 is provided on the surface of the second fixing plate 20, and the structural design is reasonable; the clamping groove 21 is in the shape of a triangle, and the number is several, the number of the clamping groove 19 is several, and is evenly distributed at the lower end of the first fixing plate 18, so that any misaligned paving operation between the paving bricks 14 can be realized, and the laying flexibility is good; the inner size of the clamping groove 21 matches the size of the clamping member 19, and the adjacent paving bricks 14 correspond to each other. The first fixed plate 18 and the second fixed plate 20 are connected by the clamping piece 19 and the clamping groove 21 to ensure the stability of the laying connection between adjacent paving bricks 14; the guide plate 16 is in the shape of a slope, and a drainage hole 17 is provided at both ends of each group of guide plates 16, which has a certain backflow effect to prevent water accumulation on the surface of the paving bricks 14; the number of infiltration tubes 6 is several, and they are evenly distributed inside the permeable concrete layer 4, and are connected with the side trough 9 through the guide tube 7, so as to improve the water permeability effect of the road permeable structure and prevent water accumulation on the road surface; the inner wall of the trough 9 is connected to the liquid level sensor 13, and the liquid level sensor 13 is electrically connected to the liquid pump 11 at the corresponding position through the controller, so as to realize auxiliary drainage operation inside the trough 9 and prevent water from overflowing from the trough 9.
[0023] The working principle and use process of the utility model are as follows: during the laying process of the road permeable structure, the infiltration pipe 6 is evenly laid inside the permeable concrete layer 4, and the paving bricks 14 used at the top are laid in a mutually staggered manner. The first fixing plate 18 at one end of a paving brick 14 is pressed on the upper end of the second fixing plate 20 corresponding to the two adjacent paving bricks 14, and the clamping piece 19 is aligned with the clamping groove 21. During the discharge process of the road structure, the guide plate 16 guides the rainwater to both sides, contacts the permeable concrete layer 4 through the drainage hole 17, enters the permeable concrete layer 4, and partially seeps The permeable water enters the pipeline under the action of the permeation tube 6, and finally flows into the water tank 9. Another part of the water will enter the gravel layer 3 and the sand and gravel layer 2 successively, and also enter the water tank 9 through the partition 8. When the internal water level of the water tank 9 is within a stable range, the water inside the water tank 9 is discharged from the drain pipe 10. When the water level inside the water tank 9 rises to the liquid level sensor 13, the liquid level sensor 13 senses and sends the corresponding signal to the controller, which converts it into an electrical signal to act on the liquid pump 11, and the liquid pump 11 carries the water inside the water tank 9 and discharges it from the outlet pipe 12.
[0024] Finally, it should be noted that the above description is only a preferred embodiment of the utility model and is not intended to limit the utility model. Although the utility model is described in detail with reference to the above embodiments, those skilled in the art can still modify the technical solutions recorded in the above embodiments or replace some of the technical features therein by equivalents. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the utility model shall be included in the protection scope of the utility model.
Claims
1. A permeable road pavement structure, comprising a base layer (1), Features: A sandstone layer (2) is provided at the upper end of the base layer (1), a crushed stone layer (3) is provided at the upper end of the sandstone layer (2), a permeable concrete layer (4) is provided at the upper end of the crushed stone layer (3), a brick layer (5) is provided at the upper end of the permeable concrete layer (4), a permeable pipe (6) is provided inside the permeable concrete layer (4), the lower end of the permeable pipe (6) is connected to a guide pipe (7), a partition (8) is provided on the side of the crushed stone layer (3), a water tank (9) is provided on one side of the partition (8), a drainage pipe (10) is provided on one side of the water tank (9), a liquid pump (11) is provided inside the water tank (9), and a water outlet pipe (12) is provided at the upper end of the liquid pump (11).
2. A road permeable pavement structure according to claim 1, Features: The paving brick layer (5) comprises a plurality of paving bricks (14), the upper end of each paving brick (14) being connected to a protrusion (15), a guide plate (16) being arranged in the middle of an adjacent protrusion (15), a drainage hole (17) being provided on the side of each paving brick (14), one end of each paving brick (14) being connected to a first fixing plate (18), the lower end of each first fixing plate (18) being connected to a clamping member (19), the other end of each paving brick (14) being connected to a second fixing plate (20), the surface of each second fixing plate (20) being provided with a clamping groove (21).
3. A road permeable pavement structure according to claim 2, Features: The shape of the card slots (21) is triangular and there are a plurality of them. The number of the card members (19) is a plurality and they are evenly distributed at the lower end of the first fixing plate (18).
4. A road permeable pavement structure according to claim 2, Features: The inner dimensions of the clamping slot (21) match the dimensions of the clamping piece (19), and the first fixing plate (18) and the second fixing plate (20) corresponding to the adjacent paving bricks (14) are clamped together via the clamping piece (19) and the clamping slot (21).
5. A road permeable pavement structure according to claim 2, Features: The guide plates (16) are in the shape of an inclined plane, and each set of guide plates (16) is provided with a drainage hole (17) at both ends.
6. A road permeable pavement structure according to claim 1, Features: The number of the permeable pipes (6) is several and they are evenly distributed inside the permeable concrete layer (4) and are connected to the water tank (9) on the side through the guide pipe (7).