Jack loading structure for hanging basket suspended pouring beam construction

By designing the jack loading structure for hanging basket hanging beam construction, the automatic lifting and position adjustment of the jack is achieved using basket hanging trusses, horizontal booms and lifting equipment, solving the difficulty of manual handling of jacks and safety hazards in the construction of hanging beam construction. The problem has improved construction efficiency and safety.

CN222100654UActive Publication Date: 2024-12-03ROAD & BRIDGE INT CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420346805.0
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-02-26
Publication Date
2024-12-03
Estimated Expiration
2034-02-26

AI Technical Summary

Technical Problem

During the construction of suspended beams, due to the large bridge span structure and limited lifting capacity of tower crane equipment, it is difficult to manually carry the jack and poses a major safety hazard. The existing technology lacks mature work platforms and protective measures.

Method used

A jack loading structure for hanging basket hanging beam construction is designed, including hanging basket truss, horizontal booms and lifting equipment. The hanging basket truss moves along the length of the hanging beam, and lifting equipment is installed on the horizontal boom to hang through a wire rope. The jack is equipped with sliding devices and walking tracks to achieve flexible position adjustment and movement of the jack.

Benefits of technology

The jacks are not required to be manually transported, which reduces safety risks, improves construction progress and efficiency, avoids the problems of insufficient lifting distance and lifting capacity of tower crane equipment, and realizes flexible adjustment of jack position and longitudinal prestressing tensioning.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222100654U_ABST
    Figure CN222100654U_ABST
Patent Text Reader

Abstract

The utility model belongs to the technical field of bridge construction, and discloses a jack loading structure for hanging basket suspended pouring beam construction. The jack loading structure for hanging basket and suspended pouring beam construction comprises a hanging basket truss, a horizontal lifting rod and lifting equipment, the hanging basket truss and a web plate are correspondingly arranged on a poured block section of a suspended pouring beam, and the hanging basket truss can move in the length direction of the suspended pouring beam; the two ends of the horizontal lifting rod are arranged on the two adjacent hanging basket trusses respectively; and the hoisting equipment is arranged on the horizontal hoisting rod in a position-adjustable manner and is used for hoisting the tensioning jack. According to the jack loading structure for hanging basket suspended pouring beam construction, the vertical position and the horizontal position of the tensioning jack can be adjusted, longitudinal prestress tensioning is conducted on all positions of a web plate and a top plate of a suspended pouring beam, manual carrying is not needed, and therefore potential safety hazards are reduced, and the construction progress and the construction efficiency are greatly improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of bridge construction, in particular to a jack loading structure for construction of hanging basket suspended beams. Background Art

[0002] During the construction of cantilever beams, tensioning jacks are required to prestress the steel bars inside the bridge. Construction workers usually need to use mechanical equipment such as tower cranes or hoists to transport and transfer the jacks. However, due to the large span structure of the bridge, the length of the tower crane's arm and the lifting capacity are limited, and the cost of configuring a large tower crane is high. When the construction length of the cantilever beam is long, it is difficult to transport the longitudinal prestressing with large-tonnage jacks manually and it is not easy to operate. If the jacks are transported manually, due to the high height of the web position and the lack of mature technology to arrange the construction work platform and safety protection measures, the construction workers rely on the reserved steel bars at the wet joints of the segments to climb up and down to transport them, which poses a great safety hazard. Utility Model Content

[0003] The utility model aims to provide a jack loading structure for hanging basket suspended beam construction, which can drive the tensioning jack to move, so as to improve the construction progress and construction efficiency.

[0004] To achieve this purpose, the utility model adopts the following technical solutions:

[0005] The utility model provides a jack loading structure for construction of a hanging basket suspended pouring beam, comprising:

[0006] A hanging basket truss, wherein the hanging basket truss and the web plate are arranged on the cast block section of the cantilever beam correspondingly, and the hanging basket truss can move along the length direction of the cantilever beam;

[0007] A horizontal suspension rod, the two ends of which are respectively arranged on two adjacent hanging basket trusses;

[0008] A lifting device is provided on the horizontal suspension rod in an adjustable manner, and the lifting device lifts the tensioning jack via a steel wire rope.

[0009] Preferably, a hanging piece is provided on the hanging basket truss, one end of the hanging piece is provided on the hanging basket truss, and the other end of the hanging piece is detachably connected to the horizontal suspension rod.

[0010] Preferably, the jack loading structure for the hanging basket suspended beam construction also includes a sliding device, the sliding device is adjustably arranged on the horizontal suspension rod, and the lifting equipment is arranged on the sliding device.

[0011] Preferably, a guide rail is provided on the horizontal boom, and the sliding device includes a drive motor, a first walking wheel and a mounting plate, the drive motor and the first walking wheel are both arranged on the mounting plate, the first walking wheel is in rolling cooperation with the guide rail, the drive motor is used to drive the first walking wheel to rotate, and the lifting equipment is connected to the mounting plate.

[0012] Preferably, a walking track is provided on the cantilever beam along the length direction, a second walking wheel is installed at the bottom of the hanging basket truss, the hanging basket truss is arranged on the walking track and the second walking wheel is in rolling cooperation with the walking track.

[0013] Preferably, the jack loading structure for the construction of the hanging basket suspended pouring beam further comprises a driving member, wherein the driving member is arranged on the suspended pouring beam, and the driving member is used to drive the hanging basket truss to move along the walking track.

[0014] Preferably, the lifting equipment is an electric hoist.

[0015] The beneficial effects of the utility model are:

[0016] The utility model provides a jack loading structure for construction of a hanging basket suspended beam, in which a hanging basket truss and a web are correspondingly arranged on a cast block section of the suspended beam, a horizontal hanger is arranged between two adjacent hanging basket trusses, and a lifting device for lifting a tensioning jack is arranged on the horizontal hanger, and the lifting device can lift the tensioning jack for vertical movement, and because the position of the lifting device on the horizontal hanger is adjustable, the lifting device can also drive the tensioning jack to adjust the lateral position, thereby realizing flexible adjustment of the position of the tensioning jack, so as to perform longitudinal prestressing tensioning on the web and the top plate of the suspended beam at various locations, without the need for manual handling, thereby reducing safety hazards and greatly improving construction progress and construction efficiency; because the hanging basket truss can move along the length direction of the suspended beam, the jack loading structure for construction of the hanging basket suspended beam can adjust the position of the tensioning jack according to the construction progress of different sections of the suspended beam, avoiding the problem of insufficient lifting distance and lifting capacity of existing equipment such as tower cranes. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] Figure 1 It is a front view of a jack loading structure for construction of a hanging basket suspended beam provided by a specific embodiment of the utility model;

[0018] Figure 2 It is a side view of a jack loading structure for construction of a hanging basket suspended beam provided by a specific implementation method of the utility model.

[0019] In the figure:

[0020] 100-cantilever beam; 110-travel track;

[0021] 200-tensioning jack;

[0022] 300-target tension point;

[0023] 1-Basket truss; 11-Lifting parts;

[0024] 2-Horizontal boom;

[0025] 3-Lifting equipment; 31-Wire rope;

[0026] 4- Sliding device. DETAILED DESCRIPTION

[0027] The present invention is further described in detail below in conjunction with the accompanying drawings and embodiments. It is to be understood that the specific embodiments described herein are only used to explain the present invention, rather than to limit the present invention. It should also be noted that, for ease of description, only the parts related to the present invention, rather than all structures, are shown in the accompanying drawings.

[0028] In the description of the present invention, unless otherwise clearly specified and limited, the terms "connected", "connected", and "fixed" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0029] In the present utility model, unless otherwise clearly specified and limited, a first feature being "above" or "below" a second feature may include that the first and second features are in direct contact, or may include that the first and second features are not in direct contact but are in contact through another feature between them. Moreover, a first feature being "above", "above" and "above" a second feature includes that the first feature is directly above and obliquely above the second feature, or simply indicates that the first feature is higher in level than the second feature. A first feature being "below", "below" and "below" a second feature includes that the first feature is directly below and obliquely below the second feature, or simply indicates that the first feature is lower in level than the second feature.

[0030] In the description of this embodiment, the terms "upper", "lower", "right", "left" and other directions or positional relationships are based on the directions or positional relationships shown in the drawings, and are only for the convenience of description and simplified operation, rather than indicating or implying that the device or element referred to must have a specific direction, be constructed and operated in a specific direction, and therefore cannot be understood as a limitation of the present invention. In addition, the terms "first" and "second" are only used to distinguish in the description and have no special meaning.

[0031] like Figure 1 and Figure 2 As shown, the utility model provides a jack loading structure for hanging basket suspended beam construction, which includes a hanging basket truss 1, a horizontal hanger 2 and a lifting device 3. The hanging basket truss 1 is arranged on the cast block section of the suspended beam 100 corresponding to the web, and the hanging basket truss 1 can move along the length direction of the suspended beam 100; the two ends of the horizontal hanger 2 are respectively arranged on two adjacent hanging basket trusses 1; the lifting device 3 is adjustably arranged on the horizontal hanger 2, and the lifting device 3 lifts the tensioning jack 200 through the wire rope 31. In this embodiment, the hanging basket truss 1 and the web are correspondingly arranged on the cantilever beam 100, and a horizontal suspension rod 2 is arranged between two adjacent hanging basket trusses 1. The horizontal suspension rod 2 is provided with a lifting device 3 for lifting the tensioning jack 200. The lifting device 3 can drive the tensioning jack 200 to move vertically. Since the position of the lifting device 3 on the horizontal suspension rod 2 is adjustable, the lifting device 3 can also drive the tensioning jack 200 to adjust the lateral position, thereby realizing flexible adjustment of the position of the tensioning jack 200, so as to move the tensioning jack 200 to the target tensioning position. At the pulling point 300, the target tensioning points 300 on the web and top plate of the suspended beam 100 are longitudinally prestressed. The entire moving process of the tensioning jack 200 does not require manual handling, thereby reducing safety hazards and greatly improving the construction progress and efficiency. Since the hanging basket truss 1 can move along the length direction of the suspended beam 100, the jack loading structure for the hanging basket suspended beam construction can adjust the position of the tensioning jack 200 according to the progress of the construction section of the suspended beam 100, avoiding the problem of insufficient lifting distance and lifting capacity of existing tower cranes and other equipment. Specifically, the hanging basket truss 1 is a common equipment in this field, and its main structure is a diamond truss structure; the lifting equipment 3 lifts the tensioning jack 200 through the wire rope 31, and the force on the wire rope 31 is transmitted to the hanging basket truss 1 through the horizontal hanger 2, and then transmitted to the suspended beam 100 by the hanging basket truss 1.

[0032] Furthermore, if Figure 2 As shown, a hanging member 11 is provided on the hanging basket truss 1, one end of the hanging member 11 is provided on the hanging basket truss 1, and the other end of the hanging member 11 is detachably connected to the horizontal suspension rod 2. In this embodiment, the hanging member 11 can be a connecting rod of fixed length, and the tensioning jack 200 can be vertically adjusted by the lifting device 3 itself; the hanging member 11 can also be a hydraulic cylinder that can be extended and retracted, thereby driving the horizontal suspension rod 2 to achieve vertical adjustment, further expanding the vertical adjustment range of the tensioning jack 200.

[0033] Furthermore, if Figure 1As shown, the jack loading structure of the cantilever beam 100 further includes a sliding device 4, which is adjustably arranged on the horizontal suspension rod 2, and the lifting device 3 is arranged on the sliding device 4. In this embodiment, the lifting device 3 is arranged on the sliding device 4, and the construction personnel can adjust the horizontal position of the lifting device 3 by controlling the sliding device 4 to move on the horizontal suspension rod 2, thereby adjusting the position of the tensioning jack 200.

[0034] Specifically, a guide rail is provided on the horizontal boom 2, and the sliding device 4 includes a drive motor, a first running wheel and a mounting plate. The drive motor and the first running wheel are both arranged on the mounting plate, the first running wheel and the guide rail are in rolling cooperation, the drive motor is used to drive the first running wheel to rotate, and the lifting device 3 is connected to the mounting plate. In this embodiment, a guide rail is provided on the horizontal boom 2, the first running wheel of the sliding device 4 can roll on the guide rail, the first running wheel is rotationally arranged on the mounting plate, the lifting device 3 is arranged on the mounting plate, and the drive motor can drive the first running wheel to rotate, thereby realizing the translation of the sliding device 4 on the horizontal boom 2; a limit baffle is provided at the end of the guide rail, and the limit baffle is used to limit the moving range of the first running wheel to prevent the first running wheel from falling off the guide rail.

[0035] Furthermore, a running track 110 is provided on the cantilever beam 100 along the length direction, a second running wheel is installed at the bottom of the hanging basket truss 1, the hanging basket truss 1 is arranged on the running track 110, and the second running wheel rolls with the running track 110. In this embodiment, the bottom of the hanging basket truss 1 is rotatably provided with a second running wheel, and the second running wheel rolls with the running track 110 on the cantilever beam 100, so the hanging basket truss 1 can move along the length direction of the cantilever beam 100 with the construction progress of different sections of the cantilever beam 100, and because the second running wheel rolls with the running track 110, the movement resistance of the hanging basket truss 1 is reduced.

[0036] Specifically, the jack loading structure for the construction of the hanging basket cantilever beam further includes a driving member, which is arranged on the cantilever beam 100 and is used to drive the hanging basket truss 1 to move along the running track 110. In this embodiment, the driving member can be a hydraulic jack or a cylinder, as long as it can push the hanging basket truss 1 to move along the running track 110 of the cantilever beam 100, and is not limited here.

[0037] Furthermore, the lifting device 3 is an electric hoist. Specifically, the electric hoist is a kind of lifting machinery commonly used in the art, which has the advantages of small size, light weight and simple operation, and the electric hoist can drive the tensioning jack 200 to move up and down, further increasing the height adjustment range and adjustment accuracy of the jack loading structure for the hanging basket suspended beam construction for the tensioning jack 200.

[0038] Obviously, the above embodiments of the present invention are merely examples for the purpose of clearly illustrating the present invention, and are not intended to limit the implementation methods of the present invention. For those skilled in the art, various obvious changes, readjustments and substitutions can be made without departing from the scope of protection of the present invention. It is not necessary and impossible to list all implementation methods here. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention shall be included in the scope of protection of the claims of the present invention.

Claims

1. A jack loading structure for hanging basket suspended beam construction, characterized in that: include: A hanging basket truss (1), wherein the hanging basket truss (1) is arranged on a cast block section of a cantilever beam (100) corresponding to the web plate, and the hanging basket truss (1) is movable along the length direction of the cantilever beam (100); A horizontal suspension rod (2), wherein two ends of the horizontal suspension rod (2) are respectively arranged on two adjacent hanging basket trusses (1); A lifting device (3) is arranged on the horizontal suspension rod (2) in an adjustable manner, and the lifting device (3) lifts the tensioning jack (200) via a steel wire rope (31).

2. The jack loading structure for construction of hanging basket suspended beam according to claim 1 is characterized in that: A hanging piece (11) is arranged on the hanging basket truss (1), one end of the hanging piece (11) is arranged on the hanging basket truss (1), and the other end of the hanging piece (11) is detachably connected to the horizontal hanging rod (2).

3. The jack loading structure for construction of hanging basket suspended beam according to claim 1 is characterized in that: The jack loading structure for the construction of hanging basket suspended beams also includes a sliding device (4), the sliding device (4) is adjustably arranged on the horizontal suspension rod (2), and the lifting equipment (3) is arranged on the sliding device (4).

4. The jack loading structure for construction of hanging basket suspended beam according to claim 3 is characterized in that: A guide rail is arranged on the horizontal suspension rod (2), and the sliding device (4) includes a driving motor, a first running wheel and a mounting plate. The driving motor and the first running wheel are both arranged on the mounting plate, and the first running wheel is in rolling cooperation with the guide rail. The driving motor is used to drive the first running wheel to rotate. The lifting equipment (3) is connected to the mounting plate, and a limit stop plate is arranged at the end of the guide rail.

5. The jack loading structure for construction of hanging basket suspended beam according to claim 1 is characterized in that: A walking track (110) is arranged on the cantilever beam (100) along the length direction, a second walking wheel is installed at the bottom of the hanging basket truss (1), the hanging basket truss (1) is arranged on the walking track (110), and the second walking wheel is in rolling cooperation with the walking track (110).

6. The jack loading structure for construction of hanging basket suspended beam according to claim 5 is characterized in that: The jack loading structure for the construction of the hanging basket cantilevered beam also includes a driving member, which is arranged on the cantilevered beam (100) and is used to drive the hanging basket truss (1) to move along the walking track (110).

7. The jack loading structure for construction of hanging basket suspended beam according to claim 1 is characterized in that: The lifting equipment (3) is an electric hoist.