Waterproof joint of fully-prefabricated floor slab and fully-prefabricated wallboard
By designing waterproof nodes of fully prefabricated floor slabs and wall panels in construction, and using grooves and connecting steel bars to combine slurry layer and concrete layer, the challenges of existing waterproofing measures to facade lines and costs are solved, and flexibility is achieved. Reliable waterproofing and earthquake-resistant adaptability.
Patent Information
- Application Number
- CN202420193890.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-01-26
- Publication Date
- 2024-12-03
- Estimated Expiration
- 2034-01-26
AI Technical Summary
During existing construction, the waterproofing measures for wall panels and floor panels have problems such as risk of destroying the facade lines, high cost, complex process and not meeting the specification requirements.
A waterproof node of fully prefabricated floor slab and fully prefabricated wall slab was designed. By setting grooves and connecting steel bars between the floor slab and wall slab, combining slurry layer, concrete layer and waterproof glue, structural waterproof measures are formed, which are suitable for the site simple pouring operation.
Flexible waterproof construction is realized, the professional skills requirements of on-site construction personnel are reduced, the connection reliability is improved, and the waterproof effect is ensured by adjusting the connecting steel structure to meet the needs of different earthquake resistance levels.
Smart Images

Figure CN222101149U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of building construction, in particular to a waterproof node of a fully prefabricated floor slab and a fully prefabricated wall panel. Background Art
[0002] The existing wall panels and floor panels are prefabricated structures. When assembled on site, the floor panel is set between two wall panels that are butted up and down, and waterproofing is required at the connection nodes. There are two existing waterproofing methods:
[0003] (1) Extend the floor slab 20mm beyond the wall slab, and make a slope at the extended position to achieve structural waterproofing. This approach has the risk of damaging the lines of the facade, and the 20mm extension of the floor slab increases the cost. In addition, the slope process is completely dependent on the experience of on-site workers and has high limitations. It will also cause some interference with the facade paint construction. After the construction is completed, if the weather-resistant glue under the slope needs to be processed, the slope part needs to be removed, and the process is relatively complicated.
[0004] (2) The fully prefabricated wall panels and fully prefabricated floor panels are completely dry-jointed, with no structural waterproofing. Only waterproof and weather-resistant glue is set between the two butted wall panels. There is a direction for water leakage and it does not meet the requirements of existing specifications. Utility Model Content
[0005] The utility model aims to provide a waterproof joint of a fully prefabricated floor slab and a fully prefabricated wall slab, optimizes the waterproof structure, does not require high professional skills of on-site construction personnel, and saves working procedures.
[0006] The technical solution of the utility model is: a waterproof node of a fully prefabricated floor slab and a fully prefabricated wall panel, which is arranged between the floor slab and two wall panels spliced up and down, a first groove is arranged in the bottom of the wall panel located on the upper layer, a second groove and a third groove are arranged in sequence from top to bottom in the top of the wall panel located on the lower layer, one end of the floor slab is placed in the second groove, the first groove, the second groove and the third groove are communicated, a slurry layer is arranged in the first groove, a second concrete layer is arranged in the third groove, and a first concrete layer is arranged in the second groove.
[0007] Preferably, a cushion block and waterproof glue are provided between the two wall panels spliced up and down, the waterproof glue is provided close to the outer side of the wall panels, and a cushion block is provided between the floor panel and the two wall panels.
[0008] Preferably, a first insulation board is provided in the wall panel, a second insulation board is provided between two wall panels spliced up and down, the first insulation board is connected to the second insulation board, and the second insulation board is located on the inner side of the cushion block.
[0009] Preferably, the upper surface of the floor slab is provided with a cast-in-place layer.
[0010] Preferably, the waterproof node between the fully prefabricated floor slab and the fully prefabricated wall panel includes a first connecting steel bar, a second connecting steel bar and a third connecting steel bar. The first connecting steel bar is arranged in the first groove, the second groove and the third groove. One end of the third connecting steel bar is placed in the floor slab and the other end extends into the second groove. The third connecting steel bars are connected one by one to the first connecting steel bars and a plurality of them are arranged in the longitudinal direction of the floor slab. The second connecting steel bar is placed in the second groove and extends along the longitudinal direction of the floor slab.
[0011] Preferably, the first connecting steel bars and the second connecting steel bars are straight rod structures.
[0012] In a specific technical solution, the third connecting steel bar is a closed ring structure.
[0013] Preferably, one end of the third connecting steel bar located in the floor slab is a square section with an opening, and one end of the third connecting steel bar located in the second groove is a U-shaped section with an opening, the U-shaped section is connected to the two openings of the square section to form the annular structure, the first connecting steel bar is connected to the U-shaped section, and the second connecting steel bar is placed in the U-shaped section and is located on the side of the first connecting steel bar away from the floor slab.
[0014] In another specific technical solution, the third connecting steel bar includes an L-shaped first side and a second side, the first side is placed in the second groove and is located on the side of the first connecting steel bar away from the floor slab, the second connecting steel bar is placed between the first side and the first connecting steel bar, and the second side extends from the second groove into the floor slab.
[0015] Preferably, the second side is arranged close to the bottom of the floor.
[0016] Compared with the related art, the beneficial effects of the utility model are:
[0017] 1. The waterproof nodes of the fully prefabricated floor slabs and fully prefabricated wall panels are partially cast on site, forming a structural waterproof measure, which is more flexible in construction and has lower requirements on the professional skills of on-site construction personnel, and only requires simple pouring actions;
[0018] Second, by setting connecting steel bars between the wall panels and the floor slabs, the reliability of the connection between the wall panels and the floor slabs is improved, and the connecting steel bars (circular or L-shaped) can be flexibly selected and adjusted according to the seismic resistance level;
[0019] 3. The slurry layer can be formed by high-strength grouting material, which has a slurry anchor structure, stable force and reliable connection;
[0020] Fourth, a second insulation board (interlayer insulation board) is installed in the wall panel to effectively achieve full-bridge connection of the wall panel;
[0021] 5. Rigid adjustment pads are set between wall panels and between floor slabs and wall panels, so that the elevation can be adjusted according to the on-site conditions. At the same time, the on-site construction progress will not be affected by the age of the on-site poured concrete and grouting materials. BRIEF DESCRIPTION OF THE DRAWINGS
[0022] Figure 1 A schematic structural diagram of the first embodiment of the waterproof joint of the fully prefabricated floor slab and the fully prefabricated wall slab provided by the utility model;
[0023] Figure 2 for Figure 1 A magnified schematic diagram of point A;
[0024] Figure 3 A structural schematic diagram of the second embodiment of the waterproof joint of the fully prefabricated floor slab and the fully prefabricated wall slab provided by the utility model;
[0025] Figure 4 for Figure 3 An enlarged schematic diagram of point B.
[0026] In the attached drawings: 1. floor slab; 2. wall panel; 3. first connecting steel bar; 4. second connecting steel bar; 5. third connecting steel bar; 51. first side; 52. second side; 6. first concrete layer; 7. second concrete layer; 8. first insulation board; 9. waterproof glue; 10. pad; 11. slurry layer; 12. cast-in-place layer; 13. first groove; 14. second groove; 15. third groove; 16. second insulation board. DETAILED DESCRIPTION
[0027] The present invention will be described in detail below with reference to the accompanying drawings and in combination with the embodiments. It should be noted that the embodiments and features in the embodiments of the present invention can be combined with each other without conflict. For the convenience of description, if the words "upper", "lower", "left" and "right" appear in the following text, they only indicate that the upper, lower, left and right directions are consistent with the drawings themselves, and do not limit the structure.
[0028] Embodiment 1
[0029] like Figure 1 , Figure 2As shown, a waterproof node of a fully prefabricated floor slab and a fully prefabricated wall slab provided in this embodiment is arranged between a floor slab 1 and two wall slabs 2 spliced up and down, a first groove 13 is arranged in the bottom of the wall slab 2 located in the upper layer, and a second groove 14 and a third groove 15 are arranged in the top of the wall slab 2 located in the lower layer from top to bottom, one end of the floor slab 1 is placed in the second groove 14, the first groove 13, the second groove 14 and the third groove 15 are connected, and a slurry layer 11 is arranged in the first groove 13. The first groove 13 is open on the side of the wall slab 2 facing the floor slab 1, and high-strength grouting material is poured into the first groove 13 at the open position to form the slurry layer 11. A second concrete layer 7 is arranged in the third groove 15, and a first concrete layer 6 is arranged in the second groove 14. The first concrete layer 6 and the second concrete layer 7 are formed by cast-in-place concrete.
[0030] The slurry layer 11, the first concrete layer 6 and the second concrete layer 7 form a waterproof node between the fully prefabricated floor and the fully prefabricated wall. At the same time, the waterproof node between the fully prefabricated floor and the fully prefabricated wall also includes a first connecting steel bar 3, a second connecting steel bar 4 and a third connecting steel bar 5. The first connecting steel bar 3 is arranged in the first groove 13, the second groove 14 and the third groove 15, and the first connecting steel bar 3 is fixed by the slurry layer 11 in the first groove 13, the first concrete layer 6 in the second groove 14 and the second concrete layer 7 in the third groove 15. One end of the third connecting steel bar 5 is placed in the floor 1, and the other end extends into the second groove 14 and is fixed by the first concrete layer 6. The third connecting steel bar 5 is connected to the first connecting steel bar 3 one by one and is arranged in plurality in the longitudinal direction of the floor 1. The second connecting steel bar 4 is placed in the second groove 14 and extends in the longitudinal direction of the floor 1. The second connecting steel bar 4 is fixed by the first concrete layer 6. The first connecting steel bar 3 and the second connecting steel bar 4 are straight rod structures.
[0031] The third connecting steel bar 5 is embedded in the floor 1. In this embodiment, the third connecting steel bar 5 is a closed ring structure. One end of the third connecting steel bar 5 located in the floor 1 is a square section with an opening, and one end of the third connecting steel bar 5 located in the second groove 14 is a U-shaped section with an opening. The U-shaped section is connected to the two openings of the square section to form the ring structure. The first connecting steel bar 3 is connected to the U-shaped section, and the second connecting steel bar 4 is placed in the U-shaped section and is located on the side of the first connecting steel bar 3 away from the floor 1.
[0032] Waterproof glue 9, cushion block 10 and second insulation board 16 are arranged in sequence from outside to inside between the two wall panels 2 spliced up and down. A first insulation board 8 is arranged inside the wall panel 2. The second insulation board 16 is located in correspondence with the positions of the two first insulation boards 8 and is connected by insulation nails.
[0033] A cushion block 10 is provided between the floor slab 1 and the two wall panels 2. The waterproof glue 9 is a waterproof and weather-resistant glue. The cushion block 10 is a rigid cushion block. A cast-in-place layer 12 is provided on the upper surface of the floor slab 1.
[0034] During construction, the wall panel 2 located on the lower layer is hoisted first. After it is in place, the floor slab 1 is hoisted, and one end of the floor slab 1 is placed in the second groove 14. The elevation can be adjusted using the pad 10. After it is in place, the second connecting steel bar 4 is placed. The second insulation board 16 is then fixed to the first insulation board 8 with insulation nails. Concrete is poured in the second groove 14 and the third groove 15. The wall panel 2 on the upper layer is hoisted again, and the elevation is adjusted by the pad 10. High-strength grouting material is then poured into the first groove 13. The cast-in-place layer 12 on the floor slab 1 can be constructed after the overall hoisting, or it can be constructed after the above actions are completed. Multiple layers are assembled according to the above method. After the overall construction is completed, waterproof glue 9 is applied between two adjacent wall panels 2. In addition, drainage holes are set at the intersection of the horizontal seams and vertical seams of every 2-3 layers of wall panels 2, and drainage holes must be set at the vertical seams of the first layer.
[0035] Embodiment 2
[0036] like Figure 3 , Figure 4 As shown, the first embodiment is repeated, except that the third connecting steel bar 5 in the waterproof joint of the fully prefabricated floor slab and the fully prefabricated wall slab provided in this embodiment includes an L-shaped first side 51 and a second side 52, the first side 51 is placed in the second groove 14 and is located on the side of the first connecting steel bar 3 away from the floor slab 1, the second connecting steel bar 4 is placed between the first side 51 and the first connecting steel bar 3, and the second side 52 extends from the second groove 14 into the floor slab 1. And the second side 52 is arranged close to the bottom of the floor slab 1.
[0037] According to the seismic resistance level of the actual project, the structure of the third connecting steel bar 5 is optimized, and at the same time, the connection structure of the first connecting steel bar 3, the second connecting steel bar 4 and the third connecting steel bar 5 is optimized to meet the requirements of the specification.
[0038] The above description is only an embodiment of the present invention, and does not limit the patent scope of the present invention. Any equivalent structure or equivalent process transformation made by using the contents of the specification and drawings of the present invention, or directly or indirectly applied in other related technical fields, are also included in the patent protection scope of the present invention.
Claims
1. A waterproof joint of a fully prefabricated floor slab and a fully prefabricated wall slab, arranged between a floor slab (1) and two upper and lower spliced wall slabs (2), characterized in that: A first groove (13) is provided in the bottom of the wall panel (2) located at the upper layer, and a second groove (14) and a third groove (15) are provided in the top of the wall panel (2) located at the lower layer in order from top to bottom; one end of the floor slab (1) is placed in the second groove (14); the first groove (13), the second groove (14) and the third groove (15) are connected; a slurry layer (11) is provided in the first groove (13); a second concrete layer (7) is provided in the third groove (15); and a first concrete layer (6) is provided in the second groove (14).
2. The waterproof joint of the fully prefabricated floor slab and the fully prefabricated wall slab according to claim 1 is characterized in that: A cushion block (10) and waterproof glue (9) are provided between two upper and lower spliced wall panels (2); the waterproof glue (9) is provided close to the outer side of the wall panel (2); and a cushion block (10) is provided between the floor panel (1) and the two wall panels (2).
3. The waterproof joint of the fully prefabricated floor slab and the fully prefabricated wall slab according to claim 1 is characterized in that: A first insulation board (8) is provided inside the wall panel (2), a second insulation board (16) is provided between the two wall panels (2) spliced together, the first insulation board (8) is connected to the second insulation board (16), and the second insulation board (16) is located on the inner side of the cushion block (10).
4. The waterproof joint of the fully prefabricated floor slab and the fully prefabricated wall slab according to claim 1, characterized in that: The upper surface of the floor slab (1) is provided with a cast-in-place layer (12).
5. The waterproof joint of the fully prefabricated floor slab and the fully prefabricated wall slab according to claim 1, characterized in that: The invention comprises a first connecting steel bar (3), a second connecting steel bar (4) and a third connecting steel bar (5), wherein the first connecting steel bar (3) is arranged in the first groove (13), the second groove (14) and the third groove (15), one end of the third connecting steel bar (5) is placed in the floor slab (1) and the other end extends into the second groove (14), and the third connecting steel bar (5) is connected to the first connecting steel bars (3) one by one and a plurality of the third connecting steel bars (5) are arranged in the longitudinal direction of the floor slab (1), and the second connecting steel bar (4) is placed in the second groove (14) and extends in the longitudinal direction of the floor slab (1).
6. The waterproof joint of the fully prefabricated floor slab and the fully prefabricated wall slab according to claim 5, characterized in that: The first connecting steel bar (3) and the second connecting steel bar (4) are straight rod structures.
7. The waterproof joint of the fully prefabricated floor slab and the fully prefabricated wall slab according to claim 5 or 6, characterized in that: The third connecting steel bar (5) is a closed ring structure.
8. The waterproof joint of the fully prefabricated floor slab and the fully prefabricated wall slab according to claim 7, characterized in that: One end of the third connecting steel bar (5) located in the floor slab (1) is a square section with an opening, and one end of the third connecting steel bar (5) located in the second groove (14) is a U-shaped section with an opening, the U-shaped section is connected to the two openings of the square section to form the annular structure, the first connecting steel bar (3) is connected to the U-shaped section, and the second connecting steel bar (4) is placed in the U-shaped section and is located on a side of the first connecting steel bar (3) away from the floor slab (1).
9. The waterproof joint of the fully prefabricated floor slab and the fully prefabricated wall slab according to claim 5 or 6, characterized in that: The third connecting steel bar (5) comprises an L-shaped first side edge (51) and a second side edge (52), the first side edge (51) being disposed in the second groove (14) and located on a side of the first connecting steel bar (3) away from the floor slab (1), the second connecting steel bar (4) being disposed between the first side edge (51) and the first connecting steel bar (3), and the second side edge (52) extending from the second groove (14) into the floor slab (1).
10. The waterproof joint of the fully prefabricated floor slab and the fully prefabricated wall slab according to claim 9, characterized in that: The second side edge (52) is arranged close to the bottom of the floor slab (1).