Fabricated operating platform for mounting super high-rise structure
By introducing infrared sensors and automatic closing fence door design into the prefabricated operating platform for ultra-high-rise structure installation, the problem of low safety in the existing technology is solved, efficient safety protection and automatic alarm functions are achieved, and construction is improved Safety of personnel.
Patent Information
- Application Number
- CN202420447603.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-08
- Publication Date
- 2024-12-03
- Estimated Expiration
- 2034-03-08
AI Technical Summary
The existing prefabricated operating platform for installation of ultra-high-rise structures has low safety and lacks effective protective measures and alarm mechanisms, resulting in greater safety risks for construction workers when working at high altitudes.
A safety protection structure including infrared sensors, buzzers, fence doors, racks, control rods, gears, impact rods and pressure sensors is designed. Through infrared sensors, people are detected and alarmed, and they are surrounded when people are on and off the platform. The door automatically closes to ensure safety.
The safety of construction workers working at high altitudes has been improved. Through the automatic alarm and closing door design, the safety protection performance of the operating platform has been significantly enhanced.
Smart Images

Figure CN222101409U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of super high-rise structure installation, in particular to an assembled operating platform for super high-rise structure installation. Background Art
[0002] High-rise buildings not only represent the symbol of a city or region, but also in cities with limited land resources, they can only seek upward development. In this case, high-rise buildings came into being. The construction of super-high-rise steel structures is usually higher than the 1-2-story civil structure. The hoisting of steel structure steel columns is high-altitude construction, and an operating platform must be set up to ensure safe construction.
[0003] Chinese patent publication number CN211037777U proposes "an assembled operating platform for super high-rise structure installation". The technical solution addresses the problem that "when the existing operating platform is raised to a high altitude to assist construction workers in their work, due to the poor stability of the high-altitude operating platform, construction workers are easily separated from the operating platform through the access door, resulting in low safety". The utility model provides the following technical solution: "By setting up pull rings and safety ropes, the access door is blocked, thereby improving the safety of construction workers during high-altitude operations."
[0004] The above scheme has the following defects: the safety protection is low by blocking the door only by a few pull rings and safety ropes, and the above device has no alarm structure. When the worker forgets to put on the pull ring, there will be no alarm prompt. Therefore, an assembled operating platform for super high-rise structure installation is proposed to solve the above problem. Utility Model Content
[0005] In view of the deficiencies in the prior art, the utility model provides an assembled operating platform for installing a super high-rise structure, which has the advantages of high safety protection.
[0006] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: an assembled operating platform for installing a super high-rise structure, comprising an assembled operating platform body, wherein a safety protection structure is arranged inside the assembled operating platform body.
[0007] The safety protection structure includes a right side plate fixedly installed on the right side of the inner cavity of the assembled operating platform body, a stop plate fixedly installed on the left side of the right side plate, a left side plate fixedly installed on the left side of the inner cavity of the assembled operating platform body, two cross bars fixedly installed inside the left side plate, connecting blocks are slidably installed on the outside of the two cross bars, an enclosure door penetrating to the right side of the left side plate is fixedly installed between the two connecting blocks, a convex plate is fixedly installed on the front of the enclosure door, a rack is fixedly installed on the surface of the convex plate, a control rod penetrating to the top of the left side plate is rotatably installed inside the left side plate, a gear is fixedly installed on the outside of the control rod, an infrared sensor is fixedly installed on the right side of the inner cavity of the assembled operating platform body, a buzzer is fixedly installed on the surface of the right side plate, an inner groove is opened inside the right side plate, a striker penetrating to the left side of the right side plate is slidably installed inside the inner groove, a spring sleeved on the outside of the striker rod is fixedly installed on the left side of the inner groove, and a pressure sensor is fixedly installed on the right side of the inner groove.
[0008] Furthermore, the right side plate and the left side plate are both located at one end close to the back of the assembled operating platform body, the retaining plate is located at one end close to the back of the right side plate, and the height of the retaining plate is less than the height of the right side plate.
[0009] Furthermore, the interior of the left side plate is a hollow structure, the left side plate and the right side plate are both located on the same horizontal line, and the two cross bars are respectively located near the top and bottom ends of the left side plate.
[0010] Furthermore, the connecting block, the enclosure door, the convex plate and the rack all slide left and right inside the left side plate, and the control rod is located at one end close to the right side of the left side plate.
[0011] Furthermore, the gear is meshed and installed in front of the rack, the infrared sensor and the buzzer are electrically connected, and the inner groove is located at the waist position of the right side plate.
[0012] Furthermore, the impact rod is located in front of the baffle plate, and the exterior of the impact rod is a "T"-shaped structure.
[0013] Furthermore, the spring is fixedly connected to the left side of the impact rod, the spring and the pressure sensor are located on the same horizontal line, and the pressure sensor is electrically connected to the buzzer.
[0014] Compared with the prior art, the technical solution of this application has the following beneficial effects:
[0015] The assembled operating platform for super-high-rise structure installation supports personnel working on the super-high-rise structure through the assembled operating platform body. When the infrared sensor detects human activity inside the assembled operating platform body, the buzzer will sound an alarm, and the enclosure door will be controlled to move to the right and dock with the right side panel to close the outside of the assembled operating platform body. The buzzer will stop the alarm, thereby achieving a high safety protection performance. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Figure 1 This is a cross-sectional view of the structure of the utility model;
[0017] Figure 2 This is a front view of the structure of the utility model;
[0018] Figure 3 This is a schematic diagram of the cross-sectional structure of the left side panel of the utility model from top view;
[0019] Figure 4 It is a schematic diagram of the three-dimensional structure of the right side plate of the utility model.
[0020] In the figure: 1. Assembled operating platform body; 2. Right side plate; 3. Stop plate; 4. Left side plate; 5. Cross bar; 6. Connecting block; 7. Enclosure door; 8. Convex plate; 9. Rack; 10. Control lever; 11. Gear; 12. Infrared sensor; 13. Buzzer; 14. Inner groove; 15. Impact rod; 16. Spring; 17. Pressure sensor. DETAILED DESCRIPTION
[0021] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0022] See also Figure 1-4 In this embodiment, an assembled operating platform for installing a super high-rise structure includes an assembled operating platform body 1, and a safety protection structure is arranged inside the assembled operating platform body 1.
[0023] The safety protection structure includes a right side plate 2 fixedly installed on the right side of the inner cavity of the assembled operating platform body 1, a stop plate 3 fixedly installed on the left side of the right side plate 2, the stop plate 3 is located at one end close to the back of the right side plate 2, and the height of the stop plate 3 is less than the height of the right side plate 2, and a left side plate 4 is fixedly installed on the left side of the inner cavity of the assembled operating platform body 1, the right side plate 2 and the left side plate 4 are both located at one end close to the back of the assembled operating platform body 1, the interior of the left side plate 4 is a hollow structure, the left side plate 4 and the right side plate 2 are both located on the same horizontal line, so that the structure inside the left side plate 4 can extend out and dock with the right side plate 2, and two cross bars 5 are fixedly installed inside the left side plate 4, and the two cross bars 5 are respectively located near the top and bottom ends of the left side plate 4, and the outsides of the two cross bars 5 are slidably installed with connecting blocks 6, and a blocking door 7 that runs through the right side of the left side plate 4 is fixedly installed between the two connecting blocks 6, and the blocking door 7 between the two connecting blocks 6 is restricted from sliding inside the left side plate 4 by the two cross bars 5.
[0024] A convex plate 8 is fixedly installed on the front of the enclosure door 7, and a rack 9 is fixedly installed on the surface of the convex plate 8. The connecting block 6, the enclosure door 7, the convex plate 8 and the rack 9 all slide left and right inside the left side plate 4. A control rod 10 that penetrates to the top of the left side plate 4 is rotatably installed inside the left side plate 4. The control rod 10 is located at one end close to the right side of the left side plate 4. A gear 11 is fixedly installed on the outside of the control rod 10, and the gear 11 is meshed and installed in front of the rack 9. Holding the control rod 10 and operating the gear 11 to rotate forward and backward in front of the rack 9 can drive the convex plate 8 and the enclosure door 7 to move left and right. When the enclosure door 7 moves to the right and docks with the right side plate 2, the outside of the assembled operating platform body 1 can be closed. At this time, the retaining plate 3 will resist the back of the enclosure door 7 to prevent the enclosure door 7 from tilting backward.
[0025] An infrared sensor 12 is fixedly installed on the right side of the inner cavity of the assembled operating platform body 1, and a buzzer 13 is fixedly installed on the surface of the right side plate 2. The infrared sensor 12 and the buzzer 13 are electrically connected. The infrared sensor 12 detects human activity inside the assembled operating platform body 1 and transmits a signal to the buzzer 13, and then the buzzer 13 sounds an alarm. An inner groove 14 is opened inside the right side plate 2. The inner groove 14 is located at the waist position of the right side plate 2. An impact rod 15 that penetrates to the left side of the right side plate 2 is slidably installed inside the inner groove 14. The impact rod 15 is located in front of the baffle plate 3, and the outside of the impact rod 15 is "T" shaped. Structure, a spring 16 mounted on the outside of the impact rod 15 is fixedly installed on the left side of the inner groove 14, and the spring 16 is fixedly connected to the left side of the impact rod 15. The retraction of the spring 16 can pull the impact rod 15 to move to the left, and a pressure sensor 17 is fixedly installed on the right side of the inner groove 14. The spring 16 and the pressure sensor 17 are located on the same horizontal line. The pressure sensor 17 is electrically connected to the buzzer 13. The movement of the enclosure door 7 to the right will push the impact rod 15 to retract into the inner groove 14 and press the pressure sensor 17. The pressure sensor 17 is pressed and transmits a signal to the buzzer 13, and the buzzer 13 stops the alarm.
[0026] The working principle of the above embodiment is:
[0027] When in use, the assembled operating platform body 1 supports and holds up personnel working on super-high floors. When the infrared sensor 12 detects human activity inside the assembled operating platform body 1, it transmits a signal to the buzzer 13, and then the buzzer 13 sounds an alarm. At this time, the control lever 10 is held to control the gear 11 to rotate clockwise in front of the rack 9, thereby driving the convex plate 8 and the enclosure door 7 to move to the right. When the enclosure door 7 moves to the right and docks with the right side plate 2, the outside of the assembled operating platform body 1 can be closed. When the enclosure door 7 moves to the right and docks with the right side plate 2, it will push the impact rod 15 to retract into the inside of the inner groove 14 and press the pressure sensor 17. The pressure sensor 17 is pressed and transmits the signal to the buzzer 13. The buzzer 13 stops the alarm after receiving the signal. Then the gear 11 is controlled to rotate counterclockwise in front of the rack 9 to drive the convex plate 8 and the enclosure door 7 to move to the left. At this time, the spring 16 loses the pressure and retracts, pulling the impact rod 15 to move to the left. As a result, the pressure sensor 17 loses the squeeze and transmits the signal to the buzzer 13, and the buzzer 13 starts to alarm again. At this time, only when personnel leave the interior of the assembled operating platform body 1 and the infrared sensor 12 detects that there is no one inside the assembled operating platform body 1, the buzzer 13 will not sound.
[0028] It should be noted that, in this article, the control method of the utility model is controlled by a controller, the control circuit of the controller can be implemented by simple programming by technicians in this field, the provision of power is also common knowledge in this field, and the utility model is mainly used to protect mechanical devices, so the utility model will no longer explain the control method and circuit connection in detail.
[0029] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device. In the absence of further restrictions, the elements defined by the sentence "comprise a ..." do not exclude the existence of other identical elements in the process, method, article or device including the elements.
[0030] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. An assembled operating platform for installing a super high-rise structure, comprising an assembled operating platform body (1), characterized in that: A safety protection structure is provided inside the assembled operating platform body (1); The safety protection structure comprises a right side plate (2) fixedly mounted on the right side of the inner cavity of the assembled operating platform body (1), a stop plate (3) fixedly mounted on the left side of the right side plate (2), a left side plate (4) fixedly mounted on the left side of the inner cavity of the assembled operating platform body (1), two cross bars (5) fixedly mounted inside the left side plate (4), connecting blocks (6) slidably mounted on the outside of the two cross bars (5), a blocking door (7) extending to the right side of the left side plate (4) fixedly mounted between the two connecting blocks (6), a convex plate (8) fixedly mounted on the front side of the blocking door (7), a rack (9) fixedly mounted on the surface of the convex plate (8), and the left side plate (4) fixedly mounted on the inner cavity of the assembled operating platform body (1). A control lever (10) extending through the top of the side panel (4) is rotatably mounted inside the side panel (4), a gear (11) is fixedly mounted outside the control lever (10), an infrared sensor (12) is fixedly mounted on the right side of the inner cavity of the assembled operating platform body (1), a buzzer (13) is fixedly mounted on the surface of the right side panel (2), an inner groove (14) is provided inside the right side panel (2), a striker rod (15) extending through the left side of the right side panel (2) is slidably mounted inside the inner groove (14), a spring (16) mounted on the outside of the striker rod (15) is fixedly mounted on the left side of the inner groove (14), and a pressure sensor (17) is fixedly mounted on the right side of the inner groove (14).
2. The assembled operating platform for super high-rise structure installation according to claim 1, characterized in that: The right side plate (2) and the left side plate (4) are both located at one end close to the back of the assembled operating platform body (1), and the retaining plate (3) is located at one end close to the back of the right side plate (2), and the height of the retaining plate (3) is less than the height of the right side plate (2).
3. The assembled operating platform for super high-rise structure installation according to claim 1 is characterized by: The interior of the left side plate (4) is a hollow structure, the left side plate (4) and the right side plate (2) are both located on the same horizontal line, and the two cross bars (5) are respectively located near the top and bottom ends of the left side plate (4).
4. The assembled operating platform for super high-rise structure installation according to claim 1 is characterized in that: The connecting block (6), the enclosure door (7), the convex plate (8) and the rack (9) all slide leftward and rightward inside the left side plate (4), and the control rod (10) is located at an end close to the right side of the left side plate (4).
5. The assembled operating platform for super high-rise structure installation according to claim 1 is characterized by: The gear (11) is meshed and installed in front of the rack (9), the infrared sensor (12) and the buzzer (13) are electrically connected, and the inner groove (14) is located at the waist position of the right side plate (2).
6. The assembled operating platform for super high-rise structure installation according to claim 1, characterized in that: The impact rod (15) is located in front of the blocking plate (3), and the outside of the impact rod (15) is a "T"-shaped structure.
7. The assembled operating platform for super high-rise structure installation according to claim 1 is characterized by: The spring (16) is fixedly connected to the left side of the impact rod (15), the spring (16) and the pressure sensor (17) are both located on the same horizontal line, and the pressure sensor (17) is electrically connected to the buzzer (13).
Citation Information
Patent Citations
Assembly type operation platform for mounting super high-rise structure
CN211037777U