Multi-layer blast ventilation cooling tower
By adopting structures such as gears, external rings, ventilation columns and spiral blades in the ventilation cooling tower, the problem of insufficient contact between water and gas is solved, and the cooling efficiency of the cooling tower and the uniformity of water spraying are improved.
Patent Information
- Application Number
- CN202420080112.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-01-12
- Publication Date
- 2024-12-03
- Estimated Expiration
- 2034-01-12
AI Technical Summary
The water and gas in the existing ventilation cooling towers are not in sufficient contact with each other, and the spray head is fixed, resulting in low cooling efficiency.
A multi-layer blowing and ventilation cooling tower is designed, adopting gears, external rings, ventilation columns, spiral blades and diverter plates, and the driving rod and gear are driven to rotate at a certain angle through the servo motor to drive the water-flow rotation ring Spray water evenly with the spray head, and assist in guiding the contact between air and water through the ventilation column and spiral blades to increase the contact area.
The full contact between water and air is achieved, the cooling efficiency of the cooling tower is improved, and the uniformity of water spray and the full exchange of feng shui is ensured.
Smart Images

Figure CN222104449U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of cooling towers, in particular to a multi-layer blast ventilation cooling tower. Background Art
[0002] A ventilation cooling tower is a cooling tower that allows air to enter the cooling tower and contact the hot water in the tower to cool the hot water. Air enters the tower from the bottom of the cooling tower and flows upward, and water enters the tower from the top and flows downward for heat exchange treatment. However, existing ventilation cooling towers have the problem of insufficient contact between water and gas. The water outlet nozzles in the cooling tower are mostly fixed, and the water is not sprayed evenly. The contact surface area between air and water is relatively small, which reduces the cooling efficiency of the cooling tower. Utility Model Content
[0003] The utility model aims to provide a multi-layer forced draft cooling tower to solve the problem of insufficient contact between water and gas in the existing ventilation cooling towers mentioned in the above background technology, the water outlet nozzles in the cooling towers are mostly fixed, the water is not sprayed evenly, the contact surface area between air and water is relatively small, and the cooling efficiency of the cooling tower is reduced.
[0004] To achieve the above-mentioned purpose, the utility model provides the following technical scheme: a multi-layer forced air ventilation cooling tower, comprising a first tower body, the top of the first tower body is fixedly connected to a support frame, the top of the support frame is fixedly connected to a second tower body, the bottom of the second tower body is fixedly connected to a connecting pipe, the connecting pipe is fixedly connected to the first tower body, the interior of the first tower body is rotatably connected to a ventilation column, the outer side of the ventilation column is fixedly connected to a spiral blade, the outer side of the ventilation column is symmetrically fixedly connected to an air outlet head, the interior of the connecting pipe is fixedly connected to a diverter plate, the interior of the second tower body is fixedly connected to a sieve plate, the inner side of the second tower body is rotatably connected to a water-passing swivel, the bottom of the water-passing swivel is equidistantly fixedly connected to a water spray head, a water pump is installed on the top of the second tower body, the input end of the water pump is fixedly connected to a water inlet pipe, and the output end of the water pump is connected to the water-passing swivel through a water supply hose.
[0005] As a preferred solution of the utility model: the interior of the No. 2 tower body is rotatably connected with a driving rotating rod, the driving rotating rod is rotatably connected to the No. 1 tower body, the outer side of the driving rotating rod is fixedly connected with a gear, the outer side of the water-passing swivel is fixedly connected with an outer gear ring, the outer gear ring is slidably connected to the No. 2 tower body, the outer gear ring is meshingly connected with the gear, a servo motor is installed inside the No. 2 tower body, and the output end of the servo motor is fixedly connected to the driving rotating rod.
[0006] As a preferred solution of the utility model: the bottom of the No. 1 tower body is fixedly connected to a connecting bottom box, the driving rotating rod is rotatably connected to the connecting bottom box, the interior of the connecting bottom box is rotatably connected to a ventilation pipe, the ventilation pipe is rotatably connected to the No. 1 tower body, the top of the ventilation pipe is fixedly connected to a ventilation column, the driving rotating rod and the outer sides of the ventilation pipe are fixedly connected to pulleys, and the two pulleys are connected by belt transmission.
[0007] As a preferred solution of the utility model: a rotary joint is installed at the bottom of the connecting bottom box, one end of the ventilation pipe is connected to the rotary joint, an air intake fan is installed at the bottom of the connecting bottom box, the output end of the air intake fan is connected to the rotary joint through an air duct, and the input end of the air intake fan is fixedly connected to the air intake pipe.
[0008] As a preferred solution of the utility model: an exhaust fan is installed on the top of the second tower body, the output end of the exhaust fan is fixedly connected to an exhaust pipe, the input end of the exhaust fan is fixedly connected to an air collecting pipe, and one end of the air collecting pipe is fixedly connected to the second tower body.
[0009] As a preferred solution of the utility model: a drain pipe is fixedly connected to one side of the No. 1 tower body, a control panel is installed on one side of the No. 1 tower body, and the servo motor, water pump, exhaust fan and intake fan are all electrically connected to the control panel.
[0010] Compared with the prior art, the beneficial effects of the utility model are as follows: the utility model adds gears and outer gear rings, thereby realizing that when the servo motor drives the driving rotating rod and the gears to perform fixed-angle reciprocating rotation adjustment, the meshing outer gear ring is driven to rotate by the gears, and the outer gear ring drives the inner water-passing rotating ring and the water spray head to perform fixed-angle reciprocating rotation, and water is sprayed evenly through the water spray head to fully contact with the air, thereby ensuring the working efficiency of the ventilation cooling tower; by adding ventilation columns, spiral blades, and air outlet heads, the spiral blades on the outside of the ventilation columns can be used to assist in guiding wind and water, thereby ensuring that the water flowing through the diverter plate is in full contact with the air outlet of the air outlet head, thereby improving working efficiency. BRIEF DESCRIPTION OF THE DRAWINGS
[0011] Figure 1 This is a schematic diagram of the internal structure of the utility model;
[0012] Figure 2 For this utility model Figure 1 Enlarged view of point A in the middle;
[0013] Figure 3 It is a bottom view of the water-passing swivel of the utility model.
[0014] In the figure: 1. Tower body No. 1; 2. Support frame; 3. Tower body No. 2; 4. Connecting bottom box; 5. Pulley; 6. Ventilation pipe; 7. Rotary joint; 8. Ventilation column; 9. Spiral blade; 10. Air outlet head; 11. Diverter plate; 12. Connecting pipe; 13. Screen plate; 14. Water swivel; 15. Sprinkler head; 16. Outer gear ring; 17. Gear; 18. Servo motor; 19. Water pump; 20. Exhaust fan; 21. Exhaust pipe; 22. Collecting pipe; 23. Control panel; 24. Intake fan; 25. Intake pipe; 26. Drain pipe; 27. Driving rod. DETAILED DESCRIPTION
[0015] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0016] See also Figures 1 to 3 The utility model provides a technical solution: a multi-layer blast ventilation cooling tower, comprising a first tower body 1, a support frame 2 is fixedly connected to the top of the first tower body 1, a second tower body 3 is fixedly connected to the top of the support frame 2, a connecting pipe 12 is fixedly connected to the bottom of the second tower body 3, the connecting pipe 12 is fixedly connected to the first tower body 1, a ventilation column 8 is rotatably connected to the inside of the first tower body 1, a spiral blade 9 is fixedly connected to the outside of the ventilation column 8, an air outlet head 10 is symmetrically fixedly connected to the outside of the ventilation column 8, and a flow divider is fixedly connected to the inside of the connecting pipe 12. Plate 11, a sieve plate 13 is fixedly connected to the inside of the No. 2 tower body 3, a water-passing swivel 14 is rotatably connected to the inner side of the No. 2 tower body 3, a water-passing swivel 14 is equidistantly fixedly connected to the bottom of the water-passing swivel 14, a water pump 19 is installed on the top of the No. 2 tower body 3, an input end of the water pump 19 is fixedly connected to a water inlet pipe, an output end of the water pump 19 is connected to the water-passing swivel 14 through a water hose, the gas released through the gas outlet head 10 is guided by the spiral blades 9, fully contacts with the incoming water, increases the contact area, and improves the cooling efficiency of the cooling tower.
[0017] Among them, the interior of the No. 2 tower body 3 is rotatably connected with a driving rotating rod 27, and the driving rotating rod 27 is rotatably connected to the No. 1 tower body 1. The outer side of the driving rotating rod 27 is fixedly connected with a gear 17. The outer side of the water-passing swivel 14 is fixedly connected with an outer gear ring 16. The outer gear ring 16 is slidably connected to the No. 2 tower body 3, and the outer gear ring 16 is meshed with the gear 17. A servo motor 18 is installed inside the No. 2 tower body 3, and the output end of the servo motor 18 is fixedly connected to the driving rotating rod 27, and the rotation of the output end of the servo motor 18 is controlled. The output of the servo motor 18 The output end of the servo motor 18 drives the driving rod 27 to rotate reciprocatingly. When the driving rod 27 rotates, it drives the outer gear 17 and one of the pulleys 5 to rotate. When the gear 17 rotates, it drives the meshing outer gear ring 16 to rotate. The outer gear ring 16 drives the inner water-passing swivel 14 and the bottom water spray head 15 to rotate reciprocatingly at a fixed angle. The water spray head 15 is used to spray water evenly. The output end of the servo motor 18 is controlled to rotate reciprocatingly to prevent the water inlet hose from being entangled and to ensure uniform water spraying.
[0018] Among them, the bottom of the No. 1 tower body 1 is fixedly connected with a connecting bottom box 4, the driving rotating rod 27 is rotatably connected to the connecting bottom box 4, the interior of the connecting bottom box 4 is rotatably connected with a ventilation pipe 6, the ventilation pipe 6 is rotatably connected to the No. 1 tower body 1, the top of the ventilation pipe 6 is fixedly connected to the ventilation column 8, the driving rotating rod 27 and the outer side of the ventilation pipe 6 are fixedly connected with a pulley 5, and the two pulleys 5 are connected by a belt transmission. When the driving rotating rod 27 drives one of the pulleys 5 to rotate, one of the pulleys 5 drives the other pulley 5 to rotate through the belt, and the other pulley 5 drives the inner ventilation pipe 6 and the ventilation column 8 to rotate, and the air outlet is evenly treated through the air outlet head 10, and comes into contact with water, thereby improving the cooling effect.
[0019] Among them, a rotary joint 7 is installed at the bottom of the bottom box 4, one end of the ventilation pipe 6 is connected to the rotary joint 7, and an air intake fan 24 is installed at the bottom of the bottom box 4. The output end of the air intake fan 24 is connected to the rotary joint 7 through an air duct, and the input end of the air intake fan 24 is fixedly connected with an air intake pipe 25. The rotary joint 7 is used to ensure normal air supply processing during rotation, uniform air intake, and improved cooling efficiency.
[0020] Among them, an exhaust fan 20 is installed on the top of the No. 2 tower body 3, the output end of the exhaust fan 20 is fixedly connected to the exhaust pipe 21, the input end of the exhaust fan 20 is fixedly connected to the air collecting pipe 22, one end of the air collecting pipe 22 is fixedly connected to the No. 2 tower body 3, and the work of the cooling tower is completed by starting the exhaust fan 20 to assist in air outlet.
[0021] Among them, a drain pipe 26 is fixedly connected to one side of the No. 1 tower body 1, and a control panel 23 is installed on one side of the No. 1 tower body 1. The servo motor 18, water pump 19, exhaust fan 20 and intake fan 24 are all electrically connected to the control panel 23. The device is controlled and processed through the control panel 23, which improves the safety of the device.
[0022] Specifically, when in use, air is extracted through the air inlet pipe 25 at the input end of the air inlet fan 24, enters the ventilation pipe 6 through the rotary joint 7, enters the ventilation column 8 through the top of the ventilation pipe 6, and exhausts air through the various air outlet heads 10 on the outside of the ventilation column 8. Water is pumped into the water-passing swivel 14 by the water pump 19, and is sprayed out through the water spray head 15 at the bottom of the water-passing swivel 14. The servo motor 18 is started through the control panel 23 to control the rotation of the output end of the servo motor 18. The output end of the servo motor 18 rotates back and forth, and the output end of the servo motor 18 drives the driving rotating rod 27 to rotate back and forth. When the driving rotating rod 27 rotates, it drives the outer gear 17 and one of the pulleys 5 to rotate. When the gear 17 rotates, it drives the meshing outer gear ring 16 to rotate. The outer gear ring 16 drives the inner water-passing swivel 14 and the water spray head 15 at the bottom to rotate back and forth at a fixed angle , water is sprayed evenly through the water spray head 15, and the gas released through the air outlet head 10 is guided by the spiral blade 9. When the driving rod 27 drives one of the pulleys 5 to rotate, one of the pulleys 5 drives the other pulley 5 to rotate through the belt, and the other pulley 5 drives the inner ventilation pipe 6 and the ventilation column 8 to rotate. The air is evenly discharged through the air outlet head 10 and contacts with water to improve the cooling effect. The air enters the No. 2 tower body 3 through the No. 1 tower body 1 on the inner side of the connecting pipe 12, and is diverted again through the sieve plate 13. The incoming air fully contacts the water sprayed from the water spray head 15, ensuring the cooling efficiency of the cooling tower. The gas and water circulating through the sieve plate 13 and the diverter plate 11 are fully cooled and contacted, and are discharged through the drain pipe 26 on the side of the No. 1 tower body 1. The exhaust fan 20 is started to assist in air discharge to complete the work of the cooling tower.
[0023] In the description of the present invention, it should be understood that the terms "coaxial", "bottom", "one end", "top", "middle", "the other end", "upper", "one side", "top", "inside", "front", "center", "both ends" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present invention.
[0024] In addition, the terms "first", "second", "third" and "fourth" are used for descriptive purposes only and are not to be understood as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Thus, the features defined as "first", "second", "third" and "fourth" may explicitly or implicitly include at least one of such features.
[0025] In the present utility model, unless otherwise clearly stipulated and limited, the terms such as "installation", "setting", "connection", "fixation" and "screw-on" should be understood in a broad sense. For example, it can be a fixed connection, a detachable connection, or an integrated connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements. Unless otherwise clearly defined, ordinary technicians in this field can understand the specific meanings of the above terms in the utility model according to the specific circumstances.
[0026] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A multi-layer forced draft cooling tower, comprising a first tower body (1), characterized in that: The top of the first tower body (1) is fixedly connected to a support frame (2), the top of the support frame (2) is fixedly connected to the second tower body (3), the bottom of the second tower body (3) is fixedly connected to a connecting pipe (12), the connecting pipe (12) is fixedly connected to the first tower body (1), the interior of the first tower body (1) is rotatably connected to a ventilation column (8), the outer side of the ventilation column (8) is fixedly connected to a spiral blade (9), the outer side of the ventilation column (8) is symmetrically fixedly connected to an air outlet head (10), the connecting pipe (12) is fixedly connected to the first tower body (1), and the connecting pipe (12) is fixedly connected to the first tower body (1). A diverter plate (11) is fixedly connected inside the pipe (12), a sieve plate (13) is fixedly connected inside the second tower body (3), a water-passing swivel (14) is rotatably connected inside the second tower body (3), a water-passing swivel (14) is equidistantly fixedly connected to the bottom of the water-passing swivel (14), a water pump (19) is installed on the top of the second tower body (3), an input end of the water pump (19) is fixedly connected to a water inlet pipe, and an output end of the water pump (19) is connected to the water-passing swivel (14) via a water hose.
2. A multi-layer forced air cooling tower according to claim 1, characterized in that: The second tower body (3) is rotatably connected to a driving rotating rod (27), the driving rotating rod (27) is rotatably connected to the first tower body (1), the outer side of the driving rotating rod (27) is fixedly connected to a gear (17), the outer side of the water-passing rotating ring (14) is fixedly connected to an outer gear ring (16), the outer gear ring (16) is slidably connected to the second tower body (3), the outer gear ring (16) is meshingly connected to the gear (17), a servo motor (18) is installed inside the second tower body (3), and the output end of the servo motor (18) is fixedly connected to the driving rotating rod (27).
3. A multi-layer forced air cooling tower according to claim 2, characterized in that: The bottom of the first tower body (1) is fixedly connected to a connecting bottom box (4), the driving rotating rod (27) is rotatably connected to the connecting bottom box (4), the interior of the connecting bottom box (4) is rotatably connected to a ventilation pipe (6), the ventilation pipe (6) is rotatably connected to the first tower body (1), the top of the ventilation pipe (6) is fixedly connected to a ventilation column (8), the outer sides of the driving rotating rod (27) and the ventilation pipe (6) are both fixedly connected to pulleys (5), and the two pulleys (5) are connected via a belt transmission.
4. A multi-layer forced air cooling tower according to claim 3, characterized in that: A rotary joint (7) is installed at the bottom of the connecting bottom box (4), one end of the ventilation pipe (6) is connected to the rotary joint (7), an air intake fan (24) is installed at the bottom of the connecting bottom box (4), the output end of the air intake fan (24) is connected to the rotary joint (7) via an air duct, and the input end of the air intake fan (24) is fixedly connected to an air intake pipe (25).
5. A multi-layer forced air cooling tower according to claim 4, characterized in that: An exhaust fan (20) is installed on the top of the second tower body (3); the output end of the exhaust fan (20) is fixedly connected to an exhaust pipe (21); the input end of the exhaust fan (20) is fixedly connected to an air collecting pipe (22); one end of the air collecting pipe (22) is fixedly connected to the second tower body (3).
6. A multi-layer forced air cooling tower according to claim 5, characterized in that: A drainage pipe (26) is fixedly connected to one side of the first tower body (1), a control panel (23) is installed on one side of the first tower body (1), and the servo motor (18), the water pump (19), the exhaust fan (20) and the intake fan (24) are all electrically connected to the control panel (23).