Portable mining outburst prevention prediction instrument operating table

Through the design of the portable mining anti-surge prediction instrument operating table, the adjustable support frame and partitioned operating platform are used to solve the problems of unstable operation and safety risks of anti-surge prediction instruments in the mine in the mine, and improve the accuracy of detection and operational convenience reduce safety risks.

CN222105463UActive Publication Date: 2024-12-03CHINA COAL XINJI ENERGY CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420312428.9
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-02-20
Publication Date
2024-12-03
Estimated Expiration
2034-02-20

AI Technical Summary

Technical Problem

In mines, anti-rain prediction instruments often pour out due to coal accumulation, uneven floor plate and construction vibration during the prediction process, which increases the workload of anti-rain predictors and inaccurate detection values, and there is safety when operating on the working surface. Risk, the instrument cannot be properly placed to observe the surrounding environment.

Method used

A portable mining anti-probe prediction instrument operating table is designed, including an operating platform and a support frame. The support frame is composed of a pallet, a telescopic support foot and a barrier. The telescopic support foot can be adjusted to accommodate different heights. The operating platform is equipped with partitioned accommodation. Coal sample tank, WTC gas outburst parameter instrument and MD-2 coal cutting gas analyzer improve stability and limit protection through connecting bolts and splicing hole adapters.

Benefits of technology

It reduces the time for anti-emergency prevention personnel to adjust the instrument, reduces the safety risks during standing observation, improves detection accuracy and operation convenience, standardizes the operation of anti-emergency prediction instruments, and reduces the safety risks and workload of operators.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222105463U_ABST
    Figure CN222105463U_ABST
Patent Text Reader

Abstract

The utility model provides a portable mining outburst prevention prediction instrument operating platform, which relates to the technical field of mining tools, and comprises an operating platform and a support frame, the support frame comprises a support plate and telescopic support legs, the telescopic support legs are hinged below the support plate, and three groups of telescopic support legs are arranged at equal included angles; the operation platform is arranged above the supporting plate, a flange is arranged at the edge of the operation platform, and a first containing cavity, a second containing cavity and a third containing cavity are formed in the operation platform; the coal sample tank, the WTC gas outburst parameter instrument and the MD-2 coal drilling cutting gas analysis instrument are contained in the operating platform, the operating platform is installed on the supporting frame, the operating platform can be kept horizontal by adjusting the telescopic supporting legs, the height can be freely adjusted according to the height of an outburst prevention person and the height of a working face roadway, the instrument adjusting time of the outburst prevention person is shortened, and the working efficiency is improved. And the safety risk when the operator squats or backs on to the equipment and the working surface observes the numerical value is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of mining tools, in particular to a portable mining outburst prevention prediction instrument operating table. Background Art

[0002] In the outburst mine, when the "four-in-one" comprehensive outburst prevention measures are adopted, the drill cuttings gas analysis index method or the drill cuttings index method is generally used to predict the outburst danger of the working face. During the prediction process, the outburst prevention prediction instrument often topples over due to the accumulation of coal or gangue at the predicted location of the mining working face, uneven floor, and large vibration during construction. The level must be adjusted before each detection, which increases the workload of the outburst prevention personnel and the inaccuracy of the detection value.

[0003] The existing technology increases the workload of burst prevention personnel and the inaccuracy of detection values; at the same time, when burst prevention personnel predict the danger of bursting at the head of the mining face, there is no suitable place to place the prediction instrument. The prediction instrument needs to be hung on the side of the tunnel or placed on the tunnel floor for operation, which is not conducive to the burst prevention personnel to observe the surrounding environment and poses a safety risk. Therefore, the utility model proposes a portable mine burst prevention prediction instrument operating table to solve the problems existing in the existing technology. Utility Model Content

[0004] In response to the above problems, the utility model proposes a portable mine-used sudden outburst prediction instrument operating table, which reduces the time for sudden outburst prevention personnel to adjust the instrument and reduces the safety risks when operators squat or turn their backs to the equipment or working face to observe numerical values.

[0005] To achieve the purpose of the utility model, the utility model is implemented by the following technical solutions: a portable mine outburst prevention prediction instrument operating table, including an operating platform and a support frame, the support frame includes a support plate and a telescopic support leg, the telescopic support leg is hinged below the support plate, and the telescopic support leg is provided with three groups at equal angles;

[0006] The operating platform is arranged above the support plate, and a rib is provided at the edge of the operating platform. The interior of the operating platform is provided with a first accommodating chamber, a second accommodating chamber and a third accommodating chamber. The interiors of the first accommodating chamber, the second accommodating chamber and the third accommodating chamber are respectively used to accommodate a coal sample tank, a WTC gas outburst parameter meter and an MD-2 coal drill cuttings gas analyzer.

[0007] A further improvement is that a connecting bolt is installed at a middle position inside the operating platform, and the operating platform is fixed to the supporting plate by the connecting bolt.

[0008] A further improvement is that the telescopic support leg comprises a bracket and a telescopic leg, the telescopic leg is movably inserted into the interior of the bracket, and an adjusting bolt is provided below one side of the bracket, and the adjusting bolt is used to fix the telescopic leg.

[0009] A further improvement is that a first partition is provided at the middle end of the operating platform, the first accommodating cavity and the second accommodating cavity are respectively located on both sides of the first partition, and the thickness of the first partition is 8-12 mm.

[0010] A further improvement is that a second partition is provided at the rear end of one side of the inner part of the operating platform, the third accommodating cavity is separated by the second partition, and the thickness of the second partition is 8-12 mm.

[0011] A further improvement is that the thickness of the retaining edge is 8-12 mm, and the top of the retaining edge is used to install the extended edge, the four corners of the top of the retaining edge are provided with first splicing holes, and the four corners of the bottom of the extended edge are provided with splicing rods compatible with the first splicing holes.

[0012] A further improvement is that second splicing holes are provided at the four corners of the top of the extended edge, and the second splicing holes are adapted to the splicing rods.

[0013] The beneficial effects of the utility model are:

[0014] 1. The utility model accommodates the coal sample tank, WTC gas outburst parameter instrument and MD-2 coal drill cuttings gas analyzer through the operating platform. The operating platform is installed on the support frame. The operating platform can be kept level by adjusting the telescopic legs. The height can be freely adjusted according to the height of the outburst prevention personnel and the height of the working face tunnel, which reduces the time for the outburst prevention personnel to adjust the instrument and reduces the safety risks when the operators squat or turn their backs to the equipment and the working face to observe the numerical values.

[0015] 2. The utility model accommodates the coal sample tank, WTC gas outburst parameter instrument and MD-2 coal drill cuttings gas analyzer respectively through the first accommodating chamber, the second accommodating chamber and the third accommodating chamber, thereby placing the instruments in partitions, which is convenient for the outburst prevention personnel to operate and observe the displayed values ​​and the surrounding environment.

[0016] 3. The utility model can add an extension edge to the retaining edge through the adaptation of the splicing rod and the first splicing hole and the second splicing hole, so as to increase the limit protection height of the instrument. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] Figure 1 It is the front view of the utility model;

[0018] Figure 2 It is a top view schematic diagram of the operating platform of the utility model;

[0019] Figure 3 It is a schematic diagram of the extended side of the utility model.

[0020] Among them: 1. operating platform; 2. support plate; 3. first accommodating chamber; 4. second accommodating chamber; 5. third accommodating chamber; 6. coal sample tank; 7. WTC gas outburst parameter instrument; 8. MD-2 coal drilling cuttings gas analyzer; 9. connecting bolts; 10. bracket; 11. telescopic legs; 12. adjusting bolts; 13. first partition; 14. second partition; 15. extended edge; 16. first splicing hole; 17. splicing rod; 18. second splicing hole. DETAILED DESCRIPTION

[0021] In order to deepen the understanding of the present invention, the present invention will be further described in detail below in conjunction with an embodiment. The embodiment is only used to explain the present invention and does not constitute a limitation on the protection scope of the present invention.

[0022] Embodiment 1

[0023] according to Figure 1 , 2 As shown in , 3, this embodiment proposes a portable mine outburst prediction instrument operating table, including an operating platform 1 and a support frame, the support frame includes a support plate 2 and a telescopic support leg, the telescopic support leg is hinged below the support plate 2, and three groups of telescopic support legs are provided at equal angles;

[0024] The operating platform 1 is arranged above the support plate 2, and a rib is arranged at the edge of the operating platform 1, and a first accommodating chamber 3, a second accommodating chamber 4 and a third accommodating chamber 5 are arranged inside the operating platform 1, and the interiors of the first accommodating chamber 3, the second accommodating chamber 4 and the third accommodating chamber 5 are respectively used to accommodate a coal sample tank 6, a WTC gas outburst parameter instrument 7 and an MD-2 coal drill cuttings gas analyzer 8. When in use, the coal sample tank 6, the WTC gas outburst parameter instrument 7 and the MD-2 coal drill cuttings gas analyzer 8 are accommodated by the operating platform 1, and the operating platform 1 is installed on a supporting frame. The operating platform 1 can be kept horizontal by adjusting the telescopic legs, and the height can be freely adjusted according to the height of the outburst prevention personnel and the height of the working face tunnel, thereby reducing the time for the outburst prevention personnel to adjust the instruments.

[0025] A connecting bolt 9 is installed at the middle position inside the operating platform 1, and the operating platform 1 is fixed to the support plate 2 through the connecting bolt 9. The fixing of the connecting bolt 9 facilitates the installation or removal of the operating platform 1 on the support plate 2.

[0026] The telescopic support leg comprises a bracket 10 and a telescopic leg 11, wherein the telescopic leg 11 is movably inserted into the interior of the bracket 10, and an adjusting bolt 12 is provided below one side of the bracket 10, and the adjusting bolt 12 is used to fix the telescopic leg 11. When in use, the telescopic leg 11 is moved in the bracket 10, and the height is changed by fixing with the adjusting bolt 12, so that the operating platform 1 can be kept horizontal, and the height can be freely adjusted according to the height of the burst prevention worker and the height of the working face tunnel, thereby reducing the time for the burst prevention worker to adjust the instrument.

[0027] A first partition 13 is provided at the middle end of the operating platform 1, and the first accommodating chamber 3 and the second accommodating chamber 4 are respectively located on both sides of the first partition 13, and the thickness of the first partition 13 is 10 mm. A second partition 14 is provided at the rear end of one side of the operating platform 1, and the third accommodating chamber 5 is separated by the second partition 14, and the thickness of the second partition 14 is 10 mm. The first accommodating chamber 3, the second accommodating chamber 4 and the third accommodating chamber 5 respectively accommodate the coal sample tank 6, the WTC gas outburst parameter instrument 7 and the MD-2 coal drilling cuttings gas analyzer 8, thereby placing the instruments in partitions, which is convenient for the operation of the outburst prevention personnel and the observation of the displayed values ​​and the surrounding environment.

[0028] Embodiment 2

[0029] according to Figure 1 , 2 As shown in , 3, this embodiment proposes a portable mine outburst prediction instrument operating table, including an operating platform 1 and a support frame, the support frame includes a support plate 2 and a telescopic support leg, the telescopic support leg is hinged below the support plate 2, and three groups of telescopic support legs are provided at equal angles;

[0030] The operating platform 1 is arranged above the support plate 2, and a rib is arranged at the edge of the operating platform 1, and a first accommodating chamber 3, a second accommodating chamber 4 and a third accommodating chamber 5 are arranged inside the operating platform 1, and the interiors of the first accommodating chamber 3, the second accommodating chamber 4 and the third accommodating chamber 5 are respectively used to accommodate a coal sample tank 6, a WTC gas outburst parameter instrument 7 and an MD-2 coal drill cuttings gas analyzer 8. When in use, the coal sample tank 6, the WTC gas outburst parameter instrument 7 and the MD-2 coal drill cuttings gas analyzer 8 are accommodated by the operating platform 1, and the operating platform 1 is installed on a supporting frame. The operating platform 1 can be kept horizontal by adjusting the telescopic legs, and the height can be freely adjusted according to the height of the outburst prevention personnel and the height of the working face tunnel, thereby reducing the time for the outburst prevention personnel to adjust the instruments.

[0031] A connecting bolt 9 is installed at the middle position inside the operating platform 1, and the operating platform 1 is fixed to the support plate 2 through the connecting bolt 9. The fixing of the connecting bolt 9 facilitates the installation or removal of the operating platform 1 on the support plate 2.

[0032] The telescopic support leg comprises a bracket 10 and a telescopic leg 11, wherein the telescopic leg 11 is movably inserted into the interior of the bracket 10, and an adjusting bolt 12 is provided below one side of the bracket 10, and the adjusting bolt 12 is used to fix the telescopic leg 11. When in use, the telescopic leg 11 is moved in the bracket 10, and the height is changed by fixing with the adjusting bolt 12, so that the operating platform 1 can be kept horizontal, and the height can be freely adjusted according to the height of the burst prevention worker and the height of the working face tunnel, thereby reducing the time for the burst prevention worker to adjust the instrument.

[0033] The thickness of the retaining edge is 10 mm, and the upper part of the retaining edge is used to install the extended edge 15. The four corners of the top of the retaining edge are provided with first splicing holes 16, and the four corners of the bottom of the extended edge 15 are provided with splicing rods 17 adapted to the first splicing holes 16. The four corners of the top of the extended edge 15 are provided with second splicing holes 18, and the second splicing holes 18 are adapted to the splicing rods 17. Through the adaptation of the splicing rods 17 to the first splicing holes 16 and the second splicing holes 18, the extended edge 15 can be installed on the retaining edge, so as to increase the limit protection height of the instrument.

[0034] When in use, fix the operating platform 1, adjust the platform to be stable and then start the parameter test. (1) Operation of WTC gas outburst parameter instrument 7: Turn on the power → preheat for 5 minutes → adjust the instrument to zero; input the critical index data of K1 value and Smax; select the drilling position and drill → drill at a constant speed → measure the K1 value once every 2m, and measure the drilling powder volume once for every meter of coal powder connected to the hole mouth → record the data in the manual; input the sampling time of 5 minutes → press the monitoring key → then input the drilling length → press the monitoring key → display the K1 value; after sampling and measuring → press the forecast key → input the Smax value → press the monitoring key → display the outburst hazard level; record the measured data in the manual → gas tester, safety inspector, and construction manager sign → fill in the forecast plate → if the forecast exceeds the standard, stop the head immediately and take anti-outburst measures; if the forecast does not exceed the standard, hang the allowed advance plate. (2) Operations when using MD-2 coal drilling cuttings gas analyzer 8 to measure △M2 and Smax: open the two-way stopcock → place the coal sample into the desorption chamber → tighten the upper cover of the desorption chamber → open the three-way stopcock → connect the desorption chamber with the water column meter and the atmosphere; expose the coal sample for 3 minutes → connect it with the water injection meter → desorption measurement → restart the timing; read the water column gauge pressure difference △h2 → measure the drilling dust volume of all coal dust per meter of the orifice - record the measured data in the manual → gas tester, safety inspector, and construction manager sign → fill in the verification plate → immediately stop the head and take anti-burst measures if the standard is exceeded; if it is not exceeded, hang the allowed advance plate.

[0035] The portable mine outburst prediction instrument operating table accommodates the coal sample tank 6, WTC gas outburst parameter instrument 7 and MD-2 coal drill cuttings gas analyzer 8 through the operating platform 1. The operating platform 1 is installed on the support frame. The operating platform 1 can be kept horizontal by adjusting the telescopic legs. The height can be freely adjusted according to the height of the outburst prevention personnel and the height of the working face tunnel, reducing the time for the outburst prevention personnel to adjust the instrument. Therefore, when standing and observing, the accuracy of the working face outburst hazard prediction and measurement indicators is improved and the time for the outburst prevention personnel to adjust the instrument and observe is reduced. The safety risk of the operator squatting or facing away from the equipment and the working face to observe the value is reduced, and the operation standard of the outburst prediction instrument is standardized, which has great safety and time benefits. In addition, this product accommodates the coal sample tank 6, WTC gas outburst parameter instrument 7 and MD-2 coal drill cuttings gas analyzer 8 through the first accommodating chamber 3, the second accommodating chamber 4 and the third accommodating chamber 5 respectively, thereby placing the instruments in partitions, which is convenient for the outburst prevention personnel to operate and observe the displayed values ​​and the surrounding environment. At the same time, through the adaptation of the splicing rod 17 and the first splicing hole 16 and the second splicing hole 18, the extended edge 15 can be installed on the retaining edge, so as to increase the limit protection height of the instrument.

[0036] The above shows and describes the basic principles, main features and advantages of the utility model. Those skilled in the art should understand that the utility model is not limited by the above embodiments. The above embodiments and descriptions are only for explaining the principles of the utility model. Without departing from the spirit and scope of the utility model, the utility model may have various changes and improvements, which fall within the scope of the utility model to be protected. The scope of protection claimed by the utility model is defined by the attached claims and their equivalents.

Claims

1. A portable mine outburst prediction instrument operating table, comprising an operating platform (1) and a support frame, characterized in that: The support frame comprises a support plate (2) and telescopic legs, wherein the telescopic legs are hingedly connected below the support plate (2), and three groups of telescopic legs are provided at equal angles; The operating platform (1) is arranged above the support plate (2), a retaining edge is arranged at the edge of the operating platform (1), and a first accommodating chamber (3), a second accommodating chamber (4) and a third accommodating chamber (5) are arranged inside the operating platform (1), and the interiors of the first accommodating chamber (3), the second accommodating chamber (4) and the third accommodating chamber (5) are respectively used to accommodate a coal sample tank (6), a WTC gas outburst parameter instrument (7) and an MD-2 coal drilling cuttings gas analyzer (8).

2. A portable mine outburst prevention prediction instrument operating table according to claim 1, characterized in that: A connecting bolt (9) is installed at a middle position inside the operating platform (1), and the operating platform (1) is fixed to the support plate (2) via the connecting bolt (9).

3. The portable mine outburst prevention prediction instrument operating table according to claim 1 is characterized in that: The telescopic support leg comprises a bracket (10) and a telescopic leg (11); the telescopic leg (11) is movably inserted into the interior of the bracket (10); an adjusting bolt (12) is provided below one side of the bracket (10); and the adjusting bolt (12) is used to fix the telescopic leg (11).

4. The portable mine outburst prevention prediction instrument operating table according to claim 1 is characterized by: A first partition (13) is provided at the middle end of the operating platform (1), the first accommodating cavity (3) and the second accommodating cavity (4) are respectively located on both sides of the first partition (13), and the thickness of the first partition (13) is 8-12 mm.

5. The portable mine outburst prevention prediction instrument operating table according to claim 4 is characterized by: A second partition (14) is provided at the rear end of one side of the interior of the operating platform (1), and the third accommodating chamber (5) is separated by the second partition (14), and the thickness of the second partition (14) is 8-12 mm.

6. A portable mine outburst prevention prediction instrument operating table according to any one of claims 1 to 5, characterized in that: The thickness of the retaining edge is 8-12 mm, and the upper part of the retaining edge is used to install the extended edge (15). The four corners of the top of the retaining edge are provided with first splicing holes (16), and the four corners of the bottom of the extended edge (15) are provided with splicing rods (17) adapted to the first splicing holes (16).

7. A portable mine outburst prevention prediction instrument operating table according to claim 6, characterized in that: Second splicing holes (18) are provided at the four corners of the top of the extended edge (15), and the second splicing holes (18) are matched with the splicing rods (17).