Novel self-elevating flat-top tower crane with jacking sleeve frame

By designing a new type of jacking flat-head tower crane, the problems of transportation and assembly of the hoisting rack are solved, low-cost transportation and efficient assembly are achieved, and the safety performance and installation efficiency of the tower crane are improved.

CN222118725UActive Publication Date: 2024-12-06SHENYANG SANYO BUILDING MASCH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202322845095.4
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-10-23
Publication Date
2024-12-06
Estimated Expiration
2033-10-23

AI Technical Summary

Technical Problem

The existing hoisting frames have super high and ultra-wide phenomena during transportation, which leads to difficult transportation and high cost, and are difficult to assemble and may lead to deformation of the steel structure, affecting the safety performance of the tower crane.

Method used

A new type of jacking flat-head tower machine with a jacking frame is designed, using a newly designed frame main structure, frame front plate and frame rear beam, a guide roller assembly is set, and the connection of the rotating lower support is adjusted. The ear plate position uses a quick-loading platform, which simplifies the assembly process.

Benefits of technology

It solves the problems of high transportation costs and difficult assembly of the hoisting frame, avoids deformation of the steel structure, improves the safety performance and installation efficiency of the tower crane, and reduces transportation and labor costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222118725U_ABST
    Figure CN222118725U_ABST
Patent Text Reader

Abstract

The jacking sleeve frame of the self-elevating flat-end tower crane is sleeved outside a standard knot, one end of the jacking sleeve frame is connected with a jacking cross beam through a jacking oil cylinder, the other end of the jacking sleeve frame is connected with a rotary lower support through a pin shaft, and the jacking sleeve frame, the rotary lower support and parts above the rotary lower support ascend along the central line of the standard knot under the action of the oil cylinder. In the transportation process of the novel jacking sleeve frame, the sleeve frame front piece, the sleeve frame rear beam, the working platform, the lower working platform, the climbing frame and the hanging boots are placed in the sleeve frame main body structure to serve as a unit for transportation. The jacking sleeve frame can be put into use after the sleeve frame front piece, the sleeve frame rear beam, the upper working platform, the lower working platform and the hanging boots are installed on the sleeve frame main body structure. The jacking sleeve frame has the beneficial effects that the transportation cost of the jacking sleeve frame, particularly the transportation cost of an overseas exit of the jacking sleeve frame, is reduced, the installation efficiency of the jacking sleeve frame is improved, the labor cost is reduced, and the safety performance of the tower crane in the jacking process is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of self-elevating flat-top tower cranes, in particular to a self-elevating flat-top tower crane with a novel jacking frame. Background Art

[0002] With the innovation and development of science and technology, the construction period of high-rise and super-high-rise large buildings is getting shorter and shorter, and the working environment is becoming more and more dense and narrow. The role of self-elevating flat-top tower cranes equipped with jacking frames is becoming more and more significant, and the market demand is also increasing. There are two types of jacking frames on the market at present, one is an integral jacking frame that cannot be disassembled, and the other is a detachable sheet-mounted jacking frame. The advantage of the integral jacking frame that cannot be disassembled is that it is quick and convenient to assemble. The disadvantage is that it will be super high and super wide during transportation on urban roads, which is very difficult to transport to the construction site. In order to transport the jacking frame, the urban roads have to be widened and renovated. At the same time, because its outer dimensions exceed the size of the container, the export freight cost will increase a lot, reducing the competitiveness of the tower crane in the overseas market. The advantage of the detachable sheet-mounted jacking frame is that it solves the problem of difficulty in transporting the jacking frame and the inability to load it into the container. The disadvantage is that it is difficult to assemble on site, and the steel structure will deform during transportation, affecting the safety performance of the tower crane. Therefore, it is particularly important to design a new type of self-elevating flat-top tower crane with a jacking frame, reduce the transportation cost of the jacking frame, and improve the assembly efficiency and safety performance of the jacking frame. Utility Model Content

[0003] The utility model aims to provide a novel self-elevating flat-top tower crane with a jacking frame, which has low transportation cost, high assembly efficiency and good safety performance, so as to solve the problems raised in the above-mentioned background technology.

[0004] In order to solve the above technical problems, the utility model provides the following technical solutions: a novel self-elevating flat-top tower crane with a jacking frame, comprising a jacking frame, a cylinder, a jacking beam, a standard section, and a slewing lower support, wherein one end of the jacking frame of the flat-top tower crane is connected to the jacking beam through the cylinder, the left and right positioning pads on the jacking beam are supported on the climbing block of the standard section, and the other end is connected to the slewing lower support through a pin shaft, and the arrangement of the connecting ear plates is that the ear plates on the front side of the jacking frame are vertically symmetrically arranged with the center line of the frame, and the ear plates on the rear side of the jacking frame are symmetrically arranged with the center line of the frame at an angle of 45°;

[0005] The jacking frame comprises a frame main structure, a frame front plate, a frame rear beam, an upper working platform, a lower working platform, a climbing frame and hanging boots.

[0006] Preferably, the main structure of the frame is a steel structure component composed of four main chords and diagonal webs, transverse webs and cross beams. A window for introducing a standard section is arranged in the front of the component, and a cylinder ear plate connected to the cylinder and a shoe ear plate connected to the shoe are arranged at the rear. A guide roller assembly is arranged in two layers on the two main chords at the rear.

[0007] Preferably, the upper working platform of the new type of flat-top tower crane frame is a C-shaped structure, with three platforms arranged behind and on both sides of the frame main structure. The three platforms are connected to the frame main structure through M bolt pairs, and flaps are set on the platforms on both sides to facilitate people to go up and down.

[0008] Preferably, the front plate of the frame and the rear beam of the frame are connected to the frame body through an M bolt pair, and four guide roller assemblies are arranged in two layers on the front plate of the frame.

[0009] Preferably, climbing frames with protective rings are arranged on both sides of the novel sleeve of the flat-top tower crane, and the climbing frames are connected to the upper working platform and the lower working platform through ladder connectors and M bolt pairs.

[0010] Preferably, the hanging shoes are connected to the middle cross beam at the rear of the main structure of the sleeve frame through a pin, and a control rod of the connecting rod mechanism is arranged between the hanging shoes.

[0011] Preferably, when assembling the jacking frame, firstly, the front plate and the rear beam of the frame are installed on the main structure of the frame through M bolt pairs, then the upper working platform and the lower working platform are installed, and finally the climbing frame and the hanging boots are installed.

[0012] Compared with the prior art, the utility model provides a new self-elevating flat-top tower crane with a jacking frame, which has the following beneficial effects:

[0013] 1. The flat-top tower crane of the new type of jacking frame abandons the conventional structural design of the inseparable integral jacking frame and the detachable plate-mounted jacking frame, and newly designs the frame main structure, frame front plate and frame rear beam, and creatively sets a guide roller assembly on the frame front plate. Compared with the inseparable integral frame, the new jacking frame will not appear over-width and over-height during urban road transportation, and the jacking frame can be smoothly loaded into the container, reducing the transportation cost of the jacking frame; compared with the detachable plate-mounted jacking frame, the new jacking frame is simple to assemble and has high installation efficiency after the jacking frame is transported to the construction site, reducing labor costs, and avoiding deformation of the steel structure during transportation, improving the safety performance of the tower crane.

[0014] 2. For the flat-top tower crane with the new jacking frame, the position of the connecting ear plate between the jacking frame and the slewing lower support is adjusted to improve the safety performance during the jacking process of the tower crane, so that the jacking frame can better maintain the stability of the tower crane. The connecting ear plate between the jacking frame and the slewing lower support is no longer arranged symmetrically at an angle of 45° to the center line of the frame, but is adjusted to a vertical symmetrical arrangement of the front ear plate of the jacking frame and the center line of the frame, and a symmetrical arrangement of the rear ear plate of the jacking frame and the center line of the frame at an angle of 45°.

[0015] 3. The flat-top tower crane of the new jacking frame has an upper working platform and a lower working platform that adopt quick-install platforms. Only the M12 bolt pair needs to be installed to complete the platform installation, thereby improving the installation efficiency of the jacking frame. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] Figure 1 This is a schematic diagram of the old type of jacking frame;

[0017] Figure 2 It is an overall schematic diagram of the utility model;

[0018] Figure 3 This is a schematic diagram of the connecting ear plate of the new jacking frame and the slewing lower support;

[0019] Figure 4 It is a schematic diagram of a new type of jacking frame;

[0020] Figure 5 It is a schematic diagram of the main frame of the new type of jacking frame;

[0021] Figure 6 It is a schematic diagram of the front piece of the new type of jacking frame;

[0022] Figure 7 It is a schematic diagram of the connection between the upper working platform and the main structure of the jacking frame in the new jacking frame;

[0023] Figure 8 It is a schematic diagram of the hanging shoe in the new type of jacking frame;

[0024] Fig. 9 It is the jacking process of the flat-top tower crane with a new jacking frame;

[0025] Fig.10 It is a schematic diagram of the standard sections that need to be introduced for the flat-top tower crane hoisting of the new type of jacking frame.

[0026] Among them: 1. Lifting frame; 2. Cylinder; 3. Lifting beam; 4. Standard section; 5. Rotating lower support; 6. Frame main structure; 7. Frame front piece; 8. Frame rear beam; 9. Upper working platform; 10. Lower working platform; 11. Climbing frame; 12. Hanging boot; 13. Cylinder ear plate; 14. Hanging boot ear plate; 15. Roller assembly; 16. Joystick; 17. Pin shaft; 18. Guide rail; 19. Section hook; 20. Movable pulley block; 21. Fixed pulley block; 22. Trolley. DETAILED DESCRIPTION

[0027] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0028] See also Figure 1-10 The utility model provides a technical solution: a self-elevating flat-top tower crane with a novel jacking frame, comprising a jacking frame 1, a cylinder 2, a jacking beam 3, a standard section 4, and a slewing lower support 5. One end of the jacking frame 1 is connected to the jacking beam 3 through the cylinder 2, the left and right positioning pads on the jacking beam 3 are supported on the climbing block of the standard section 4, and the other end is connected to the slewing lower support 5 through a pin shaft, and the arrangement of the connecting ear plates is that the ear plates on the front side of the jacking frame 1 are vertically symmetrically arranged with the center line of the frame, and the ear plates on the rear side of the jacking frame are symmetrically arranged at an angle of 45° with the center line of the frame;

[0029] The jacking frame 1 comprises a frame main structure 6, a frame front plate 7, a frame rear beam 8, an upper working platform 9, a lower working platform 10, a climbing frame 11 and a hanging shoe 12.

[0030] When in use, the jacking frame of the flat-top tower crane should first be transported to the construction site, where the jacking frame will be assembled. After the assembly is completed, the initial installation of the flat-top tower crane can be carried out. The jacking of the flat-top tower crane is the work performed after the initial installation of the tower crane, and the final use height of the tower crane is reached through the jacking operation of the jacking frame. When the jacking frame 1 is transported on urban roads, the frame front piece 7, the frame rear beam 8 and the hanging boot 12 are installed on the frame main structure 6, and the upper working platform 9, the lower working platform 10 and the climbing frame 11 are placed in the frame main structure 6. After being transported to the construction site, the upper working platform 9, the lower working platform 10 and the climbing frame 11 are assembled on the assembled components to complete the assembly of the jacking frame 1; when the jacking frame 1 is transported in a container, the frame front piece 7, the frame rear beam 8, the upper working platform 9, the lower working platform 10, and the climbing frame 11 are placed in the frame main structure 6. After being transported to the construction site, the frame front piece 7, the frame rear beam 8, the upper working platform 9, the lower working platform 10, the climbing frame 11 and the hanging boot 12 are installed on the frame main structure 6 to complete the assembly of the jacking frame 1.

[0031] After the new jacking frame of the flat-top tower crane is assembled, the jacking and sectioning preparation is carried out. The jacking and sectioning preparation refers to the installation of the components required for jacking, mainly including:

[0032] 1. Installation of oil cylinder 2 and lifting beam 3;

[0033] 2. Putting the jacking frame 1 into place means connecting the jacking frame 1 to the slewing lower support 5. This work is best done when the tower is erected. The jacking frame 1 can be lifted by a cylinder or a sling, and the ear plates on the main chord of the jacking frame 1 are inserted into the four corners of the slewing lower support 5 and connected with a pin 17.

[0034] 3. Installation of the guide rail 18: Fix the guide rail 18 to the slewing lower support 5 with a pin.

[0035] 4. Installation of the additional section hook 19: To hoist the standard section 4, the luffing trolley adopts a double-rate additional section. The additional section hook 19 is installed on the movable pulley block 20 through a pin shaft, and the fixed pulley block 21 is raised and fixed on the luffing trolley;

[0036] 5. The installation of the introduction trolley 22 should be installed on the guide rail 18, and the lower part of the introduction trolley 22 should be installed on the standard section 4 to be introduced with a bolt pair.

[0037] After the preparation for the top-down tower crane to be lifted and added to sections is completed, the lifting and adding section operation should be carried out. The wind speed during the lifting and adding section should not be greater than 13m / s. The lifting and adding section is a series of repeated operations, and the steps are as follows:

[0038] 1. Tower crane balancing: Before balancing, the connection between the slewing lower support 5 and the jacking frame 1 must be removed. During balancing, it is strictly forbidden to slew the boom and move the luffing trolley;

[0039] 2. Start the oil cylinder 2, and support the left and right positioning pads on the lifting beam 3 on the climbing block on the standard section 4 to lift up the part of the flat-top tower crane to be lifted;

[0040] 3. The hanging boots 12 on the lifting frame 1 are supported on the climbing blocks on the standard section 4. The safety pins on the left and right positioning pads in the lifting beam 3 are pulled out to separate the lifting beam 3 from the climbing blocks on the standard section 4. Then the oil cylinder 4 is retracted to drive the lifting beam 3 to rise.

[0041] 4. Support the left and right positioning blocks on the lifting beam 3 on the next climbing block on the standard section 4;

[0042] 5. Step 2 to step 4 completes the first step of jacking. Repeat the above jacking operation three times to obtain the space required for introducing the standard section 4 into the jacking frame 1;

[0043] 6. The standard section is introduced. The hanging shoe 12 on the lifting frame 1 is supported on the climbing block of the last standard section. The piston rod in the oil cylinder 2 is almost fully extended. However, the entire stroke will not cause the upper guide roller assembly 15 of the lifting frame 1 to exceed the fixed part of the standard section 4. The standard section to be introduced is pulled into the lifting frame 1.

[0044] 7. Fix the newly introduced standard section with the standard section 4 using the pin, remove the introduction trolley 22 and slide out the lifting frame 1;

[0045] 8. Use the introduction trolley 22 to hang the second standard section on the guide rail 18. Before the operation, the part of the flat-top tower crane to be jacked up should be connected with the lower standard section 4, and the jacking and sectioning process is completed.

[0046] 9. Repeat the above steps, repeatedly lifting and adding sections until the final installation height of the flat-top tower crane is reached.

[0047] Specifically, the main structure 6 of the frame is a steel structure member composed of four main chords and diagonal webs, transverse webs and cross beams. A window for introducing a standard section is arranged in the front of the member, and a cylinder ear plate 13 connected to the cylinder and a shoe ear plate 14 connected to the shoe are arranged in the rear. Four guide roller assemblies 15 are arranged in two layers on the two main chords at the rear.

[0048] Specifically, the upper working platform 9 of the new frame of the flat-top tower crane is a C-shaped structure, and three platforms are arranged behind and on both sides of the frame main structure 6. The three platforms are connected to the frame main structure 6 through M12 bolt pairs, and flaps are set on the platforms on both sides to facilitate people to go up and down.

[0049] Specifically, the frame front plate 7 and the frame rear beam 8 are connected to the frame body through a pair of M22 bolts, and four guide roller assemblies 15 are arranged in two layers on the frame front plate 7.

[0050] Specifically, climbing frames 11 with protective rings are arranged on both sides of the novel sleeve of the flat-top tower crane, and the climbing frames 11 are connected to the upper working platform 9 and the lower working platform 10 through ladder connectors and M16 bolt pairs.

[0051] Specifically, the hanging shoes 12 are connected to the middle crossbeam at the rear of the main structure of the sleeve frame through a pin shaft, and an operating rod 16 of a connecting rod mechanism is arranged between the hanging shoes 12.

[0052] Specifically, when assembling the jacking frame 1, firstly, the frame front plate 7 and the frame rear beam 8 are installed on the frame main structure 6 through the M22 bolt pair, and then the upper working platform 9 and the lower working platform 10 are installed, and finally the climbing frame 11 and the hanging boot 12 are installed.

[0053] Although the embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit thereof, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. A novel self-elevating flat-top tower crane with a jacking frame, comprising a jacking frame (1), a cylinder (2), a jacking beam (3), a standard section (4), and a slewing lower support (5), characterized in that: One end of the lifting frame (1) is connected to the lifting beam (3) through the oil cylinder (2), the left and right positioning pads on the lifting beam (3) are supported on the climbing block of the standard section (4), and the other end is connected to the slewing lower support (5) through a pin shaft, and the arrangement of the connecting ear plates is that the ear plates on the front side of the lifting frame (1) are arranged vertically and symmetrically with the center line of the frame, and the ear plates on the rear side of the lifting frame are arranged symmetrically with the center line of the frame at an angle of 45°; The jacking frame (1) comprises a frame main structure (6), a frame front plate (7), a frame rear beam (8), an upper working platform (9), a lower working platform (10), a climbing frame (11) and a hanging boot (12).

2. The novel self-elevating flat-top tower crane with a jacking frame according to claim 1 is characterized in that: The main structure (6) of the frame is a steel structure member composed of four main chords, diagonal webs, transverse webs and cross beams. A window for introducing a standard section is arranged in the front of the member, and a cylinder ear plate (13) connected to the oil cylinder and a shoe ear plate (14) connected to the shoe are arranged in the rear. Four guide roller assemblies (15) are arranged in two layers on the two main chords at the rear.

3. The novel self-elevating flat-top tower crane with a jacking frame according to claim 1 is characterized in that: The frame front plate (7) and the frame rear beam (8) are connected to the frame body through a pair of M22 bolts. Four guide roller assemblies (15) are arranged in two layers on the frame front plate (7).

4. The novel self-elevating flat-top tower crane with a jacking frame according to claim 1 is characterized in that: The upper working platform is connected to the main structure (6) of the frame via an M12 bolt pair, and flaps are provided on the platforms on both sides for the convenience of personnel to go up and down; the lower working platform (10) is connected to the main structure (6) of the frame and the front plate (7) of the frame via an M12 bolt pair, and a pump station is provided on the rear platform of the lower working platform (10).

5. The novel self-elevating flat-top tower crane with a jacking frame according to claim 1 is characterized in that: The climbing frame (11) is connected to the upper working platform (9) and the lower working platform (10) through a ladder connector and an M16 bolt pair; the hanging shoes (12) are connected to the middle crossbeam behind the main structure of the frame through a pin shaft, and a control lever (16) of a connecting rod mechanism is arranged between the hanging shoes (12).