FC plate mounting structure for constructional engineering

By using components such as positioning columns, sliding columns and draw ropes in the FC plate installation structure, the rapid positioning and disassembly between the FC plate and the bracket is solved, and the problems of complex installation and disassembly difficulty in FC plates in the prior art are improved. Installation efficiency and work efficiency extend the service life of the board.

CN222120709UInactive Publication Date: 2024-12-06山东益程建设工程有限公司
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202422697494.5
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-11-06
Publication Date
2024-12-06
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

The existing FC panel installation structure is complicated during disassembly and replacement, resulting in extended construction cycle, easy to damage nearby structures or finishes, and hinder maintenance work, affecting the long-term performance of the panel.

Method used

An installation structure including a bracket and an FC plate main body is designed. Through the equidistantly installed connecting components, the FC plate main body and bracket are realized by using components such as positioning columns, sliding columns, rubber blocks, driving tooth plates, rotating gears and draw ropes. Quick positioning and disassembly between simplifies installation and replacement.

Benefits of technology

It improves installation efficiency, reduces time and labor costs, simplifies the disassembly and replacement process of FC boards, reduces the construction cycle and maintenance difficulty, and extends the service life of the boards.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222120709U_ABST
    Figure CN222120709U_ABST
Patent Text Reader

Abstract

The utility model discloses an FC plate mounting structure for constructional engineering, and relates to the technical field of construction engineering. Comprising a support and an FC board body installed on the surface of the support, and connecting assemblies are installed on the surface of the support at equal intervals. According to the utility model, through the arrangement of the connecting assembly, after the FC board main body is placed on the support, the pressure is applied to the FC board main body, so that the positioning columns can be inserted into the clamping slots, the rubber blocks abut against the tops of the clamping slots, the side plates can be expanded, and the convex blocks abut against the inner walls of the clamping slots, so that rapid positioning between the FC board main body and the support is realized; compared with a traditional screw fixing and concrete pouring mode, the mounting efficiency is higher, when the FC plate body is damaged and needs to be replaced, the sliding blocks and the clamping plates can move and be separated from the clamping teeth by pulling the pull ropes, at the moment, the sliding columns can freely slide, the FC plate body can be rapidly disassembled and replaced, the disassembling and replacing time is shortened, the labor intensity is reduced, and the practicability is high. And the working efficiency is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of construction engineering, in particular to an FC board installation structure for construction engineering. Background Art

[0002] FC board, or fiber cement board, is a building material made of cement as the main raw material, with a certain proportion of fiber materials (usually wood fiber or asbestos fiber) added, and made through mixing, pulping, molding, curing and other processes. This board has excellent fireproof, moisture-proof, durable, sound-insulating and other properties.

[0003] In the prior art, when installing FC boards, the FC boards are mainly fixed directly on the brackets by self-tapping screws or by adhesives. Therefore, when the FC boards are damaged and need to be replaced, it is difficult to quickly disassemble the FC boards. The disassembly process is complicated and the time required is greatly increased, especially when multiple boards need to be replaced. The overall construction period is lengthened, and other nearby structures or finishes may be accidentally damaged during the disassembly process, resulting in additional maintenance needs. In addition, the FC boards need to be regularly inspected and maintained. If each disassembly and replacement is difficult, the maintenance work will be forced to be postponed, affecting the long-term performance of the boards. Utility Model Content

[0004] In view of the deficiencies of the prior art, the utility model provides an FC board installation structure for construction engineering, which solves the problems of the prior art.

[0005] To achieve the above objectives, the utility model is implemented through the following technical solutions: an FC board installation structure for construction engineering, comprising a bracket and an FC board body installed on the surface of the bracket, the surface of the bracket is equidistantly installed with connection components, and the surface of the FC board body close to the bracket is equidistantly opened with card slots;

[0006] The connecting assembly includes a positioning column fixedly connected to the surface of the bracket, a sliding column is slidably connected inside the positioning column, a rubber block is fixedly connected to the upper surface of the sliding column, driving tooth plates are symmetrically fixedly connected on both sides of the sliding column, the surface of the driving tooth plate is meshed with a driving gear, the surface of the driving gear is meshed with a sliding tooth plate, the positioning column is rotatably connected to the inside of the positioning column, a rotating gear and a side plate are fixedly connected to the fixed shaft, a protrusion is fixedly installed on the side end top of the side plate, and a positioning assembly is arranged between the positioning column and the sliding column.

[0007] Preferably, the positioning assembly includes latch teeth equidistantly fixedly connected to the side of the sliding column, a sliding groove is provided inside the positioning column, a slider is slidably connected inside the sliding groove, a clamping plate is fixedly connected to the side of the slider, a pull rope is fixedly connected at the center of the other side of the slider, and a spring is arranged inside the sliding groove.

[0008] Preferably, the surface of the rotating gear is meshingly connected to the surface of the sliding tooth plate, and both sides of the sliding tooth plate have teeth.

[0009] Preferably, the latch tooth is triangular, and the bottom of the latch plate abuts against the top of the latch tooth.

[0010] Preferably, the outer surface of the pull rope is slidably connected to the inside of the positioning column and the bracket, and one end of the pull rope away from the slider extends to the outside of the bracket and is fixedly connected to a ring.

[0011] Compared with the prior art, the utility model has the following beneficial effects:

[0012] 1. The FC board installation structure for construction engineering, by setting a connection component, after placing the FC board body on the bracket, by applying pressure to the FC board body, the positioning column can be inserted into the card slot, and the side panel can be opened by the abutment of the rubber block with the top of the card slot, and the protrusion can be abutted against the inner wall of the card slot, so as to realize the rapid positioning between the FC board body and the bracket. Compared with the traditional screw fixing and concrete pouring method, the installation efficiency is higher and the time cost can be reduced.

[0013] 2. The FC board installation structure used in the construction project is provided with latches and latches. When the FC board body is damaged and needs to be replaced, the slider and the latch can be moved and separated from the latches by pulling the pull rope. At this time, the sliding column can slide freely, and the FC board body can be quickly disassembled and replaced, which reduces the time and labor intensity of disassembly and replacement and improves work efficiency. BRIEF DESCRIPTION OF THE DRAWINGS

[0014] Figure 1 It is a schematic diagram of the structure of the utility model;

[0015] Figure 2 It is a structural schematic diagram of the FC board main body in the utility model;

[0016] Figure 3 It is a structural schematic diagram of the connection assembly in the utility model;

[0017] Figure 4 for Figure 3 The enlarged view of point A in the middle;

[0018] Figure 5 It is a schematic diagram of the connection between the positioning column and the sliding column in the utility model.

[0019] In the figure: 1, bracket; 2, FC board body; 201, slot; 3, connecting assembly; 301, positioning column; 302, sliding column; 303, rubber block; 304, driving tooth plate; 305, driving gear; 306, sliding tooth plate; 307, fixed shaft; 308, rotating gear; 309, side plate; 310, protrusion; 311, positioning assembly; 3111, tooth; 3112, sliding slot; 3113, slider; 3114, card plate; 3115, pull rope; 3116, spring. DETAILED DESCRIPTION

[0020] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0021] See also Figure 1-Figure 5 The utility model provides a technical solution: an FC board installation structure for construction engineering, including a bracket 1 and an FC board body 2 installed on the surface of the bracket 1, the surface of the bracket 1 is equidistantly installed with connecting components 3, and the surface of the FC board body 2 close to the bracket 1 is equidistantly opened with card slots 201.

[0022] The connecting component 3 includes a positioning column 301 fixedly connected to the surface of the bracket 1, the positioning column 301 is internally slidably connected with a sliding column 302, the upper surface of the sliding column 302 is fixedly connected with a rubber block 303, the two sides of the sliding column 302 are symmetrically fixedly connected with a driving tooth plate 304, the surface of the driving tooth plate 304 is meshed with a driving gear 305, the surface of the driving gear 305 is meshed with a sliding tooth plate 306, the driving gear 305 is rotatably installed on the positioning column 301, and the sliding tooth plate 306 is slidably installed on the positioning column 301, the positioning column 301 is internally rotatably connected with a fixed shaft 307, the fixed shaft 307 is fixedly connected with a rotating gear 308 and a side plate 309, the side end top of the side plate 309 is fixedly installed with a protrusion 310, the protrusion 310 is a hemispherical shape convex outward at noon, and a positioning component 311 is arranged between the positioning column 301 and the sliding column 302. The driving gear 305 and the rotating gear 308 are respectively disposed on opposite sides of the sliding tooth plate 306 and mesh with the teeth on both sides of the sliding tooth plate 306 , respectively. The driving gear 305 is located between the sliding tooth plate 306 and the sliding column 302 .

[0023] By setting the connection component 3, after the FC board body 2 is placed on the bracket 1, by applying pressure to the FC board body 2, the positioning column 301 can be inserted into the card slot 201, and the side panel 309 can be opened by the abutment of the rubber block 303 and the top of the card slot 201, and the protrusion 310 can be abutted against the inner wall of the card slot 201, so as to realize the rapid positioning between the FC board body 2 and the bracket 1. Compared with the traditional screw fixing and concrete pouring method, the installation efficiency is higher and the time cost can be reduced.

[0024] The positioning assembly 311 includes latch teeth 3111 equidistantly fixedly connected to the side of the sliding column 302, a sliding groove 3112 is provided inside the positioning column 301, a slider 3113 is slidably connected inside the sliding groove 3112, a clamping plate 3114 is fixedly connected to the side of the slider 3113, a pull rope 3115 is fixedly connected at the center of the other side of the slider 3113, a spring 3116 is provided inside the sliding groove 3112, the spring 3116 pushes the slider 3113 to move, and makes the end of the clamping plate 3114 extend between two adjacent latch teeth 3111 to position the sliding column 302.

[0025] By setting the latching teeth 3111 and the latching plate 3114, when the FC board main body 2 is damaged and needs to be replaced, the slider 3113 and the latching plate 3114 can be moved by pulling the pull rope 3115, and the latching plate 3114 can be separated from the latching teeth 3111. At this time, the sliding column 302 can slide freely, and the FC board main body 2 can be quickly disassembled and replaced, which reduces the time and labor intensity of disassembly and replacement and improves work efficiency.

[0026] The surface of the rotating gear 308 is meshedly connected to the surface of the sliding tooth plate 306 , and both sides of the sliding tooth plate 306 have teeth, which can ensure that the driving gear 305 drives the rotating gear 308 to transmit normally through the sliding tooth plate 306 .

[0027] The top of the rubber block 303 abuts against the inner top of the slot 201 , and the side of the protrusion 310 abuts against the inner wall of the slot 201 .

[0028] The latch tooth 3111 is a right triangle, wherein one right-angled side of the latch tooth 3111 is fixedly connected to the sliding column 302, and the other right-angled side is located at the top and is arranged horizontally. The bottom of the clamping plate 3114 abuts against the top of the latch tooth 3111. Due to the shape of the latch tooth 3111, an inclined pushing portion is arranged at the end of the clamping plate 3114. When the sliding column 302 slides downward, the inclined side of the latch tooth 3111 can push the clamping plate 3114 away from the latch tooth 3111 through the pushing portion, thereby achieving a one-way locking effect, and being able to position the rotation angle of the side plate 309.

[0029] The outer surface of the pull rope 3115 is slidably connected to the inside of the positioning column 301 and the bracket 1, and the end of the pull rope 3115 away from the slider 3113 extends to the outside of the bracket 1 and is fixedly connected to a ring. The setting of the ring can facilitate pulling the pull rope 3115.

[0030] During construction, the bracket 1 is fixed at a specified position, and then the FC board body 2 is placed on the bracket 1, so that the positioning column 301 is inserted into the slot 201, and then pressure is applied to the FC board body 2. The FC board body 2 drives the sliding column 302 and the driving tooth plate 304 to slide through the rubber block 303, and the driving tooth plate 304 drives the rotating gear 308 to rotate through the driving gear 305 and the sliding tooth plate 306. The rotating gear 308 drives the side plate 309 to rotate, and the surface of the protrusion 310 is tightly against the inner wall of the slot 201, so as to achieve rapid positioning between the FC board body 2 and the bracket 1. Compared with the traditional screw fixing and concrete pouring methods, the installation efficiency is higher and the time cost can be reduced. When the FC board body 2 is damaged and needs to be replaced, the slider 3113 and the card plate 3114 are driven to move and separate from the card tooth 3111 by pulling the pull rope 3115. At this time, the sliding column 302 can slide freely, and the FC board body 2 can be quickly disassembled and replaced, which reduces the time and labor intensity of disassembly and replacement and improves work efficiency.

[0031] Meanwhile, the contents not described in detail in this specification belong to the prior art known to those skilled in the art.

Claims

1. An FC panel mounting structure for construction engineering, comprising a bracket (1) and an FC panel body (2) mounted on the surface of the bracket (1), characterized in that: The surface of the bracket (1) is provided with connection components (3) installed at equal intervals, and the surface of the FC board body (2) close to the bracket (1) is provided with card slots (201) at equal intervals; The connection assembly (3) comprises a positioning column (301) fixedly connected to the surface of the bracket (1); a sliding column (302) is slidably connected inside the positioning column (301); a rubber block (303) is fixedly connected to the upper surface of the sliding column (302); driving tooth plates (304) are symmetrically fixedly connected to both sides of the sliding column (302); a driving gear (305) is meshedly connected to the surface of the driving tooth plate (304); a sliding tooth plate (306) is meshedly connected to the surface of the driving gear (305); a fixed shaft (307) is rotatably connected inside the positioning column (301); a rotating gear (308) and a side plate (309) are fixedly connected to the fixed shaft (307); a convex block (310) is fixedly mounted on the top of the side end of the side plate (309); and a positioning assembly (311) is provided between the positioning column (301) and the sliding column (302).

2. The FC board installation structure for construction engineering according to claim 1, characterized in that: The positioning assembly (311) comprises latch teeth (3111) fixedly connected to the side of the sliding column (302) at equal intervals; a sliding groove (3112) is provided inside the positioning column (301); a sliding block (3113) is slidably connected inside the sliding groove (3112); a latch plate (3114) is fixedly connected to the side of the sliding block (3113); a pull rope (3115) is fixedly connected at the center of the other side of the sliding block (3113); and a spring (3116) is provided inside the sliding groove (3112).

3. The FC board installation structure for construction engineering according to claim 1, characterized in that: The surface of the rotating gear (308) is meshedly connected to the surface of the sliding tooth plate (306), and both side surfaces of the sliding tooth plate (306) are provided with teeth.

4. The FC board installation structure for construction engineering according to claim 1, characterized in that: The top of the rubber block (303) abuts against the inner top of the slot (201), and the side of the protrusion (310) abuts against the inner wall of the slot (201).

5. The FC board installation structure for construction engineering according to claim 2, characterized in that: The outer surface of the pull rope (3115) is slidably connected to the inside of the positioning column (301) and the bracket (1), and one end of the pull rope (3115) away from the slider (3113) extends to the outside of the bracket (1) and is fixedly connected to a ring.