Precast concrete slab component
By adopting diversified casting and sealing designs in concrete prefabricated component molds, the problems of side leakage and cleaning difficulties during the casting process are solved, and the casting diversity and sealing are achieved, and the production efficiency and surface flatness are improved.
Patent Information
- Application Number
- CN202420243495.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-01-31
- Publication Date
- 2024-12-10
- Estimated Expiration
- 2034-01-31
AI Technical Summary
The casting method of existing concrete prefabricated component molds is single, which can easily lead to side leakage of mud and difficulty in cleaning.
A precast concrete slab member is designed, and a casting table with multiple bolts and threads is installed, equipped with a bidirectional screw, a transmission assembly, a leak-proof assembly, a vibration table and a limiting rod. The transmission assembly drives the two-directional screw to rotate, adjust the plate to slide, and prevent the The leakage assembly compresses the buffer spring, the vibration table generates vibration, and the limit rod limits sliding, achieving diversified casting and sealing to prevent side leakage of mud.
The cast concrete slab components are adjusted according to demand, which enhances the sealing of the casting table, prevents slurry leakage, simplifies the cleaning process, and pretreats the concrete by vibration, improving surface flatness and production efficiency.
Smart Images

Figure CN222135364U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of concrete slab components, and in particular relates to a prefabricated concrete slab component. Background Art
[0002] Precast concrete components are building components made in advance in factories using precast component molds. Precast component molds are industrial products that shape materials in a specific structural form through a certain method. They are also a production tool that can batch produce industrial product parts with certain shape and size requirements. Common ones include precast concrete floor slabs, concrete box girders for bridges, precast concrete roof beams for industrial plants, culvert frames, precast concrete piles for foundation treatment, etc.
[0003] In the prior art, precast concrete components are often directly cast through the cavity in the mold. This method is often used in the mass production of concrete slab components. However, the existing molds are generally fixed structures, and the casting method is relatively simple. During the casting process, mud is prone to leakage from the bottom of the mold, which makes it difficult to clean the casting table later.
[0004] Therefore need a kind of prefabricated concrete slab component to meet people's needs. Utility Model Content
[0005] In view of some or all of the problems existing in the above-mentioned prior art, the utility model provides a precast concrete slab component, which can realize casting of the return slab component according to demand and also prevent the occurrence of mud side leakage.
[0006] In order to achieve the above purpose, the utility model adopts the following technical solutions:
[0007] A precast concrete slab component comprises a casting platform, wherein an installation cover is threadedly installed on the upper surface of the casting platform through a plurality of bolts, bidirectional screws are rotatably installed on the left and right sides of the inner wall of the casting platform, threaded blocks are threadedly installed on the left and right sides of the rod walls of the two bidirectional screws, sliding openings are provided on the opposite sides of the inner wall of the casting platform, a plurality of threaded blocks are slidably installed on the inner walls corresponding to the sliding openings, transmission components are provided on the left sides of the two bidirectional screw rod walls, a rotating opening is provided on the left side surface of the casting platform, an adjustment plate is commonly installed on the opposite side surface corresponding to a group of threaded blocks, sliding blocks are slidably installed inside the two adjustment plates, anti-leakage components are provided on the inner walls of the two adjustment plates, and a measuring device is installed on the upper surface of the left adjustment plate.
[0008] Preferably, the transmission assembly includes two driving wheels, and the inner walls of the two driving wheels are respectively fixed to the rod walls of the corresponding bidirectional screw rods.
[0009] Preferably, the two driving wheels are rotatably connected together through a rotating chain, a driving motor is installed at the left end of the rear bidirectional screw, a fixing plate is installed on the lower surface of the driving motor, and the right surface of the fixing plate is fixed to the left surface of the casting table.
[0010] Preferably, the anti-leakage component includes multiple buffer springs, the upper ends of the multiple buffer springs are fixed to the lower surface of the sliding block, the lower ends of the multiple buffer springs are jointly installed with a sealing gasket, the upper surface of the sliding block is installed with a threaded rod, the rod wall of the threaded rod is threadedly connected to the inner wall of the adjusting plate, and the upper end of the threaded rod is installed with a turntable.
[0011] Preferably, a vibration table is installed on the lower surface of the casting table, and vibration springs and resistors are installed at the four corners of the lower surface of the vibration table. Scale plates are installed on the front and rear sides of the upper surface of the installation cover, and the upper surfaces of the two scale plates are provided with multiple scale grooves.
[0012] Preferably, a support platform is commonly installed at the lower ends of the plurality of vibration springs and the resistor, and a vibration motor is installed above the inner wall of the support platform.
[0013] Preferably, limit rods are installed on both the front and rear sides of the upper surfaces of the two sliding blocks, and the upper ends of the plurality of limit rods pass through the tops of the inner walls of the corresponding adjustment plates and extend to the outside.
[0014] Preferably, limit slide rails are slidably installed on the upper parts of the outer walls of the two threaded blocks, and the upper surfaces of the two limit slide rails are fixed to the upper part of the inner wall of the installation cover.
[0015] Compared with the prior art, the beneficial effects of the utility model are:
[0016] 1. The rotating chain and driving motor in the transmission assembly drive the two-way screws on both sides to rotate, thereby driving the adjustment plate to move along the inner wall of the sliding port, so as to realize the casting and production of concrete slab components according to demand, and improve the diversification of mold casting methods. At the same time, the threaded rod in the leak-proof assembly rotates, thereby pushing the sliding block to compress the buffer spring along the inner wall of the adjustment plate, thereby enhancing the sealing performance between the sealing gasket and the inner wall of the casting table, preventing the mud from leaking from the bottom of the mold during the casting process, and causing trouble in cleaning the casting table later;
[0017] 2. Through the setting of the vibration table, vibration spring, resistor, support table and vibration motor, the vibration motor can be controlled to produce vibration in cooperation with the vibration spring and resistor, so as to pre-treat the bubbles in the poured cement in advance. At the same time, the uniform vibration generated by the vibration spring and resistor can make the surface of the poured cement smoother, which is convenient for the subsequent mechanical leveling operation. The displacement positions of the adjustment plate and the threaded block are limited by the limit rod and the limit slide rail respectively, thereby improving the stability of the equipment operation. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] Figure 1 It is a schematic diagram of the structure of the utility model;
[0019] Figure 2 for Figure 1 A cross-sectional view of
[0020] Figure 3 for Figure 2 A in the enlarged view;
[0021] Figure 4 This is a schematic diagram of the cross-sectional installation structure of the sliding block of the utility model;
[0022] Figure 5 for Figure 4 Enlarged view of point A in .
[0023] Description of reference numerals:
[0024] 1. Casting table; 2. Mounting cover; 3. Bidirectional screw; 4. Threaded block; 41. Sliding port; 5. Adjusting plate; 6. Driving wheel; 7. Rotating chain; 8. Rotating port; 9. Driving motor; 10. Fixed plate; 11. Sealing gasket; 12. Buffer spring; 13. Sliding block; 14. Threaded rod; 15. Turntable; 16. Measuring device; 17. Scale plate; 18. Scale groove; 19. Vibrating table; 20. Vibrating spring; 21. Resistor; 22. Support table; 23. Vibrating motor; 24. Limit rod; 25. Limit slide rail. DETAILED DESCRIPTION
[0025] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0026] like Figures 1 to 5As shown, a precast concrete slab component provided in this embodiment includes a casting platform 1, an installation cover 2 is threadedly installed on the upper surface of the casting platform 1 through a plurality of bolts, bidirectional screws 3 are rotatably installed on the left and right sides of the inner wall of the casting platform 1, and thread blocks 4 are threadedly installed on the left and right sides of the rod walls of the two bidirectional screws 3, a sliding opening 41 is opened on the opposite side of the inner wall of the casting platform 1, and a plurality of thread blocks 4 are respectively slidably installed on the inner wall corresponding to the sliding opening 41, a transmission assembly is arranged on the left side of the rod walls of the two bidirectional screws 3, a rotating opening 8 is opened on the left side surface of the casting platform 1, an adjusting plate 5 is commonly installed on the opposite side surface of a group of thread blocks 4, and sliding blocks 13 are slidably installed inside the two adjusting plates 5, The inner walls of the two adjustment plates 5 are both provided with anti-leakage components. A measuring device 16 is installed on the upper surface of the left adjustment plate 5. The two-way screws 3 on both sides are driven to rotate through the rotating chain 7 and the driving motor 9 in the transmission component, thereby driving the adjustment plate 5 to move along the inner wall of the sliding opening 41, so as to realize the casting and production of concrete slab components according to demand, thereby improving the diversification of the mold casting method. At the same time, the threaded rod 14 in the anti-leakage component rotates, thereby pushing the sliding block 13 to compress the buffer spring 12 along the inner wall of the adjustment plate 5, thereby enhancing the sealing performance of the sealing gasket 11 and the inner wall of the casting table 1, preventing the mud from leaking sideways at the bottom of the mold during the casting process, and causing the problem of troublesome cleaning of the casting table 1 in the later stage.
[0027] like Figure 1 and 4 As shown, it is convenient to remove bubbles in the concrete prefabricated parts more cleanly in the later stage. After each pouring, the bubbles in the concrete are pretreated first. A vibration table 19 is installed on the lower surface of the pouring table 1. Vibration springs 20 and resistors 21 are installed at the four corners of the lower surface of the vibration table 19. Scale plates 17 are installed on the front and rear sides of the upper surface of the installation cover 2. The upper surfaces of the two scale plates 17 are provided with multiple scale grooves 18. A support table 22 is installed together at the lower ends of multiple vibration springs 20 and resistors 21. A vibration motor 23 is installed above the inner wall of the support table 22. Through the setting of the vibration table 19, the vibration spring 20, the resistor 21, the support table 22, and the vibration motor 23, the vibration motor 23 can be controlled to produce vibration in cooperation with the vibration spring 20 and the resistor 21, so as to pretreat the bubbles in the poured cement in advance. At the same time, the uniform vibration generated by the vibration spring 20 and the resistor 21 can make the surface of the poured cement smoother, which is convenient for the later mechanical smoothing operation.
[0028] like Figure 4 and 5As shown, limit rods 24 are installed on the front and rear sides of the upper surfaces of the two sliding blocks 13, and the upper ends of multiple limit rods 24 pass through the upper part of the inner wall of the corresponding adjustment plate 5 and extend to the outside. Limit rails 25 are slidably installed on the upper part of the outer walls of the two threaded blocks 4. The upper surfaces of the two limit rails 25 are fixed to the upper part of the inner wall of the installation cover 2. The displacement positions of the adjustment plate 5 and the threaded block 4 are limited by the limit rods 24 and the limit rails 25, respectively, thereby improving the stability of the equipment operation.
[0029] Working principle: The utility model prevents the problem of side leakage during the pouring of cement through the anti-leakage component, and realizes the pouring of prefabricated plate component templates of different specifications through the transmission component. It is convenient and practical. Before use, according to production needs, the bidirectional screw 3 is driven to rotate together by controlling the driving motor 9, and the bidirectional screw 3 and the driving wheel 6 on both sides are driven to rotate together through the rotating chain 7. At the same time, the threaded blocks 4 and the adjusting plate 5 on both sides are driven to move to the opposite side along the inner wall of the sliding port 41, so as to adjust the specifications of the concrete prefabricated parts. During the adjustment process, the adjustment distance is set in advance with the measuring device 16. The adjustment speed and accuracy are greatly improved, and the production efficiency of the product is improved. In order to prevent the side leakage of the mud during the pouring process, the turntable 15 is rotated to drive the threaded rod 14 to move up and down along the inner wall of the adjusting plate 5. While moving, the outer wall of the sliding block 13 is limited by the inner wall of the adjusting plate 5, thereby driving the sliding block 13 to move vertically together. By moving the sliding block 13, multiple buffer springs 12 are pushed downward, and the sealing gasket 11 is moved downward together. With the buffering force of the buffer spring 12, the sealing between the sealing gasket 11 and the casting table 1 is greatly improved, and the occurrence of mud leakage is prevented.
[0030] Obviously, those skilled in the art can make various changes and modifications to the present invention without departing from the spirit and scope of the present invention. Thus, if these modifications and variations of the present invention fall within the scope of the claims of the present invention and their equivalents, the present invention is also intended to include these modifications and variations.
Claims
1. A precast concrete slab component, comprising a casting platform (1), characterized in that: The upper surface of the pouring platform (1) is threadedly mounted with a mounting cover (2) through a plurality of bolts. Two bidirectional screws (3) are symmetrically arranged inside the pouring platform (1). The left and right sides of the inner wall of the bidirectional screws (3) are both rotatably mounted. The left and right sides of the rod wall of the two bidirectional screws (3) are both threadedly mounted with thread blocks (4). The opposite side of the inner wall of the pouring platform (1) is provided with a sliding opening (41). The plurality of thread blocks (4) are respectively slidably mounted on the inner wall of the corresponding sliding opening (41). The left sides of the rod wall of the two bidirectional screws (3) are both provided with a transmission assembly. The left side of the casting platform (1) is provided with a rotating opening (8). An adjustment plate (5) is commonly installed on the opposite side surfaces of a corresponding group of the threaded blocks (4), and a sliding block (13) is slidably installed inside the two adjustment plates (5); The inner walls of the two adjustment plates (5) are both provided with anti-leakage components, and the upper surface of the left adjustment plate (5) is installed with a measuring device (16).
2. A precast concrete slab member according to claim 1, characterized in that: The transmission assembly comprises two driving wheels (6), and the inner walls of the two driving wheels (6) are respectively fixed to the rod walls of the corresponding bidirectional screw rods (3).
3. A precast concrete slab member according to claim 2, characterized in that: The two driving wheels (6) are connected in rotation via a rotating chain (7); a driving motor (9) is installed at the left end of the rear bidirectional screw (3); a fixing plate (10) is installed on the lower surface of the driving motor (9); and the right side surface of the fixing plate (10) is fixed to the left side surface of the casting table (1).
4. The precast concrete slab member according to claim 1, characterized in that: The anti-leakage component comprises a plurality of buffer springs (12), the upper ends of the plurality of buffer springs (12) are fixed to the lower surface of a sliding block (13), a sealing gasket (11) is commonly installed at the lower ends of the plurality of buffer springs (12), a threaded rod (14) is installed on the upper surface of the sliding block (13), the rod wall of the threaded rod (14) is threadedly connected to the inner wall of the adjustment plate (5), and a rotating disk (15) is installed at the upper end of the threaded rod (14).
5. The precast concrete slab member according to claim 4, characterized in that: A vibration table (19) is installed on the lower surface of the pouring table (1), and vibration springs (20) and resistors (21) are installed at the four corners of the lower surface of the vibration table (19). Scale plates (17) are installed on the front and rear sides of the upper surface of the installation cover (2), and the upper surfaces of the two scale plates (17) are provided with a plurality of scale grooves (18).
6. The precast concrete slab member according to claim 5, characterized in that: A support platform (22) is commonly installed at the lower ends of the plurality of vibration springs (20) and resistors (21), and a vibration motor (23) is installed above the inner wall of the support platform (22).
7. The precast concrete slab member according to claim 1, characterized in that: Limiting rods (24) are installed on both the front and rear sides of the upper surfaces of the two sliding blocks (13), and the upper ends of the plurality of limiting rods (24) pass through the top of the inner wall of the corresponding adjustment plate (5) and extend to the outside.
8. The precast concrete slab member according to claim 1, characterized in that: Limiting slide rails (25) are slidably mounted on the upper sides of the outer walls of the two threaded blocks (4), and the upper surfaces of the two limiting slide rails (25) are fixed to the upper sides of the inner walls of the mounting cover (2).