Anchoring device of template pull rod

By using a combination of steel stranded wire and pulling components, the problem of difficulty in extracting traditional anchoring devices in space-constrained areas is solved, efficient formwork fixation and material savings are achieved, and construction efficiency and concrete appearance quality are improved.

CN222160942UActive Publication Date: 2024-12-13INNER MONGOLIA ROAD & BRIDGE
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420176189.9
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-01-25
Publication Date
2024-12-13
Estimated Expiration
2034-01-25

AI Technical Summary

Technical Problem

In bridge construction, the length of the pull rod needs to be processed according to the formwork size, which makes it difficult to extract in space-constrained parts, waste materials and affect the appearance of the concrete.

Method used

Steel strands are used as pulling material to position, length adjustment and lock the steel strands through positioning, adjustment and locking components, and the bending of the steel strands is used to facilitate extraction in space-constrained parts.

Benefits of technology

Effectively prevent the template from rising, the material utilization rate is improved, the structure is simple and the strength is higher than that of ordinary steel bars.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222160942U_ABST
    Figure CN222160942U_ABST
Patent Text Reader

Abstract

The utility model discloses an anchoring device of a template pull rod, which comprises two templates used for oppositely pulling and fixing, a through hole is fixed between the two templates in a penetrating way, a steel strand penetrates through the through hole, the penetrating end of the steel strand is locked and sleeved with an oppositely-pulling component, the side end of the oppositely-pulling component is attached to the templates, and the opposite-pulling component is fixed on the template. The steel strands are adopted for opposite pulling, the formworks can be effectively prevented from expanding, meanwhile, due to the fact that the steel strands can be locally bent, the steel strands can be conveniently pulled out of concrete at the limited space position, the formed structure is simple, and the strength of the steel strands is far higher than that of common steel bars.
Need to check novelty before this filing date? Find Prior Art

Description

Technical field:

[0001] The utility model relates to the technical field of anchoring, in particular to an anchoring device for a template tie rod. Background technology:

[0002] During bridge construction, tie rods are often used to reinforce the formwork to prevent the concrete formwork from expanding. This is especially true for pedestal foundations, small bridge culvert abutments, pier caps, cap beams and precast beams. To ensure that the tie rods can be used multiple times, PVC sleeves can be added to the parts that pass through the concrete body, and the tie rods can be pulled out when the formwork is removed.

[0003] Traditional processes generally use round steel with threads on both ends to process tie rods. The length of the tie rods must be processed according to the size of the template. In areas with limited space on both sides of the pedestal and foundation, the tie rods are often not pulled out equally. Disposable steel tie rods are used, and the exposed tie rod heads are cut off after the template is removed, which wastes materials and affects the appearance of the concrete. Utility model content:

[0004] To this end, the utility model provides an anchoring device for a template tie rod, which is used to overcome the problem that the prior art generally uses round steel with threads on both ends to process the tie rod, the length of the tie rod must be processed according to the corresponding template size, and the tie rods are often not pulled out equally in places with limited space on both sides of the pedestal and foundation, etc., and a disposable steel tie rod is used, and the exposed tie rod head is cut off after the template is removed, which wastes materials and affects the appearance of the concrete.

[0005] The utility model is implemented by the following technical solutions:

[0006] An anchoring device for a template tie rod comprises two templates for tensioning and fixing, and a through hole is fixed through the two templates, a steel strand is passed through the through hole, and a tensioning component is locked and sleeved on the outlet end of the steel strand, the side end of the tensioning component is arranged to fit the template, and the two tensioning components can pull the steel strand to pull and fix the two templates.

[0007] Preferably, the tensioning assembly includes a positioning assembly, an adjusting assembly and a locking assembly. The positioning assembly can realize the positioning and installation of the tensioning assembly and is arranged in a fit with the template. The adjusting assembly can adjust the length of the steel strand. The adjusting assembly is threadedly slidably connected to the positioning assembly. The locking assembly can lock the steel strand and is arranged at the side end of the adjusting assembly.

[0008] Preferably, the positioning assembly includes a pad, and a hollow steel pipe is fixed to the side of the pad.

[0009] Preferably, the adjustment assembly includes a hollow bolt and a screw, the hollow bolt is threaded onto the screw and inserted into the hollow steel pipe, and the screw is fixedly connected to the hollow steel pipe.

[0010] Preferably, the locking assembly includes an anchor, and the anchor is fitted on the side end of the hollow bolt, and a clip is inserted into the anchor, and the clip is arranged between the anchor and the steel strand.

[0011] The utility model has the advantages that the steel strands are used for pulling, which can effectively prevent the formwork from expanding. At the same time, because the steel strands can be partially bent, they can be conveniently pulled out of the concrete in places where space is limited. The structure formed is simple and the strength is much higher than that of ordinary steel bars. Description of the drawings:

[0012] In order to more clearly illustrate the embodiments of the utility model or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0013] Figure 1 This is a schematic diagram of the structure of the utility model.

[0014] In the figure: formwork 1, steel strand 2, pad 3, hollow steel pipe 4, screw 5, hollow bolt 6, anchor 7, clip 8. Specific implementation method:

[0015] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments of the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0016] like Figure 1 As shown, the utility model provides the following technical solutions: an anchoring device for a template tie rod, comprising two templates 1 for tensioning and fixing, and a through hole is passed through and fixed between the two templates 1, a steel strand 2 is passed through the through hole, and a tensioning component is locked and sleeved on the outlet end of the steel strand 2, the side end of the tensioning component is fitted with the template 1, and the two tensioning components can pull the steel strand 2 to pull and fix the two templates 1.

[0017] Specifically, the steel strand 2 is used for pulling, which can effectively prevent the formwork 1 from expanding. At the same time, because the steel strand 2 can be partially bent, it can be easily pulled out of the concrete in a space-constrained area. Moreover, the structure formed by it is simple and its strength is much higher than that of ordinary steel bars.

[0018] The tensioning assembly includes a positioning assembly, an adjusting assembly and a locking assembly. The positioning assembly can realize the positioning and installation of the tensioning assembly and is fitted with the template 1. The adjusting assembly can adjust the length of the steel strand 2. The adjusting assembly is threadedly connected to the positioning assembly. The locking assembly can lock the steel strand 2 and is arranged at the side end of the adjusting assembly. The positioning assembly includes a pad 3, and a hollow steel pipe 4 is fixed to the side of the pad 3. The adjusting assembly includes a hollow bolt 6 and a screw 5. The hollow bolt 6 is threaded on the screw 5 and inserted into the hollow steel pipe 4. The screw 5 is fixedly connected to the hollow steel pipe 4. The locking assembly includes an anchor 7, and the anchor 7 is fitted on the side end of the hollow bolt 6, and a clip 8 is inserted into the anchor 7, and the clip 8 is arranged between the anchor 7 and the steel strand 2.

[0019] Specifically, the positioning functions of the pad 3 and the hollow steel pipe 4 are respectively utilized to position the steel strand 2 and pass through. At the same time, the adjusting function of the hollow bolt 6 can be used to adjust the length of the steel strand 2 to achieve the pulling reinforcement of the template 1. During the adjustment process, the anchor 7 and the clip 8 are used to lock the steel strand 2.

[0020] Actual working process:

[0021] A φ15.2 prestressed steel strand 2 is used, and at both ends of the steel strand 2, a combination of a DSM15-1 single-hole anchor 7 and an M15.0V clip 8 matching the steel strand 2 is used. The anchor 7 is used to lock the steel strand 2, and the hollow bolt 6 is adjusted and tightened to achieve tension reinforcement of the formwork 1.

[0022] The pad 3 has a size of 100*100mm and is made of 10mm thick steel plate. A circular hole with a diameter of 25mm is opened in the center of the pad 3 to facilitate the smooth passage of the steel strand 2. A hollow steel pipe 4 (150mm long, 45mm in diameter, and 6mm in wall thickness) is welded on the pad 3.

[0023] The adjusting component includes a hollow bolt 6 and a screw 5. The M30*150 high-strength screw 5 is used. The screw 5 and the hollow steel pipe 4 are spot-welded and fixed. The hollow bolt 6 is screwed into the screw 5. The expansion and contraction of the adjusting component can be ensured by adjusting the tightness of the hollow bolt 6. The adjustment amount can be set up to 100mm.

[0024] A PVC sleeve is set in the template 1, and the steel strand 2 is passed into the sleeve. Both ends extend out of the template 1 respectively. The pad 3 and the adjustment assembly are installed. The hollow bolt 6 is screwed to the bottom. The DSM15-1 single-hole anchor 7 and the M15.0V clip 8 are installed at the outer end. The clip 8 is wedged with the steel strand 2. The function of the template 1 pull rod can be achieved by rotating the hollow bolt 6.

[0025] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. An anchoring device for a template tie rod, comprising two templates for tensioning and fixing, and a through hole is fixed through the two templates, characterized in that: A steel strand is passed through the through hole, and a tensioning component is locked and sleeved on the outlet end of the steel strand. The side end of the tensioning component is fitted with the template, and the two tensioning components can pull the steel strand to fix the two templates. The tensioning component includes a positioning component, an adjustment component and a locking component. The positioning component can realize the positioning and installation of the tensioning component and is fitted with the template. The adjustment component can adjust the length of the steel strand. The adjustment component is threadedly slidably connected to the positioning component. The locking component can lock the steel strand and is arranged at the side end of the adjustment component.

2. The anchoring device for a template tie rod according to claim 1, characterized in that: The positioning assembly comprises a backing plate, and a hollow steel pipe is fixed on the side of the backing plate.

3. The anchoring device for the template tie rod according to claim 2, characterized in that: The adjusting assembly comprises a hollow bolt and a screw. The hollow bolt is threaded onto the screw and inserted into the hollow steel pipe. The screw is fixedly connected to the hollow steel pipe.

4. The anchoring device for the template tie rod according to claim 3, characterized in that: The locking assembly comprises an anchor, and the anchor is fitted on the side end of the hollow bolt, and a clip is inserted into the anchor, and the clip is arranged between the anchor and the steel strand.