Embedded part positioning and adjusting device for fixing cable bracket of electric power inspection well

The pre-embedded parts positioning and adjustment device addresses the inefficiency in cable bracket positioning within power inspection wells by using a support frame and adjustable rods with bubble levels for rapid, accurate alignment, thereby improving construction speed and quality.

CN222162057UActive Publication Date: 2024-12-13NO 22 METALLURGICAL ROAD & BRIDGE CONSTR (HEBEI) CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420506235.7
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-15
Publication Date
2024-12-13
Estimated Expiration
2034-03-15

AI Technical Summary

Technical Problem

The challenge in constructing power inspection wells is the inefficient and time-consuming process of accurately positioning multiple cable brackets due to the narrow space within the steel bars of the well wall, which hinders construction progress.

Method used

A pre-embedded parts positioning and adjustment device with a support frame, adjustable support rods, and bubble levels to ensure accurate and rapid positioning of cable brackets by measuring once and adjusting multiple rods to the same horizontal level.

Benefits of technology

The device enables precise and efficient positioning of cable brackets, reducing the need for repetitive measurements and significantly enhancing construction efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222162057U_ABST
    Figure CN222162057U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of municipal engineering electric power tube banks, in particular to an embedded part positioning and adjusting device for fixing an electric power inspection well cable support, which comprises a supporting frame arranged on the periphery of an electric power well wall reinforcing steel bar and composed of an upper layer frame, a lower layer frame and four adjustable supporting rods. Mounting holes are formed in the two opposite cross rods of the upper-layer frame according to the spacing distance of the support embedded plates, horizontal positioning rods are detachably connected to the two opposite cross rods through bolts, the other ends of the positioning rods are inserted into electric power well wall body steel bars, the support embedded plates to be fixed can be accurately positioned, the positioning speed of the support embedded plates is increased, and the positioning efficiency is improved. According to the technical scheme, a worker only needs to measure the elevation position of the to-be-fixed support embedded plate once, then the adjustable supporting rods are adjusted to enable the positioning rods to be located at the same horizontal position, the positions of all the support embedded plates on the side are positioned, then the support embedded plates and electric power well wall body steel bars are welded, multiple times of measurement are not needed, and the construction efficiency can be effectively improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of municipal engineering electric power pipe laying, in particular to an embedded part positioning and adjusting device for fixing a cable bracket of an electric power inspection well. Background Art

[0002] During the construction of the power inspection well line, the cable bracket needs to be fixedly connected with the 150*150*10mm bracket embedded plate pre-buried in advance. When multiple bracket embedded plates are embedded and positioned, personnel need to enter the steel bars of the power well wall, and then measure the embedded height and embedded interval to ensure the accurate positioning of the bracket embedded plate, thereby ensuring the quality of the cable bracket installed later. However, due to the narrow space between the steel bars of the power well wall, personnel cannot measure inside, and there are a large number of bracket embedded plates. Measuring one by one will waste a lot of time and delay the construction progress. For this reason, a pre-embedded parts positioning and adjustment device for fixing the cable bracket of the power inspection well is proposed. Utility Model Content

[0003] The utility model aims to solve the above problems, thereby providing an embedded part positioning and adjusting device for fixing a cable bracket of an electric power inspection well.

[0004] The utility model solves the above problems and adopts the following technical solutions:

[0005] A pre-embedded parts positioning and adjustment device for fixing a cable bracket of an electric power inspection well comprises a support frame, which is arranged on the outer periphery of the steel bars of the wall of the electric power well, is rectangular as a whole, and is composed of an upper frame, a lower frame and four adjustable support rods, wherein the four adjustable support rods are respectively connected to the four corners between the upper frame and the lower frame, and are connected by a buckle assembly; mounting holes are provided on two opposite cross bars of the upper frame according to the spacing distance of the embedded plates of the bracket, and are detachably connected with a horizontal positioning rod by bolts; the other end of the positioning rod is inserted into the steel bars of the wall of the electric power well, and is flush with the inner side of the steel bars of the wall of the electric power well.

[0006] Compared with the prior art, the utility model adopting the above technical solution has the following outstanding features:

[0007] The utility model has a simple structure and is easy to use. It can accurately position the embedded plate of the bracket to be fixed and speed up the positioning speed of the embedded plate of the bracket. The personnel only need to measure the elevation position of the embedded plate of the bracket to be fixed once, and then adjust the adjustable support rod to make multiple positioning rods at the same horizontal position to complete the position positioning of all the embedded plates of the bracket on this side. Then the embedded plate of the bracket can be welded to the steel bar of the wall of the power well. There is no need for multiple measurements, which can effectively improve the construction efficiency.

[0008] As a preferred embodiment, a further technical solution of the utility model is:

[0009] Bubble levels are respectively arranged on two cross bars with mounting holes on the upper frame. BRIEF DESCRIPTION OF THE DRAWINGS

[0010] Figure 1 This is a schematic diagram of the main structure of an embodiment of the utility model;

[0011] Figure 2 It is a side view structural schematic diagram of an embodiment of the utility model;

[0012] Figure 3 It is a schematic diagram of the top view of the structure of an embodiment of the utility model;

[0013] Figure 4 This is a schematic diagram of the use state of an embodiment of the utility model;

[0014] Marked in the figure are: support frame 1, positioning rod 2, bubble level 3, bracket embedded plate 4, power well wall steel bar 5, upper frame 1-1, lower frame 1-2, adjustable support rod 1-3. DETAILED DESCRIPTION

[0015] The present invention is further described below in conjunction with embodiments, the purpose of which is only to provide a better understanding of the content of the present invention. Therefore, the examples given do not limit the protection scope of the present invention.

[0016] See also Figure 1-Figure 4 A pre-embedded part positioning and adjustment device for fixing a cable bracket of an electric inspection well comprises a support frame 1, which is arranged on the outer periphery of the steel bars 5 of the wall of the electric inspection well. The support frame 1 is rectangular as a whole and is composed of an upper frame 1-1, a lower frame 1-2 and four adjustable support rods 1-3. The four adjustable support rods 1-3 are respectively connected to the four corners between the upper frame 1-1 and the lower frame 1-2, and the connection method is a buckle assembly. The two opposite cross bars of the upper frame 1-1 are provided with mounting holes according to the spacing distance of the bracket embedded plate 4, and are detachably connected with a horizontal positioning rod 2 by bolts. The other end of the positioning rod 2 is inserted into the steel bars 5 of the wall of the electric inspection well and is flush with the inner side of the steel bars 5 of the wall of the electric inspection well.

[0017] Bubble levels 3 are respectively provided on the two crossbars with mounting holes of the upper frame 1-1 to ensure that the positioning points of the bracket embedded plate 4 are at the same horizontal height.

[0018] When the utility model is used, the device is installed on the outer periphery of the steel bars 5 of the wall of the power shaft. After the installation is completed, the elevation position of one of the embedded plates 4 of the bracket to be fixed is measured, and the positioning rod 2 at the corresponding position is adjusted to reach the height. Then, by observing the bubble level 3, the upper frame 1-1 is adjusted to the level through the adjustable support rods 1-3, and the positioning work of multiple embedded plates of the brackets 4 is completed.

[0019] The utility model has a simple structure and is easy to use. It can accurately position the embedded plate of the bracket to be fixed and speed up the positioning speed of the embedded plate of the bracket. The personnel only need to measure the elevation position of the embedded plate of the bracket to be fixed once, and then adjust the adjustable support rod to make multiple positioning rods at the same horizontal position to complete the position positioning of all the embedded plates of the bracket on this side. Then the embedded plate of the bracket can be welded to the steel bar of the wall of the power well. There is no need for multiple measurements, which can effectively improve the construction efficiency.

[0020] The above description is only a preferred feasible embodiment of the present utility model, and does not limit the scope of rights of the present utility model. All equivalent changes made using the contents of the present utility model specification and its drawings are included in the scope of rights of the present utility model.

Claims

1. An embedded part positioning and adjustment device for fixing a cable bracket in an electric inspection well, comprising a support frame, characterized in that: The support frame is arranged on the outer periphery of the steel bars of the power well wall. It is rectangular as a whole and consists of an upper frame, a lower frame and four adjustable support rods. The four adjustable support rods are respectively connected to the four corners between the upper frame and the lower frame. The connection method is a buckle assembly. The two opposite cross bars of the upper frame are provided with installation holes according to the spacing distance of the embedded plates of the bracket, and are detachably connected with horizontal positioning rods by bolts. The other end of the positioning rod is inserted into the steel bars of the power well wall and is flush with the inner side of the steel bars of the power well wall.

2. The embedded part positioning and adjusting device for fixing the cable support of the electric inspection well according to claim 1 is characterized in that: Bubble levels are respectively arranged on two cross bars with mounting holes on the upper frame.