Full-assembly building construction system with gutter as tie bar
By using thick-wall U-shaped steel and bolt connections, combined with rubber pads to fill gaps, the problem of gutter corrosion and construction conflicts in traditional steel structure factories is solved, and the corrosion resistance and drainage function is achieved, simplifying the construction process .
Patent Information
- Application Number
- CN202322814447.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-10-20
- Publication Date
- 2024-12-17
- Estimated Expiration
- 2033-10-20
AI Technical Summary
The gutters of traditional steel structure factories are prone to corrosion in humid environments, and welding connections lead to deformation and water leakage. During construction, the tie rods and drainage gutters are prone to conflict, affecting construction efficiency and quality.
U-shaped steel is used as the tie rod, with a wall thickness of more than 3mm. The gap is filled with bolted connections and rubber pads to ensure the compactness of the connection and avoid the positional conflict between the tie rod and the drainage gutter in the design.
It improves the corrosion resistance and drainage function of the gutter, simplifies the construction process of the steel structure factory, and ensures the longitudinal stiffness and construction efficiency of the building.
Smart Images

Figure CN222183897U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the field of steel structure factory building construction, in particular to a fully assembled building construction system using gutters as tie rods. Background Art
[0002] Traditional steel structure workshops transfer axial loads through horizontal tie rods set along the longitudinal direction of the building; the organized drainage function of the workshop is undertaken by the inner or outer gutters. The gutter wall thickness is only 1mm. In a humid environment, steel is prone to corrosion, penetrating the thin wall and affecting the drainage function. At the same time, the gutters are usually connected by spot welding. The welding stress causes the gutters to deform, and the welds are prone to leakage and accelerated corrosion. In addition, during the construction process, the tie rods and the drainage gutters are prone to conflict in position during the design deepening process, but this point is usually ignored. Utility Model Content
[0003] (I) Problem to be solved: The purpose of the utility model is to provide a fully assembled building construction system using gutters as tie rods, so as to simplify the current steel structure plant construction process and improve the corrosion resistance of the gutters.
[0004] (II) Technical Solution: To achieve the above purpose, the utility model provides a technical solution: a fully assembled building construction system using the gutter as a tie rod, as a horizontal support, arranged along the steel column to transmit the axial load. The gutter is made of U-shaped steel.
[0005] Furthermore, the wall thickness of the U-shaped steel is greater than 3 mm, and the cross-sectional dimensions are determined according to the local rainfall, wherein the cross-sectional web width needs to be smaller than the column width. Based on the slenderness ratio verification and the overall strength stability verification, the gutter also serves as a horizontal force transmission member of the roof support system.
[0006] Furthermore, the gutter is arranged along the steel column, and the connection method between the gutter and the adjacent steel column is bolt connection, and the distance from the center of the bolt connection opening to the edge of the plate must be greater than or equal to 1.5 times the hole diameter; the center-to-center distance of the hole must be greater than 3 times the hole diameter and less than 8 times the hole diameter.
[0007] Furthermore, rubber pads with holes are arranged between each gutter section, between the gutter end and the steel plate, and between the gutter drainage hole and the rainwater pipe. The rubber pads are 3 mm thick and then bolted together. The elastic deformation of the rubber is used to fill the connecting gaps to increase the density of the interface.
[0008] The utility model proposes a fully assembled building construction system using gutters as tie rods, which has the following beneficial effects:
[0009] 1. When building a steel structure workshop, directly install U-shaped steel between columns instead of tie rods to avoid component position conflicts during the design process and simplify the construction process.
[0010] 2. Ensure the longitudinal rigidity of the steel structure factory while improving the drainage function and corrosion resistance of the gutter. BRIEF DESCRIPTION OF THE DRAWINGS
[0011] Figure 1 This is a schematic diagram of the cross-sectional dimensions of the gutter U-shaped steel that replaces the tie rod.
[0012] Figure 2 This is a schematic diagram of the gutter connection node
[0013] Figure 3 This is a schematic diagram of the cross-sectional dimensions of the gutter rubber pad
[0014] Figure 4 This is a schematic diagram of the end of the gutter
[0015] Figure 5 This is a schematic diagram of the cross-sectional dimensions of the rainwater pipe rubber pad
[0016] Figure 6 This is the effect diagram of the connection between the gutters of the utility model. The number description in the figure is: 1-U-shaped steel gutter, 2-steel column, 3-rubber gasket, 4-steel plate DETAILED DESCRIPTION
[0017] It should be noted that the following detailed descriptions are exemplary and are intended to provide further explanation of the present application. Unless otherwise specified, all technical and scientific terms used herein have the same meanings as those commonly understood by those skilled in the art to which the present application belongs.
[0018] It should be noted that the terms used herein are only for describing specific embodiments and are not intended to limit the exemplary embodiments according to the present application. As used herein, unless the context clearly indicates otherwise, the singular form is also intended to include the plural form. In addition, it should be understood that when the terms "comprise" and / or "include" are used in this specification, it indicates the presence of features, steps, operations, devices, components and / or combinations thereof.
[0019] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of the utility model.
[0020] The steel column spacing l of the steel structure roof truss with the gutter as the tie rod is 7500mm, the U-shaped steel is Q235B steel, the cross-section web width h is 300mm, and the flange height b is 400mm. Figure 1According to the above dimensions, the slenderness ratio is verified, and the support conditions at both ends of the gutter are considered to be fixed. It can be obtained that the gutter can be used as a rigid tie rod to bear both tension and pressure; the gutter is used as an axial compression member to verify the overall stability, and the strength is verified after the stability coefficient is obtained by looking up the table, which is in compliance with the specifications.
[0021] The gutter connection method is bolt connection. Figure 2 Holes 1-6 are used for bolt connection between gutters, holes 7-8 are used for bolt connection between gutters and steel columns, the hole diameter is 20mm, and the cross section of the rubber pad with holes at the gutter connection is as follows: Figure 3 As shown in the figure, bolts mainly bear axial loads, and general strength bolts are used. After the size is determined, the axial pressure is verified. The end of the gutter is sealed with a steel plate, such as Figure 4 The cross section of the rubber pad with holes at the connection between the reserved drainage outlet at the end of the gutter and the rainwater pipe is as follows Figure 5 As shown, it is completed using general strength bolt connections.
[0022] The first span gutter with one side of the steel plate sealed is connected to the steel column through the front and back Figure 2 Holes 7-8 are bolted together, and the rubber pads with holes are passed through them in sequence. Figure 2 Holes 1-6 are connected to the last span of the gutter, and the drainage outlet is fixed with a perforated rubber pad and connected to the rainwater pipe through bolts to complete the construction.
[0023] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
[0024] Unless otherwise stated, any technical solution disclosed in the above utility model, if it discloses a numerical range, then the disclosed numerical range is a preferred numerical range. Any technician in the field should understand that the preferred numerical range is only a numerical value with a more obvious technical effect or representative value among many feasible numerical values. Since there are too many numerical values to be exhaustive, the utility model discloses only some numerical values to illustrate the technical solution of the utility model, and the numerical values listed above should not constitute a limitation on the scope of protection of the utility model.
[0025] If the present invention discloses or involves components or structures that are fixedly connected to each other, then, unless otherwise stated, the fixed connection can be understood as: a detachable fixed connection (for example, connection using bolts or screws), and can also be understood as: a non-detachable fixed connection (for example, riveting, welding). Of course, the mutual fixed connection can also be replaced by an integrated structure (for example, manufactured by one-piece molding using a casting process) (except where it is obviously impossible to use an one-piece molding process).
[0026] In addition, unless otherwise stated, the terms used to indicate positional relationships or shapes in any of the technical solutions disclosed in the above utility model include states or shapes that are approximate, similar or close thereto.
[0027] Any component provided by the utility model can be assembled from multiple separate components, or can be a separate component manufactured by an integrated molding process.
[0028] The above is only the preferred embodiment of the utility model, and does not limit the utility model in other forms. Any technician familiar with the profession may use the technical content disclosed above to change or modify it into an equivalent embodiment with equivalent changes. However, any simple modification, equivalent change and modification made to the above embodiment based on the technical essence of the utility model without departing from the technical solution of the utility model still belongs to the protection scope of the technical solution of the utility model.
Claims
1. A fully assembled building construction system using gutters as tie rods, characterized in that: The tie rod is replaced by a gutter (1) as a horizontal force transmission member. The gutter (1) adopts U-shaped steel (2) with a wall thickness of 3 mm. The gutter (1) is arranged along the steel column (3), and adjacent steel columns (3) are connected by bolts. Rubber pads (5) with holes are arranged at the connection between the gutter (1) and the connection between the end of the gutter (1) and the steel plate (4). The rubber pads are 3 mm thick and connected by bolts.
2. A fully assembled building construction system using gutters as tie rods according to claim 1, characterized in that: The holes are used to realize the connection of bolts between the gutter (1) and the steel plate (4).