Prefabricated finished product through-wall pipe assembly of gas pipeline

Through the prefabricated gas pipeline through-wall pipe components, including through-wall casing, centering ring and structural adhesive, the problems of inaccurate material estimates and low efficiency of high altitude operation in gas pipeline renovation are solved, and more efficient installation and improvement are achieved Good corrosion resistance.

CN222297200UActive Publication Date: 2025-01-03DONGYING LUCHEN GAS CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421159501.X
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-05-27
Publication Date
2025-01-03
Estimated Expiration
2034-05-27

AI Technical Summary

Technical Problem

In gas pipeline renovation projects, the existing technology has problems of wasting or delayed construction periods caused by inaccurate material estimates. At the same time, workers have large workloads, long construction periods and high costs for working at high altitudes, and the gas pipeline is susceptible to wall compression. and corrosion.

Method used

Provide a prefabricated gas pipeline through-wall pipe assembly, including a gas pipe body, a through-wall sleeve, a center ring, a structural glue and a foam glue, by customizing fixed-size through-wall sleeves and support structures in the factory, Reduce on-site processing, improve installation efficiency, and protect the pipeline from corrosion through heat shrink sleeves.

Benefits of technology

It has achieved the reduction of material waste and construction period delays, improved installation efficiency and safety performance, reduced the risks of high-altitude operations, and had good corrosion resistance, avoided wall extrusion and corrosion.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222297200U_ABST
    Figure CN222297200U_ABST
Patent Text Reader

Abstract

The utility model discloses a prefabricated finished product wall feed-through pipe assembly of a gas pipeline, which comprises a wall feed-through sleeve, a gas lead-in pipe, a connecting part and the like, and relates to the technical field of gas transformation, the prefabricated finished product wall feed-through pipe assembly comprises a gas pipe body, the gas pipe body is sleeved with the wall feed-through sleeve installed in a wall, and the wall feed-through sleeve is sleeved with the gas lead-in pipe. A centering ring is arranged between the gas pipe body and the wall bushing, structural adhesive is filled between the centering ring and the gas pipe body, and polystyrene foam is filled between the gas pipe body and the wall bushing. According to the utility model, the link of on-site processing of the prefabricated member is omitted, the working efficiency is improved, the wall bushing has a stronger supporting effect, the wall bushing can be better protected from being extruded by a wall body, the problem of deviation between estimated material consumption and actual use amount is solved, the workload of workers in the overhead working process is reduced, and the working efficiency is improved. And meanwhile, good safety performance and corrosion resistance are achieved in actual use.