I-shaped steel surface scaffold mounting and fixing structure in steel frame structure in open caisson
By using the fixing mechanism of limit blocks, welded plates and bolts in the caisson, the problem of low fixing efficiency and insufficient safety of I-steel and scaffolding is solved, and the rapid and firm connection is achieved, and construction efficiency and safety are improved. , and simplifies the disassembly and assembly process.
Patent Information
- Application Number
- CN202421081219.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-17
- Publication Date
- 2025-01-07
- Estimated Expiration
- 2034-05-17
AI Technical Summary
In caisson construction, the connection between traditional I-steel and scaffolding is at risk of safety and low efficiency, making it difficult to connect quickly and firmly.
Using a fixing mechanism including limit blocks, welding plates and bolts, the limit grooves to the bottom of the scaffolding are formed through the connection between the limit blocks and the welding plates, and the through holes of the bolts and placement blocks are used to achieve rapid fixing to ensure the scaffolding and I-shaped characters. Steel stable connection.
It improves the fixing efficiency of the scaffolding, reduces construction time, enhances safety, and is easy to disassemble and assemble, reusable, and saves resources and materials.
Smart Images

Figure CN222314052U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of municipal engineering, in particular to an I-beam surface scaffolding installation and fixing structure in a steel frame structure in a caisson. Background Art
[0002] With the rapid development of urbanization, urban buildings are becoming increasingly dense, which puts higher requirements on the construction of underground pipe corridors in municipal engineering. The construction and application of caissons are also more common. The geological conditions in some caissons are complex. When using traditional scaffolding for construction, the scaffolding is erected at a high height, and the foundation also needs to be hardened. Some companies will use the pre-buried beam caisson internal frame construction method in engineering caisson construction, which optimizes the scaffolding erection method inside the caisson, reduces the scaffolding erection height, and shortens the caisson scaffolding construction period. However, it is difficult to connect and fix the I-beam with its upper steel pipe scaffolding, and there are certain safety risks. How to quickly connect and fix the scaffolding and I-beam while ensuring safety and firmness is a problem that needs to be solved now. Utility Model Content
[0003] The technical problem to be solved by the utility model is to provide a scaffolding installation and fixing structure on the surface of an I-beam in a steel frame structure in a caisson, so as to overcome the deficiencies in the above-mentioned prior art.
[0004] The technical solution of the utility model to solve the above-mentioned technical problems is as follows: a scaffolding installation fixing structure on the surface of an I-beam in a steel frame structure in a caisson, comprising: a plurality of fixing mechanisms fixed on the I-beam in the steel frame structure in the caisson, the fixing mechanisms comprising: a limit block and a welding plate, the limit block is located between two I-beams distributed side by side, and its two ends respectively extend into the abdominal cavity of the two I-beams; the welding plate is arranged above the two I-beams, and its two ends are respectively fixed to the wing plates of the two I-beams; the limit block is connected to the welding plate through a connecting column, two placement blocks are fixed side by side on the welding plate, and a limit groove for limiting the bottom of the scaffolding is formed between the two placement blocks.
[0005] On the basis of the above technical solution, the present invention can also be improved as follows.
[0006] Furthermore, at least two through holes are formed on the placement block along the length direction of the I-beam, and all the through holes on one of the two placement blocks are coaxial with all the through holes on the other placement block;
[0007] The fixing mechanism also includes: a plurality of bolts, one end of the bolt is inserted into the through hole on the other placement block through the through hole on one of the two placement blocks; the bottom of the scaffold is located in the area between two adjacent bolts in the limiting groove.
[0008] Furthermore, a placement groove is formed on each placement block along the width direction of the I-beam, and the through hole on each placement block is connected to the placement groove thereon, and the nut of the bolt is located in the placement groove on one of the placement blocks.
[0009] Furthermore, the width of the limit block along the length direction of the I-beam is smaller than the distance between the wing plates of the two I-beams.
[0010] Furthermore, the welding plate is fixed to the flange of the I-beam by spot welding.
[0011] The beneficial effects of the utility model are:
[0012] The fixing mechanism can be fixed on the steel frame structure after the steel frame structure is laid, and then the bottom of the scaffolding cooperates with the fixing mechanism to achieve rapid fixation, effectively improving the fixing efficiency of the entire scaffolding, thereby effectively improving the efficiency of the entire project, saving time and effort, and it is easy to disassemble and assemble and can be reused, saving energy and materials. BRIEF DESCRIPTION OF THE DRAWINGS
[0013] Figure 1 It is a three-dimensional diagram of the installation and fixing structure of the scaffolding on the surface of the I-beam in the steel frame structure in the caisson of the utility model;
[0014] Figure 2 It is a partial enlarged view of the scaffolding installation and fixing structure on the surface of the I-beam in the steel frame structure in the caisson of the utility model.
[0015] In the accompanying drawings, the components represented by the reference numerals are listed as follows:
[0016] 1. Caisson, 2. I-beam, 3. Fixing mechanism, 310. Limiting block, 320. Welding plate, 330. Connecting column, 340. Placement block, 341. Placement groove, 342. Through hole, 350. Bolt, 360. Limiting groove. DETAILED DESCRIPTION
[0017] The principles and features of the present invention are described below in conjunction with the accompanying drawings. The examples given are only used to explain the present invention and are not used to limit the scope of the present invention.
[0018] Example 1
[0019] like Figure 1 , Figure 2 As shown, a scaffolding installation fixing structure on the surface of an I-beam in a steel frame structure in a caisson comprises: a plurality of fixing mechanisms 3 fixed on an I-beam 2 in a steel frame structure in a caisson 1, wherein the I-beam 2 in the steel frame structure is fixedly connected to the inner side of the caisson 1 through the fixing mechanism 3, and the bottom of the scaffolding can be fixed in a limited position. In this embodiment, the fixing mechanism 3 of the following structure is used to fix the bottom of the scaffolding in a limited position;
[0020] The fixing mechanism 3 includes: a limit block 310 and a welding plate 320. The limit block 310 is located between two I-beams 2 arranged side by side, and the two ends of the limit block 310 extend into the abdominal cavity of the two I-beams 2 respectively. The welding plate 320 is arranged above the two I-beams 2, and the two ends of the welding plate 320 are fixed to the wing plates of the two I-beams 2 respectively.
[0021] The limit block 310 and the welding plate 320 are connected by a connecting column 330, and the distance between the limit block 310 and the welding plate 320 is preferably slightly larger than the thickness of the wing plate of the I-beam 2; two placement blocks 340 are fixed side by side on the welding plate 320, and a limit groove 360 for limiting the bottom of the scaffolding is formed between the two placement blocks 340 on the welding plate 320.
[0022] During installation, the fixing mechanism 3 is placed vertically between the two I-beams 2, and then the limit block 310 is inserted under the wing plates of the two I-beams 2 and aligned with the abdominal cavities of the two I-beams 2, and then the fixing mechanism 3 is rotated 90° to allow the two ends of the limit block 310 to enter the abdominal cavities of the I-beams 2 respectively to achieve the limit; then the two ends of the welding plate 320 are first fixed to the wing plates of the two I-beams 2 respectively, and then the bottom of the scaffolding is placed in the limit groove 360 in turn to complete the fixed and limited effect of the scaffolding. Through the fixing mechanism 3, the scaffolding and the I-beams 2 in the steel frame structure can be effectively connected and fixed, and certain restrictions are maintained on the scaffolding, thereby effectively improving the fixing efficiency of the entire scaffolding, and it is easy to disassemble and can be reused, thereby effectively improving the efficiency of the entire project, saving time and labor, and saving energy and materials.
[0023] Example 2
[0024] like Figure 2 As shown, this embodiment is a further improvement on the basis of embodiment 1, and the details are as follows:
[0025] At least two through holes 342 are formed on the placement block 340 along the length direction of the I-beam 2. All through holes 342 on one of the two placement blocks 340 are coaxial with all through holes 342 on the other placement block 340. If the number of through holes 342 on the placement block 340 is two, then the two through holes 342 on one of the two placement blocks 340 are coaxial with the two through holes 342 on the other placement block 340.
[0026] The fixing mechanism 3 further includes: a plurality of bolts 350, one end of each bolt 350 is inserted into a through hole 342 on one of the two placement blocks 340 through a through hole 342 on the other placement block 340, and the bottom of the scaffold is located in the area between two adjacent bolts 350 in the limiting groove 360, and the gap between the two bolts 350 is preferably equal to the diameter of the bottom of the scaffold, so that the bottom of the scaffold can be completely restricted to prevent shaking;
[0027] After the bottom of the scaffold is placed in the limiting groove 360 and is limited, the bolts 350 are quickly installed to limit and fix the bottom of the scaffold in the limiting groove 360 to prevent it from falling off and improve the stability of the scaffold after being fixed.
[0028] Example 3
[0029] like Figure 2 As shown, this embodiment is a further improvement on the basis of Embodiment 1 or 2, and the details are as follows:
[0030] A placement groove 341 is formed on each placement block 340 along the width direction of the I-beam 2, and the through holes 342 on each placement block 340 are connected to the placement groove 341 thereon. The nut of the bolt 350 is located in the placement groove 341 on one of the placement blocks 340. When the bolt 350 is removed, the nut can fall directly into the placement groove 341 to prevent the nut from falling into the caisson 1.
[0031] Furthermore, the width of the limit block 310 along the length direction of the I-beam 2 is smaller than the distance between the wing plates of the two I-beams 2, which facilitates the installation of the fixing mechanism 3 between the two I-beams 2 in the early stage.
[0032] Example 4
[0033] like Figure 2 As shown, this embodiment is a further improvement on the basis of Embodiment 1, 2 or 3, and the details are as follows:
[0034] The welding plate 320 is fixed to the wing plate of the I-beam 2 by spot welding, and the fixing method is simple and has good stability.
[0035] Although the embodiments of the present invention have been shown and described above, it can be understood that the above embodiments are exemplary and cannot be understood as limitations of the present invention. Ordinary technicians in the field can change, modify, replace and modify the above embodiments within the scope of the present invention.
Claims
1. A scaffolding installation and fixing structure for the I-beam surface in a steel frame structure in a caisson, characterized in that: include: A plurality of fixing mechanisms (3) fixed on I-beams (2) in a steel frame structure in a caisson (1), the fixing mechanisms (3) comprising: a limit block (310) and a welding plate (320), the limit block (310) being located between two I-beams (2) arranged side by side, and having two ends thereof extending into the abdominal cavities of the two I-beams (2); the welding plate (320) being arranged above the two I-beams (2), and having two ends thereof being fixed to the wing plates of the two I-beams (2); the limit block (310) and the welding plate (320) being connected via a connecting column (330), two placement blocks (340) being fixed side by side on the welding plate (320), and a limit groove (360) for limiting the bottom of a scaffold being formed between the two placement blocks (340).
2. According to the scaffolding installation and fixing structure of the I-beam surface in the steel frame structure in the caisson according to claim 1, it is characterized in that: At least two through holes (342) are formed on the placement block (340) along the length direction of the I-beam (2), and all the through holes (342) on one of the two placement blocks (340) are coaxial with all the through holes (342) on the other placement block (340); The fixing mechanism (3) further comprises: a plurality of bolts (350), one end of each of the bolts (350) being inserted into a through hole (342) on one of the two placement blocks (340) through a through hole (342) on the other placement block (340); and the bottom of the scaffold is located in an area between two adjacent bolts (350) in the limiting groove (360).
3. The scaffolding installation and fixing structure on the surface of the I-beam in the steel frame structure in the caisson according to claim 2 is characterized in that: A placement groove (341) is formed on each placement block (340) along the width direction of the I-beam (2), and a through hole (342) on each placement block (340) is connected to the placement groove (341) thereon, and a nut of the bolt (350) is located in the placement groove (341) on one of the placement blocks (340).
4. The scaffolding installation and fixing structure on the surface of the I-beam in the steel frame structure in the caisson according to claim 1 is characterized in that: The width of the limit block (310) along the length direction of the I-beam (2) is smaller than the distance between the wing plates of the two I-beams (2).