Efficient heat exchange coil pipe and steam generator thereof
By improving the heat exchange coil structure of the steam generator, the heating area and evaporation rate of water are increased, solving the problem of high water cost in the existing technology and realizing efficient heat exchange and low-cost steam production.
Patent Information
- Application Number
- CN202421164935.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-24
- Publication Date
- 2025-01-10
- Estimated Expiration
- 2034-05-24
AI Technical Summary
In existing steam generators, the inner diameter of the evaporator coil limits the single evaporation capacity in the heat exchange chamber. Increasing the inner diameter requires increasing the single water intake, which leads to increased water costs.
The structure is designed with input section one, input section two, heat exchange section one and heat exchange section two, so that water enters different parts of the heat exchange chamber for heat exchange, increasing the heat exchange area. The design of the flow guide is optimized for the flow of water vapor and heat preservation, combined with the positioning section for stable installation.
Without changing the single water intake volume, the single evaporation rate of the heat exchange chamber was increased, water costs were reduced, and heat exchange efficiency and steam delivery efficiency were improved.
Smart Images

Figure CN222336134U_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of steam generators, and in particular to a high-efficiency heat exchange coil and a steam generator thereof. Background Art
[0002] Steam generator, also called steam heat source machine, is a mechanical equipment that uses the thermal energy of fuel or other energy sources to heat water into hot water or steam. It is now widely used in power generation, heating, chemical industry, food processing and other industries.
[0003] The existing steam generator mainly consists of an evaporation coil, a burner, a heat exchange chamber, and an exhaust system. When working, water flows into the evaporation coil inside the heat exchange chamber, and the high-temperature flue gas is passed into the heat exchange chamber through the burner to exchange heat with the water flowing in the evaporation coil, so that the water vapor after heating and evaporation is output from the other end of the evaporation coil, and the flue gas after combustion is sent out from the exhaust port on one side of the heat exchange chamber.
[0004] However, due to the limitation of the inner diameter of the evaporator coil, it is difficult to increase the single evaporation amount of water in the heat exchange chamber. If the single evaporation amount is increased simply by increasing the inner diameter of the evaporator coil, the single water intake amount needs to be increased accordingly, which will also lead to an increase in water use costs, which is not conducive to the company's cost control. Utility Model Content
[0005] In order to effectively increase the single evaporation amount of water in the existing heat exchange chamber while reducing the water cost, the present application provides a high-efficiency heat exchange coil and a steam generator thereof.
[0006] The present application provides an efficient heat exchange coil adopting the following technical solution:
[0007] A high-efficiency heat exchange coil comprises: an input part 1, an input part 2, a heat exchange part 1, a heat exchange part 2 and an output part, wherein the input part 1 and the input part 2 are respectively connected and arranged at the ends on the same side of the heat exchange part 1 and the heat exchange part 2 and are used to be connected to one side of a heat exchange chamber, and the output part is connected and arranged at the other end of the heat exchange part 1 and the heat exchange part 2 and is used to be connected to the other side of the heat exchange chamber, and the input part 1, the input part 2 and the output part can stably arrange the heat exchange part and the heat exchange part 2 inside the heat exchange chamber, and the input part 1 and the input part 2 can respectively pass water into the heat exchange part and the heat exchange part 2 and simultaneously perform heat exchange inside the heat exchange chamber.
[0008] By adopting the above technical scheme, the arrangement of the input part one, the input part two, the heat exchange part one and the heat exchange part two can make water enter the heat exchange part one and the heat exchange part two inside the heat exchange chamber respectively from the input part one and the input part two for heat exchange, which can effectively increase the heating area of the water when it exchanges heat with the high-temperature flue gas in the heat exchange part one and the heat exchange part two, thereby increasing the heating area of the water without changing the single water intake amount, thereby achieving the purpose of reducing the water cost while increasing the single evaporation amount inside the heat exchange chamber.
[0009] Optionally, the input part 1 and the input part 2 both include: a first connecting member, which is arranged at the input ends of the heat exchange part 1 and the heat exchange part 2 and is used to be connected to an external water source.
[0010] By adopting the above technical solution, the first connecting member can facilitate the stable connection of the input ends of the heat exchange part 1 and the heat exchange part 2 with the external water source, thereby improving the stability of the input ends of the heat exchange part 1 and the heat exchange part 2 when water flows in.
[0011] Optionally, the heat exchange part one and the heat exchange part two both include: a first flow guide, a second flow guide and a third flow guide, the two ends of the second flow guide are respectively connected to the first flow guide and the third flow guide, the second flow guide is arranged at the innermost side and the third flow guide is located between the first flow guide and the second flow guide, the other end of the first flow guide is connected to the input part one or the input part two, and the third flow guide is connected to the output part.
[0012] By adopting the above technical scheme, water can be introduced from input part one and input part two into heat exchange part one and heat exchange part two respectively, and then flow through the first guide member, the second guide member and the third guide member of heat exchange part one and heat exchange part two in turn and gradually be heated and vaporized into water vapor, and then sent out from the output part to the external steam-using equipment. Among them, by arranging the second guide member at the innermost side close to the heat source, it is beneficial for the water to gradually transition to the second guide member for heating after entering the first guide member, so that the heating area of the water inside the heat exchange chamber is larger, and the contact time with the heat source can also be guaranteed. At the same time, the water vapor obtained after vaporization is sent out from the third guide member located between the first guide member and the second guide member, which can also effectively keep the water vapor inside the third guide member warm, and reduce the phenomenon of water vapor being liquefied when it flows inside the third guide member.
[0013] Optionally, the diameters of the first flow guide member, the second flow guide member and the third flow guide member increase sequentially.
[0014] By adopting the above technical solution, the pipe diameters of the first flow guide member, the second flow guide member and the third flow guide member adaptively change from small to large as the phase change process of water gradually vaporizes into steam, thereby facilitating the efficient flow of the fluid inside the first flow guide member, the second flow guide member and the third flow guide member, thereby improving the heat exchange efficiency inside the heat exchange chamber to a certain extent.
[0015] Optionally, the output part includes: a conduit and a second connecting piece, the third flow guide pieces of the heat exchange part 1 and the heat exchange part 2 are both connected to the conduit, and the second connecting piece is arranged on the conduit and is used to connect to external steam-using equipment.
[0016] By adopting the above technical solution, the steam fluid flowing through the two third flow guides can be collected by the confluence piece and then centrally delivered to the external steam-using equipment connected to the second connecting piece, thereby effectively improving the delivery efficiency of the steam fluid.
[0017] On the other hand, the present application also provides a steam generator, wherein the side wall of the heat exchange chamber is provided with a positioning portion connected to the input portion 1, the input portion 2 and the output portion.
[0018] By adopting the above technical solution, the positioning part can limit the input part one, the input part two and the output part, so that the input part one, the input part two and the output part can be stably installed on the side wall of the heat exchange chamber, thereby effectively improving the use stability of the input part one, the input part two and the output part.
[0019] Optionally, the positioning portion includes: a first abutment member and a second abutment member, wherein the first abutment member and the second abutment member are both arranged on the side wall of the heat exchange chamber and can limit the outer walls of the input portion 1, the input portion 2 and the output portion.
[0020] By adopting the above technical solution, the outer walls of the input part 1, the input part 2 and the output part can be tightly pressed by the first abutment member and the second abutment member, so that the input part 1, the input part 2 and the output part can stably perform fluid conveying operations.
[0021] Optionally, the positioning portion further includes: a mounting member, and the first abutting member and the second abutting member are both detachably arranged on the side wall of the heat exchange chamber through the mounting member.
[0022] By adopting the above-mentioned technical scheme, the mounting member can detachably arrange the first abutment member and the second abutment member on the side wall of the heat exchange chamber, which can be beneficial for adaptively changing the positions of the first abutment member and the second abutment member on the side wall of the heat exchange chamber according to the sizes of the input part one, the input part two and the output part, thereby effectively improving the practicality of the first abutment member and the second abutment member.
[0023] In summary, the present application includes at least one of the following beneficial technical effects:
[0024] 1. The arrangement of the input part 1, the input part 2, the heat exchange part 1 and the heat exchange part 2 enables water to enter the heat exchange part 1 and the heat exchange part 2 inside the heat exchange chamber from the input part 1 and the input part 2 respectively for heat exchange, which can effectively increase the heating area of the water when the water exchanges heat with the high-temperature flue gas in the heat exchange part 1 and the heat exchange part 2, thereby increasing the heating area of the water without changing the single water intake amount, thereby increasing the single evaporation amount inside the heat exchange chamber and achieving the purpose of reducing the water cost;
[0025] 2. By arranging the first flow guide, the second flow guide and the third flow guide, water can be introduced from the input part one and the input part two into the heat exchange part one and the heat exchange part two respectively, and then flow through the first flow guide, the second flow guide and the third flow guide of the heat exchange part one and the heat exchange part two in turn and gradually be heated and vaporized into water vapor, and then sent out from the output part to the external steam-using equipment, wherein, by arranging the second flow guide at the innermost side close to the heat source, it is beneficial for the water to gradually transition to the second flow guide for heating after entering the first flow guide, so that the heating area of the water inside the heat exchange chamber is larger, and the contact time with the heat source can also be guaranteed. At the same time, the water vapor obtained after vaporization is sent out from the third flow guide located between the first flow guide and the second flow guide, which can also effectively keep the water vapor inside the third flow guide warm, and reduce the phenomenon of water vapor being cooled and liquefied when flowing inside the third flow guide. BRIEF DESCRIPTION OF THE DRAWINGS
[0026] Figure 1 It is a partial structural schematic diagram of a steam generator according to an embodiment of the present application;
[0027] Figure 2 is a schematic diagram of the internal structure of a steam generator according to an embodiment of the present application;
[0028] Figure 3 It is a schematic diagram of the structure of the heat exchange coil in the embodiment of the present application;
[0029] Figure 4 yes Figure 1 A magnified view of part A;
[0030] Figure 5 It is a schematic diagram of the structure of the busbar and the second connecting member according to an embodiment of the present application.
[0031] Explanation of the reference numerals: 1. Input section 1; 11. First connecting member; 2. Input section 2; 3. Heat exchange section 1; 31. First flow guide member; 32. Second flow guide member; 33. Third flow guide member; 4. Heat exchange section 2; 5. Output section; 51. Converging member; 511. Joining pipe; 512. Converging pipe; 52. Second connecting member; 6. Heat exchange chamber; 7. Positioning section; 71. First abutting member; 72. Second abutting member; 73. Mounting member; 8. Smoke exhaust port. DETAILED DESCRIPTION
[0032] The following is combined with Figure 1-5 This application is described in further detail. Example
[0033] The present application embodiment discloses a highly efficient heat exchange coil. Figure 1-2 The heat exchange coil includes an input part 1, an input part 2, a heat exchange part 1 3 and a heat exchange part 2 4. The input part 1 and the input part 2 2 are respectively connected to the heat exchange part 1 3 and the heat exchange part 2 4, and the heat exchange part 1 3 and the heat exchange part 2 4 are connected to the inside of the heat exchange chamber 6 through the input part 1 and the input part 2 2, and the heat exchange part 1 3 and the heat exchange part 2 4 are arranged side by side in the heat exchange chamber 6. At the same time, an output part 5 is installed on the side wall of the heat exchange chamber 6 away from the input part 1 and the input part 2 2, and the output ends of the heat exchange part 1 3 and the heat exchange part 2 4 are both connected to the output part 5.
[0034] During operation, water from the external water source is respectively sent into the heat exchange part 1 3 and the heat exchange part 2 4 from the input ends of the input part 1 and the input part 2, and produces heat exchange with the heat source inside the heat exchange chamber 6, so that the water vapor obtained after heat exchange gasification is finally sent out from the output part 5 on the other side to the external steam using equipment for application.
[0035] Reference Figure 2-4 In this embodiment, both the input part 1 and the input part 2 include a first connector 11. The first connector 11 is disposed at the input end of the heat exchange part 1 3 and the heat exchange part 2 4 and can be connected to the output end of the external water source, thereby stably connecting the input end of the heat exchange part 1 3 and the heat exchange part 2 4 to the output end of the external water source, thereby improving the water inlet stability of the input end of the heat exchange part 1 3 and the heat exchange part 2 4.
[0036] Meanwhile, in the present embodiment, the output part 5 includes a conduit 51 and a second connecting member 52. The conduit 51 is connected to the input end of the heat exchange part 1 3 and the heat exchange part 2 4, and the second connecting member 52 is installed on the outer wall of the conduit 51, so as to facilitate the output side of the conduit 51 to be connected to the external steam-using equipment. In addition, in the present embodiment, the conduit 51 includes a coupling pipe 511 and a confluence pipe 512. One side of the coupling pipe 511 is simultaneously connected to the input end of the heat exchange part 1 3 and the heat exchange part 2 4, and the confluence pipe 512 is connected to the middle of the other side of the coupling pipe 511 and is connected to the second connecting member 52. In addition, in the present embodiment, the first connecting member 11 and the second connecting member 52 can be selected as flanges.
[0037] Reference Figure 2-3 In this embodiment, the heat exchange part 1 3 and the heat exchange part 2 4 both include a first flow guide 31, a second flow guide 32 and a third flow guide 33. Among them, the first flow guide 31, the second flow guide 32 and the third flow guide 33 are all located inside the heat exchange chamber 6. At the same time, the two ends of the second flow guide 32 are respectively connected to one end of the first flow guide 31 and the third flow guide 33. In addition, the other end of the first flow guide 31 is respectively connected to the input part 1 or the input part 2 2, while the other end of the third flow guide 33 is connected to the output part 5. In addition, the second flow guide 32 is located at the innermost side, and the third flow guide 33 is located between the first flow guide 31 and the second flow guide 32. And in this embodiment, the pipe diameters of the first flow guide 31, the second flow guide 32 and the third flow guide 33 increase successively.
[0038] On the other hand, referring to Figure 1-2 The embodiment of the present application further provides a steam generator, including a burner and a smoke exhaust port 8. The burner is installed on one side of the heat exchange chamber 6 close to the input part 1 and the input part 2, and the output end extends to the middle of the inner side of the heat exchange chamber 6. At the same time, the smoke exhaust port 8 is connected and arranged at the side wall of the heat exchange chamber 6 to facilitate the discharge of high-temperature smoke inside the heat exchange chamber 6.
[0039] In addition, refer to Figure 1 and 5 In order to effectively improve the use stability of the input part 1, the input part 2 and the output part 5, a positioning part 7 is provided on the outer wall of the heat exchange chamber 6. The outer walls of the input part 1, the input part 2 and the output part 5 are all in contact with the positioning part 7.
[0040] In this embodiment, the positioning part 7 includes a first abutment member 71 and a second abutment member 72. The first abutment member 71 and the second abutment member 72 are both installed on the outer wall of the heat exchange chamber 6, and the outer walls of both sides of the input part 1, the input part 2 and the output part 5 are respectively abutted against the first abutment member 71 and the second abutment member 72 to achieve the positioning installation of the input part 1, the input part 2 and the output part 5.
[0041] At the same time, refer to Figure 1 and 5 In order to improve the connection stability between the first abutment 71 and the second abutment 72, a nut and a first screw are provided at the connection between the first abutment 71 and the second abutment 72. During installation, the first abutment 71 and the second abutment 72 can be respectively pressed against the two sides of the outer wall of the input part 1, the input part 2 or the output part 5, and then the first screw is passed through the through hole provided at the connection between the first abutment 71 and the second abutment 72, and then the nut is threadedly connected to one end of the first screw passing through the through hole and the nut is pressed against the connection between the first abutment 71 and the second abutment 72, thereby achieving a stable connection between the first abutment 71 and the second abutment 72, which is conducive to enhancing the positioning of the first abutment 71 and the second abutment 72 on the input part 1, the input part 2 and the output part 5.
[0042] In addition, in order to facilitate the position adjustment of the first abutting member 71 and the second abutting member 72, in this embodiment, the positioning portion 7 further includes a mounting member 73. The mounting member 73 is arranged on a side of the first abutting member 71 and the second abutting member 72 away from the outer wall of the heat exchange chamber 6 and connected to the outer wall of the heat exchange chamber 6.
[0043] In this embodiment, the mounting member 73 includes a limiting strip and a second screw. The limiting strip is installed on the outer wall of the first abutment member 71 and the second abutment member 72, and the limiting strip is detachably connected to the outer wall of the heat exchange chamber 6 through the first screw, so that the positions of the first abutment member 71 and the second abutment member 72 on the outer wall of the heat exchange chamber 6 can be changed according to the size of the input part 1, the input part 2 and the output part 5, which is conducive to improving the practicality of the first abutment member 71 and the second abutment member 72.
[0044] Working principle: When in use, firstly, water from the external water source is sent from the input part 1 and the input part 2 to the heat exchange part 1 3 and the heat exchange part 2 4 respectively, and then the water in the heat exchange part 1 3 and the heat exchange part 2 4 is heated simultaneously through the burner output end extending to the inside of the heat exchange chamber 6, and the water vapor obtained after the heat vaporization is sent from the output part 5 to the external steam-using equipment for use;
[0045] Among them, the high-temperature flue gas inside the heat exchange chamber 6 is used to heat the outer walls of the first guide member 31, the second guide member 32 and the third guide member 33 in the heat exchange part 1 3 and the heat exchange part 2 4 at the same time, which can effectively increase the heating area of water inside the heat exchange chamber 6, thereby increasing the single evaporation amount inside the heat exchange chamber 6 while achieving the purpose of reducing water use costs.
[0046] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.
Claims
1. A highly efficient heat exchange coil, characterized in that: include: An input part 1 (1), an input part 2 (2), a heat exchange part 1 (3), a heat exchange part 2 (4) and an output part (5), wherein the input part 1 (1) and the input part 2 (2) are respectively arranged at the ends of the same side of the heat exchange part 1 (3) and the heat exchange part 2 (4) and are used to be connected to one side of a heat exchange chamber (6), and the output part (5) is arranged at the other end of the heat exchange part 1 (3) and the heat exchange part 2 (4) and is used to be connected to the other side of the heat exchange chamber (6). The input part 1 (1), the input part 2 (2) and the output part (5) can stably arrange the heat exchange part 1 (3) and the heat exchange part 2 (4) inside the heat exchange chamber (6), and the input part 1 (1) and the input part 2 (2) can respectively pass water into the heat exchange part 1 (3) and the heat exchange part 2 (4) and simultaneously perform heat exchange inside the heat exchange chamber (6).
2. The efficient heat exchange coil according to claim 1, characterized in that: The input part 1 (1) and the input part 2 (2) both comprise a first connecting member (11), the first connecting member (11) being arranged at the input ends of the heat exchange part 1 (3) and the heat exchange part 2 (4) and being used for connecting to an external water source.
3. The efficient heat exchange coil according to claim 2, characterized in that: The heat exchange part 1 (3) and the heat exchange part 2 (4) both comprise: a first flow guide (31), a second flow guide (32) and a third flow guide (33); two ends of the second flow guide (32) are respectively connected to the first flow guide (31) and the third flow guide (33); the third flow guide (33) is located between the first flow guide (31) and the second flow guide (32); the other end of the first flow guide (31) is connected to the input part 1 (1) or the input part 2 (2); and the third flow guide (33) is connected to the output part (5).
4. The efficient heat exchange coil according to claim 3, characterized in that: The diameters of the first flow guide member (31), the second flow guide member (32) and the third flow guide member (33) increase sequentially.
5. The efficient heat exchange coil according to claim 3, characterized in that: The output part (5) comprises: a flow collector (51) and a second connecting part (52); the third flow guides (33) of the heat exchange part 1 (3) and the heat exchange part 2 (4) are both connected to the flow collector (51); and the second connecting part (52) is arranged on the flow collector (51) and is used to connect to external steam-using equipment.
6. A steam generator, using the heat exchange coil according to any one of claims 1 to 5, characterized in that: The side wall of the heat exchange chamber (6) is provided with a positioning portion (7) connected to the input portion 1 (1), the input portion 2 (2) and the output portion (5).
7. A steam generator according to claim 6, characterized in that: The positioning portion (7) comprises: a first abutment member (71) and a second abutment member (72); the first abutment member (71) and the second abutment member (72) are both arranged on the side wall of the heat exchange chamber (6) and are capable of limiting the outer walls of the input portion 1 (1), the input portion 2 (2) and the output portion (5).
8. A steam generator according to claim 7, characterized in that: The positioning portion (7) further comprises a mounting member (73), wherein the first abutting member (71) and the second abutting member (72) are both detachably arranged on the side wall of the heat exchange chamber (6) via the mounting member (73).