Auxiliary installation assembly and electronic equipment

By arranging auxiliary installation components in the chassis of the multi-GPU server, including installation space and pipeline fixed structure, the problem of limited operating space during GPU installation is solved, rapid installation and removal of cooling components is achieved, easy maintenance and reduced leakage fluid risk.

CN222380075UActive Publication Date: 2025-01-21LENOVO (BEIJING) LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323482246.0
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-20
Publication Date
2025-01-21
Estimated Expiration
2033-12-20

AI Technical Summary

Technical Problem

In the prior art, the GPU installation process of multi-GPU servers is more difficult, mainly due to the limited operating space, which makes it difficult to install and disassemble the water-cooled pipe.

Method used

An auxiliary installation component is provided, which includes a first auxiliary installation piece and a pressing structure. By arranging an installation space and a pipeline fixing structure in the chassis, rapid installation and removal of the heat dissipation element is achieved.

Benefits of technology

It reduces the difficulty of GPU installation, enables quick disassembly and installation of cooling components, facilitates replacement and later maintenance, and reduces the relative movement between the cooling components and water-cooling tubes, reducing the risk of leakage.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222380075U_ABST
    Figure CN222380075U_ABST
Patent Text Reader

Abstract

The utility model discloses an auxiliary installation assembly and electronic equipment. The auxiliary installation assembly comprises a first auxiliary installation part which is detachably arranged in the case, an installation space used for installing a heat dissipation element is formed between the first auxiliary installation part and the inner wall of the case, the first auxiliary installation part is provided with a pipeline fixing structure and a pressing structure, and the pipeline fixing structure is used for fixing a water cooling pipe connected with the heat dissipation element; wherein the heat dissipation element has a mounting state and a to-be-disassembled state, and when the heat dissipation element is in the mounting state, the pressing structure applies first pressure to the heat dissipation element, so that the heat dissipation element is pressed in the mounting space; when the heat dissipation element is in the to-be-disassembled state, the pressing structure is subjected to second pressure, the pressing structure is separated from the heat dissipation element through the second pressure, and the heat dissipation element can be taken out of the installation space. According to the auxiliary mounting assembly, the heat dissipation element can be quickly disassembled and assembled, and replacement and later maintenance of the heat dissipation element are facilitated.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of auxiliary installation components, in particular to an auxiliary installation component and an electronic device. Background Art

[0002] Currently, for servers with multiple GPUs (Graphics Processing Unit), a crossbeam is usually set in the server chassis to fix the GPU. Since the water cooling pipe of the GPU needs to pass under the crossbeam and then be inserted into the GPU interface, the operating space is limited, making the GPU installation process more difficult.

[0003] Therefore, how to reduce the difficulty of GPU installation is a technical problem that technicians in this field currently need to solve. Utility Model Content

[0004] In view of this, an object of the present invention is to provide an auxiliary installation component to reduce the difficulty of installing a GPU.

[0005] In order to achieve the above purpose, the utility model provides the following technical solutions:

[0006] An auxiliary installation component, comprising:

[0007] A first auxiliary mounting piece is detachably arranged inside the chassis, and an installation space for installing a heat dissipation element is formed between the first auxiliary mounting piece and the inner wall of the chassis, and the first auxiliary mounting piece is provided with a pipe fixing structure and a pressing structure, and the pipe fixing structure is used to fix a water cooling pipe connected to the heat dissipation element;

[0008] The heat dissipation element has an installed state and a to-be-removed state. When the heat dissipation element is in the installed state, the clamping structure applies a first pressure to the heat dissipation element so that the heat dissipation element is pressed in the installation space. When the heat dissipation element is in the to-be-removed state, the clamping structure is subjected to a second pressure, and the second pressure causes the clamping structure to break contact with the heat dissipation element, so that the heat dissipation element can be taken out of the installation space.

[0009] Optionally, in the auxiliary installation assembly, the pressing structure is an elastic structure, and based on the squeezing of the heat dissipation element on the elastic structure, the elastic structure undergoes elastic deformation, so that the elastic structure applies a first pressure to the heat dissipation element.

[0010] Optionally, in the above-mentioned auxiliary mounting assembly, the elastic structure includes an elastic hook, which extends from a side of the first auxiliary mounting component close to the heat dissipation element along a first direction, and the first direction is inclined to the installation direction of the heat dissipation element, and the angle between the first direction and the installation direction of the heat dissipation element is greater than 0° and less than 90°.

[0011] Optionally, in the above auxiliary mounting assembly, the auxiliary mounting assembly further comprises a second auxiliary mounting member, the second auxiliary mounting member is connected to the heat dissipation element, and the second auxiliary mounting member is located between the heat dissipation element and the first auxiliary mounting member;

[0012] Wherein, a first sliding connection structure is provided on a side of the first auxiliary mounting member close to the second auxiliary mounting member, and a second sliding connection structure is provided on the second auxiliary mounting member, and the first sliding connection structure and the second sliding connection structure are slidably matched.

[0013] Optionally, in the above-mentioned auxiliary installation assembly, one of the first sliding connection structure and the second sliding connection structure is a sliding groove, and the other is a sliding plate that cooperates with the sliding groove.

[0014] Optionally, in the above auxiliary installation assembly, one end of the slide groove is provided with a sliding guide port;

[0015] The sliding inlet includes two opposite first inclined walls and a second inclined wall, and along the installation direction of the heat dissipation element, the distance between the plane where the first inclined wall is located and the plane where the second inclined wall is located gradually decreases.

[0016] Optionally, in the above auxiliary installation assembly, the pipeline fixing structure includes a sliding slot, and the sliding slot is formed extending along the installation direction of the water cooling pipe at the end of the first auxiliary installation member;

[0017] Wherein, the water cooling tube is an elastic hose that can be squeezed in its radial direction, and the water cooling tube is interference fit with the sliding slot; or, an elastic clamping piece is provided in the sliding slot, and the elastic clamping piece presses the water cooling tube in the sliding slot.

[0018] Optionally, in the above auxiliary mounting assembly, the auxiliary mounting assembly further includes a third auxiliary mounting member connected to the first auxiliary mounting member, and the third auxiliary mounting member is detachably connected to the chassis.

[0019] An electronic device, comprising:

[0020] A chassis, wherein a receiving space is provided inside the chassis;

[0021] A heat dissipation element is disposed in the accommodation space;

[0022] A water cooling pipe connected to the heat dissipation element;

[0023] A first auxiliary mounting piece is detachably arranged inside the chassis, and an installation space for installing a heat dissipation element is formed between the first auxiliary mounting piece and the inner wall of the chassis, and the first auxiliary mounting piece is provided with a pipe fixing structure and a pressing structure, and the pipe fixing structure is used to fix a water cooling pipe connected to the heat dissipation element;

[0024] The heat dissipation element has an installed state and a to-be-removed state. When the heat dissipation element is in the installed state, the clamping structure applies a first pressure to the heat dissipation element so that the heat dissipation element is pressed in the installation space. When the heat dissipation element is in the to-be-removed state, the clamping structure is subjected to a second pressure, and the second pressure causes the clamping structure to break contact with the heat dissipation element, so that the heat dissipation element can be taken out of the installation space.

[0025] Optionally, in the above electronic device, the pressing structure is an elastic structure, and based on the compression of the heat dissipation element on the elastic structure, the elastic structure undergoes elastic deformation, so that the elastic structure applies a first pressure to the heat dissipation element.

[0026] When the auxiliary mounting assembly provided by the utility model needs to be used to install a heat dissipation element and a water-cooling pipe connected to the heat dissipation element, the first auxiliary mounting piece is detachably arranged inside the chassis in advance, so that an mounting space is formed between the first auxiliary mounting piece and the inner wall of the chassis, and then the heat dissipation element and the water-cooling pipe are pre-connected together outside the chassis, and the heat dissipation element and the water-cooling pipe are placed together inside the chassis, so that the heat dissipation element is located in the mounting space between the inner wall of the chassis and the first auxiliary mounting piece. After the heat dissipation element and the water-cooling pipe are installed in place, the heat dissipation element is in an installed state, and at this time, the pressing structure applies a first pressure to the heat dissipation element, so that the heat dissipation element is pressed in the mounting space. At the same time, the water-cooling pipe of the heat dissipation element is fixed in the chassis through the pipe fixing structure of the first auxiliary mounting part to realize the installation of the heat dissipation element; when the heat dissipation element and the water-cooling pipe connected to the heat dissipation element need to be removed, it is only necessary to apply a second pressure to the clamping structure, and the clamping structure is disengaged from the heat dissipation element based on the second pressure, so that the first pressure of the clamping structure on the heat dissipation element disappears, which is convenient for the staff to take the heat dissipation element out of the installation space. At the same time, the water-cooling pipe connected to the heat dissipation element is removed from the pipe fixing structure. After the heat dissipation element and the water-cooling pipe connected to the heat dissipation element are moved as a whole to the outside of the chassis, the heat dissipation element and the water-cooling pipe are disassembled to realize the disassembly of the heat dissipation element.

[0027] It can be seen that the auxiliary installation assembly provided by the utility model does not need to install and disassemble the water-cooling pipe under the crossbeam, which solves the technical problem of difficulty in installing the heat dissipation element due to limited operating space, and can realize the rapid disassembly and installation of the heat dissipation element, which is convenient for the replacement and subsequent maintenance of the heat dissipation element; and, since the heat dissipation element and the water-cooling pipe are both fixed by the first auxiliary installation component, the relative movement between the heat dissipation element and the water-cooling pipe can be reduced, thereby reducing the risk of leakage. BRIEF DESCRIPTION OF THE DRAWINGS

[0028] In order to more clearly illustrate the embodiments of the utility model or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0029] Figure 1 A schematic diagram of the assembly structure of an auxiliary mounting assembly provided by an embodiment of the utility model for mounting a heat dissipation element and a water cooling pipe on a chassis;

[0030] Figure 2 A schematic diagram of a disassembly process for simultaneously disassembling any heat dissipation element and its corresponding water cooling pipe provided by an embodiment of the utility model;

[0031] Figure 3 A schematic diagram of an assembly structure of a first auxiliary mounting member and a third auxiliary mounting member provided in an embodiment of the utility model;

[0032] Figure 4 A partial structural schematic diagram of a first auxiliary mounting member provided in an embodiment of the utility model;

[0033] Figure 5 A schematic diagram of an assembly structure for installing 16 GPUs in a chassis through auxiliary mounting components provided by an embodiment of the utility model.

[0034] Among them, 100 is the first auxiliary mounting part, 101 is the pipeline fixing structure, 102 is the clamping structure, 103 is the first sliding connection structure, 104 is the sliding introduction port, 200 is the second auxiliary mounting part, 300 is the third auxiliary mounting part, 400 is the heat dissipation element, 500 is the water cooling pipe, 600 is the chassis, and X is the installation direction of the heat dissipation element. DETAILED DESCRIPTION

[0035] In view of this, the core of the present invention is to provide an auxiliary installation component to reduce the difficulty of installing a GPU.

[0036] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0037] like Figures 1 to 5 As shown, the embodiment of the utility model discloses an auxiliary installation assembly, including a first auxiliary installation member 100 .

[0038] Among them, the first auxiliary mounting part 100 is detachably arranged inside the chassis 600, and an installation space for installing the heat dissipation element 400 is formed between the first auxiliary mounting part 100 and the inner wall of the chassis 600, and the first auxiliary mounting part 100 is provided with a pipeline fixing structure 101 and a clamping structure 102, and the pipeline fixing structure 101 is used to fix the water cooling pipe 500 connected to the heat dissipation element 400; the heat dissipation element 400 has an installed state and a to-be-disassembled state. When the heat dissipation element 400 is in the installed state, the clamping structure 102 applies a first pressure to the heat dissipation element 400, so that the heat dissipation element 400 is clamped in the installation space; when the heat dissipation element 400 is in the to-be-disassembled state, the clamping structure 102 is subjected to a second pressure, and the second pressure causes the clamping structure 102 to break contact with the heat dissipation element 400, so that the heat dissipation element 400 can be taken out from the installation space.

[0039] When the auxiliary mounting assembly provided by the utility model needs to be used to install the heat dissipation element 400 and the water-cooling tube 500 connected to the heat dissipation element 400, the first auxiliary mounting member 100 is pre-detachably arranged inside the chassis 600 to form an installation space between the first auxiliary mounting member 100 and the inner wall of the chassis 600, and then the heat dissipation element 400 and the water-cooling tube 500 are pre-connected together outside the chassis 600, and the heat dissipation element 400 and the water-cooling tube 500 are placed together inside the chassis 600 so that the heat dissipation element 400 is located in the installation space between the inner wall of the chassis 600 and the first auxiliary mounting member 100. After the heat dissipation element 400 and the water-cooling tube 500 are installed in place, the heat dissipation element 400 is in an installed state. At this time, the pressing structure 102 applies a first pressure to the heat dissipation element 400, so that the heat dissipation element 400 is pressed in the installation space. The water-cooling pipe 500 of the heat dissipation element 400 is fixed in the chassis 600 through the pipe fixing structure 101 of the first auxiliary mounting part 100, so that the installation of the heat dissipation element 400 is realized; when the heat dissipation element 400 and the water-cooling pipe 500 connected to the heat dissipation element 400 need to be removed, it is only necessary to apply a second pressure to the clamping structure 102, and the clamping structure 102 is disengaged from the heat dissipation element 400 based on the second pressure, so that the first pressure between the clamping structure 102 and the heat dissipation element 400 disappears, so that the staff can take the heat dissipation element 400 out of the installation space, and at the same time, remove the water-cooling pipe 500 connected to the heat dissipation element 400 from the pipe fixing structure 101, and after the heat dissipation element 400 and the water-cooling pipe 500 connected to the heat dissipation element 400 are moved as a whole to the outside of the chassis 600, the heat dissipation element 400 and the water-cooling pipe 500 are disassembled to realize the disassembly of the heat dissipation element 400.

[0040] It can be seen that the auxiliary installation assembly provided by the utility model does not need to install and disassemble the water-cooling pipe 500 under the crossbeam, which solves the technical problem of the difficulty in installing the heat dissipation element 400 due to limited operating space, and can realize the rapid disassembly and installation of the heat dissipation element 400, which is convenient for the replacement and subsequent maintenance of the heat dissipation element 400; and, since the heat dissipation element 400 and the water-cooling pipe 500 are both fixed by the first auxiliary installation component 100, the relative movement between the heat dissipation element 400 and the water-cooling pipe 500 can be reduced, thereby reducing the risk of leakage.

[0041] It should be noted that the above-mentioned heat dissipation element 400 can be but not limited to a GPU, and can also be a hard disk, a power supply or a CPU and other types of components. The present invention does not specifically limit the type of the above-mentioned heat dissipation element 400; and the number of the above-mentioned heat dissipation elements 400 can be one or more. In practical applications, the number of heat dissipation elements 400 can be adaptively adjusted according to actual needs, as long as it can meet the use requirements.

[0042] In addition, the above-mentioned clamping structure 102 can apply a first pressure to the heat dissipation element 400 through the deformation force of the elastic structure or the friction force of the friction part and other types of forces. As long as the clamping structure 102 can meet the use requirements, it belongs to the protection scope of the present utility model; optionally, the clamping structure 102 provided by the present utility model applies a first pressure to the heat dissipation element 400 through the deformation force of the elastic structure.

[0043] Specifically, Figure 3 and Figure 4 As shown, the pressing structure 102 is an elastic structure. Based on the compression of the heat dissipation element 400 on the elastic structure, the elastic structure undergoes elastic deformation, so that the elastic structure applies a first pressure to the heat dissipation element 400 .

[0044] It should be understood that the elastic structure can be an elastic hook, an elastic telescopic rod, or a combination of a spring and a metal sheet. As long as the structure can apply pressure to the heat dissipation element 400 after deformation, it falls within the protection scope of the present utility model.

[0045] Optionally, in a specific embodiment of the utility model, the elastic structure includes an elastic hook, which extends from a side of the first auxiliary mounting member 100 close to the heat dissipation element 400 along a first direction, the first direction is inclined to the installation direction X of the heat dissipation element, and the angle between the first direction and the installation direction X of the heat dissipation element is greater than 0° and less than 90°, so as to form an elastic hook in the forward direction of the installation direction X of the heat dissipation element. When the heat dissipation element 400 and the water cooling tube 500 are installed together into the chassis 600, the heat dissipation element 400 or a structure additionally provided on the heat dissipation element 400 squeezes the elastic hook in the forward direction, causing the elastic hook to undergo elastic deformation. After being installed in place, the elastic hook applies a first pressure to the heat dissipation element 400, so that the heat dissipation element 400 is pressed tightly in the installation space.

[0046] The present invention does not specifically limit the angle between the first direction and the installation direction X of the heat dissipation element 400 , and can be adaptively adjusted according to actual needs in practical applications, as long as it can meet the use requirements.

[0047] In addition, the auxiliary mounting assembly provided by the utility model also includes a second auxiliary mounting member 200, which is connected to the heat dissipation element 400, and the second auxiliary mounting member 200 is located between the heat dissipation element 400 and the first auxiliary mounting member 100; wherein, the first auxiliary mounting member 100 is provided with a first sliding connection structure 103 on the side close to the second auxiliary mounting member 200, and the second auxiliary mounting member 200 is provided with a second sliding connection structure, and the first sliding connection structure 103 and the second sliding connection structure are slidably matched, so that when the heat dissipation element 400 and the water cooling tube 500 are installed together into the chassis 600, the heat dissipation element 400 and the water cooling tube 500 are smoothly installed into the chassis 600 through the relative sliding between the first sliding connection structure 103 and the second sliding connection structure, so that the clamping structure 102 indirectly presses the heat dissipation element 400 by pressing the second auxiliary mounting member 200.

[0048] The above-mentioned first sliding connection structure 103 and the second sliding connection structure can be a type of cooperation between a sliding rod and a sliding block, a cooperation between a sliding block and a sliding groove, or a cooperation between a sliding block and a sliding rail. As long as the structural form can meet the sliding cooperation requirements, it belongs to the protection scope of the present utility model; optionally, in a specific embodiment of the present utility model, one of the first sliding connection structure 103 and the second sliding connection structure is a sliding groove, and the other is a sliding plate that cooperates with the sliding groove, so that the sliding plate slides in the sliding groove, which not only facilitates the installation of the heat dissipation element 400 and the water cooling tube 500 as a whole into the chassis 600, but also can guide the installation through the sliding groove.

[0049] In addition, a sliding introduction port 104 is provided at one end of the above-mentioned slide groove; wherein, the sliding introduction port 104 includes two opposite first inclined walls and a second inclined wall, and along the loading direction X of the heat dissipation element 400, the distance between the plane where the first inclined wall is located and the plane where the second inclined wall is located gradually decreases, so that the sliding plate can be introduced into the slide groove through the sliding introduction port 104, and even if there is a slight position deviation during installation, it can be corrected, which is convenient for installation.

[0050] Furthermore, the pipeline fixing structure 101 includes a sliding slot, which is formed by extending at the end of the first auxiliary mounting member 100 along the installation direction X of the water-cooling pipe and the heat dissipation element; wherein the water-cooling pipe 500 is an elastic hose that can be squeezed in its radial direction, and the water-cooling pipe 500 is interference fit with the sliding slot, so that after the water-cooling pipe 500 is installed in the sliding slot, the water-cooling pipe 500 is fixed by the interference fit between the water-cooling pipe 500 and the sliding slot; or, an elastic pressing piece is provided in the sliding slot, and the elastic pressing piece presses the water-cooling pipe 500 in the sliding slot to fix the water-cooling pipe 500.

[0051] It should be understood that the above-mentioned elastic hose can be a rubber hose or a metal hose coated with a rubber pad or felt. As long as the elastic hose can be clamped in the sliding slot by interference fit, it falls within the protection scope of the present utility model; similarly, the above-mentioned elastic clamping part can be a metal spring or a rubber block or other type of element. As long as the elastic structure type can press the water-cooling pipe 500 in the sliding slot, it falls within the protection scope of the present utility model.

[0052] The first auxiliary mounting component 100 provided by the present invention can be directly installed in the chassis 600, and can also be installed in the chassis 600 through a separately arranged connecting component. As long as the installation method can meet the use requirements, it belongs to the protection scope of the present invention; optionally, in the embodiment of the present invention, the auxiliary mounting assembly also includes a third auxiliary mounting component 300 connected to the first auxiliary mounting component 100, and the third auxiliary mounting component 300 is detachably connected to the chassis 600.

[0053] The above-mentioned third auxiliary mounting member 300 and the chassis 600 can be installed on the chassis 600 by means of threaded connection or snap-on connection. As long as the connection method can satisfy the detachable connection, it belongs to the protection scope of the present utility model; optionally, the third auxiliary mounting member 300 and the chassis 600 provided in the embodiment of the present utility model are connected to the box body by screws.

[0054] In addition, the utility model also discloses an electronic device, including a chassis 600 , a heat dissipation element 400 , a water cooling pipe 500 and a first auxiliary mounting member 100 .

[0055] Among them, a accommodating space is provided inside the chassis 600; the heat dissipation element 400 is arranged in the accommodating space; the water cooling pipe 500 is connected to the heat dissipation element 400; the first auxiliary mounting member 100 is detachably arranged inside the chassis 600, and an installation space for installing the heat dissipation element 400 is formed between the first auxiliary mounting member 100 and the inner wall of the chassis 600, and the first auxiliary mounting member 100 is provided with a pipeline fixing structure 101 and a clamping structure 102, and the pipeline fixing structure 101 is used to fix the water cooling pipe 500 connected to the heat dissipation element 400; the heat dissipation element 400 has an installed state and a to-be-removed state. When the heat dissipation element 400 is in the installed state, the clamping structure 102 applies a first pressure to the heat dissipation element 400, so that the heat dissipation element 400 is clamped in the installation space; when the heat dissipation element 400 is in the to-be-removed state, the clamping structure 102 is subjected to a second pressure, and the second pressure causes the clamping structure 102 to break contact with the heat dissipation element 400, so that the heat dissipation element 400 can be taken out from the installation space.

[0056] The electronic device provided by the utility model pre-disposes the first auxiliary mounting member 100 detachably inside the chassis 600, so that an installation space is formed between the first auxiliary mounting member 100 and the inner wall of the chassis 600, and then the heat dissipation element 400 and the water cooling tube 500 are pre-connected together outside the chassis 600, and the heat dissipation element 400 and the water cooling tube 500 are placed together inside the chassis 600, so that the heat dissipation element 400 is located in the installation space between the inner wall of the chassis 600 and the first auxiliary mounting member 100. After the heat dissipation element 400 and the water cooling tube 500 are installed in place, the heat dissipation element 400 is in an installed state. At this time, the pressing structure 102 applies a first pressure to the heat dissipation element 400, so that the heat dissipation element 400 is pressed in the installation space. At the same time, the pipe fixing structure 102 of the first auxiliary mounting member 100 is used to fix the heat dissipation element 400. 101 fixes the water-cooling pipe 500 of the heat dissipation element 400 in the chassis 600 to achieve the installation of the heat dissipation element 400; when the heat dissipation element 400 and the water-cooling pipe 500 connected to the heat dissipation element 400 need to be removed, it is only necessary to apply a second pressure to the clamping structure 102, and the clamping structure 102 is disengaged from the heat dissipation element 400 based on the second pressure, so that the first pressure of the clamping structure 102 on the heat dissipation element 400 disappears, making it convenient for the staff to take the heat dissipation element 400 out of the installation space. At the same time, the water-cooling pipe 500 connected to the heat dissipation element 400 is removed from the pipe fixing structure 101. After the heat dissipation element 400 and the water-cooling pipe 500 connected to the heat dissipation element 400 are moved as a whole to the outside of the chassis 600, the heat dissipation element 400 and the water-cooling pipe 500 are disassembled to achieve the disassembly of the heat dissipation element 400.

[0057] It can be seen that the electronic equipment provided by the utility model does not need to install and disassemble the water-cooling tube 500 under the crossbeam, which solves the technical problem of the difficulty in installing the heat dissipation element 400 due to limited operating space, and can realize the rapid disassembly and installation of the heat dissipation element 400, which is convenient for the replacement and subsequent maintenance of the heat dissipation element 400; and, since the heat dissipation element 400 and the water-cooling tube 500 are both fixed by the first auxiliary mounting member 100, the relative movement between the heat dissipation element 400 and the water-cooling tube 500 can be reduced, thereby reducing the risk of leakage.

[0058] It should be noted that the above-mentioned heat dissipation element 400 can be but not limited to a GPU, and can also be a hard disk, a power supply or a CPU and other types of components. The present invention does not specifically limit the type of the above-mentioned heat dissipation element 400; and the number of the above-mentioned heat dissipation elements 400 can be one or more. In actual applications, the number of heat dissipation elements 400 can be adaptively adjusted according to actual needs, as long as it can meet the use requirements.

[0059] Alternatively, if Figure 2 and Figure 5As shown, in a specific embodiment of the present invention, the heat dissipation element 400 is a GPU, and the number of GPUs is sixteen. Any one of the sixteen GPUs can be disassembled and maintained separately from its corresponding water cooling pipe 500 without being affected by other GPUs.

[0060] In addition, the above-mentioned clamping structure 102 can apply a first pressure to the heat dissipation element 400 through the deformation force of the elastic structure or the friction force of the friction part and other types of forces. As long as the clamping structure 102 can meet the use requirements, it belongs to the protection scope of the present utility model; optionally, the clamping structure 102 provided by the present utility model applies a first pressure to the heat dissipation element 400 through the deformation force of the elastic structure.

[0061] Specifically, Figure 3 and Figure 4 As shown, the pressing structure 102 is an elastic structure. Based on the compression of the heat dissipation element 400 on the elastic structure, the elastic structure undergoes elastic deformation, so that the elastic structure applies a first pressure to the heat dissipation element 400 .

[0062] It should be understood that the elastic structure can be an elastic hook, an elastic telescopic rod, or a combination of a spring and a metal sheet. As long as the structure can apply pressure to the heat dissipation element 400 after deformation, it falls within the protection scope of the present utility model.

[0063] The terms "first" and "second" in the specification and claims of the utility model and the above-mentioned drawings are used to distinguish different objects, rather than to describe a specific order. In addition, the terms "including" and "having" and any of their variations are intended to cover non-exclusive inclusions. For example, a process, method, system, product or device that includes a series of steps or units is not limited to the listed steps or units, but may include steps or units that are not listed.

[0064] The above description of the disclosed embodiments enables those skilled in the art to implement or use the present invention. Various modifications to these embodiments will be apparent to those skilled in the art, and the general principles defined herein may be implemented in other embodiments without departing from the spirit or scope of the present invention. Therefore, the present invention will not be limited to the embodiments shown herein, but will conform to the widest scope consistent with the principles and novel features disclosed herein.

Claims

1. An auxiliary installation assembly, characterized in that: include: A first auxiliary mounting piece is detachably arranged inside the chassis, and an installation space for installing a heat dissipation element is formed between the first auxiliary mounting piece and the inner wall of the chassis, and the first auxiliary mounting piece is provided with a pipe fixing structure and a pressing structure, and the pipe fixing structure is used to fix a water cooling pipe connected to the heat dissipation element; The heat dissipation element has an installed state and a to-be-removed state. When the heat dissipation element is in the installed state, the pressing structure applies a first pressure to the heat dissipation element so that the heat dissipation element is pressed in the installation space. When the heat dissipation element is in the state to be disassembled, the pressing structure is subjected to a second pressure, and the second pressure causes the pressing structure to break away from contact with the heat dissipation element, so that the heat dissipation element can be taken out of the installation space.

2. The auxiliary installation assembly according to claim 1, characterized in that: The pressing structure is an elastic structure. Based on the compression of the heat dissipation element on the elastic structure, the elastic structure undergoes elastic deformation, so that the elastic structure applies a first pressure to the heat dissipation element.

3. The auxiliary installation assembly according to claim 2, characterized in that: The elastic structure includes an elastic hook, which extends from a side of the first auxiliary mounting part close to the heat dissipation element along a first direction, the first direction is inclined to the installation direction of the heat dissipation element, and the angle between the first direction and the installation direction of the heat dissipation element is greater than 0° and less than 90°.

4. The auxiliary installation assembly according to claim 1, characterized in that: The auxiliary mounting assembly further comprises a second auxiliary mounting member, the second auxiliary mounting member is connected to the heat dissipation element, and the second auxiliary mounting member is located between the heat dissipation element and the first auxiliary mounting member; Wherein, a first sliding connection structure is provided on a side of the first auxiliary mounting member close to the second auxiliary mounting member, and a second sliding connection structure is provided on the second auxiliary mounting member, and the first sliding connection structure and the second sliding connection structure are slidably matched.

5. The auxiliary installation assembly according to claim 4, characterized in that: One of the first sliding connection structure and the second sliding connection structure is a sliding groove, and the other is a sliding plate matched with the sliding groove.

6. The auxiliary installation assembly according to claim 5, characterized in that: One end of the slide groove is provided with a sliding introduction port; The sliding inlet includes two opposite first inclined walls and a second inclined wall, and along the installation direction of the heat dissipation element, the distance between the plane where the first inclined wall is located and the plane where the second inclined wall is located gradually decreases.

7. The auxiliary installation assembly according to claim 1, characterized in that: The pipeline fixing structure comprises a sliding slot, and the sliding slot is formed extending along the installation direction of the water cooling pipe at the end of the first auxiliary mounting member; Wherein, the water cooling tube is an elastic hose that can be squeezed in its radial direction, and the water cooling tube is interference fit with the sliding slot; or, an elastic clamping piece is provided in the sliding slot, and the elastic clamping piece presses the water cooling tube in the sliding slot.

8. The auxiliary installation assembly according to claim 1, characterized in that: The auxiliary mounting assembly further comprises a third auxiliary mounting piece connected to the first auxiliary mounting piece, and the third auxiliary mounting piece is detachably connected to the chassis.

9. An electronic device, characterized in that: include: A chassis, wherein a receiving space is provided inside the chassis; A heat dissipation element is disposed in the accommodation space; A water cooling pipe connected to the heat dissipation element; A first auxiliary mounting piece is detachably arranged inside the chassis, and an installation space for installing a heat dissipation element is formed between the first auxiliary mounting piece and the inner wall of the chassis, and the first auxiliary mounting piece is provided with a pipe fixing structure and a pressing structure, and the pipe fixing structure is used to fix a water cooling pipe connected to the heat dissipation element; The heat dissipation element has an installed state and a to-be-removed state. When the heat dissipation element is in the installed state, the pressing structure applies a first pressure to the heat dissipation element so that the heat dissipation element is pressed in the installation space. When the heat dissipation element is in the state to be disassembled, the pressing structure is subjected to a second pressure, and the second pressure causes the pressing structure to break away from contact with the heat dissipation element, so that the heat dissipation element can be taken out of the installation space.

10. The electronic device according to claim 9, characterized in that: The pressing structure is an elastic structure. Based on the compression of the heat dissipation element on the elastic structure, the elastic structure undergoes elastic deformation, so that the elastic structure applies a first pressure to the heat dissipation element.