Prefabricated energy storage cabin pile foundation
Through the stitching installation of the foundation of the prefabricated energy storage compartment pile and the stable support of the steel burial parts, the problem of long -term infrastructure and weather restrictions in the existing technology in the existing technology has achieved convenient installation and efficient construction.
Patent Information
- Application Number
- CN202421203709.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-30
- Publication Date
- 2025-01-24
- Estimated Expiration
- 2034-05-30
AI Technical Summary
The existing energy storage compartment foundation uses cast-in-place raft foundation, which leads to a long construction period and is unable to be constructed in rainy weather, affecting construction efficiency and increasing the work intensity of staff.
The foundation of the prefabricated energy storage compartment pile is adopted, and the support platform is packed through multiple groups of fixed parts and activity parts, and the stable support of steel burial parts is combined with the stable support of steel burials to achieve stitching installation and convenient disassembly.
It has achieved convenient installation in different terrain, avoiding venue and weather restrictions, simplifying the construction process, improving construction efficiency, and reducing the work intensity of staff.
Smart Images

Figure CN222390427U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of prefabricated piles, and more specifically to a prefabricated energy storage cabin pile foundation. Background Art
[0002] The current domestic land transfer procedures for booster station construction are complicated, the construction period is long, and the construction period of booster stations is tight. The size of energy storage containers is the same as that of ordinary containers, and the common ones are 20 feet, 40 feet and 45 feet. Energy storage containers have the characteristics of strong mobility and easy operation. Most of them are standard sizes and are widely used in various scenarios.
[0003] The existing energy storage cabin foundation mainly adopts cast-in-place raft foundation and brick wall construction, which leads to a long construction period for on-site civil engineering. In addition, pouring work cannot be carried out unless it is rainy. This will affect the construction efficiency of the energy storage cabin and seriously delay the construction progress. The cast-in-place raft slab will also increase the workload of the staff. Summary of the invention
[0004] In order to overcome the above-mentioned defects of the prior art, the utility model provides a prefabricated energy storage cabin pile foundation, in which multiple support platforms are spliced and supported by multiple groups of fixed parts and multiple groups of movable parts, and the splicing installation allows workers to install and fix in different terrains, avoiding site and weather restrictions, and is also convenient for workers to disassemble and fix, thereby achieving the effect of convenient transportation. At the same time, the prefabricated components are firmly supported by steel embedded parts to ensure the stability of the prefabricated components. Since the steel embedded parts are movably nested with the fixed piles and movable piles, the workers can also conveniently disassemble and assemble the steel embedded parts, thereby improving the practicality of the utility model to solve the problems arising from the above-mentioned background technology.
[0005] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: a prefabricated energy storage cabin pile foundation, comprising a prefabricated assembly for installing the energy storage cabin;
[0006] The prefabricated assembly includes two groups of fixed parts and multiple groups of movable parts, the multiple groups of movable parts are arranged between the two groups of fixed parts, and support platforms are arranged between adjacent fixed parts and movable parts and between two adjacent movable parts;
[0007] Each set of fixing members includes two fixing piles, which are symmetrically distributed about the central axis of the support platform, and a fixing groove is formed through one side of the fixing pile close to the support platform;
[0008] Each group of movable parts includes two movable piles, which are symmetrically distributed about the central axis of the support platform. A support groove is formed through one side of the movable pile close to the support platform.
[0009] In a preferred embodiment, the bottoms of the fixed piles and movable piles are both provided with steel embedded parts, and the bottoms of the fixed piles and movable piles are both provided with embedding grooves for fitting the steel embedded parts, and the top ends of the steel embedded parts are arranged inside the embedding grooves.
[0010] In a preferred embodiment, the cross-section of the top end of the steel embedded part and the cross-section of the embedding groove are both set to be rectangular, and the outer portion of the top end of the steel embedded part is in contact with the inner wall of the embedding groove.
[0011] In a preferred embodiment, a first positioning hole is formed through the top of the fixed pile on a side away from the support platform, and two second positioning holes are formed through the top of the movable pile on a side away from the support platform, and the two second positioning holes are symmetrically distributed about the central axis of the movable pile.
[0012] In a preferred embodiment, the support platform is provided with an engaging groove on one side close to the first positioning hole and one side close to the second positioning hole.
[0013] In a preferred embodiment, a positioning rod is provided inside each of the first positioning hole and the second positioning hole, a positioning column is installed at one end of the positioning rod close to the support platform, the positioning column extends to the inside of the engaging groove at one end away from the positioning rod, a rubber ring is sleeved on the outside of the positioning rod, the outer diameter of the rubber ring is larger than the diameter of the first positioning hole and the diameter of the second positioning hole; a pull rod is installed at one end of the positioning rod away from the positioning column.
[0014] Technical effects and advantages of the utility model:
[0015] Multiple support platforms are spliced and supported by multiple groups of fixing parts and multiple groups of movable parts, and the spliced installation allows workers to install and fix in different terrains, avoiding site and weather restrictions, and is also convenient for workers to disassemble and fix, achieving the effect of convenient transportation. At the same time, the prefabricated components are firmly supported by steel embedded parts to ensure the stability of the prefabricated components. Since the steel embedded parts are movably nested with the fixed piles and the movable piles, the workers can also conveniently disassemble and assemble the steel embedded parts, thereby improving the practicality of the utility model;
[0016] By connecting the positioning column and the engaging groove, the tightness of the connection between the support platform and the movable pile and the fixed pile can be enhanced, while the up and down movement of the support platform can be avoided, thereby ensuring the stability of the support platform. At the same time, with the help of the easy deformation of the rubber ring, the rubber ring can be deformed and in close contact with the first positioning hole or the second positioning hole, thereby ensuring the stability of the positioning column and avoiding the loosening and separation of the positioning column. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] Figure 1 It is a schematic diagram of the overall structure of the utility model;
[0018] Figure 2This is a top view of the support platform of the utility model;
[0019] Figure 3 This is an exploded view of the fixed pile of the utility model;
[0020] Figure 4 This is a front view of the support platform of the utility model;
[0021] Figure 5 It is a cross-sectional view of a fixed pile of the utility model;
[0022] Figure 6 It is a cross-sectional view of a movable pile of the utility model.
[0023] The accompanying drawings are marked as follows: 1. support platform; 2. fixed pile; 3. fixed groove; 4. movable pile; 5. support groove; 6. embedded steel part; 7. embedded groove; 8. first positioning hole; 9. second positioning hole; 10. embedded groove; 11. positioning rod; 12. positioning column; 13. rubber ring; 14. pull rod. DETAILED DESCRIPTION
[0024] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0025] Refer to the instruction manual Figure 1-6 , the utility model provides a prefabricated energy storage cabin pile foundation, including a prefabricated assembly for installing the energy storage cabin;
[0026] like Figure 1-4 As shown, the prefabricated assembly includes two groups of fixed parts and multiple groups of movable parts, the multiple groups of movable parts are arranged between the two groups of fixed parts, and a support platform 1 is arranged between adjacent fixed parts and movable parts and between two adjacent movable parts;
[0027] Each set of fixing parts includes two fixing piles 2, which are symmetrically distributed about the central axis of the support platform 1, and a fixing groove 3 is penetrated through the side of the fixing pile 2 close to the support platform 1; each set of movable parts includes two movable piles 4, which are symmetrically distributed about the central axis of the support platform 1, and a supporting groove 5 is penetrated through the side of the movable pile 4 close to the support platform 1.
[0028] like Figure 1 and 3As shown, the bottom of the fixed pile 2 and the movable pile 4 are both provided with steel embedded parts 6, and the bottom of the fixed pile 2 and the movable pile 4 are both provided with embedding grooves 7 for inserting the steel embedded parts 6, and the top of the steel embedded parts 6 is arranged inside the embedding groove 7. By embedding the steel embedded parts 6 into the soil layer, the stability of the steel embedded parts 6 can be improved, thereby improving the supporting strength of the steel embedded parts 6 for the prefabricated components, ensuring the stability of the prefabricated components, and avoiding the prefabricated components from tilting and collapsing. The cross-section of the top of the steel embedded parts 6 and the cross-section of the embedding groove 7 are both set to be rectangular, and the outside of the top of the steel embedded parts 6 is in contact with the inner wall of the embedding groove 7. By setting the cross-section of the steel embedded parts 6 and the cross-section of the embedding groove 7 to be rectangular, the steel embedded parts 6 embedded in the soil layer can limit the movable pile 4 and the fixed pile 2, avoiding the movable pile 4 and the fixed pile 2 from rotating, and ensuring the stability of the fixed pile 2 and the movable pile 4.
[0029] like Figure 4-6 As shown, a first positioning hole 8 is formed on the side of the top of the fixed pile 2 away from the support platform 1, and two second positioning holes 9 are formed on the side of the movable pile 4 away from the support platform 1. The two second positioning holes 9 are symmetrically distributed about the central axis of the movable pile 4. Through the provision of the first positioning hole 8 and the second positioning hole 9, it is convenient for the staff to subsequently install the positioning column 12 into the embedded groove 7 through the first positioning hole 8 or the second positioning hole 9 to fix the support platform 1, avoid the support platform 1 from moving up and down, and ensure the stability of the support platform 1. The support platform 1 is provided with an embedded groove 10 on one side close to the first positioning hole 8 and the second positioning hole 9. Through the correspondence between the embedded groove 10 and the first positioning hole 8 or the second positioning hole 9, the staff can embed the positioning column 12 into the embedded groove 10, thereby enhancing the connection stability between the support platform 1 and the movable pile 4 and the fixed pile 2. A positioning rod 11 is provided inside the first and second positioning holes 9, and a positioning column 12 is installed at one end of the positioning rod 11 close to the support platform 1, and the positioning column 12 extends to the inside of the engaging groove 10 at one end away from the positioning rod 11, and a rubber ring 13 is sleeved on the outside of the positioning rod 11, and the outer diameter of the rubber ring 13 is larger than the diameter of the first positioning hole 8 and the diameter of the second positioning hole 9; a pull rod 14 is installed at one end of the positioning rod 11 away from the positioning column 12, and the connection between the positioning column 12 and the engaging groove 10 can enhance the tightness of the connection between the support platform 1 and the movable pile 4 and the fixed pile 2, and at the same time, it can also avoid the support platform 1 from moving up and down, thereby ensuring the stability of the support platform 1, and at the same time, with the help of the easy deformation of the rubber ring 13, the rubber ring 13 can be deformed and in close contact with the first positioning hole 8 or the second positioning hole 9, so as to ensure the stability of the positioning column 12 and avoid the loosening and separation of the positioning column 12.
[0030] By using multiple groups of fixed piles 2 on fixed parts and multiple groups of movable piles 4 on movable parts, multiple support platforms 1 can be spliced and supported, so that workers can install and fix them under different terrains to avoid site and weather restrictions, and the splicing installation can be convenient for workers to disassemble and fix them, thereby achieving the effect of convenient transportation. At the same time, with the help of multiple steel embedded parts 6 embedded in the soil layer, the prefabricated components can be firmly supported to ensure the stability of the prefabricated components. Since the steel embedded parts 6 are movably nested with the fixed piles 2 and the movable piles 4, the workers can also conveniently disassemble and assemble the steel embedded parts 6, thereby improving the practicality of the utility model.
[0031] Finally: The above description is only a preferred embodiment of the present utility model and is not intended to limit the present utility model. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present utility model should be included in the protection scope of the present utility model.
Claims
1. A prefabricated energy storage cabin pile foundation, characterized in that: Includes prefabricated components for installing energy storage compartments; The prefabricated assembly comprises two groups of fixed parts and a plurality of groups of movable parts, the plurality of groups of movable parts are arranged between the two groups of fixed parts, and a support platform (1) is arranged between adjacent fixed parts and movable parts and between two adjacent movable parts; Each set of fixing members comprises two fixing piles (2), the two fixing piles (2) are symmetrically distributed about the central axis of the support platform (1), and a fixing groove (3) is formed through one side of the fixing pile (2) close to the support platform (1); Each group of movable parts comprises two movable piles (4), the two movable piles (4) are symmetrically distributed about the central axis of the support platform (1), and a support groove (5) is provided through one side of the movable pile (4) close to the support platform (1).
2. The prefabricated energy storage cabin pile foundation according to claim 1, characterized in that: The bottoms of the fixed piles (2) and the movable piles (4) are both provided with steel embedded parts (6), and the bottoms of the fixed piles (2) and the movable piles (4) are both provided with embedded grooves (7) for fitting the steel embedded parts (6) to be inserted, and the top ends of the steel embedded parts (6) are arranged inside the embedded grooves (7).
3. The prefabricated energy storage cabin pile foundation according to claim 2 is characterized in that: The cross-section of the top end of the steel embedded part (6) and the cross-section of the embedding groove (7) are both set to be rectangular, and the outer portion of the top end of the steel embedded part (6) is in contact with the inner wall of the embedding groove (7).
4. The prefabricated energy storage cabin pile foundation according to claim 1, characterized in that: A first positioning hole (8) is formed through the top of the fixed pile (2) on a side away from the support platform (1), and two second positioning holes (9) are formed through the top of the movable pile (4) on a side away from the support platform (1). The two second positioning holes (9) are symmetrically distributed about the central axis of the movable pile (4).
5. The prefabricated energy storage cabin pile foundation according to claim 4 is characterized in that: The support platform (1) is provided with an engaging groove (10) on one side close to the first positioning hole (8) and on one side close to the second positioning hole (9).
6. The prefabricated energy storage cabin pile foundation according to claim 5, characterized in that: A positioning rod (11) is provided inside each of the first positioning hole (8) and the second positioning hole (9); a positioning column (12) is installed at one end of the positioning rod (11) close to the support platform (1); an end of the positioning column (12) away from the positioning rod (11) extends to the inside of the fitting groove (10); a rubber ring (13) is sleeved on the outside of the positioning rod (11); the outer diameter of the rubber ring (13) is larger than the diameter of the first positioning hole (8) and the diameter of the second positioning hole (9); A pull rod (14) is installed at one end of the positioning rod (11) away from the positioning column (12).