Air lift drainage bag of pre-pressing water bag
By installing the design of drainage gasbags and one -way valves on the pre -pressing water bottle, the problem of leakage and residual water emissions during the bridge construction process is solved, and rapid drainage is achieved, saving manpower, and improving construction efficiency.
Patent Information
- Application Number
- CN202421031218.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-13
- Publication Date
- 2025-01-28
- Estimated Expiration
- 2034-05-13
AI Technical Summary
During the bridge construction process, pre-pressed water bags are prone to difficulties in discharge of water leakage and residual water during unloading, resulting in large labor consumption and impact on construction progress.
Design a pre -pressure water bottle air -lifting exhaust capsule, through the installation of drainage gasbags on the main body of the water bottle, and set the air pipe and one -way valve on one side. drain.
Effectively prevent the water leakage of the water bottle when receiving water, and quickly drain the water when uninstalling, save manpower, improve the construction efficiency, and shorten the exit time.
Smart Images

Figure CN222412662U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of pre-pressurized water bags, in particular to a pre-pressurized water bag air-lift drainage bag. Background Art
[0002] Pre-pressure water bag is also known as test pressure water bag or pre-pressure water bag. Its products are widely used in the construction of railway and highway bridges, airport terminals. During the bridge construction phase, pre-pressure testing of bridge load is a key task in the inspection of engineering quality compliance. The traditional method is to pile up iron cans or sandbags on the bridge for actual pressure testing. It takes a lot of manpower and material resources to move a large number of these load-bearing items from a low place to the bridge.
[0003] During the construction of roadbed preloading water bags, due to roadbed filling materials, half-cut and half-filled roadbed treatment, mechanical equipment and construction technology, environmental factors and special geological conditions, after the water bag preloading is completed, the preloading ground will be uneven and bumpy, which will easily affect the quality and life of the water bag and leak after being punctured. When the preloading is unloaded, there will be a part of residual water in the water bag, which makes it difficult to discharge the residual water. It needs to be manually drained through a series of methods such as moving, lifting, and squeezing, which increases physical labor and labor consumption, seriously affects the unloading and exit time, and affects the construction progress. Utility Model Content
[0004] In view of the deficiencies of the existing technology in the above-mentioned background technology, the purpose of the utility model is to provide a pre-pressurized water bag air lift drainage bag to prevent water leakage when the pre-pressurized water bag receives water, and to quickly drain water during pre-pressurization unloading, thereby saving manpower, improving efficiency, and shortening the unloading and exit time.
[0005] Compared with the prior art, the technical solution of the utility model is:
[0006] A pre-pressurized water bag air lift drainage bag comprises a drainage air bag body, one side of the drainage air bag body is connected to an air inlet pipe, a one-way valve is fixedly installed on the air inlet pipe, a water bag body is arranged on the drainage air bag body, the top of the water bag body is connected to a water inlet, a water inlet pipe is threadedly connected to the water inlet, and a locking ring is sleeved at the connection between the water inlet and the water inlet pipe.
[0007] As a further solution of the utility model, a mounting seat is installed inside the water inlet, and two groups of the mounting seats are symmetrically arranged along the central axis of the water inlet. A fixing frame is fixedly installed between the two groups of the mounting seats, and a filter is fixed on the fixing frame.
[0008] As a further solution of the present invention, the locking ring includes a locking ring body and a locking washer, the locking washer is fixedly mounted on the locking ring body, and the locking ring body and the locking washer are integrally formed.
[0009] As a further solution of the utility model, a threaded opening is provided on the locking gasket.
[0010] As a further solution of the utility model, limited guardrails are fixed on both sides of the drainage airbag body.
[0011] As a further solution of the utility model, one side of the water bag body is connected to a drain pipe.
[0012] Compared with the prior art, the beneficial effects of the utility model are:
[0013] (1) The utility model has a drainage airbag body, and there are limit guardrails on both sides of the drainage airbag body to prevent the drainage airbag body from rolling. One side of the drainage airbag body is connected to an air inlet pipe, and a one-way valve is fixedly installed on the air inlet pipe. Before the construction of the pre-pressurized water bag, the drainage airbag body is first flattened and laid, and the water bag body is installed on the drainage airbag body. Such an arrangement can prevent the water bag body from being damaged, protect the water bag body, and extend the service life of the water bag body. At the end of the pre-pressurization period, the one-way valve is opened to allow the air inlet pipe to inflate the drainage airbag body. The one-way valve is provided to prevent the gas from escaping, thereby raising the height of one side of the water bag body. When the pre-pressurization is unloaded, the water can be quickly drained, so that no part of the water will remain in the water bag body, saving manpower, improving efficiency, and shortening the unloading and exit time.
[0014] (2) The utility model ensures the sealing performance between the water inlet pipe and the water inlet through the cooperation between the locking ring body and the locking gasket, and can also ensure the tightness between the water inlet pipe and the water inlet.
[0015] (3) The utility model uses a fixing frame fixedly installed between the mounting seats to install the filter screen inside the fixing frame, and uses the filter screen to filter out large particles in the water to prevent sand and gravel from accumulating in the water bag. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Figure 1 It is a schematic diagram of the overall structure of the utility model;
[0017] Figure 2 This is a schematic diagram of the separation of the water bag main body and the exhaust bag of the utility model;
[0018] Figure 3 This is a schematic diagram of the water inlet structure of the utility model;
[0019] Figure 4 It is a schematic diagram of the locking ring of the utility model.
[0020] In the figure: 1- water bag body; 2- water inlet; 3- water inlet pipe; 4- locking ring; 5- drainage airbag body; 6- air inlet pipe; 7- one-way valve; 8- mounting seat; 9- fixing frame; 10- filter screen; 11- locking ring body; 12- locking gasket; 13- limiting guardrail; 14- drainage pipe. DETAILED DESCRIPTION
[0021] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0022] In the description of the present utility model, it should be understood that the terms "center", "longitudinal", "lateral", "length", "width", "thickness", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", "clockwise", "counterclockwise", "axial", "radial", "circumferential" and the like indicate positions or positional relationships based on the positions or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present utility model and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present utility model. In addition, features defined as "first" and "second" may explicitly or implicitly include one or more of the features. In the description of the present utility model, unless otherwise specified, "multiple" means two or more.
[0023] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installation", "connection" and "connection" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0024] Please see attached Figure 1-4A pre-pressurized water bag air-lift drainage bag comprises a drainage air bag body 5, one side of the drainage air bag body 5 is connected to an air inlet pipe 6, a one-way valve 7 is fixedly installed on the air inlet pipe 6, the drainage air bag body 5 is provided with a water bag body 1, the top of the water bag body 1 is connected to a water inlet 2, the water inlet 2 is threadedly connected to a water inlet pipe 3, a locking ring 4 is sleeved at the connection between the water inlet 2 and the water inlet pipe 3, limited guardrails 13 are fixed on both sides of the drainage air bag body 5, and one side of the water bag body 1 is connected to a drainage pipe 14. Before the construction of the pre-pressurized water bag, the drainage air bag body 5 is first flattened and laid, and the water bag body 1 is installed on the drainage air bag body 5. Such a setting can prevent the water bag body 1 from being damaged, protect the water bag body 1, and extend the service life of the water bag body 1. At the end of the pre-pressing period, the one-way valve 7 is opened to allow the air inlet pipe 6 to inflate the drainage airbag 5. The one-way valve 7 prevents the gas from escaping, thereby raising the height of one side of the water bag body 1. During pre-pressing unloading, the water can be drained quickly, so that no water will remain in the water bag body 1, thereby saving manpower, improving efficiency, and shortening the unloading and exit time.
[0025] A mounting seat 8 is installed inside the water inlet 2, and two groups of the mounting seats 8 are symmetrically arranged along the central axis of the water inlet 2. A fixing frame 9 is fixedly installed between the two groups of the mounting seats 8, and a filter screen 10 is fixed on the fixing frame 9. The filter screen 10 is used to filter out impurities in the water to prevent impurities such as sand and gravel from accumulating in the water bag body 1.
[0026] The locking ring 4 includes a locking ring body 11 and a locking washer 12, wherein the locking washer 12 is fixedly mounted on the locking ring body 11, the locking ring body 11 and the locking washer 12 are integrally formed, and a threaded opening is provided on the locking washer 12. The locking washer 12 is locked by passing a bolt through the threaded opening, so that the locking ring body 11 and the locking washer 12 cooperate with each other, thereby ensuring the sealing performance of the water inlet pipe 3 and the water inlet 2, and also ensuring the tightness between the water inlet pipe 3 and the water inlet 2.
[0027] The above description is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can make equivalent replacements or changes within the technical scope disclosed by the present invention according to the technical scheme and the utility model concept of the present invention, which should be covered by the protection scope of the present invention.
Claims
1. A pre-pressurized water bag air lift drainage bag, characterized in that: The invention comprises a drainage airbag body (5), one side of which is connected to an air inlet pipe (6), a one-way valve (7) is fixedly installed on the air inlet pipe (6), a water bag body (1) is arranged on the drainage airbag body (5), the top of the water bag body (1) is connected to a water inlet (2), a water inlet pipe (3) is threadedly connected to the water inlet (2), and a locking ring (4) is sleeved at the connection between the water inlet (2) and the water inlet pipe (3).
2. A pre-pressurized water bag air lift drainage bag according to claim 1, characterized in that: A mounting seat (8) is installed inside the water inlet (2), and two groups of the mounting seats (8) are symmetrically arranged along the central axis of the water inlet (2). A fixing frame (9) is fixedly installed between the two groups of the mounting seats (8), and a filter screen (10) is fixed on the fixing frame (9).
3. A pre-pressurized water bag air lift drainage bag according to claim 1, characterized in that: The locking ring (4) comprises a locking ring body (11) and a locking washer (12); the locking washer (12) is fixedly mounted on the locking ring body (11); and the locking ring body (11) and the locking washer (12) are integrally formed.
4. A pre-pressurized water bag air lift drainage bag according to claim 3, characterized in that: The locking gasket (12) is provided with a threaded opening.
5. The pre-pressurized water bag air lift drainage bag according to claim 1, characterized in that: Limiting guardrails (13) are fixed on both sides of the drainage airbag body (5).
6. A pre-pressurized water bag air lift drainage bag according to claim 1, characterized in that: One side of the water bag body (1) is connected to a drainage pipe (14).