Hoisting mechanism of fan tower drum production workshop
By designing a fan tower lifting mechanism combining clamping device and lifting drive device, the problems of inconvenience and shaking of fan tower lifting are solved, and a fast and firm clamping fixing and balanced lifting process is achieved, which improves safety Sex and reliability.
Patent Information
- Application Number
- CN202421331881.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-12
- Publication Date
- 2025-02-11
- Estimated Expiration
- 2034-06-12
AI Technical Summary
In the prior art, when lifting the fan tower, it is not convenient to tie and fix, and it is easy to shake during lifting and transporting, which poses safety hazards.
A lifting mechanism of the fan tower production workshop is designed, and the clamping device and the lifting drive device are combined to push the clamping rod to rotate through the hydraulic cylinder drive link, and clamping and fixing the fan tower with the clamping plate. The lifting of the lifting rod is achieved through the cooperation of gears and worms, ensuring balance and stability of the fan tower during the lifting process.
It realizes rapid and firm clamping and fixing of the fan tower, avoids inconvenience and shaking during traditional lifting, and improves the safety and reliability of the lifting process.
Smart Images

Figure CN222454322U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of wind turbine tower workshop hoisting, in particular to a hoisting mechanism for a wind turbine tower production workshop. Background Art
[0002] The wind turbine tower is the tower pole for wind power generation. The production of wind turbine tower is generally completed in the production workshop, during which welding technology is required. The flange is welded first, and then the weld is non-destructively tested and the flatness is checked, sandblasted, painted, etc. After the internal parts are installed and the finished product is inspected, it is transported to the installation site before it can be transported to the site for installation. When welding the wind turbine tower in the workshop, since the wind turbine tower is relatively heavy, it needs to be transferred with the help of lifting equipment.
[0003] In the prior art, when hoisting and transferring a tower, the tower is generally tied and fixed by a lifting rope, and then lifted and transported. In practical applications, there are some shortcomings: it is very inconvenient to use the lifting rope to tie and fix the tower, and the tower is cylindrical and not easy to tie. During hoisting and transportation, the lifting rope is easy to shake, and the tower will also shake, which is easy to collide with surrounding objects, which is not safe enough. Therefore, improvements are needed. Utility Model Content
[0004] The technical problem to be solved by the utility model is that in the prior art, it is inconvenient to tie and fix the wind turbine tower when it is hoisted, and it is easy to shake during hoisting and transportation, which poses a safety hazard.
[0005] In order to realize the above functions, the technical scheme adopted by the utility model is as follows: a hoisting mechanism for a wind turbine tower production workshop comprises a frame, a wheel is arranged at the bottom of the frame, a crossbeam is arranged at the top of the frame, a lifting rod is passed through the crossbeam, a tooth row is arranged on the side wall of the lifting rod, a lifting drive device is arranged on the crossbeam, and a clamping device is arranged at the lower end of the lifting rod; the clamping device comprises a connecting frame, the connecting frame is fixedly connected to the lower end of the lifting rod, a connecting plate is fixedly connected to the lower end of the connecting frame, a hydraulic cylinder is arranged between the connecting frame and the connecting plate, the output end of the hydraulic cylinder passes through the connecting plate, an ear plate is arranged on the side wall of the connecting plate, a clamping rod is hinged on the ear plate, a clamping plate is arranged on the lower end of the clamping rod, a connecting block is arranged at the output end of the hydraulic cylinder, a connecting rod is hinged on the connecting block, and the other end of the connecting rod is hingedly connected to the clamping rod, the connecting block is pushed by the hydraulic cylinder, and the connecting rod can push the clamping rod to rotate, and the wind turbine tower can be clamped and fixed by the clamping plate, and the clamping is firm and fast.
[0006] Furthermore, the lifting drive device includes a fixed frame, which is arranged on a cross beam, a connecting shaft is rotated between the fixed frames, a gear is fixedly connected to the connecting shaft, the gear is always meshed with the gear row, a worm wheel is provided at the outer end of the connecting shaft, a fixed plate is provided on the side wall of the fixed frame, a motor is provided on the fixed plate, a worm is provided at the output end of the motor, the worm is meshed with the worm wheel, the worm wheel is driven to rotate by the worm, the gear will mesh with the gear row, so that the lifting rod is lifted and lowered in the cross beam, and the wind turbine tower is hoisted with the help of a clamping device.
[0007] Preferably, a control console is provided on the frame, and the control console is connected with the motor and the hydraulic cylinder via electrical control signals.
[0008] Preferably, an anti-slip pad is provided on the inner wall of the clamping plate.
[0009] Preferably, the tooth row is embedded in the lifting rod.
[0010] The utility model adopts the above structure to achieve the following beneficial effects:
[0011] 1. The utility model can realize the rapid clamping and fixing of the wind turbine tower by arranging the clamping device, thus solving the problem that it is inconvenient to tie and fix the wind turbine tower during the traditional hoisting of the wind turbine tower.
[0012] 2. The utility model can realize the hoisting of the clamped and fixed wind turbine tower by setting a lifting drive device. The two sets of clamping devices can maintain the balance of the hoisting. During the transportation process, there will be no shaking, and the safety factor is high. BRIEF DESCRIPTION OF THE DRAWINGS
[0013] Figure 1 This is an overall stereogram of a hoisting mechanism of a wind turbine tower production workshop of the utility model;
[0014] Figure 2 It is a three-dimensional diagram of a clamping device of a hoisting mechanism in a wind turbine tower production workshop of the utility model;
[0015] Figure 3 for Figure 1 A partial enlarged view of point A in the middle.
[0016] Among them, 1. frame, 2. wheels, 3. crossbeam, 4. lifting rod, 5. gear row, 6. lifting drive device, 7. clamping device, 8. connecting frame, 9. connecting plate, 10. hydraulic cylinder, 11. ear plate, 12. clamping rod, 13. connecting block, 14. connecting rod, 15. splint, 16. fixed frame, 17. coupling, 18. gear, 19. worm gear, 20. fixed plate, 21. motor, 22. worm, 23. anti-slip pad, 24. control console. DETAILED DESCRIPTION
[0017] The technical solution of the utility model will be described clearly and completely below in conjunction with the accompanying drawings. Obviously, the described embodiments are part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments of the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0018] In the description of the present invention, it should be noted that the terms "center", "up", "down", "left", "right", "vertical", "horizontal", "inside", "outside", etc. indicate directions or positional relationships based on the directions or positional relationships shown in the accompanying drawings. They are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific direction, be constructed and operated in a specific direction. Therefore, they cannot be understood as limitations on the present invention.
[0019] like Figure 1-3 The utility model is a hoisting mechanism for a wind turbine tower production workshop, comprising a frame 1, a wheel 2 is arranged at the bottom of the frame 1, a control console 24 is arranged on the frame 1, the control console 24 is connected with the motor 21 and the hydraulic cylinder 10 by electrical control signals, a crossbeam 3 is arranged on the top of the frame 1, a lifting rod 4 is passed through the crossbeam 3, a tooth row 5 is arranged on the side wall of the lifting rod 4, the tooth row 5 is embedded in the lifting rod 4, a lifting drive device 6 is arranged on the crossbeam 3, and a clamping device 7 is arranged at the lower end of the lifting rod 4;
[0020] like Figure 1-2 The clamping device 7 includes a connecting frame 8, which is fixed to the lower end of the lifting rod 4. A connecting plate 9 is fixed to the lower end of the connecting frame 8. A hydraulic cylinder 10 is arranged between the connecting frame 8 and the connecting plate 9. The output end of the hydraulic cylinder 10 passes through the connecting plate 9. An ear plate 11 is arranged on the side wall of the connecting plate 9. A clamping rod 12 is hinged on the ear plate 11. A clamping plate 15 is arranged at the lower end of the clamping rod 12. An anti-slip pad 23 is arranged on the inner wall of the clamping plate 15. A connecting block 13 is arranged at the output end of the hydraulic cylinder 10. A connecting rod 14 is hinged on the connecting block 13. The other end of the connecting rod 14 is hingedly connected to the clamping rod 12. The connecting block 13 is pushed by the hydraulic cylinder 10, and the connecting rod 14 can push the clamping rod 12 to rotate. The wind turbine tower can be clamped and fixed by the clamping plate 15, and the clamping is firm and fast.
[0021] like Figure 1 and 3The lifting drive device 6 includes a fixed frame 16, which is arranged on the beam 3. A connecting shaft 17 rotates between the fixed frames 16. A gear 18 is fixed to the connecting shaft 17. The gear 18 is always meshed with the gear row 5. A worm wheel 19 is provided at the outer end of the connecting shaft 17. A fixed plate 20 is provided on the side wall of the fixed frame 16. A motor 21 is provided on the fixed plate 20. A worm 22 is provided at the output end of the motor 21. The worm 22 is meshed with the worm wheel 19. The worm wheel 19 is driven to rotate by the worm 22, and the gear 18 will mesh with the gear row 5, so that the lifting rod 4 is lifted and lowered in the beam 3. With the help of the clamping device 7, the wind turbine tower can be hoisted.
[0022] During specific use, the vehicle frame 1 is moved across the wind turbine tower by the wheels 2, and the motor 21 is started, so that the worm 22 engages with the worm wheel 19 to rotate, and the worm wheel 19 drives the connecting shaft 17 to rotate, and the connecting shaft 17 drives the gear 18 to rotate, and the gear 18 engages with the lifting rod 4 to move up and down in the crossbeam 3 until the clamping plate 15 is located on both sides of the wind turbine tower, and the hydraulic cylinder 10 is started, and the extension and contraction of the hydraulic cylinder 10 can pull the connecting block 13, and the connecting block 13 will pull the connecting rod 14, and the connecting rod 14 will pull the clamping rod 12 to rotate, and the side wall of the wind turbine tower can be clamped by the clamping plate 15, and then the wind turbine tower is hoisted to a suitable height with the help of the lifting drive device 6, and then it can be transferred and transported, which is very convenient and quick.
[0023] During the transportation process, the lifting rod 4 is a rigid rod and will not shake. The wind turbine tower can be hoisted safely and reliably. When the motor 21 stops, the height of the lifting rod 4 can be kept from decreasing by the reverse locking effect of the worm 22 on the worm wheel 19.
[0024] The above description of the utility model and its implementation methods is not restrictive. The drawings show only one implementation method of the utility model, and the actual structure is not limited thereto. In short, if ordinary technicians in this field are inspired by it and design structural methods and embodiments similar to the technical solution without creativity without departing from the purpose of the invention of the utility model, they should all fall within the protection scope of the utility model.
Claims
1. A hoisting mechanism for a wind turbine tower production workshop, comprising a frame, a wheel is provided at the bottom of the frame, and is characterized in that: A crossbeam is arranged on the top of the frame, a lifting rod is passed through the crossbeam, a tooth row is arranged on the side wall of the lifting rod, a lifting drive device is arranged on the crossbeam, and a clamping device is arranged at the lower end of the lifting rod.
2. The hoisting mechanism for a wind turbine tower production workshop according to claim 1 is characterized in that: The clamping device includes a connecting frame, which is fixedly connected to the lower end of the lifting rod, and a connecting plate is fixedly connected to the lower end of the connecting frame. A hydraulic cylinder is provided between the connecting frame and the connecting plate, and the output end of the hydraulic cylinder passes through the connecting plate. An ear plate is provided on the side wall of the connecting plate, and a clamping rod is hinged on the ear plate. A clamping plate is provided on the lower end of the clamping rod, and a connecting block is provided at the output end of the hydraulic cylinder. A connecting rod is hinged on the connecting block, and the other end of the connecting rod is hingedly connected to the clamping rod.
3. The hoisting mechanism for a wind turbine tower production workshop according to claim 2 is characterized in that: The lifting drive device includes a fixed frame, which is arranged on a crossbeam, a connecting shaft is rotated between the fixed frames, a gear is fixedly connected to the connecting shaft, the gear is always meshed with the gear row, a worm gear is arranged at the outer end of the connecting shaft, a fixed plate is arranged on the side wall of the fixed frame, a motor is arranged on the fixed plate, a worm is arranged at the output end of the motor, and the worm is meshed with the worm gear.
4. The hoisting mechanism for a wind turbine tower production workshop according to claim 3 is characterized in that: The frame is provided with a control console, which is connected with the motor and the hydraulic cylinder by electrical control signals.
5. The hoisting mechanism for a wind turbine tower production workshop according to claim 4 is characterized in that: An anti-slip pad is arranged on the inner wall of the clamping plate.
6. The hoisting mechanism for a wind turbine tower production workshop according to claim 5, characterized in that: The tooth row is embedded in the lifting rod.