Pay-off rack for house building construction

By designing a stable support structure on the wire laying frame for building construction, the problem of traditional wire laying frames falling when the power pulling force is too large is solved, the stability and construction efficiency of the wire laying process are improved, and safety risks are reduced and maintenance costs.

CN222475734UActive Publication Date: 2025-02-14FUJIAN SOUTHEAST DESIGN GRP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421369401.X
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-06-17
Publication Date
2025-02-14
Estimated Expiration
2034-06-17

AI Technical Summary

Technical Problem

Traditional wire laying frames are prone to dump when the power pulls too much, resulting in interruption of wire laying operations, affecting construction progress and efficiency, and increasing labor costs and safety risks.

Method used

A wire laying frame for building construction was designed. By welding the bearings on the chassis and installing the bearing plates and connecting parts on the cable posts, combining the installation of the butt columns, top plates, crossbars and supporting feet, a stable Support structure and reduce dumping risk.

Benefits of technology

This design makes the wire laying frame more stable during the wire laying process, reduces the risk of dumping, improves the efficiency and safety of construction, and reduces interruption and maintenance costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222475734U_ABST
    Figure CN222475734U_ABST
Patent Text Reader

Abstract

The utility model belongs to the technical field of pay-off racks, and particularly relates to a pay-off rack for house building construction, which comprises a base plate, a bearing welded on the surface of the base plate, a wire sleeving column fixedly mounted in an inner ring of the bearing, wire bearing discs movably sleeved on the outer wall of the wire sleeving column, and two groups of bolts respectively arranged at the bottoms of the two wire bearing discs close to the upper end of the wire sleeving column. A lead plate is fixedly mounted on one side of the chassis; the top end of the wire sleeving column is connected with a connecting piece, the top end of the connecting piece is connected with a butt-joint column, and the top end of the butt-joint column is fixedly provided with a top plate. Wire coils for building construction are sequentially sleeved on the wire sleeving column, the bottoms of the wire coils for building construction are carried on the wire bearing disc, and then the bottom of the connecting piece is in butt joint with the top of the wire sleeving column; in this way, the top plate, the cross rod and the supporting legs can be installed around the base plate through the butt joint columns, the whole device can be supported in three directions through the top plate, the cross rod and the supporting legs in the using process, and therefore the device is more stable in the paying-off process.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the technical field of wire-laying frames, and in particular relates to a wire-laying frame used for building construction. Background Art

[0002] Housing construction, also known as housing construction engineering, is an architectural term that refers to various types of housing buildings and their ancillary facilities and the supporting lines, pipelines, equipment installation projects and indoor and outdoor decoration projects. It covers the various technical work such as survey, planning, design, construction, installation and maintenance for the construction, reconstruction or expansion of housing buildings and ancillary structures and the completed engineering entities. Specifically, housing construction includes multiple stages and links, such as foundation construction, main structure construction, roofing construction, decoration construction, etc. During the construction process, various building materials, machinery and equipment will be used, and production activities will be carried out according to specific design blueprints. This requires construction workers to use their ingenuity and creatively apply theories such as materials, mechanics, structure, and technology to solve technical problems that continue to arise in construction, and ensure project quality and construction safety.

[0003] In the process of building construction, wire laying is a crucial link, which is usually carried out with the help of a wire payout frame. However, traditional wire payout frames often face a significant problem during operation: when the force of the electric pull is too large, the wire payout frame is prone to tipping over, which will not only directly lead to the forced interruption of the wire laying operation, but also have a chain reaction on the overall construction process, thus affecting the construction progress and efficiency. When the wire payout frame topples over, the construction personnel need to suspend the current operation and reset or repair the wire payout frame. Such an interruption not only wastes precious time resources, but may also increase additional labor costs and safety risks. At the same time, if this situation occurs frequently, it will also have an adverse impact on the overall progress and quality of the project, and may even cause safety accidents. Utility Model Content

[0004] The purpose of the utility model is to provide a wire pay-off stand for building construction, aiming to solve the problem that when the pulling force of the electric power is too large, the wire pay-off stand is prone to tipping over, which will not only directly lead to the forced interruption of the wire-laying operation, but also produce a chain reaction on the overall construction process, thereby affecting the construction progress and efficiency. When the wire pay-off stand tips over, the construction personnel need to suspend the current operation and reset or repair the wire pay-off stand. Such an interruption not only wastes precious time resources, but may also increase additional labor costs and safety risks. At the same time, if this situation occurs frequently, it will also have an adverse impact on the overall progress and quality of the project, and may even cause safety accidents.

[0005] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: a wire-laying frame for building construction, comprising a chassis, a bearing is welded on the surface of the chassis, a wire-laying column is fixedly installed in the inner ring of the bearing, a wire-receiving disc is movably sleeved on the outer wall of the wire-receiving column, two groups of bolts are respectively arranged at the bottom of two wire-receiving discs near the upper end of the wire-receiving column, and a lead plate is fixedly installed on one side of the chassis;

[0006] The top of the wire sleeve column is connected to a connector, the top of the connector is connected to a docking column, the top of the docking column is fixedly installed with a top plate, three cross bars are evenly spaced on the outer wall of the top plate, and a supporting foot is welded to one end of each cross bar.

[0007] In order to enable the wire column to be clamped inside the connecting piece, as a preferred embodiment of the utility model of a wire-laying frame for building construction, four clamping plates are welded at equal intervals on the top of the wire column.

[0008] In order to connect the connecting piece between the wire sleeve column and the docking column, as a preferred embodiment of the utility model for a wire pay-out frame for building construction, the bottom center end of the connecting piece is provided with a socket, the inner wall of the socket is provided with a bayonet extending to the inside of the wire sleeve column, the top center end of the connecting piece is provided with an inner cavity, and the inner wall of the inner cavity is provided with an annular groove.

[0009] In order to prevent the wire column from rotating when installed inside the socket, as a preferred embodiment of the utility model for a wire pay-off rack for building construction, the sizes of the socket and the bayonet are adapted to the sizes of the end of the wire column and the clamping plate.

[0010] In order to prevent the rotating column from being detached when installed inside the inner cavity, as a preferred embodiment of the utility model for a wire pay-out frame for building construction, a rotating column is installed inside the inner cavity, a circular ring is fixedly sleeved on the outer wall of the rotating column, and the top of the rotating column is fixedly installed on the bottom of the docking column.

[0011] In order to enable the connecting piece to rotate on the outer wall of the ring, as a preferred wire-laying frame for building construction of the utility model, the outer wall of the ring is in active contact with the inner wall of the ring groove, and the rotating column forms a rotating structure through the ring, the ring groove and the inner cavity.

[0012] Compared with the prior art, the beneficial effects of the utility model are:

[0013] By sequentially putting the wire reels for building construction on the wire-covering columns, and placing the bottom of the wire reels for building construction on the wire-receiving reel, and then docking the bottom of the connector with the top of the wire-covering column, the docking column can install the top plate, crossbars and support legs around the chassis. When in use, the top plate, crossbars and support legs can support the entire device in three directions, thereby making the device more stable when laying out the wires and reducing the risk of tipping over. BRIEF DESCRIPTION OF THE DRAWINGS

[0014] The accompanying drawings are used to provide a further understanding of the present invention and constitute a part of the specification. Together with the embodiments of the present invention, they are used to explain the present invention and do not constitute a limitation of the present invention. In the accompanying drawings:

[0015] Figure 1 This is a schematic diagram of the main structure of the utility model;

[0016] Figure 2 This is a schematic diagram of the structure of the connecting end of the sleeve pole of the utility model when viewed from above;

[0017] Figure 3 This is a schematic diagram of the jack structure of the utility model;

[0018] Figure 4 This is a schematic diagram of the cross-sectional structure of the connector of the utility model;

[0019] Figure 5 This is a schematic diagram of the ring groove structure of the utility model.

[0020] In the figure: 1. chassis; 2. bearing; 3. wire sleeve column; 301. clamping plate; 4. wire receiving drum; 5. bolt; 6. lead plate; 7. connector; 701. socket; 702. bayonet; 703. inner cavity; 704. ring groove; 8. docking column; 801. rotating column; 802. ring; 9. top plate; 10. cross bar; 11. supporting foot. DETAILED DESCRIPTION

[0021] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0022] See also Figure 1-5 The utility model provides the following technical solutions: a wire-laying frame for building construction, comprising a chassis 1, a bearing 2 is welded on the surface of the chassis 1, a wire-sleeving column 3 is fixedly installed in the inner ring of the bearing 2, a wire-receiving disc 4 is movably sleeved on the outer wall of the wire-receiving column 3, two sets of bolts 5 are respectively arranged at the bottom of two wire-receiving discs 4 near the upper end of the wire-receiving column 3, and a lead plate 6 is fixedly installed on one side of the chassis 1;

[0023] The chassis 1, the bearing 2, the wire-sleeving column 3 and the wire-receiving drum 4 constitute a wire-paying frame for building construction of the present technical solution. When in use, the three groups of coils are placed in sequence on the wire-sleeving columns 3 corresponding to the wire-receiving drum 4, and then the ends of the coils are passed through the lead plate 6. In this way, when the wires used for building construction are pulled, the wires can be spread out in circles, thereby playing the role of paying out the wires.

[0024] The top of the wire column 3 is connected to a connector 7, the top of the connector 7 is connected to a docking column 8, the top of the docking column 8 is fixedly installed with a top plate 9, three cross bars 10 are evenly spaced on the outer wall of the top plate 9, and a supporting foot 11 is welded to one end of each cross bar 10.

[0025] Preferably, four clamping plates 301 are welded at equal intervals on the top of the wire-covering column 3 . The sizes of the jack 701 and the clamping port 702 match the sizes of the end of the wire-covering column 3 and the clamping plates 301 .

[0026] During specific use, four bayonet holes 702 are also provided in the jack 701 , and the angle between each bayonet hole 702 is the same as the angle between each clamping plate 301 . During installation, the clamping plate 301 and the bayonet holes 702 are in a mortise and tenon structure.

[0027] Preferably, a plug hole 701 is provided at the bottom center end of the connector 7, a bayonet 702 extending to the inside of the sleeve column 3 is provided on the inner wall of the plug hole 701, an inner cavity 703 is provided at the top center end of the connector 7, and an annular groove 704 is provided on the inner wall of the inner cavity 703. A rotating column 801 is installed inside the inner cavity 703, a circular ring 802 is fixedly sleeved on the outer wall of the rotating column 801, and the top of the rotating column 801 is fixedly installed at the bottom of the docking column 8. The outer wall of the circular ring 802 is in active contact with the inner wall of the annular groove 704, and the rotating column 801 forms a rotating structure with the inner cavity 703 through the circular ring 802 and the annular groove 704.

[0028] When in use, the docking column 8 can be rotated inside the inner cavity 703 through the rotating column 801 and the ring 802, so that the positions of the three supporting legs 11 can be adjusted according to the placement requirements;

[0029] In addition, the thread post 3 can also drive the connecting member 7 to rotate on the outer wall of the ring 802 through the clamping plate 301, so that the thread post 3 can be rotated when in use.

[0030] Working principle: When in use, place three sets of coils for house construction on the wire receiving plate 4 on the wire column 3 in sequence, then align the jack 701 and the bayonet 702 at the bottom of the connector 7 with the end of the wire column 3 and the four clamping plates 301, and adjust the connector 7 downward to make the jack 701 and the bayonet 702 dock with the end of the wire column 3 and the four clamping plates 301;

[0031] In this way, the connecting piece 7 can be installed on the wire-sleeving column 3. Since the docking column 8 and the top plate 9 are installed inside the connecting piece 7 through the rotating column 801 and the ring 802, the top plate 9 will also be installed on the connecting piece 7. At the same time, the three groups of cross bars 10 and the supporting feet 11 around the top plate 9 will also be supported around the chassis 1. Therefore, when pulling the coil used for building construction, the supporting feet 11 will enhance the stability of the wire-releasing device, so that the device can be better used.

[0032] Finally, it should be noted that the above description is only a preferred embodiment of the utility model and is not intended to limit the utility model. Although the utility model is described in detail with reference to the above embodiments, those skilled in the art can still modify the technical solutions recorded in the above embodiments or replace some of the technical features therein by equivalents. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the utility model shall be included in the protection scope of the utility model.

Claims

1. A wire-laying frame for building construction, comprising a chassis (1), characterized in that: A bearing (2) is welded on the surface of the chassis (1); a wire-sleeving column (3) is fixedly installed in the inner ring of the bearing (2); a wire-receiving plate (4) is movably sleeved on the outer wall of the wire-sleeving column (3); two groups of bolts (5) are respectively arranged at the bottom of two wire-receiving plates (4) near the upper end of the wire-sleeving column (3); and a lead plate (6) is fixedly installed on one side of the chassis (1); The top end of the wire sleeve column (3) is connected to a connecting piece (7), the top end of the connecting piece (7) is connected to a docking column (8), the top end of the docking column (8) is fixedly mounted with a top plate (9), three cross bars (10) are evenly spacedly mounted on the outer wall of the top plate (9), and a supporting foot (11) is welded to one end of each cross bar (10).

2. The wire rack for building construction according to claim 1, characterized in that: Four clamping plates (301) are welded at equal intervals on the top of the wire sleeve column (3).

3. The wire rack for building construction according to claim 1, characterized in that: The bottom center end of the connecting piece (7) is provided with an insertion hole (701), the inner wall of the insertion hole (701) is provided with a bayonet (702) extending to the inside of the sleeve pole (3), the top center end of the connecting piece (7) is provided with an inner cavity (703), and the inner wall of the inner cavity (703) is provided with an annular groove (704).

4. The wire rack for building construction according to claim 3, characterized in that: The sizes of the insertion hole (701) and the bayonet (702) are matched with the sizes of the end of the sleeve pole (3) and the clamping plate (301).

5. The wire rack for building construction according to claim 3, characterized in that: A rotating column (801) is installed inside the inner cavity (703), a circular ring (802) is fixedly sleeved on the outer wall of the rotating column (801), and the top of the rotating column (801) is fixedly installed on the bottom of the docking column (8).

6. The wire rack for building construction according to claim 5, characterized in that: The outer wall of the circular ring (802) is in active contact with the inner wall of the annular groove (704), and the rotating column (801) forms a rotating structure with the inner cavity (703) through the circular ring (802) and the annular groove (704).