Mud powder sieve for quarry
By simulating up and down jitter and quantitative discharge in the screening equipment of the quarry, the screening mesh clogging and waste caused by wet stones is solved, and the screening efficiency and efficiency are improved.
Patent Information
- Application Number
- CN202420323432.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-02-21
- Publication Date
- 2025-03-04
- Estimated Expiration
- 2034-02-21
AI Technical Summary
During the sieving process of the quarry, wet stones cause the screen to be blocked, which requires manual cleaning, affecting efficiency, and wet soil and dust stick to the rock, resulting in smaller rocks being removed and waste.
A mud powder screen for quarry was designed to speed up the screening speed by simulating up and down shaking to avoid mesh blockage, and to prevent blockage by quantitative discharge.
It improves screening efficiency, avoids the need for manual cleaning and blocking mesh, reduces waste, and ensures effective classification of stones.
Smart Images

Figure CN222551327U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of stone mining, in particular to a mud powder screen for a quarry. Background Art
[0002] A quarry is a place dedicated to mining stones. It mainly extracts stones from underground or rocks for use in construction, road construction, concrete manufacturing, etc. During the quarrying process, screening equipment is needed to classify stones of different sizes.
[0003] According to a mud powder screen for quarries with application number 202320613991.5, this solution effectively solves the problem that during actual screening, water is needed to moisten rocks and the like during mining to facilitate drilling. At this time, the soil and dust on the bottom rocks will stick to the rocks, making it difficult to make these adhered soil and dust fall off during actual screening. At the same time, during screening, some smaller rocks will also stick to large rocks through the moist soil. These smaller rocks are easily removed during screening due to their small size, resulting in waste.
[0004] However, the following problems still exist in the operation of this solution:
[0005] (1) In the above scheme, only multiple screens can be used to screen the stones during operation. However, during the screening process, the stones are wet, which may cause the mesh of the screen to become clogged, and manual clearing is required, which affects the overall screening efficiency.
[0006] (2) During the screening process, when the amount that the screen can screen is lower than the discharge amount, blockage will occur during the discharge of stones and the problem of unmanageable blockage will occur. Utility Model Content
[0007] In view of the deficiencies in the prior art, the utility model provides a mud powder screen for a quarry, which has the advantages of simulating up and down shaking to speed up screening and quantitative discharge, and solves the problems raised in the background technology.
[0008] The utility model provides the following technical solutions: a mud powder screen for a quarry comprises an equipment shell, two sides of an inner wall of the equipment shell are respectively fixedly installed with fixed blocks, the sides of the fixed blocks are fixedly connected with an extension sleeve, a first connecting shaft is fixedly clamped inside the extension sleeve, a first connecting block is movably connected with a first connecting block on the surface of the first connecting shaft, a first connecting column is fixedly connected with a side of the first connecting block, a fixed shell is fixedly installed on the other side of the first connecting column, a circular hole is opened on the side of the fixed shell, and a second connecting column is fitted inside the circular hole, a second connecting block is fixedly connected with the side of the second connecting column, a second connecting shaft is fitted inside the second connecting block, a mounting block is fixedly connected with the surface of the second connecting shaft, and a large-aperture screen is inserted on the side of the mounting block.
[0009] Preferably, the top of the equipment housing is fixedly connected to a connecting sleeve, the top of the connecting sleeve is fixedly connected to a feeding shell, the interior of the connecting sleeve is fixedly clamped with a connecting cross plate, the interior of the connecting cross plate is fixedly installed with a conveying pipe, the bottom of the connecting cross plate is fixedly installed with a damping rod, the surface of the damping rod is fixedly connected to an anti-slip plate, the surface of the damping rod is fitted with a sealing plate, the top of the sealing plate is fitted with a conveying pipe, and the upper surface of the sealing plate is fixedly connected to a second cylinder and a second spring.
[0010] Preferably, a connecting disc is attached to the inner wall of the fixed sleeve, and a second connecting column is fixedly connected to the side surface of the connecting disc.
[0011] Preferably, a first spring is fixedly mounted on one side of the inner wall of the fixed sleeve, and a connecting disc is fixedly connected to the side surface of the first spring.
[0012] Preferably, two first cylinders are fixedly connected to the bottom end of the interior of the device housing, and small-aperture screens are attached to the tops of the two first cylinders.
[0013] Preferably, a trigger rod is attached to the bottom of the large-aperture screen, and a medium-aperture screen is fixedly connected to the bottom of the trigger rod.
[0014] Compared with the prior art, the utility model has the following beneficial effects:
[0015] 1. The quarry uses a mud powder screen, and the small-aperture screen is lifted by the first cylinder. At the same time, the trigger rods inside the small-aperture screen and the medium-aperture screen are triggered, and then the medium-aperture screen is lifted by the small-aperture screen, and the large-aperture screen is lifted by the medium-aperture screen. In the process of lifting, the second connecting block on the surface of the second connecting column inside the mounting block on both sides of the small-aperture screen, the medium-aperture screen and the large-aperture screen rotates, and in the process of rotating, the connecting disc fixedly connected to the second connecting column on the side of the second connecting block squeezes the first spring, and at the same time, the first connecting block fixedly installed by the first connecting column on the side of the fixed housing rotates on the surface of the first connecting shaft, so that the small-aperture screen, the medium-aperture screen and the large-aperture screen are in an up and down swing state, so that the internal stones are quickly screened. In the whole operation, the screening speed is accelerated by the simulated shaking method to avoid the clogging of the screening mesh due to the wetting of the stone during the screening process, and then there is no need to manually clean the clogged mesh, and the overall screening efficiency is higher.
[0016] 2. The quarry uses a mud powder screen, and the second cylinder pushes the sealing plate. During the pushing process, the second spring on the top of the sealing plate is stretched, and during the stretching process, the sealing plate drives the damping rod to contract, so that the sealing plate and the conveying pipe are in a non-fitting state, and then the feeding shell enters the connecting shell. The stone on the top of the connecting cross plate falls, and then the second cylinder contracts to control the sealing plate to be retracted to block the conveying pipe. The whole operation process can effectively achieve the effect of timed discharge, and thus in the process of discharge, it can avoid blockage caused by the discharge volume being greater than the processing volume and being unable to screen. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] Figure 1 This is a schematic diagram of the overall structure of the utility model device;
[0018] Figure 2 For this utility model Figure 1 Schematic diagram of the local structure;
[0019] Figure 3 For this utility model Figure 1 Schematic diagram of some structures;
[0020] Figure 4 It is a schematic diagram of the internal structure of the connecting sleeve of the utility model.
[0021] In the figure: 1. Equipment casing; 2. Connecting sleeve; 3. Feeding shell; 4. Large-aperture screen; 5. First cylinder; 6. Trigger rod; 7. Damping rod; 8. Anti-slip plate; 9. Fixed block; 10. Extension sleeve; 11. First connecting shaft; 12. First connecting block; 13. First connecting column; 14. Fixed sleeve; 15. First spring; 16. Connecting disc; 17. Second connecting column; 18. Second connecting block; 19. Second connecting shaft; 20. Mounting block; 21. Connecting cross plate; 22. Delivery pipe; 23. Second cylinder; 24. Sealing plate; 25. Second spring. DETAILED DESCRIPTION
[0022] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0023] See also Figure 1-4A mud powder screen for a quarry comprises an equipment shell 1, on both sides of the inner wall of the equipment shell 1 are fixedly installed fixed blocks 9, the side of the fixed block 9 is fixedly connected with an extension shell 10, the interior of the extension shell 10 is fixedly clamped with a first connecting shaft 11, the surface of the first connecting shaft 11 is movably connected with a first connecting block 12, the side of the first connecting block 12 is fixedly connected with a first connecting column 13, the other side of the first connecting column 13 is fixedly installed with a fixed shell 14, a circular hole is opened on the side of the fixed shell 14, and a second connecting column 17 is fitted inside the circular hole, a second connecting block 18 is fixedly connected to the side of the second connecting column 17, a second connecting shaft 19 is fitted inside the second connecting block 18, and a mounting block 20 is fixedly connected to the surface of the second connecting shaft 19, and the mounting A large-aperture screen 4 is inserted into the side of the mounting block 20. During the jacking process, the second connecting block 18 on the surface of the second connecting shaft 19 inside the mounting block 20 on both sides of the small-aperture screen, the medium-aperture screen and the large-aperture screen 4 rotates, and during the rotation, the connecting disc 16 fixedly connected to the second connecting column 17 on the side of the second connecting block 18 squeezes the first spring 15, and at the same time, the first connecting block 12 fixedly installed on the first connecting column 13 on the side of the fixed housing 14 rotates on the surface of the first connecting shaft 11, thereby making the small-aperture screen, the medium-aperture screen and the large-aperture screen 4 swing up and down, so that the internal stones can be quickly screened. During the entire operation, the screening speed is accelerated by means of simulated shaking to avoid the screening process caused by the wetting of stones. The mesh of the screening is clogged, and there is no need to manually clean the clogged mesh, so the overall screening efficiency is higher. The top of the equipment shell 1 is fixedly connected to a connecting shell 2, and the top of the connecting shell 2 is fixedly connected to a feeding shell 3. The interior of the connecting shell 2 is fixedly clamped with a connecting transverse plate 21, and the interior of the connecting transverse plate 21 is fixedly installed with a conveying pipe 22. The bottom of the connecting transverse plate 21 is fixedly installed with a damping rod 7, and the surface of the damping rod 7 is fixedly connected with an anti-slip plate 8. The surface of the damping rod 7 is attached with a blocking plate 24, and the top of the blocking plate 24 is attached with a conveying pipe 22. The upper surface of the blocking plate 24 is fixedly connected with a second cylinder 23 and a second spring 25, and the blocking plate 24 is pushed up by the second cylinder 23. During the pushing process, the second spring 25 on the top of the blocking plate 24 forms The plugging plate 24 is stretched, and during the stretching process, the blocking plate 24 drives the damping rod 7 to contract, thereby making the blocking plate 24 and the conveying pipe 22 in a non-fitting state, and then the feeding shell 3 enters the connecting sleeve 2, and the stones on the top of the connecting cross plate 21 inside the connecting sleeve 2 fall down, and then the second cylinder 23 contracts to control the blocking plate 24 to be retracted to block the conveying pipe 22. The effect of timed discharge can be effectively achieved during the whole operation, and then in the process of discharge, it can avoid the blockage caused by the discharge amount being greater than the processing amount and being unable to be screened. The inner wall of the fixed sleeve 14 is fitted with a connecting disc 16, and the side of the connecting disc 16 is fixedly connected to the second connecting column 17. One side of the inner wall of the fixed sleeve 14 is fixedly installed with a first spring 15, and the side of the first spring 15 is fixedly connected with a connecting disc 16.Two first cylinders 5 are fixedly connected to the bottom of the device housing 1, and a small-aperture screen is attached to the top of the two first cylinders 5. A trigger rod 6 is attached to the bottom of the large-aperture screen 4, and a medium-aperture screen is fixedly connected to the bottom of the trigger rod 6.
[0024] Working principle: During the operation, the operator uses the second cylinder 23 to push the blocking plate 24. During the pushing process, the second spring 25 on the top of the blocking plate 24 is stretched, and during the stretching process, the blocking plate 24 drives the damping rod 7 to contract, so that the blocking plate 24 and the conveying pipe 22 are not in a fitting state, and then the feeding shell 3 enters the connecting cross plate 21 inside the connecting sleeve 2, and the stones on the top fall down, and then the second cylinder 23 contracts to control the blocking plate 24 to be retracted to block the conveying pipe 22 to achieve the purpose of timed discharge. At the same time, the small-aperture screen is lifted by the first cylinder 5, and the trigger rod 6 inside the small-aperture screen and the medium-aperture screen is triggered during the lifting, and then The medium-aperture sieve is lifted up by the small-aperture sieve, and the large-aperture sieve 4 is lifted up by the medium-aperture sieve. During the lifting process, the second connecting block 18 on the surface of the second connecting shaft 19 inside the mounting block 20 on both sides of the small-aperture sieve, the medium-aperture sieve and the large-aperture sieve 4 rotates. During the rotation, the connecting disc 16 fixedly connected to the second connecting column 17 on the side of the second connecting block 18 squeezes the first spring 15, and at the same time, the first connecting block 12 fixedly installed on the first connecting column 13 on the side of the fixed shell 14 rotates on the surface of the first connecting shaft 11, thereby making the small-aperture sieve, the medium-aperture sieve and the large-aperture sieve 4 swing up and down, so that the stones inside can be quickly screened.
[0025] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device.
[0026] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A mud powder screen for quarry, characterized in that: The invention comprises an equipment shell (1), wherein fixing blocks (9) are fixedly installed on both sides of the inner wall of the equipment shell (1), an extension sleeve (10) is fixedly connected to the side of the fixing block (9), a first connecting shaft (11) is fixedly clamped inside the extension sleeve (10), a first connecting block (12) is movably connected to the surface of the first connecting shaft (11), a first connecting column (13) is fixedly connected to the side of the first connecting block (12), a fixing sleeve (14) is fixedly installed on the other side of the first connecting column (13), a circular hole is opened on the side of the fixing sleeve (14), and a second connecting column (17) is fitted inside the circular hole, a second connecting block (18) is fixedly connected to the side of the second connecting column (17), a second connecting shaft (19) is fitted inside the second connecting block (18), a mounting block (20) is fixedly connected to the surface of the second connecting shaft (19), and a large-aperture screen (4) is inserted into the side of the mounting block (20).
2. The quarry mud powder screen according to claim 1, characterized in that: The top of the equipment housing (1) is fixedly connected to a connecting sleeve (2), the top of the connecting sleeve (2) is fixedly connected to a feed shell (3), the interior of the connecting sleeve (2) is fixedly clamped with a connecting transverse plate (21), the interior of the connecting transverse plate (21) is fixedly installed with a conveying pipe (22), the bottom of the connecting transverse plate (21) is fixedly installed with a damping rod (7), the surface of the damping rod (7) is fixedly connected to an anti-slip plate (8), the surface of the damping rod (7) is bonded with a blocking plate (24), the top of the blocking plate (24) is bonded with a conveying pipe (22), and the upper surface of the blocking plate (24) is fixedly connected to a second cylinder (23) and a second spring (25).
3. The mud powder screen for quarry according to claim 1, characterized in that: A connecting disc (16) is attached to the inner wall of the fixed sleeve (14), and a second connecting column (17) is fixedly connected to the side surface of the connecting disc (16).
4. The mud powder screen for quarry according to claim 1, characterized in that: A first spring (15) is fixedly mounted on one side of the inner wall of the fixed sleeve (14), and a connecting disc (16) is fixedly connected to the side surface of the first spring (15).
5. The mud powder screen for quarry according to claim 1, characterized in that: Two first cylinders (5) are fixedly connected to the bottom end of the interior of the device housing (1), and small-aperture screens are attached to the tops of the two first cylinders (5).
6. The mud powder screen for quarry according to claim 1, characterized in that: A trigger rod (6) is attached to the bottom of the large-aperture screen (4), and a medium-aperture screen is fixedly connected to the bottom of the trigger rod (6).
Citation Information
Patent Citations
Mud powder sieve for quarry
CN219899009U