Bridge cantilever casting hanging basket prepressing system

By using water bags and water bags in the bridge suspension hanging basket prepressing system, equipped with an infusion subsystem and a high-energy compound ignition device, the problems of inaccurate load control and slow accident response in the traditional hanging basket prepressing method are solved, precise control and rapid response of loads are achieved, and recycling is economical.

CN222557440UActive Publication Date: 2025-03-04GUANGDONG GUANYUE HIGHWAY & BRIDGE +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420443925.2
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-07
Publication Date
2025-03-04
Estimated Expiration
2034-03-07

AI Technical Summary

Technical Problem

The traditional hanging basket prepression method requires a large number of concrete prefabricated blocks, with high site requirements, low working efficiency, and difficult to accurately control pressure.

Method used

A bridge suspension hanging basket prepress system including water bags and water bags is used to transport water bags and water bags to apply loads through the infusion subsystem. Both the water bag and the water bag are equipped with a check valve and a flowmeter to ensure accurate load control. The water bag is also equipped with high-energy compounds and a ignition device, which can quickly discharge water from the water bag for emergency unloading.

Benefits of technology

It realizes precise control of load, can quickly respond to abnormal situations in the hanging basket, and prevent major accidents. Compared with traditional methods, the recycling of water bags and water bags is more convenient and economical.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222557440U_ABST
    Figure CN222557440U_ABST
Patent Text Reader

Abstract

The utility model relates to a pre-pressing system for a bridge cantilever casting hanging basket. The bridge suspended pouring hanging basket pre-pressing system comprises at least two water bags used for being arranged on a bottom die platform of a hanging basket, a plurality of water bags used for being hung on a front lower cross beam and a rear lower cross beam of the hanging basket, and a liquid conveying subsystem used for conveying water into the water bags and the water bags. According to the bridge cantilever casting hanging basket prepressing system, the load applied to the hanging basket is easy to control, and after prepressing is completed, compared with traditional concrete precast blocks, water bags, water bags and the like are more convenient to recycle and good in economical efficiency.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of road and bridge construction, in particular to a bridge suspended pouring hanging basket preloading system. Background Art

[0002] Traditional hanging basket preloading uses concrete precast blocks to apply loads, which requires a large number of concrete precast blocks, has high site requirements, low work efficiency, is time-consuming and labor-intensive, and is difficult to accurately control the pressure. Utility Model Content

[0003] In view of the above problems, the present utility model is proposed to provide a bridge suspended casting hanging basket preloading system that overcomes the above problems or at least partially solves the above problems.

[0004] The bridge suspended casting hanging basket preloading system includes at least two water bags arranged on the bottom mold platform of the hanging basket, a plurality of water bags hung on the front lower beam and the rear lower beam of the hanging basket, and an infusion subsystem for conveying water to each water bag and each water bag;

[0005] The infusion subsystem includes a first liquid channel connecting a water source and a water inlet of a corresponding water bag, a second liquid channel connecting a water source and a water inlet of a corresponding water bag, a first water pump for promoting water from the water source to enter the corresponding water bag through the first liquid channel, and a second water pump for promoting water from the water source to enter the corresponding water bag through the second liquid channel, and both the first liquid channel and the second liquid channel are equipped with a check valve and a flow meter;

[0006] The water bag comprises a water bag body, and a webbing net adhered to the outer surface of the water bag body and the outer surface of the top; the water bag body is generally rectangular when the inside is filled with fluid, and the water bag further comprises a plurality of straps fixedly connected to the portions of the webbing net adhered to the outer surface of the water bag body, and the straps are used to fix the water bag filled with fluid on the bottom mold platform; the top of the water bag body is provided with an air hole, and the water bag further comprises an air channel connected to the air hole, and the air channel is provided with a regulating valve;

[0007] The water bag comprises a water bag body and a sling group surrounding the water bag body; the lower ends of the slings of the sling group are fixed to the same circular ring bearing member, and the upper ends of the slings are connected to the sling buckle; the outer surface of the water bag body surrounded by the circular ring bearing member is attached with a reinforcing film, and the reinforcing film and the outer surface of the water bag body together form an arc-shaped space in a superior arc shape, and a high-energy compound and an ignition device that creates conditions for the high-energy compound to release energy are arranged in the arc space; the energy released by the high-energy compound can form an opening in the part of the water bag body surrounded by the circular ring bearing member to quickly discharge the water contained in the water bag body;

[0008] The bridge suspended casting hanging basket preloading system also includes a control circuit that is communicatively connected to the ignition device.

[0009] In one embodiment, the water bag further comprises a circular ring-shaped support member, which is arranged above the water bag body and fixedly connected to each sling, and is used to stretch out the four sides of the upper part of the water bag body containing water inside.

[0010] In one embodiment, an exhaust channel is formed on the top of the water bag body.

[0011] In one embodiment, the water bladder and the water bag are both provided with a drain outlet and a drain valve installed at the drain outlet.

[0012] The utility model of the bridge hanging basket preloading system can easily control the load applied to the basket. During the preloading process, if the basket is found to be in an abnormal condition, it can be quickly unloaded to prevent a major accident. After the preloading is completed, the water bag and water bladder are more convenient to recycle and more economical than the traditional concrete prefabricated blocks. BRIEF DESCRIPTION OF THE DRAWINGS

[0013] The included drawings are used to provide a further understanding of the embodiments of the present application, which constitute a part of the specification, are used to illustrate the implementation methods of the present application, and together with the text description, explain the principles of the present application. Obviously, the drawings described below are only some embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work. In the drawings:

[0014] Figure 1 It is a structural schematic diagram of an exemplary embodiment of a bridge suspended casting hanging basket preloading system of the utility model;

[0015] Figure 2 It is the layout diagram of water bladder and water bag in the pre-pressing process of hanging basket;

[0016] Figure 3 It is another perspective of the arrangement of water bladders and water bags during the pre-pressing process of the hanging basket;

[0017] Figure 4 It is a schematic diagram of the structure of the water bag;

[0018] Figure 5 This is a schematic diagram of the structure of the water bag from another perspective;

[0019] Figure 6 It is a schematic diagram of the structure of the water bag.

[0020] Explanation of the accompanying drawings: 1. water bag; 2. water bag; 3. first liquid channel; 4. second liquid channel; 5. first water pump; 6. second water pump; 7. check valve; 8. flow meter; 10. water bag body; 11. webbing net; 12. binding strap; 13. gas channel; 20. water bag body; 21. sling set; 22. circular ring bearing member; 23. hanging buckle; 24. reinforcing membrane; 25. arc space; 26. circular ring support member; 27. exhaust channel; 30. bottom mold platform; 31. front lower cross beam; 32. rear lower cross beam; 33. water source; 34. solenoid valve. DETAILED DESCRIPTION

[0021] The embodiments of the utility model are described in detail below, and examples of the embodiments are shown in the accompanying drawings. The embodiments described below with reference to the accompanying drawings are exemplary and are intended to be used to explain the utility model, but cannot be understood as limiting the utility model. Ordinary technicians in this field can make various changes, modifications, substitutions and variations to these embodiments without departing from the principles and purpose of the utility model. The scope of the utility model is defined by the claims and their equivalents.

[0022] The terms "center", "longitudinal", "lateral", "length", "up", "down", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", "axial", "radial", "circumferential" and the like mentioned or may be mentioned in the description of the present invention indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation to the present invention.

[0023] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Thus, a feature defined as "first" or "second" may explicitly or implicitly include one or more of the features. In addition, the terms "include", "comprises" and any variations thereof are intended to cover non-exclusive inclusions.

[0024] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installation" and "connection" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be an indirect connection through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0025] A bridge suspended casting hanging basket preloading system according to an embodiment of the utility model is described below with reference to the accompanying drawings.

[0026] See also Figures 1 to 3 According to an embodiment of the utility model, a preloading system for a suspended cast-in-place hanging basket for a bridge comprises at least two water bags 1 for arrangement on the bottom mold platform of the hanging basket, a plurality of water bags 2 for hanging on the front lower beam and the rear lower beam of the hanging basket, and an infusion subsystem for conveying water into each water bag 1 and each water bag 2. The number of the water bags 1 and the number of the water bags 2 can be determined according to the conditions of the bridge construction site, the specific structure of the hanging basket, the volume of the water bags 1, the volume of the water bags 2, etc. As an example, in this embodiment, the number of the water bags 1 is three, and the number of the water bags 2 is six. The three water bags 1 can be arranged side by side on the bottom mold platform of the hanging basket to be preloaded. Among the six water bags 2, three are hung on the front lower beam of the hanging basket at equal distances, and the remaining three are hung on the rear lower beam of the hanging basket at equal distances.

[0027] The infusion subsystem includes a first liquid channel 3 connecting a water source and a water inlet of a corresponding water bag 1, a second liquid channel 4 connecting a water source and a water inlet of a corresponding water bag 2, a first water pump 5 for promoting water from the water source to enter the corresponding water bag 1 through the first liquid channel 3, and a second water pump 6 for promoting water from the water source to enter the corresponding water bag 2 through the second liquid channel 4. In one embodiment, the number of the first liquid channels 3 may be three, the number of the first water pumps 5 may also be three, and each water bag 1 may be individually supplied with water by a first water pump 5 and a first liquid channel 3; the number of the second liquid channels 4 may be six, the number of the second water pumps 6 may also be six, and each water bag 2 may be individually supplied with water by a second water pump 6 and a second liquid channel 4. In another embodiment, each water bag 1 may share the same first water pump 5 and a part of the first liquid channel 3, and each water bag 2 may also share the same second water pump 6 and a part of the second liquid channel 4. Figure 1 Example: This embodiment does not limit the number of the first liquid channel 3 , the second liquid channel 4 , the first water pump 5 , and the second water pump 6 .

[0028] The first liquid channel 3 and the second liquid channel 4 can be installed with a check valve 7, a flow meter 8, etc. The flow meter 8 can obtain the capacity of the water in the corresponding water bag 1 and the water bag 2, and then determine the load applied by the water bag 1 and the water bag 2 to the hanging basket.

[0029] See now Figure 4 and Figure 5The water bag 1 includes a water bag body 10, and a webbing net 11 that is bonded to the outer surface of the water bag body 10 and the outer surface of the top. The water bag body 10 can be made of soft and durable materials such as PVC and rubber, and a space for accommodating fluids such as air and water is formed inside the water bag body 10. The webbing net 11 is composed of a longitudinal webbing and a transverse webbing, and each intersection of the longitudinal webbing and the transverse webbing is fixedly connected, which can be fixed by glue or fiber thread. The webbing net 11 can enhance the pressure resistance of the water bag body 10.

[0030] The water bag body 10 is generally rectangular in shape when filled with fluid. The water bag 1 also includes a plurality of straps 12 fixedly connected to the portions of the webbing net 11 that are adhered to the outer surfaces of the water bag body 10. The straps 12 can be used to fix the water bag 1 to the bottom mold platform. When the water bag 1 is placed on the bottom mold platform of the hanging basket, the water bag 1 can be filled with air, then moved to a set position, and then fixed with the straps 12, and then filled with water. This method can accurately position and fix the water bag 1 to avoid squeezing and shifting adjacent water bags 1. Using at least two water bags 1 can reduce the amount of water collected to one side when the bottom mold platform is tilted.

[0031] The top of the water bag body 10 is provided with an air hole, and the water bag 1 also includes an air channel 13 connected to the air hole, and the air channel 13 is provided with a regulating valve. When the water bag 1 is arranged on the bottom mold platform of the hanging basket, the water bag 1 needs to be filled with air, so in the process of filling the water bag 1 with water, the corresponding flow of air needs to be discharged. In this process, the regulating valve can be used to control the gas discharge speed so that the discharged air position can be quickly occupied by the input water to avoid the water bag 1 from sinking and shifting.

[0032] See now Figure 6 The water bag 2 includes a water bag body 20 and a sling set 21 surrounding the water bag body 20. The lower ends of the slings of the sling set 21 are fixed to the same circular bearing member 22, and the upper ends of the slings are connected to the buckle 23. The sling set 21 and the circular bearing member 22 jointly support the water bag body 20 after being filled with water.

[0033] The outer surface of the water bag body 20 surrounded by the annular bearing member 22 is attached with a reinforcing film 24, which can be a membrane structure made of the same material as the water bag body 20, or a membrane structure made of a material different from the water bag body 20, for example, a membrane structure made of soft and durable materials such as PVC and rubber. The reinforcing film 24 can reduce the risk of rupture of the part surrounded by the annular bearing member 22 due to lack of the carrying capacity of the sling.

[0034] The reinforcing membrane 24 and the outer surface of the water bag body 20 together form an arc-shaped arc space 25, in which a high-energy compound and an ignition device that creates conditions for the high-energy compound to release energy are arranged. During the pre-pressing process, if an abnormal condition is found in the hanging basket, the energy released by the high-energy compound can form a large opening in the part of the water bag body 20 surrounded by the annular bearing member 22, so as to quickly discharge the water contained in the water bag body 20, quickly unload it, and prevent major accidents. The high-energy compound can be trinitrotoluene, gunpowder, etc., and the ignition device can be a detonator. The bridge suspended casting hanging basket pre-pressing system also includes a control circuit (not shown in the figure) that is communicatively connected to the ignition device.

[0035] In this embodiment, the water bag 2 further includes a circular ring-shaped support member 26, which is arranged above the water bag body 20 and fixedly connected to each sling, and is used to open the four sides of the upper part of the water bag body 20 containing water. The circular ring-shaped support member 26 and the circular ring bearing member 22 can both be ring-shaped objects made of steel material.

[0036] Preferably, an exhaust channel 27 is formed at the top of the water bag body 20, and the water bag 1 and the water bag 2 are both provided with a drain port and a drain valve installed at the drain port.

[0037] The bridge hanging basket preloading system of this embodiment can easily control the load applied to the basket. During the preloading process, if the basket is found to be abnormal, it can be quickly unloaded to prevent major accidents. After the preloading is completed, the water bag 2, the water bag 1, etc. are more convenient to recycle and more economical than traditional concrete precast blocks.

Claims

1. A bridge suspended casting hanging basket preloading system, characterized in that: It includes at least two water bags for being arranged on the bottom mold platform of the hanging basket, a plurality of water bags for being hung on the front lower beam and the rear lower beam of the hanging basket, and an infusion subsystem for conveying water to each water bag and each water bag; The infusion subsystem includes a first liquid channel connecting a water source and a water inlet of a corresponding water bag, a second liquid channel connecting a water source and a water inlet of a corresponding water bag, a first water pump for promoting water from the water source to enter the corresponding water bag through the first liquid channel, and a second water pump for promoting water from the water source to enter the corresponding water bag through the second liquid channel, and both the first liquid channel and the second liquid channel are equipped with a check valve and a flow meter; The water bag comprises a water bag body, and a webbing net adhered to the outer surface of the water bag body and the outer surface of the top; the water bag body is generally rectangular when the inside is filled with fluid, and the water bag further comprises a plurality of straps fixedly connected to the portions of the webbing net adhered to the outer surface of the water bag body, and the straps are used to fix the water bag filled with fluid on the bottom mold platform; the top of the water bag body is provided with an air hole, and the water bag further comprises an air channel connected to the air hole, and the air channel is provided with a regulating valve; The water bag comprises a water bag body and a sling group surrounding the water bag body; the lower ends of the slings of the sling group are fixed to the same circular ring bearing member, and the upper ends of the slings are connected to the sling buckle; the outer surface of the water bag body surrounded by the circular ring bearing member is attached with a reinforcing film, and the reinforcing film and the outer surface of the water bag body together form an arc-shaped space in an excellent arc shape, and a high-energy compound and an ignition device that creates conditions for the high-energy compound to release energy are arranged in the arc space; The energy released by the high-energy compound can form an opening in the portion of the water bag body surrounded by the annular carrier, so as to quickly discharge the water contained in the water bag body; The bridge suspended casting hanging basket preloading system also includes a control circuit that is communicatively connected to the ignition device.

2. The bridge suspended casting hanging basket preloading system according to claim 1 is characterized in that: The water bag also includes a circular ring-shaped support member, which is arranged above the water bag body and fixedly connected to each sling, and is used to open the four sides of the upper part of the water bag body containing water inside.

3. The bridge suspended casting hanging basket preloading system according to claim 2 is characterized in that: An exhaust channel is formed on the top of the water bag body.

4. The bridge suspended casting hanging basket preloading system according to claim 3 is characterized in that: The water bag and the water bladder are both provided with a drainage outlet and a drainage valve installed at the drainage outlet.