Angle positioning tool for welding wind power generation tower

By designing an angle positioning tool for welding of wind power towers with drive motors, magnets and electric push rods, the problem that existing tools cannot automatically adjust the welding angle is solved, and efficient welding operation and device stability are achieved.

CN222588598UActive Publication Date: 2025-03-11SHENGSHI QIANKUN (TIANJIN) CONSTRUCTION CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421155238.7
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-05-24
Publication Date
2025-03-11
Estimated Expiration
2034-05-24

AI Technical Summary

Technical Problem

Existing positioning tools cannot automatically adjust the welding angle, resulting in high workload and low efficiency for users.

Method used

An angle positioning tool for welding wind power towers was designed, using a driving motor to drive the rotation of the shaft, adsorb the steel pipe through a magnet, and an electric push rod was used to achieve angle adjustment and steel pipe movement.

Benefits of technology

Automatic adjustment of welding angle is achieved, reducing the workload of users, improving welding efficiency, and ensuring the stability and safety of the device through structures such as limiting plates and rubber pads.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222588598U_ABST
    Figure CN222588598U_ABST
Patent Text Reader

Abstract

The utility model discloses an angle positioning tool for welding of a wind power generation tower, which belongs to the technical field of positioning tools and comprises a first supporting plate, two fixing plates are fixedly connected to the side face of the first supporting plate, a shell is fixedly connected to the side face of one fixing plate, and the other side face of the other fixing plate is fixedly connected with a second supporting plate. A driving motor is fixedly installed in the shell, bearings are fixedly connected to the side faces of the two fixing plates, rotating shafts are rotatably connected to the interiors of the two bearings, one ends of the rotating shafts are fixedly connected with an output shaft of the driving motor, and a second supporting plate is fixedly connected to the surface of each rotating shaft; magnets are arranged at the bottom of the first supporting plate and the bottom of the second supporting plate, the rotating shaft is driven to rotate through work of the driving motor, then the second supporting plate drives the steel pipe to conduct angle adjustment, the steel pipe is attracted and fixed through the magnets, and through work of an electric push rod, the steel pipe can be fixed. And the purpose that the placing plate drives the steel pipe to move is achieved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of positioning tools, and more specifically, to an angle positioning tool for welding a wind power tower. Background Art

[0002] A wind turbine tower is a tower pole for wind power generation. It mainly plays a supporting role in the wind turbine generator set and absorbs the vibration of the set. The construction of a wind turbine tower involves the welding of multiple steel materials with different welding angles.

[0003] At present, positioning tools are needed when welding steel pipes on wind power towers. However, most of the existing positioning tools are unable to automatically adjust the angle, which greatly increases the workload of users, reduces efficiency, and brings many inconveniences to use. Utility Model Content

[0004] (1) Technical issues to be solved

[0005] In view of the shortcomings of the prior art, the utility model aims to provide an angle positioning tool for welding a wind power tower, which has the characteristic of automatic adjustment.

[0006] (2) Technical solution

[0007] To achieve the above-mentioned purpose, the utility model provides an angle positioning tool for welding a wind power tower, comprising a first support plate, a fixing plate fixedly connected to the side surface of the first support plate, two fixing plates, one of the fixing plates is fixedly connected to a shell on the side surface, a driving motor is fixedly installed in the shell, the two fixing plates are fixedly connected to the side surfaces of the two fixing plates, a rotating shaft is rotatably connected in the two bearings, one end of the rotating shaft is fixedly connected to the output shaft of the driving motor, a second support plate is fixedly connected to the surface of the rotating shaft, magnets are provided on the bottom of the first support plate and the bottom of the second support plate, eight magnets are provided, a vertical plate is fixedly connected to the side surface of the first support plate, four vertical plates are provided, and connecting plates are fixedly connected to the sides of the four vertical plates, an electric push rod is fixedly installed on the bottom of the connecting plate, and a placement plate is fixedly connected to the top of the electric push rod.

[0008] When the angle positioning tool for welding a wind power tower according to the technical solution is used, the driving motor is driven to drive the rotating shaft to rotate, thereby achieving the purpose of enabling the second support plate to drive the steel pipe to adjust the angle.

[0009] Furthermore, the top of the placement plate is fixedly connected with a limiting plate, and there are four limiting plates.

[0010] Furthermore, the bottoms of the four vertical plates are fixedly connected to a bottom plate, and the bottoms of the four bottom plates are provided with rubber pads.

[0011] Furthermore, a support frame is fixedly connected to the side surfaces of the two vertical plates, a storage box is clamped inside the support frame, and an operation panel is fixedly installed on the top of the first support plate.

[0012] Furthermore, a shovel plate is placed inside the storage box, and a first handle is fixedly connected to the top of the shovel plate.

[0013] Furthermore, second handles are fixedly connected to both sides of the storage box, and rubber sleeves are provided on the surfaces of the two second handles.

[0014] Furthermore, the surface of the shovel plate is provided with an inclined surface.

[0015] (3) Beneficial effects

[0016] In summary, the utility model has the following beneficial effects:

[0017] 1. The driving motor drives the rotating shaft to rotate, so that the second support plate drives the steel pipe to adjust the angle. The steel pipe is adsorbed and fixed by the magnet. The electric push rod drives the placement plate to move the steel pipe.

[0018] 2. The purpose of limiting the steel pipe is achieved by setting the limit plate, the purpose of supporting and preventing the device from slipping is achieved by setting the bottom plate and rubber pad, and the purpose of supporting and limiting the storage box is achieved by setting the support frame and storage box, which is also convenient for storing the shovel board;

[0019] 3. By providing the shovel plate and the first handle, it is convenient to hold the shovel plate to scoop up the adsorbed steel pipe. By providing the second handle and the rubber sleeve, it is convenient to move the storage box and protect the hands during the movement. BRIEF DESCRIPTION OF THE DRAWINGS

[0020] In order to more clearly illustrate the specific implementation of the utility model or the technical solution in the prior art, the drawings required for describing the specific implementation or the prior art will be briefly introduced below. Obviously, the drawings described below are only one implementation of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0021] Figure 1 This is a schematic diagram of the front view structure of the utility model;

[0022] Figure 2 for Figure 1 A schematic diagram of the cross-sectional structure of the middle fixed plate when viewed from above;

[0023] Figure 3 for Figure 1 Schematic diagram of the side structure of the middle shovel plate.

[0024] The markings in the accompanying drawings are:

[0025] 1. First support plate; 2. Fixed plate; 3. Shell; 4. Vertical plate; 5. Connecting plate; 6. Electric push rod; 7. Placement plate; 8. Limiting plate; 9. Bottom plate; 10. Rubber pad; 11. Support frame; 12. Storage box; 13. Shovel plate; 14. First handle; 15. Second handle; 16. Rubber sleeve; 17. Operation panel; 18. Drive motor; 19. Bearing; 20. Rotating shaft; 21. Second support plate; 22. Magnet; 23. Inclined surface. DETAILED DESCRIPTION

[0026] In order to make the technical means, creative features, objectives and effects achieved by the utility model easy to understand, the technical scheme in the specific implementation mode of the utility model is clearly and completely described below to further illustrate the utility model. Obviously, the specific implementation mode described is only a part of the implementation mode of the utility model, rather than all styles.

[0027] Example:

[0028] The following is combined with Figure 1-3 The utility model is described in further detail.

[0029] See also Figure 1-3 The utility model provides a technical solution: an angle positioning tool for welding a wind power tower, comprising a first support plate 1, a fixed plate 2 is fixedly connected to the side of the first support plate 1, there are two fixed plates 2, a housing 3 is fixedly connected to the side of one fixed plate 2, a driving motor 18 is fixedly installed in the housing 3, bearings 19 are fixedly connected to the sides of the two fixed plates 2, a rotating shaft 20 is rotatably connected in the two bearings 19, one end of the rotating shaft 20 is fixedly connected to the output shaft of the driving motor 18, a second support plate 21 is fixedly connected to the surface of the rotating shaft 20, and the rotating shaft 2 is driven by the driving motor 18 to work. 0 rotates, thereby achieving the purpose of making the second support plate 21 drive the steel pipe to adjust the angle, the bottom of the first support plate 1 and the bottom of the second support plate 21 are both provided with magnets 22, and there are eight magnets 22. By means of the magnets 22, the purpose of adsorbing and fixing the steel pipe is achieved, and the side of the first support plate 1 is fixedly connected with a vertical plate 4, and there are four vertical plates 4. The sides of the four vertical plates 4 are fixedly connected with connecting plates 5, and the bottom of the connecting plate 5 is fixedly installed with an electric push rod 6, and the top of the electric push rod 6 is fixedly connected with a placement plate 7. Through the operation of the electric push rod 6, the purpose of making the placement plate 7 drive the steel pipe to move is achieved.

[0030] Specifically, the top of the placement plate 7 is fixedly connected to a limiting plate 8 , and there are four limiting plates 8 . The bottoms of the four vertical plates 4 are fixedly connected to a bottom plate 9 , and the bottoms of the four bottom plates 9 are provided with rubber pads 10 .

[0031] By adopting the above technical solution, by setting the limiting plate 8, the purpose of limiting the steel pipe is achieved, and by setting the bottom plate 9 and the rubber pad 10, the purpose of supporting and preventing the device from slipping is achieved.

[0032] Specifically, a support frame 11 is fixedly connected to the sides of the two vertical plates 4, a storage box 12 is clamped inside the support frame 11, an operation panel 17 is fixedly installed on the top of the first support plate 1, a shovel plate 13 is placed inside the storage box 12, and a first handle 14 is fixedly connected to the top of the shovel plate 13.

[0033] By adopting the above technical solution, by setting the support frame 11 and the storage box 12, the storage box 12 can be supported and limited, and the purpose of storing the shovel board 13 is also convenient. By setting the shovel board 13 and the first handle 14, the purpose of conveniently holding the shovel board 13 to scoop up the adsorbed steel pipe is achieved.

[0034] Specifically, the second handles 15 are fixedly connected to both sides of the storage box 12 , the surfaces of the two second handles 15 are provided with rubber sleeves 16 , and the surface of the shovel plate 13 is provided with an inclined surface 23 .

[0035] By adopting the above technical solution and providing the second handle 15 and the rubber sleeve 16 , the storage box 12 can be easily moved and the hands can be protected during the movement.

[0036] The working principle of the utility model is as follows: when the positioning tool is needed, the steel pipe is first placed between the two limit plates 8, and then the electric push rod 6 is operated to make the placement plate 7 drive the steel pipe to the position of the magnet 22, and the steel pipe is adsorbed and fixed with the help of the magnet 22, and then the driving motor 18 is operated to drive the rotating shaft 20 to rotate, so that the second support plate 21 is adjusted to a suitable angle, and then another steel pipe is located at the position of the magnet 22 on the second support plate 21, and the steel pipe is adsorbed with the help of the magnet 22, and finally the staff can weld the two steel pipes. After the welding is completed, the first handle 14 can be held to take out the shovel plate 13, and then the steel pipe can be shoveled with the help of the inclined surface 23 on the shovel plate 13, and the steel pipe can be subsequently processed after shoveling.

[0037] This specific embodiment is merely an explanation of the present invention and is not a limitation of the present invention. After reading this specification, those skilled in the art may make non-creative modifications to the present embodiment as needed, but such modifications are protected by patent law as long as they are within the scope of the claims of the present invention.

Claims

1. An angle positioning tool for welding a wind power tower, comprising a first support plate (1), characterized in that: The side of the first support plate (1) is fixedly connected to a fixing plate (2), and there are two fixing plates (2). The side of one of the fixing plates (2) is fixedly connected to a housing (3), and a driving motor (18) is fixedly installed in the housing (3). The sides of the two fixing plates (2) are fixedly connected to bearings (19), and a rotating shaft (20) is rotatably connected in the two bearings (19), and one end of the rotating shaft (20) is fixedly connected to the output shaft of the driving motor (18). The first support plate (1) and the second support plate (21) are fixedly connected to the surface, the bottom of the first support plate (1) and the bottom of the second support plate (21) are both provided with magnets (22), and there are eight magnets (22). The side of the first support plate (1) is fixedly connected to a vertical plate (4), and there are four vertical plates (4). The sides of the four vertical plates (4) are fixedly connected to connecting plates (5), and the bottom of the connecting plate (5) is fixedly installed with an electric push rod (6), and the top of the electric push rod (6) is fixedly connected to a placement plate (7).

2. The angle positioning tool for wind power tower welding according to claim 1, characterized in that: The top of the placement plate (7) is fixedly connected to a limiting plate (8), and there are four limiting plates (8).

3. The angle positioning tool for wind power tower welding according to claim 1, characterized in that: The bottoms of the four vertical plates (4) are all fixedly connected to a bottom plate (9), and the bottoms of the four bottom plates (9) are all provided with rubber pads (10).

4. The angle positioning tool for wind power tower welding according to claim 1, characterized in that: The sides of the two vertical plates (4) are fixedly connected with a support frame (11), the interior of the support frame (11) is clamped with a storage box (12), and the top of the first support plate (1) is fixedly mounted with an operation panel (17).

5. The angle positioning tool for welding a wind power tower according to claim 4, characterized in that: A shovel plate (13) is placed inside the storage box (12), and a first handle (14) is fixedly connected to the top of the shovel plate (13).

6. The angle positioning tool for welding a wind power tower according to claim 4, characterized in that: Second handles (15) are fixedly connected to both sides of the storage box (12), and rubber sleeves (16) are provided on the surfaces of the two second handles (15).

7. The angle positioning tool for welding a wind power tower according to claim 5, characterized in that: The surface of the shovel plate (13) is provided with an inclined surface (23).