Large-slope-ratio rough concentrate pipeline stilling device

By setting up multiple square boxes and multiple connecting pipes in the coarse concentrate pipeline to form a force-removing device, the problem of severe wear of coarse concentrate pipelines in large slopes is solved, extending the service life and reducing the difficulty of maintenance.

CN222597428UActive Publication Date: 2025-03-11BENXI IRON & STEEL (GRP) MINING CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421464085.4
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-06-25
Publication Date
2025-03-11
Estimated Expiration
2034-06-25

AI Technical Summary

Technical Problem

The coarse concentrate pipeline wears severely in large slopes, shortens service life, and is difficult to perform daily maintenance and replacement.

Method used

A large slope-to-coarse concentrate pipeline force-removing device is designed. By setting up multiple square boxes for extinguishing power and multiple connecting pipes in the pipeline, a force-to-coarse concentrate device is formed to reduce the pipeline pressure and reduce the impact force of the crude concentrate.

Benefits of technology

It extends the service life of crude concentrate pipelines, reduces wear, reduces pipe leakage accidents, reduces labor intensity for maintenance workers, and saves costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222597428U_ABST
    Figure CN222597428U_ABST
Patent Text Reader

Abstract

The utility model provides a large-slope-ratio rough concentrate pipeline stilling device which comprises a plurality of stilling square boxes and a support, the support is obliquely fixed to a mountain slope, and the multiple stilling square boxes are fixedly connected to the support. The top of the square stilling box is open, and a containing cavity is formed in the square stilling box. The multiple square baffle boxes are sequentially arranged in series from top to bottom in the same inclination direction through pipelines, the top of one side and the bottom of the other side of each square baffle box are connected with the pipelines correspondingly, and the pipelines communicate with the containing cavities in the square baffle boxes. The top of the square baffle box located on the uppermost portion of the slope surface is connected with an ore collecting box of a two-pump-station recycling room plant through a first pipeline, and the bottom of the square baffle box located on the lowermost portion of the slope surface is connected with the one-thousand-cubic concentrate box through a third pipeline. Every two adjacent square baffle boxes communicate with each other through a second pipeline. The utility model can reduce the pressure of the pipeline, reduce the impact force of rough concentrate in the pipeline, reduce the wear degree of the rough concentrate pipeline, reduce pipe leakage accidents and prolong the service life of the pipeline.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of pipeline accessories, in particular to a force dissipation device for a large slope ratio coarse concentrate pipeline. Background Art

[0002] In June 2020, a mineral processing plant built a new low-powder recovery system. The coarse concentrate recovered from the recovery plant of the second pump station needs to flow by gravity through a Φ273mm pipe to a 1,000 cubic meter concentrate box. The total length of the gravity pipeline is 450 meters, of which the length of the large slope section is 78 meters, with a height difference of 37 meters and a slope angle of 29°. The coarse concentrate contains coarse particles, which cause great wear on the coarse concentrate pipeline. The -200 mesh content of the coarse concentrate is about 20%, which has a large scouring force on the pipeline, shortening the service life of the coarse concentrate pipeline. In addition, since the coarse concentrate pipeline is laid along the mountain and passes through railway bridges and culverts, daily maintenance and replacement are difficult.

[0003] Therefore, in summary, it is necessary to provide a new type of force dissipation device to solve the shortcomings of the prior art. Utility Model Content

[0004] In view of the above technical problems, a large slope ratio coarse concentrate pipeline energy dissipation device is provided. The technical means adopted by the utility model are as follows:

[0005] A force dissipation device for a rough concentrate pipeline with a large slope ratio, comprising: a plurality of force dissipation square boxes and a bracket, wherein the bracket is tilted and fixed on a mountain slope, and the plurality of force dissipation square boxes are fixedly connected to the bracket; the top of the force dissipation square box is open, and a containing chamber is provided inside;

[0006] The multiple energy dissipation boxes are arranged in series from top to bottom in the same inclined direction through pipes, and each energy dissipation box is connected to a pipe at the top on one side and the bottom on the other side, and the pipe is connected to the accommodation chamber in the energy dissipation box;

[0007] The top of the energy-dissipating box located at the top of the slope is connected to the ore collecting box in the recovery room of the second pumping station through the first pipeline, and the bottom of the energy-dissipating box located at the bottom of the slope is connected to the 1,000 cubic meter box of concentrate through the third pipeline; two adjacent energy-dissipating boxes are connected through the second pipeline, wherein the upper end of each second pipeline is connected to the bottom of the energy-dissipating box located on the upper side, and the lower end is connected to the top of the energy-dissipating box located on the lower side.

[0008] Furthermore, the first pipeline, the second pipeline and the third pipeline are arranged in an inclined and parallel manner.

[0009] Furthermore, the pipe connected to the top of the energy dissipation box is inserted into the interior of the energy dissipation box from one side of the energy dissipation box to the other side. The pipe section inserted into the top of the energy dissipation box is the first pipe section, and one end of the first pipe section is fixedly connected to the other side of the energy dissipation box. The first pipe section is provided on the first pipe connected to the top of each energy dissipation box and the multiple second pipes.

[0010] Furthermore, the first pipe section is provided with an outlet communicating with the accommodating chamber.

[0011] Furthermore, the outlet is arranged at the top of the first pipe section, with the opening direction facing upward.

[0012] Furthermore, the first pipeline, the second pipeline and the third pipeline are respectively connected to the energy dissipation box by welding.

[0013] Furthermore, the inner wall of the energy dissipation box is inlaid with cast stone plates.

[0014] Furthermore, the energy dissipation box is connected to the bracket by welding.

[0015] Furthermore, the bracket is fixed on the mountain slope by multiple sets of bolts.

[0016] Compared with the prior art, the utility model has the following advantages:

[0017] 1. The utility model arranges a plurality of energy dissipation boxes and a plurality of connecting pipes in the coarse and concentrate pipeline to form an energy dissipation device, which can reduce the pipeline pressure, reduce the impact force of the coarse and concentrate in the pipeline, reduce the wear degree of the coarse and concentrate pipeline, reduce the leakage accidents, extend the service life of the pipeline, and reduce the labor intensity of the maintenance workers.

[0018] 2. The utility model can play a better buffering role by opening an outlet at the top of the pipeline. The top of the energy dissipation box 1 is open, and a cast stone plate 12 is embedded in the energy dissipation box 1 to increase the wear resistance of the energy dissipation box.

[0019] Based on the above reasons, the utility model can be widely promoted in the fields of pipeline force dissipation and the like. BRIEF DESCRIPTION OF THE DRAWINGS

[0020] In order to more clearly illustrate the embodiments of the utility model or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some embodiments of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative labor.

[0021] Figure 1 It is a structural schematic diagram of the utility model.

[0022] Figure 2 It is a structural schematic diagram of the energy dissipation square box of the utility model.

[0023] In the figure: 1. Energy dissipation box; 11. Outlet; 12. Cast stone slab; 2. Bracket; 3. First pipeline; 4. Second pipeline; 5. Third pipeline; 6. Recovery room of the second pumping station; 7. Ore collecting box. DETAILED DESCRIPTION

[0024] In order to make the purpose, technical solution and advantages of the embodiment of the utility model clearer, the technical solution in the embodiment of the utility model will be clearly and completely described below in conjunction with the drawings in the embodiment of the utility model. Obviously, the described embodiment is a part of the embodiment of the utility model, not all of the embodiments. Based on the embodiment of the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0025] like Figure 1-2 As shown, the utility model provides a large slope ratio rough concentrate pipeline energy dissipation device, comprising: a plurality of energy dissipation boxes 1 and a bracket 2, the bracket 2 being fixed to the mountain slope by a plurality of groups of bolts. The plurality of energy dissipation boxes 1 are connected by pipelines. In this embodiment, 6 energy dissipation boxes 1 are added to the 78-meter rough concentrate large slope ratio section Φ273mm pipeline, and the 6 energy dissipation boxes 1 are welded on the bracket 2 in sequence from top to bottom in the same inclined direction, and the energy dissipation box 1 has a accommodating chamber inside. The specific structural shape of the energy dissipation box 1 is shown in FIG. Figure 2 shown.

[0026] As a preferred embodiment, an energy dissipation box 1 is provided at every interval L=12 meters, and 6 energy dissipation boxes 1 are arranged in series through pipelines, and a pipeline is connected to the top of one side and the bottom of the other side of each energy dissipation box 1, and the pipeline is connected to the accommodating chamber in the energy dissipation box 1. The energy dissipation box 1 located at the top of the slope is the first energy dissipation box, the energy dissipation box 1 located at the bottom of the slope is the second energy dissipation box, and the four energy dissipation boxes 1 located in the middle are all third energy dissipation boxes. The top of the first energy dissipation box is connected to the ore collecting box 7 of the existing second pump station recovery room 6 through the first pipeline 3. The bottom of the first energy dissipation box is connected to the top of the adjacent third energy dissipation box through the second pipeline 4. Two adjacent third energy dissipation boxes are connected through the second pipeline 4, and the upper end of the second pipeline 4 is connected to the bottom of the third energy dissipation box located on the upper side, and the lower end is connected to the top of the third energy dissipation box located on the lower side. The top of the second energy dissipation box is connected to the bottom of the adjacent third energy dissipation box through the second pipeline 4, and the bottom of the second energy dissipation box is connected to the existing 1,000 cubic meter box of concentrate through the third pipeline 5.

[0027] As a preferred embodiment, the first pipeline 3, the second pipeline 4, and the third pipeline 5 are all arranged in parallel and inclined. The inclination angle of the interface between the pipeline in the energy dissipation box 1 and the energy dissipation box 1 is θ=23°, that is, the angle between the first pipeline 3, the second pipeline 4, and the third pipeline 5 and the horizontal plane after being connected to the energy dissipation box 1 is 23°. In this embodiment, the diameters of the first pipeline 3, the second pipeline 4, and the third pipeline 5 are the same, and Φ273 ceramic tubes can be used, and the first pipeline 3, the second pipeline 4, and the third pipeline 5 are connected to the corresponding energy dissipation box 1 by welding.

[0028] As a preferred embodiment, the top of the energy dissipation box 1 is open, and a cast stone plate 12 is inlaid in the energy dissipation box 1, wherein the cast stone plate 12 is inlaid on each inner wall of the energy dissipation box 1.

[0029] As a preferred embodiment, the external dimensions of the six energy dissipation boxes 1 are all 800×800×2800 mm (length×width×height). It should be noted that the dimensions of the energy dissipation boxes 1 can be designed according to actual use conditions.

[0030] As a preferred embodiment, the pipe connected to the top of the energy dissipation box 1 is inserted into the interior of the energy dissipation box 1 from one side of the energy dissipation box 1 to the other side. The pipe section inserted into the top of the energy dissipation box 1 is the first pipe section, and one end of the first pipe section is fixedly connected to the other side of the energy dissipation box 1; the first pipe 3 and the plurality of second pipes 4 connected to the top of each energy dissipation box 1 are provided with a first pipe section. The first pipe section is provided with an outlet 11, which is located inside the energy dissipation box 1 and is connected to the accommodating chamber in the energy dissipation box 1. It should be noted that the outlet 11 can be opened at any position in the circumferential direction of the first pipe section. In this embodiment, the outlet 11 is opened at the top of the first pipe section, and the opening direction is upward, which has a better buffering effect. The material is transported to the energy dissipation box 1 through the outlet 11 of the first pipe section of the pipe located above, and then output from the energy dissipation box 1 through the pipe located below.

[0031] The utility model can reduce the pressure of the coarse concentrate pipeline, reduce the impact force of the coarse concentrate in the coarse concentrate pipeline, extend the service life of the coarse concentrate pipeline, reduce the wear degree of the coarse concentrate pipeline, reduce pipe leakage accidents, reduce the replacement frequency of Φ273mm wear-resistant rubber lined pipeline, and reduce the labor intensity of maintenance workers by adding multiple energy dissipation square boxes and multiple connecting pipelines in the 78-meter coarse concentrate pipeline with a large slope ratio.

[0032] The estimated service life of the Φ273mm wear-resistant rubber-lined pipe is 2 years. After adding the energy dissipation device of the utility model, the service life of the coarse and concentrate pipeline can be extended by 0.8 years. There is no need to replace the Φ273mm wear-resistant rubber-lined pipe as a whole, which can save costs and reduce the replacement frequency of the Φ273mm wear-resistant rubber-lined pipe, reduce the labor intensity of maintenance workers, and save labor costs. The plan has been implemented and has been operating normally for more than 18 months without any leakage accidents.

[0033] Finally, it should be noted that the above embodiments are only used to illustrate the technical solution of the utility model, rather than to limit it. Although the utility model has been described in detail with reference to the aforementioned embodiments, ordinary technicians in this field should understand that they can still modify the technical solutions recorded in the aforementioned embodiments, or replace some or all of the technical features therein with equivalents. However, these modifications or replacements do not make the essence of the corresponding technical solution deviate from the scope of the technical solution of the embodiments of the utility model.

Claims

1. A large slope ratio coarse concentrate pipeline energy dissipation device, characterized in that: include: A plurality of energy dissipation boxes (1) and a support (2), wherein the support (2) is tilted and fixed on a mountain slope, and the plurality of energy dissipation boxes (1) are fixedly connected to the support (2); the top of the energy dissipation box (1) is open and has a containing chamber inside; The plurality of energy dissipation boxes (1) are arranged in series from top to bottom in the same inclined direction through pipes, and each energy dissipation box (1) is connected to a pipe at the top on one side and the bottom on the other side, and the pipe is connected to the accommodating chamber in the energy dissipation box (1); The top of the energy dissipation box (1) located at the top of the slope is connected to the ore collecting box (7) of the recovery room (6) of the second pumping station through a first pipeline (3), and the bottom of the energy dissipation box (1) located at the bottom of the slope is connected to a 1,000 cubic meter box of concentrate through a third pipeline (5); two adjacent energy dissipation boxes (1) are connected through a second pipeline (4), wherein the upper end of each second pipeline (4) is connected to the bottom of the energy dissipation box (1) located on the upper side, and the lower end is connected to the top of the energy dissipation box (1) located on the lower side.

2. The large slope ratio rough concentrate pipeline energy dissipation device according to claim 1 is characterized in that: The first pipeline (3), the second pipeline (4) and the third pipeline (5) are arranged in an inclined and parallel manner.

3. The large slope ratio rough concentrate pipeline energy dissipation device according to claim 1 is characterized in that: The pipe connected to the top of the energy dissipation box (1) is inserted into the interior of the energy dissipation box (1) from one side to the other side of the energy dissipation box (1); the pipe section inserted into the top of the energy dissipation box (1) is a first pipe section, and one end of the first pipe section is fixedly connected to the other side of the energy dissipation box (1); the first pipe (3) connected to the top of each energy dissipation box (1) and the plurality of second pipes (4) all have the first pipe section.

4. The large slope ratio rough concentrate pipeline energy dissipation device according to claim 3 is characterized in that: The first pipe section is provided with an outlet (11) which is connected to the accommodating chamber.

5. The large slope ratio rough concentrate pipeline energy dissipation device according to claim 4 is characterized in that: The outlet (11) is arranged at the top of the first pipe section, with the opening direction facing upward.

6. The large slope ratio rough concentrate pipeline energy dissipation device according to claim 1 is characterized in that: The first pipeline (3), the second pipeline (4) and the third pipeline (5) are respectively connected to the energy dissipation box (1) by welding.

7. The large slope ratio rough concentrate pipeline energy dissipation device according to claim 1 is characterized in that: The inner wall of the energy dissipation box (1) is inlaid with a cast stone plate (12).

8. The large slope ratio rough concentrate pipeline energy dissipation device according to claim 1 is characterized in that: The energy dissipation box (1) is connected to the bracket (2) by welding.

9. The large slope ratio rough concentrate pipeline energy dissipation device according to claim 1 is characterized in that: The support (2) is fixed on the mountain slope by means of multiple groups of bolts.