Lifting appliance tool
By designing a spreader tool including a hanging frame, a hanging rod and locking parts, the safety risks of traditional large concrete block lifting structures are solved, and a more stable and safe lifting process is achieved.
Patent Information
- Application Number
- CN202421338700.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-12
- Publication Date
- 2025-03-14
- Estimated Expiration
- 2034-06-12
AI Technical Summary
The traditional large concrete block lifting structure has a great safety risk. The sling is prone to stress imbalance during the lifting process, causing the concrete block to slide, and directly setting up a hook outside the block can easily affect the quality of the block and lead to cracks.
A sling tool is designed, including a hanger, a hanger and a locking member. The hanger extends into the inside of the concrete block, and the locking member rotates and snaps in the reserved groove to ensure that the hanger and the concrete block are lifted together.
It improves the lifting stability and safety of concrete blocks, avoids the problems of unbalanced stress of slings and damage to block quality, and ensures the safety and efficiency of the lifting process.
Smart Images

Figure CN222612689U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of large concrete block hoisting, in particular to a hoisting tool. Background Art
[0002] Large concrete revetment blocks of 100 tons are large in size and heavy in weight. They are usually lifted directly by wire rope slings. The process requires the concrete blocks to be placed on pads, and the slings pass through the bottom of the pads and are then fastened with two circular slings at both ends. The above traditional lifting / fixing method not only has requirements on the placement environment of the concrete blocks for installing the slings, but also, if the slings are subjected to unbalanced force during the lifting process, the concrete blocks will slide, which poses a greater safety risk to the lifting process.
[0003] If hooks are directly set on the outside of the concrete block, many problems will arise: for example, when the number of hooks is small, they are not firmly fixed. Therefore, the hooks need to be fixed at multiple locations on the outside of the concrete block. This can easily affect the quality of the concrete block itself and cause cracks. Utility Model Content
[0004] The utility model aims to provide a lifting tool, aiming to solve the technical problem that a traditional large concrete block lifting structure has a great safety risk when lifting.
[0005] To achieve the above-mentioned purpose, the utility model provides a sling tool, comprising a sling;
[0006] A suspension rod, which is used to extend into the interior of the concrete block, and a plurality of the suspension rods are provided on the hanger;
[0007] A locking piece is arranged at one end of the suspension rod extending into the concrete block, and the suspension rod is rotatably arranged on the hanger, so that: after the suspension rod extends into the reserved groove of the concrete block, the suspension rod is rotated to drive the locking piece to rotate synchronously so that it is buckled and fixed in the reserved groove.
[0008] Preferably, the reserved groove includes a through groove and a clamping groove that penetrate each other, the through groove is located above the clamping groove, and the width W1 of the through groove = the width W2 of the clamping groove, the length W3 of the locking member < the width W1 of the through groove, the thickness D1 of the through groove < the length of the locking member < the thickness D2 of the clamping groove, so that:
[0009] After the locking member passes through the through slot and enters the clamping slot, the suspension rod rotates 90 degrees, and the locking member turns and is buckled and fixed in the clamping slot.
[0010] Preferably, the length of the locking member decreases gradually from top to bottom.
[0011] Preferably, the hanger comprises a first connecting rod, a second connecting rod, a third connecting rod and a fourth connecting rod connected end to end, the first connecting rod and the third connecting rod are arranged in parallel, and the second connecting rod and the fourth connecting rod are arranged in parallel;
[0012] The length of the first connecting rod=the length of the third connecting rod, the length of the second connecting rod=the length of the fourth connecting rod, and the length of the first connecting rod>the length of the second connecting rod.
[0013] Preferably, at least two suspension rods are respectively provided on the first connecting rod and the third connecting rod.
[0014] Preferably, the hanger is further provided with a plurality of adjustment plates, each of which corresponds to one of the hangers, and the adjustment plates are provided with adjustment slots, in which an adjustment rod is movably arranged, and one end of the adjustment rod passes through the adjustment slot and is connected to the hanger.
[0015] Preferably, a marking line is further provided at the top of the adjusting rod, and the marking line includes a first marking line and a second marking line, the first marking line and the second marking line are arranged to cross each other vertically, and the length of the first marking line is greater than the length of the second marking line;
[0016] The first marking line is parallel to the length direction of the locking member, and the second marking line is parallel to the width direction of the locking member.
[0017] Preferably, the hanger is further provided with a plurality of lifting ears, and the lifting ears are provided with lifting holes for external lifting ropes to pass through.
[0018] Preferably, the outer wall of the suspension rod is also provided with scale lines.
[0019] The utility model discloses a lifting tool, which has the following beneficial effects: the lifting rod of the present invention can be extended into the interior of a concrete block, a locking piece is additionally provided under the lifting rod, after the locking piece is inserted along the reserved groove of the concrete block, the lifting rod is rotated above the hanger, and the locking piece at the bottom of the lifting rod is simultaneously rotated in the bottom direction, and the locking piece is stuck in the reserved groove of the concrete, so that the hanger and the concrete are lifted together, the stability is better, and it is safer during lifting. BRIEF DESCRIPTION OF THE DRAWINGS
[0020] In order to more clearly illustrate the embodiments of the utility model or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the utility model. For ordinary technicians in this field, other drawings can be obtained based on the structures shown in these drawings without paying creative work.
[0021] Figure 1This is a front view structural diagram of the utility model lifting tool when extending into concrete;
[0022] Figure 2 It is a side view structural diagram of the utility model lifting tool when extending into concrete;
[0023] Figure 3 This is a front view structural diagram of the utility model's lifting tooling when it is not extended into concrete;
[0024] Figure 4 It is a side view structural diagram of the utility model lifting tool when it is not extended into concrete;
[0025] Figure 5 It is a schematic diagram of the structure of the utility model when the lifting tool is not extended into the concrete;
[0026] Figure 6 The utility model is a structural schematic diagram of the adjustment plate of the lifting tool.
[0027] In the accompanying drawings: 1-hanging bracket, 11-first connecting rod, 12-second connecting rod, 13-third connecting rod, 14-fourth connecting rod, 15-adjusting plate, 151-adjusting slot, 152-adjusting rod, 153-marking line, 16-lifting ear, 161-lifting hole, 2-hanging rod, 3-concrete block, 31-reserved slot, 311-through slot, 312-card slot, 4-locking piece.
[0028] The realization of the purpose, functional features and advantages of the utility model will be further explained in conjunction with embodiments and with reference to the accompanying drawings. DETAILED DESCRIPTION
[0029] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments of the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0030] It should be noted that if a directional indication is involved in the embodiments of the present invention, the directional indication is only used to explain the relative position relationship, movement status, etc. between the components in a certain specific posture. If the specific posture changes, the directional indication will also change accordingly.
[0031] In addition, if there are descriptions involving "first", "second", etc. in the embodiments of the utility model, the descriptions of "first", "second", etc. are only used for descriptive purposes and cannot be understood as indicating or suggesting their relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features defined as "first" and "second" may explicitly or implicitly include at least one of the features. In addition, the technical solutions between the various embodiments can be combined with each other, but they must be based on the ability of ordinary technicians in the field to implement them. When the combination of technical solutions is contradictory or cannot be implemented, it should be deemed that such a combination of technical solutions does not exist and is not within the scope of protection required by the utility model.
[0032] like Figures 1 to 6 As shown, a sling tool comprises a sling 1;
[0033] A suspension rod 2, which is used to extend into the interior of the concrete block 3, and a plurality of suspension rods 2 are provided on the hanger 1;
[0034] The locking member 4 is arranged at one end of the suspension rod 2 extending into the concrete block 3, and the suspension rod 2 is rotatably arranged on the hanger 1, so that: after the suspension rod 2 extends into the reserved groove 31 of the concrete block 3, the suspension rod 2 is rotated to drive the locking member 4 to rotate synchronously so that it is buckled and fixed in the reserved groove 31.
[0035] This solution provides a new type of lifting tool, which greatly improves the lifting safety and lifting efficiency of the concrete block 3 by arranging a hanging rod 2 and a locking member 4 on the hanger 1 and pre-arranging a reserved groove 31 in the concrete block 3.
[0036] Specifically, before pouring the large concrete block 3, a reserved groove 31 for inserting the hanger 2 and the locking member 4 is reserved through template design. The retention of the reserved groove 31 will not affect the shape and strength of the concrete block 3. The hanger 1 is located above the concrete block 3, one end of the hanger 2 is fixed on the hanger 1, and the other end is just inserted into the reserved groove 31 reserved for the concrete block 3. There is a locking member 4 (which can be a locking iron shoe during actual lifting) under the hanger 2 that can withstand the weight of the concrete block. The locking member 4 can be fixed to the hanger 2 through a threaded pipe. The reserved groove 31 of the concrete block 3 is usually rectangular. After the locking member 4 is inserted along the reserved groove 31, the hanger 2 is rotated above the hanger 1, and the locking member 4 at the bottom of the hanger 2 is simultaneously rotated in the bottom direction, and the locking member 4 is stuck in the reserved groove 31 of the concrete, so that the hanger 1 and the concrete are lifted together, which has better stability and is safer during lifting.
[0037] Further, the reserved groove 31 includes a through groove 311 and a clamping groove 312 that penetrate each other, the through groove 311 is located above the clamping groove 312, and the width W1 of the through groove 311 is equal to the width W2 of the clamping groove 312, the length of the locking member 4 is less than the width W1 of the through groove 311, and the thickness D1 of the through groove 311 is less than the length of the locking member 4 and less than the thickness D2 of the clamping groove 312, so that:
[0038] After the locking member 4 passes through the through slot 311 and enters the locking slot 312 , the suspension rod 2 rotates 90°, and the locking member 4 turns and is buckled and fixed in the locking slot 312 .
[0039] The reserved groove 31 in the concrete includes two sections distributed up and down - a through groove 311 and a clamping groove 312, wherein the width of the suspension rod 2 and the locking portion are both smaller than the width of the through groove 311 and the clamping groove 312, so the suspension rod 2 and the locking portion can freely extend up and down; but the thickness of the through groove 311 is relatively small, and the thickness of the clamping groove 312 is relatively large, so after the suspension rod 2 and the locking portion extend into the clamping groove 312, the suspension rod 2 rotates 90 degrees in the forward or reverse direction so that the locking portion is perpendicular to the entry direction, and since the thickness of the clamping groove 312 is greater than the width of the locking portion and the width of the through groove 311, the locking portion will be firmly stuck in the clamping groove 312 to ensure that the concrete block 3 and the sling tooling are locked and fixed.
[0040] Furthermore, the length of the locking member 4 decreases gradually from top to bottom. The bottom end of the locking member 4 is smaller, which makes it easier for the locking member 4 to extend into the through slot 311 or the clamping slot 312 .
[0041] Furthermore, the hanger 1 comprises a first connecting rod 11, a second connecting rod 12, a third connecting rod 13 and a fourth connecting rod 14 connected end to end, the first connecting rod 11 and the third connecting rod 13 are arranged in parallel, and the second connecting rod 12 and the fourth connecting rod 14 are arranged in parallel;
[0042] The length of the first connecting rod 11 = the length of the third connecting rod 13 , the length of the second connecting rod 12 = the length of the fourth connecting rod 14 , and the length of the first connecting rod 11 > the length of the second connecting rod 12 .
[0043] like Figure 5 As shown, the lifting tool is used to make a balanced hanger 1 according to the reserved holes near the four corners of the concrete block 3. The hanger 1 includes four connecting rods, namely a first connecting rod 11, a second connecting rod 12, a third connecting rod 13 and a fourth connecting rod 14. It has better balance and stability, which is conducive to the lifting of large or heavy concrete blocks 3.
[0044] Of course, in other embodiments, the hanger 1 may be provided with more connecting rods to further improve its stability. Alternatively, the hanger 1 may also be a stable triangular structure, that is, the hanger 1 of this solution is composed of three connecting rods.
[0045] Furthermore, at least two suspension rods 2 are respectively disposed on the first connecting rod 11 and the third connecting rod 13 .
[0046] The first connecting rod 11 and the third connecting rod 13 are the long sides of the hanger 1, and the hanging rod 2 is arranged on the long sides of the hanger 1, which has better stability. At least two hanging rods 2 are arranged on the first connecting rod 11 and the third connecting rod 13, that is, there are four fixing points on the concrete block 3, which has better balance, and the concrete block 3 is not easy to move during the hoisting process, which further improves the safety during hoisting.
[0047] Furthermore, the hanger 1 is provided with a plurality of adjustment plates 15, each adjustment plate 15 corresponds to one of the hangers 2, an adjustment slot 151 is opened on the adjustment plate 15, an adjustment rod 152 is movably arranged in the adjustment slot 151, and the adjustment rod 152 passes through one end of the adjustment slot 151 and is connected to the hanger 2.
[0048] Due to errors and other reasons, the position of the reserved groove 31 of each batch of concrete blocks 3 may be different. In order to align the position of the hanger 2 with the reserved groove 31, an adjustment plate 15 including an adjustment groove 151 is provided on the hanger 1. The adjustment groove 151 is a long waist-shaped hole. The adjustment rod 152 can move forward and backward along the adjustment groove 151. Since the adjustment rod 152 is fixed to the hanger 2, the hanger 2 also moves synchronously when the adjustment rod 152 moves, so that the position of the hanger 2 and the reserved groove 31 is more consistent, which is convenient for fixing the concrete block 3.
[0049] Furthermore, a marking line 153 is further provided at the top of the adjusting rod 152, and the marking line 153 includes a first marking line and a second marking line, the first marking line and the second marking line are vertically intersected, and the length of the first marking line is greater than the length of the second marking line;
[0050] The first marking line is parallel to the length direction of the locking member 4 , and the second marking line is parallel to the width direction of the locking member 4 .
[0051] like Figure 6 As shown, by setting a marking line 153 on the adjusting rod 152 above the hanger 1, it is determined whether the hanger 2 is locked in place. The marking line 153 includes a first marking line (long line) and a second marking line (short line), and the two are in a cross shape. The marking line 153 corresponds to the length and width direction of the locking piece 4 at the bottom of the hanger 2. The first marking line corresponds to the length direction of the locking piece 4, and the second marking line corresponds to the width direction of the locking piece 4. The direction of the locking part can be known through the marking line 153 on the hanger 1.
[0052] Furthermore, the hanger 1 is provided with a plurality of lifting ears 16, and the lifting ears 16 are provided with lifting holes 161 for external lifting ropes to pass through. The hanger 1 is hoisted by the lifting ears 16, and the four corners of the hanger 1 can be provided with lifting ears 16. The lifting rope of the lifting equipment passes through the lifting holes 161 of the four lifting ears 16 on the hanger 1, and the balance is better, and the concrete block 3 can be better hoisted.
[0053] Furthermore, the outer wall of the suspension rod 2 is also provided with scale lines. In addition to the setting of the above-mentioned marking line 153, during the trial lifting / lifting process, the scale lines reserved on the suspension rod 2 can also be used to check whether the four suspension rods 2 are locked in place. After the suspension rod 2 is inserted into the concrete block 3, if the scale lines on the outside of the four suspension rods 2 remain consistent (a small error is allowed), it means that the insertion depth of all the suspension rods 2 is the same, which doubles the safety of the suspension tooling of this solution.
[0054] The above description is only a preferred embodiment of the present invention, and does not limit the patent scope of the present invention. All equivalent structural changes made by using the contents of the present invention specification and drawings under the inventive concept of the present invention, or directly / indirectly applied in other related technical fields are included in the patent protection scope of the present invention.
Claims
1. A lifting tool, characterized in that: include: Hanger (1); A suspension rod (2) is used to extend into the interior of the concrete block (3), and a plurality of suspension rods (2) are provided on the hanger (1); A locking member (4) is arranged at one end of the suspension rod (2) extending into the concrete block (3), and the suspension rod (2) is rotatably arranged on the hanger (1), so that: after the suspension rod (2) extends into the reserved groove (31) of the concrete block (3), the suspension rod (2) is rotated, driving the locking member (4) to rotate synchronously so that it is buckled and fixed in the reserved groove (31).
2. A sling tool according to claim 1, characterized in that: The reserved groove (31) comprises a through groove (311) and a clamping groove (312) which are interpenetrating with each other, the through groove (311) is located above the clamping groove (312), and the width W1 of the through groove (311) is equal to the width W2 of the clamping groove (312), the length of the locking member (4) is less than the width W1 of the through groove (311), the thickness D1 of the through groove (311) is less than the length of the locking member (4) and is less than the thickness D2 of the clamping groove (312), so that: After the locking member (4) passes through the through slot (311) and enters the clamping slot (312), the suspension rod (2) rotates 90 degrees, and the locking member (4) turns and is buckled and fixed in the clamping slot (312).
3. A sling tool according to claim 1, characterized in that: From top to bottom, the length of the locking member (4) gradually decreases.
4. A sling tool according to claim 1, characterized in that: The hanger (1) comprises a first connecting rod (11), a second connecting rod (12), a third connecting rod (13) and a fourth connecting rod (14) connected end to end, the first connecting rod (11) and the third connecting rod (13) are arranged in parallel, and the second connecting rod (12) and the fourth connecting rod (14) are arranged in parallel; The length of the first connecting rod (11) = the length of the third connecting rod (13), the length of the second connecting rod (12) = the length of the fourth connecting rod (14), and the length of the first connecting rod (11) > the length of the second connecting rod (12).
5. A sling tool according to claim 4, characterized in that: At least two suspension rods (2) are respectively provided on the first connecting rod (11) and the third connecting rod (13).
6. A sling tool according to claim 2, characterized in that: The hanger (1) is also provided with a plurality of adjustment plates (15), each adjustment plate (15) corresponds to one of the hangers (2), an adjustment slot (151) is provided on the adjustment plate (15), an adjustment rod (152) is movably arranged in the adjustment slot (151), and the adjustment rod (152) passes through one end of the adjustment slot (151) and is connected to the hanger (2).
7. A sling tool according to claim 6, characterized in that: The top of the adjusting rod (152) is also provided with a marking line (153), the marking line (153) comprises a first marking line and a second marking line, the first marking line and the second marking line are arranged to cross each other vertically, and the length of the first marking line is greater than the length of the second marking line; The first marking line is parallel to the length direction of the locking member (4), and the second marking line is parallel to the width direction of the locking member (4).
8. The sling tool according to claim 1, characterized in that: The hanger (1) is also provided with a plurality of lifting ears (16), and the lifting ears (16) are provided with lifting holes (161) for external lifting ropes to pass through.
9. The sling tool according to claim 1, characterized in that: The outer wall of the suspension rod (2) is also provided with scale lines.
Citation Information
Cited By
Lifting method capable of adjusting posture of prefabricated square block and lifting appliance thereof
CN120573586A