A ground-type scaffolding settlement observation device
By designing a floor-standing scaffolding settlement observation device including a rangefinder, a protective cover, a horizontal level bubble meter and a settlement column, the problem of poor protection of the settlement observation device in the prior art is solved, and higher protection capabilities and observation accuracy are achieved.
Patent Information
- Application Number
- CN202421355874.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-14
- Publication Date
- 2025-04-08
- Estimated Expiration
- 2034-06-14
AI Technical Summary
During the construction of floor-standing scaffolding facilities, when using instruments for settlement observation in the prior art, the installation is poorly protected and easy to affect the settlement observation effect.
A floor-standing scaffolding settlement observation device is designed, including fastener steel pipe scaffolding, top and bottom connecting pipes, rangefinders, protective covers, horizontal level bubble meter and settlement column. Through the coordinated work of these components, the protection, bottom observation and connection capabilities of the device are improved.
The device not only improves the protection capability, enhances the accuracy and reliability of settlement observations, but also improves the connection capability, ensuring the effectiveness of settlement observations.
Smart Images

Figure CN222733581U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of settlement observation, in particular to a ground-type scaffold settlement observation device. Background Art
[0002] Floor-type scaffolding is a kind of supporting equipment used in construction sites. It is characterized by being directly erected on the ground or floor slab and fixed on the ground to provide a stable working platform for workers to perform aerial work. This type of scaffolding is usually made of aluminum alloy or steel, and its connection methods include steel pipe fastener connection;
[0003] Among them, the fastener-type steel pipe scaffolding is also set up for construction. It has the ability to bear loads. The scaffolding and support frame are composed of fasteners and steel pipes. The fasteners are snap-on connectors fastened with bolts. During the construction of ground-type scaffolding, it is essential to monitor the settlement value of the scaffolding. Therefore, a settlement observation device will be needed to complete the settlement observation work. Generally speaking, instruments will be used for use, and when in use, it is usually installed in a leaky manner. At this time, if the protection is poor, it will easily directly affect the settlement observation effect. Utility Model Content
[0004] The purpose of the utility model is to provide a ground-type scaffolding settlement observation device to solve the problem proposed in the above-mentioned background technology that generally instruments are used, but when in use they are generally installed in a leaky manner. At this time, if the protection is poor, it is easy to directly affect the settlement observation effect.
[0005] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: a ground-type scaffolding settlement observation device, comprising a coupler-type steel pipe scaffolding and a bottom connecting pipe, top connecting pipes are fixed at positions near the top on both sides of the coupler-type steel pipe scaffolding, the front end of the top connecting pipe is connected with a first connecting piece, a fixing plate is installed at a position near the top at the front end of the first connecting piece, side vertical plates are installed on both sides of the bottom end of the fixing plate, a rangefinder is connected between the side vertical plates, a mounting plate is connected to the front end of the side vertical plate, a mounting plate is installed at the top of the mounting plate, a protective cover is fixed between the mounting plates, an arc groove is opened at the back end of the protective cover, and a first protective pad is fixed to the inner wall of the arc groove.
[0006] Preferably, the top connecting pipes are symmetrically distributed about the central axis of the fastener-type steel pipe scaffolding, and the side uprights are symmetrically distributed about the central axis of the fixed plate.
[0007] Preferably, the mounting plates are symmetrically distributed about the central axis of the protective cover, and an adhesive connection is formed between the arc-shaped groove and the first protective pad.
[0008] Preferably, the back end of the first connecting piece is connected to the second connecting piece, the top and bottom ends of the first connecting piece and the second connecting piece are both installed with docking pieces, one end of the first connecting piece and the second connecting piece is connected to a retaining spring, one end of the retaining spring is connected to an arc-shaped clamping plate, and one end of the arc-shaped clamping plate is bonded and connected to a second protective pad.
[0009] Preferably, the butt joint plates are symmetrically distributed about the central axis of the first connecting plate, and the two butt joint plates are connected by bolts.
[0010] Preferably, three groups of the clips are evenly distributed on one end of the arc-shaped clamping plate, and an adhesive connection is formed between the arc-shaped clamping plate and the second protective pad.
[0011] Preferably, a settlement column is installed at the bottom end of the bottom connecting pipe, and the settlement columns are symmetrically distributed about the central axis of the fastener type steel pipe scaffolding.
[0012] Preferably, a horizontal level bubble meter is installed at a position near the top of the front end of the sedimentation column, and a marking line is installed on one side of the front end of the sedimentation column.
[0013] Compared with the prior art, the beneficial effects of the utility model are: the ground-type scaffolding settlement observation device not only improves the protection capability, but also improves the bottom observation capability and connection capability of the settlement observation device;
[0014] (1) The top connecting pipe is installed on both sides of the fastener-type steel pipe scaffold near the top, and then the connection and installation of the first connecting plate are completed. The fixing plate is fixed at the front end of the first connecting plate near the top, and the connection and installation of the rangefinder are completed by using the side stand plate. The connection and installation between the protective cover and the side stand plate are completed by using the installation plate. Therefore, the protective cover can be installed at the front end of the side stand plate, and an arc groove is provided inside the protective cover. The position of the arc groove is adapted to the rangefinder. The first protective pad is used for contact protection, so that the protective cover can be used to provide external protection for the rangefinder, thereby better improving the overall protection capability when the rangefinder is detected;
[0015] (2) By installing the sedimentation column at the bottom end of the bottom connecting pipe, and then installing the horizontal bubble level at the front end of the sedimentation column near the top end, the horizontal bubble level can be used for horizontal observation, and the front end of the sedimentation column is fixed with a scale line, which can visually observe the sedimentation distance of the sedimentation column, thereby better improving the overall bottom observation ability during the work process;
[0016] (3) The connection and installation between the first connecting piece and the second connecting piece are completed by using the docking piece, so that the two can be installed on the outside of the bottom connecting pipe. During installation, the arc-shaped clamping plate is used for contact protection, and when in contact, the second protection pad directly contacts with it to play a soft protection role, thereby better improving the overall connection ability during the working process. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] Figure 1 This is a schematic diagram of the main structure of the utility model;
[0018] Figure 2 It is a partial front view structural diagram of the top connecting pipe of the utility model;
[0019] Figure 3 This is a schematic diagram of the top view structure of the protective cover of the utility model;
[0020] Figure 4 It is a schematic diagram of the side structure of the first connecting piece of the utility model.
[0021] In the figure: 1. fastener-type steel pipe scaffolding; 2. top connecting pipe; 3. bottom connecting pipe; 4. settlement column; 5. marking line; 6. horizontal bubble level; 7. first connecting plate; 8. fixing plate; 9. rangefinder; 10. side plate; 11. mounting plate; 12. protective cover; 13. arc groove; 14. first protective pad; 15. mounting plate; 16. retaining spring; 17. arc clamping plate; 18. docking plate; 19. second connecting plate; 20. second protective pad. DETAILED DESCRIPTION
[0022] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0023] See also Figure 1-4The utility model provides an embodiment: a ground-type scaffolding settlement observation device, comprising a coupler-type steel pipe scaffolding 1 and a bottom connecting pipe 3. Top connecting pipes 2 are fixed at positions near the top on both sides of the coupler-type steel pipe scaffolding 1, and the front end of the top connecting pipe 2 is connected with a first connecting piece 7. A fixing plate 8 is installed at a position near the top of the front end of the first connecting piece 7. Side vertical plates 10 are installed on both sides of the bottom end of the fixing plate 8. A rangefinder 9 is connected between the side vertical plates 10. A mounting plate 11 is connected to the front end of the side vertical plate 10. A mounting plate 15 is installed at the top of the mounting plate 11. A protective cover 12 is fixed between the mounting plates 11. An arc groove 13 is opened at the back end of the protective cover 12. A first protective pad 14 is fixed to the inner wall of the arc groove 13.
[0024] The top connecting pipe 2 is symmetrically distributed about the central axis of the fastener type steel pipe scaffold 1 , and the side vertical plates 10 are symmetrically distributed about the central axis of the fixed plate 8 .
[0025] The mounting plates 11 are symmetrically distributed about the central axis of the protective cover 12 , and an adhesive connection is formed between the arc groove 13 and the first protective pad 14 .
[0026] The back end of the first connecting piece 7 is connected to the second connecting piece 19, and the top and bottom ends of the first connecting piece 7 and the second connecting piece 19 are both installed with docking pieces 18. One end of the first connecting piece 7 and the second connecting piece 19 is connected to a retaining spring 16, one end of the retaining spring 16 is connected to an arc-shaped clamping plate 17, and one end of the arc-shaped clamping plate 17 is bonded and connected to a second protective pad 20.
[0027] The butt joint pieces 18 are symmetrically distributed about the central axis of the first connecting piece 7 , and the two butt joint pieces 18 are connected by bolts.
[0028] Three groups of the clamping springs 16 are evenly distributed at one end of the arc-shaped clamping plate 17 , and an adhesive connection is formed between the arc-shaped clamping plate 17 and the second protective pad 20 .
[0029] A settlement column 4 is installed at the bottom end of the bottom connecting pipe 3 , and the settlement columns 4 are symmetrically distributed about the central axis of the fastener type steel pipe scaffold 1 .
[0030] A horizontal bubble level 6 is installed at the front end of the sedimentation column 4 near the top, and a marking line 5 is installed on one side of the front end of the sedimentation column 4;
[0031] The first connecting piece 7 and the second connecting piece 19 are further connected and installed by using the butt joint piece 18, and bolts are used to fit with them to form an integrated connection during installation;
[0032] Furthermore, the detection value of the rangefinder 9 is transmitted to a remote terminal, which may be a mobile phone or computer terminal of a staff member.
[0033] Working principle: First, during operation, the top connecting pipe 2 is installed on both sides of the coupler type steel pipe scaffolding 1 near the top, and the connection and installation between the first connecting piece 7 and the second connecting piece 19 are completed by the docking piece 18, so that the two can be installed on the outside of the bottom connecting pipe 3. During installation, the arc-shaped clamping plate 17 is used for contact protection, and the side vertical plate 10 is used to complete the connection and installation of the rangefinder 9. The rangefinder 9 detects the distance to the ground to obtain the settlement data, and the horizontal level bubble meter 6 is installed at the front end of the settlement column 4 near the top position. The horizontal level bubble meter 6 is used to observe the horizontal state of the coupler type steel pipe scaffolding 1, and the front end of the settlement column 4 is fixed with a marking line 5. The marking line 5 can intuitively observe the settlement distance of the settlement column 4, so as to obtain the settlement value through the data of both parties.
[0034] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installation", "connection" and "connection" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
Claims
1. A ground-type scaffolding settlement observation device, comprising a fastener-type steel pipe scaffolding (1) and a bottom connecting pipe (3), characterized in that: A top connecting pipe (2) is fixed at a position close to the top on both sides of the fastener-type steel pipe scaffold (1), the front end of the top connecting pipe (2) is connected to a first connecting piece (7), a fixing plate (8) is installed at a position close to the top on the front end of the first connecting piece (7), side vertical plates (10) are installed on both sides of the bottom end of the fixing plate (8), a distance meter (9) is connected between the side vertical plates (10), the front end of the side vertical plates (10) is connected to a mounting plate (11), the top end of the mounting plate (11) is installed with a mounting piece (15), a protective cover (12) is fixed between the mounting plates (11), an arc groove (13) is opened at the back end of the protective cover (12), and a first protective pad (14) is fixed to the inner wall of the arc groove (13).
2. A ground-type scaffolding settlement observation device according to claim 1, characterized in that: The top connecting pipe (2) is symmetrically distributed about the central axis of the fastener-type steel pipe scaffold (1), and the side upright plates (10) are symmetrically distributed about the central axis of the fixing plate (8).
3. A ground-type scaffolding settlement observation device according to claim 1, characterized in that: The mounting plate (11) is symmetrically distributed about the central axis of the protective cover (12), and an adhesive connection is formed between the arc-shaped groove (13) and the first protective pad (14).
4. A ground-type scaffolding settlement observation device according to claim 1, characterized in that: The back end of the first connecting piece (7) is connected to the second connecting piece (19), the top and bottom ends of the first connecting piece (7) and the second connecting piece (19) are both installed with docking pieces (18), one end of the first connecting piece (7) and the second connecting piece (19) is connected to a retaining spring (16), one end of the retaining spring (16) is connected to an arc-shaped clamping plate (17), and one end of the arc-shaped clamping plate (17) is bonded and connected to a second protective pad (20).
5. A ground-type scaffolding settlement observation device according to claim 4, characterized in that: The butt joint pieces (18) are symmetrically distributed about the central axis of the first connecting piece (7), and the two butt joint pieces (18) are connected by bolts.
6. A ground-type scaffolding settlement observation device according to claim 4, characterized in that: The clamping spring (16) is evenly distributed in three groups at one end of the arc-shaped clamping plate (17), and an adhesive connection is formed between the arc-shaped clamping plate (17) and the second protective pad (20).
7. The ground-type scaffolding settlement observation device according to claim 1, characterized in that: A settlement column (4) is installed at the bottom end of the bottom connecting pipe (3), and the settlement columns (4) are symmetrically distributed about the central axis of the fastener-type steel pipe scaffold (1).
8. A ground-type scaffolding settlement observation device according to claim 7, characterized in that: A horizontal bubble level (6) is installed at a position near the top of the front end of the sedimentation column (4), and a marking line (5) is installed on one side of the front end of the sedimentation column (4).