Anchoring assembly and steel pipe concrete column
By pre-embedding the anchor components in the steel pipe concrete column, the problems of unstable connection between the steel beam and the steel pipe concrete column are solved, and high-strength and strong earthquake resistance are achieved, and the construction process is simplified, which is suitable for reuse.
Patent Information
- Application Number
- CN202421377934.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-17
- Publication Date
- 2025-05-13
- Estimated Expiration
- 2034-06-17
AI Technical Summary
During construction, the quality of the connection between the steel beam and the steel pipe concrete column depends on welding and drilling operations, resulting in unstable connections, low construction efficiency, and unsuitable for reuse.
Design a steel pipe concrete column with pre-embedded anchor components. Through the pre-embedded anchor components and concrete filling of the anchor components, the fastening connection between the steel beams and the steel pipe concrete columns can be achieved. Flexible disassembly and assembly and reused without welding or drilling.
The tightness, stability, structural stiffness and strength of the connection positions between the steel pipe concrete columns and steel beams is improved, the compressive bearing capacity and earthquake resistance are enhanced, the construction process is simplified, the construction convenience is improved, and the reuse of the steel pipe concrete columns and steel beams is realized.
Smart Images

Figure CN222862503U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of building components, in particular to an anchoring assembly and a steel tube concrete column with the anchoring assembly. Background Art
[0002] Concrete-filled steel tube components, also known as steel tube concrete columns, have been widely used in the construction industry due to their superior strength, ductility, aesthetics, bearing capacity and ease of construction. The performance of steel tube concrete columns mainly depends on the composite effect between the outer steel tube and the inner concrete. The outer steel tube provides sufficient restraint effect for the concrete core, while the filled concrete core delays the occurrence of local buckling of the outer steel tube.
[0003] During the construction process, steel beams need to be connected to steel tube concrete columns to form a building frame. Usually, steel beams are connected to the outer steel pipes of steel tube concrete columns by welding. However, the quality of welding at the construction site depends closely on the experience of the workers and the temperature and humidity conditions at the construction site, which leads to unstable welding quality, thus affecting the quality of the stable connection between the steel beam and the outer steel pipe of the steel tube concrete column, and increasing the work intensity of the workers, resulting in low construction efficiency, and both the steel tube concrete column and the steel beam cannot be reused.
[0004] In order to avoid the adverse effects of welding, the existing method is to open a through hole in the outer steel pipe of the steel tube concrete column. When installing the steel beam, the worker needs to hold a drilling device to drill the corresponding position of the concrete core of the steel tube concrete column and the through hole of the outer steel pipe to form a blind hole at the corresponding position of the concrete core and the through hole, and place an expansion sleeve in the blind hole, and then pass the threaded end of the bolt through the connecting wall of the steel beam and the through hole of the outer steel pipe to connect with the expansion sleeve, so as to connect the steel beam to the steel tube concrete column. However, the quality of the worker holding the drilling equipment to drill the corresponding position of the concrete core and the through hole depends on the worker's experience. The blind hole formed by the drilling has an offset phenomenon, which affects the coaxiality of the blind hole and the through hole, thereby affecting the connection stability of the steel beam and the steel tube concrete column, and increases the work intensity of the workers. The construction efficiency is low, and the drilling operation causes damage to the concrete core. When reused, the old expansion sleeve needs to be taken out and a new expansion sleeve is put in, which makes the disassembly and assembly operation of reuse complicated, and the removal operation of the old expansion sleeve causes pull-out damage to the concrete core. Utility Model Content
[0005] In order to achieve the first purpose of the utility model, the utility model provides a steel tube concrete column with a pre-embedded anchor component, which can be fastened to the steel beam without the need for workers to weld or drill holes, so that the disassembly and assembly of the steel tube concrete column and the steel beam are flexible and simple, thereby achieving the purpose of reuse and saving resources, and improving the tightness, stability, structural stiffness and strength, compressive bearing capacity and seismic resistance of the connection position between the steel tube concrete column and the steel beam, thereby improving the bearing capacity of the steel tube concrete column and the convenience of construction.
[0006] In order to achieve the second purpose of the utility model, the utility model provides an anchoring assembly pre-buried in the above-mentioned steel tube concrete column, which can realize the fastening connection between the steel tube concrete column and the steel beam without the need for workers to weld or drill holes, so that the disassembly and assembly of the steel tube concrete column and the steel beam are flexible and simple, achieving the purpose of reuse and saving resources, and improving the fastening, stability, structural stiffness and strength, compressive bearing capacity and seismic resistance of the connection position between the steel tube concrete column and the steel beam, thereby improving the bearing capacity of the steel tube concrete column and the convenience of construction.
[0007] In order to achieve the first purpose of the utility model, the utility model provides a steel tube concrete column, including a steel tube and an anchor assembly, the circumferential wall of the steel tube is penetrated with a through hole, the anchor assembly includes a first anchor block and a first fastener, the first end face of the first anchor block is provided with a first threaded hole, the threaded rod of the first fastener is detachably threadedly connected to the first threaded hole, the first anchor block can be inserted into the interior of the circumferential wall through the through hole, the rod section of the first fastener is penetrated in the through hole and can be rotatably and / or movably arranged relative to the through hole, the first The fastener can drive the first anchor block located inside the circumferential wall to rotate and / or move, so that the abutting end face of the first end face protruding from the first threaded hole abuts against the inner wall surface of the circumferential wall, and the head of the first fastener can abut against the outer wall surface of the circumferential wall, and concrete is filled in the interior of the circumferential wall to restrict the first anchor block with the abutting end face abutting against the inner wall surface within the circumferential wall, and the steel beam can be detachably threadedly connected to the first threaded hole of the first anchor block confined inside the circumferential wall through the first fastener or the second fastener.
[0008] A further solution is that the through hole is arranged in a polygonal or elliptical shape, and the shape of the cross-section of the first anchor block perpendicular to the axial direction of the first threaded hole is adapted to the shape of the through hole; and / or, the abutment end face and the inner wall surface are arc-shaped surfaces adapted to abut each other; and / or, the abutment end face and the inner wall surface are flat surfaces adapted to abut each other.
[0009] A further solution is that a first groove is formed inwardly on the outer peripheral surface of the first anchor block in the circumferential direction of the first threaded hole, and the first groove can be filled with concrete.
[0010] A further solution is that the rod segment is a partial rod segment of a threaded rod, the head is a nut, the nut and the threaded rod are detachably threadedly connected, and the nut can abut against the outer wall surface or the connecting wall of the steel beam; or, the first fastener is a first bolt; and / or, the second fastener is a second bolt.
[0011] A further solution is that the rod section is provided with a first gasket, which abuts against the outer wall surface or between the connecting wall and the head of the steel beam; and / or the rod portion of the second fastener is provided with a second gasket, which abuts against the connecting wall of the steel beam and the shoulder of the second fastener.
[0012] A further solution is that the anchor assembly also includes a second anchor block and a connecting rod, the first anchor block is provided with a second threaded hole at a second end face arranged opposite to the first end face in the axial direction of the first threaded hole, the second anchor block is provided with a third threaded hole at an end face close to the first anchor block, the first threaded end of the connecting rod is detachably threadedly connected to the second threaded hole, and the second threaded end of the connecting rod is detachably threadedly connected to the third threaded hole; the second anchor block and the connecting rod can be inserted into the interior of the annular wall through the through hole, and the concrete will limit the second anchor block and the connecting rod inserted into the interior of the annular wall to the interior of the annular wall.
[0013] A further solution is that the second anchor block is provided with a second groove on the outer peripheral surface in the circumferential direction of the connecting rod, and the second groove can be filled with concrete; and / or, the cross-section of the first anchor block perpendicular to the axial direction of the first threaded hole is rectangular or elliptical, and the cross-section of the second anchor block perpendicular to the axial direction of the first threaded hole is rectangular or elliptical, and the long axis direction of the first anchor block and the long axis direction of the second anchor block are arranged perpendicular to each other; and / or, the connecting rod is coaxially arranged with the first threaded hole.
[0014] In order to achieve the second purpose of the utility model, the utility model provides an anchoring assembly, including a first anchoring block, a first fastener, a second anchoring block and a connecting rod, a first end face of the first anchoring block is provided with a first threaded hole, the threaded rod of the first fastener is detachably threadedly connected to the first threaded hole, a head is provided at an end of the first fastener away from the first anchoring block, a second threaded hole is provided on the second end face of the first anchoring block which is arranged opposite to the first end face in the axial direction of the first threaded hole, a third threaded hole is provided on the end face of the second anchoring block close to the first anchoring block, the first threaded end of the connecting rod is detachably threadedly connected to the second threaded hole, and the second threaded end of the connecting rod is detachably threadedly connected to the third threaded hole.
[0015] It can be seen from the above scheme that during the construction process of the steel tube concrete column of the utility model, the specific construction method of the steel tube concrete column includes: first, the first anchor block of the anchor assembly is inserted into the interior of the circumferential wall of the steel tube through the through hole on the circumferential wall of the steel tube, at which time the threaded rod of the first fastener of the anchor assembly is threadedly connected with the first threaded hole of the first anchor block, so that the worker can grasp the first fastener of the anchor assembly to quickly pass the first anchor block of the anchor assembly through the through hole on the circumferential wall of the steel tube and insert it into the interior of the circumferential wall of the steel tube, and the worker's operation is convenient; then, the worker grasps the first fastener of the anchor assembly to control the first fastener of the anchor assembly to rotate and / or move, so as to drive the first anchor block located inside the circumferential wall of the steel tube to rotate and / or move, so that the abutting end face of the first anchor block abuts against the inner wall surface of the circumferential wall of the steel tube; then, the worker fastens the first fastener of the anchor assembly The head of the member abuts against the outer wall surface of the circumferential wall of the steel pipe to fasten the anchor assembly as a whole to the circumferential wall of the steel pipe. Specifically, the gap between the first fastener and the through hole can be filled with a sealing member, so that the inner cavity of the circumferential wall of the steel pipe is in a sealed state, thereby avoiding overflow at the through hole during subsequent concrete filling; further, concrete is filled into the interior of the circumferential wall of the steel pipe to limit the first anchor block whose abutting end face abuts against the inner wall surface of the circumferential wall to the interior of the circumferential wall of the steel pipe, so that the first anchor block of the anchor assembly is fastened and embedded in the concrete filled inside the circumferential wall of the steel pipe; thereafter, the first fastener of the anchor assembly is removed from the first anchor block restricted by the concrete inside the circumferential wall; then, the steel beam is threadedly connected to the first threaded hole of the first anchor block restricted inside the circumferential wall of the steel pipe through the first fastener or the second fastener.
[0016] Therefore, the steel tube concrete column of the utility model is pre-embedded with an anchoring assembly before pouring the concrete core. After the concrete is filled into the circumferential wall of the steel tube of the steel tube concrete column, the first anchoring block of the pre-embedded anchoring assembly can be firmly confined inside the circumferential wall of the steel tube, so that the first anchoring block of the anchoring assembly is firmly embedded in the concrete filled inside the circumferential wall of the steel tube, and the steel beam can be threadedly connected to the first threaded hole of the first anchoring block confined inside the circumferential wall of the steel tube through the first fastener or the second fastener. Among them, the abutting end face of the first anchoring block of the anchoring assembly of the utility model abuts against the inner wall surface of the circumferential wall of the steel tube, which can improve the stiffness, compressive bearing capacity and anchoring effect of the connection between the steel tube concrete column and the steel beam, thereby improving the tightness, stability, structural stiffness and strength, compressive bearing capacity and earthquake resistance of the connection position between the steel tube concrete column and the steel beam. Moreover, the entire construction process of the steel tube concrete column of the utility model can be fastened to the steel beam without welding or drilling by workers. During the installation of the steel beam, the first fastener only needs to be disassembled from the first anchor block restricted by concrete inside the circumferential wall, and the steel beam can be threadedly connected to the first threaded hole of the first anchor block restricted inside the circumferential wall of the steel pipe through the first fastener or the second fastener. During the disassembly of the steel beam, the steel beam can be disassembled from the steel tube concrete column only needs to be disassembled from the first fastener or the second fastener, and the first fastener can be threadedly connected to the first threaded hole of the first anchor block restricted inside the circumferential wall of the steel pipe, so as to avoid dust or debris entering the first threaded hole of the first anchor block restricted inside the circumferential wall of the steel pipe and affecting the subsequent reuse, so that the disassembly and assembly operation of the steel tube concrete column and the steel beam is flexible and simple, so as to achieve the purpose of reuse and resource saving. Therefore, the steel tube concrete column of the utility model improves the bearing capacity of the steel tube concrete column while also improving the convenience of construction. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] Figure 1 It is a structural diagram of the connection between an embodiment of a steel tube concrete column of the utility model and a steel beam.
[0018] Figure 2 It is a cross-sectional view of the connection between the concrete-concrete steel tube column embodiment of the utility model and the steel beam.
[0019] Figure 3 yes Figure 2 Enlarged view at A.
[0020] Figure 4 It is a structural diagram of the anchoring assembly in the embodiment of the steel tube concrete column of the utility model.
[0021] Figure 5 It is an exploded view of the anchoring assembly in the embodiment of the steel tube concrete column of the utility model.
[0022] Figure 6 It is a structural diagram of the second anchor block in the embodiment of the steel tube concrete column of the utility model.
[0023] Figure 7 It is a structural diagram of the first anchor block in the embodiment of the steel tube concrete column of the utility model.
[0024] Figure 8 It is a structural diagram of the steel pipe in the embodiment of the steel pipe concrete column of the utility model.
[0025] Fig. 9 It is a schematic diagram of the first construction state of the steel tube concrete column embodiment of the utility model.
[0026] Fig.10 It is a schematic diagram of a second construction state of an embodiment of a steel tube concrete column of the utility model.
[0027] Fig.11 It is a cross-sectional view of a second construction state of a steel tube concrete column embodiment of the utility model.
[0028] Fig.12 It is a schematic diagram of the third construction state of the steel tube concrete column embodiment of the utility model.
[0029] Fig.13 It is a schematic diagram of the fourth construction state of the steel tube concrete column embodiment of the utility model.
[0030] Fig.14 It is a sectional view of the fourth construction state of the steel tube concrete column embodiment of the utility model.
[0031] Fig.15 It is a schematic diagram of another implementation of the steel tube in the steel tube concrete column embodiment of the utility model.
[0032] Fig.16 It is another schematic diagram of the steel beam in the embodiment of the steel tube concrete column of the utility model.
[0033] Fig.17 It is a schematic diagram of a first implementation mode of cooperation between a first anchor block and a through hole in an embodiment of a steel tube concrete column of the utility model.
[0034] Fig.18 It is a schematic diagram of a second implementation mode of the cooperation between the first anchor block and the through hole in the embodiment of the steel tube concrete column of the utility model.
[0035] Fig.19 It is a schematic diagram of a third implementation mode of the cooperation between the first anchor block and the through hole in the embodiment of the steel tube concrete column of the utility model.
[0036] Fig. 20 It is a schematic diagram of a fourth implementation method of the first anchor block and the through hole in the embodiment of the steel tube concrete column of the utility model.
[0037] The present invention will be further described below with reference to the accompanying drawings and embodiments. DETAILED DESCRIPTION
[0038] See also Figures 1 to 8 The present embodiment discloses a steel tube concrete column, comprising a steel tube 10 and an anchor assembly 15. A through hole 111 is formed through the circumferential wall 11 of the steel tube 10. The anchor assembly 15 comprises a first anchor block 151 and a first fastener 154. A first threaded hole 1512 is formed on the first end surface of the first anchor block 151. The threaded rod of the first fastener 154 is detachably threadedly connected to the first threaded hole 1512 of the first anchor block 151. In the present embodiment, the first anchor block 151 can be inserted into the circumferential wall 11 of the steel tube 10 through the through hole 111 of the steel tube 10. The rod section of the first fastener 154 is inserted into the through hole 111 of the steel tube 10 and can be rotatably and / or movably arranged relative to the through hole 111. Furthermore, the first fastener 154 of the present embodiment can drive the first anchor block 151 located inside the circumferential wall 11 of the steel pipe 10 to rotate and / or move, so that the abutting end face 1514 of the first end face of the first anchor block 151 protruding from the first threaded hole 1512 abuts against the inner wall surface of the circumferential wall 11 of the steel pipe 10, and the head of the first fastener 154 can abut against the outer wall surface of the circumferential wall 11 of the steel pipe 10. In addition, the concrete 12 is filled inside the circumferential wall 11 of the steel pipe 10 to restrict the first anchor block 151 whose abutting end face 1514 abuts against the inner wall surface of the circumferential wall 11 inside the circumferential wall 11 of the steel pipe 10, and the steel beam 13 can be detachably threadedly connected to the first threaded hole 1512 of the first anchor block 151 restricted inside the circumferential wall 11 of the steel pipe 10 by the first fastener 154 or the second fastener 14.
[0039] During the construction of the steel tube concrete column in this embodiment, the specific construction method of the steel tube concrete column includes:
[0040] First, the first anchor block 151 of the anchor assembly 15 is inserted into the interior of the circumferential wall 11 of the steel pipe 10 through the through hole 111 on the circumferential wall 11 of the steel pipe 10. At this time, the threaded rod of the first fastener 154 of the anchor assembly 15 is threadedly connected with the first threaded hole 1512 of the first anchor block 151, so that the worker can grasp the first fastener 154 of the anchor assembly 15 to quickly insert the first anchor block 151 of the anchor assembly 15 through the through hole 111 on the circumferential wall 11 of the steel pipe 10 into the interior of the circumferential wall 11 of the steel pipe 10, which is convenient for the worker to operate;
[0041] Next, the worker grasps the first fastener 154 of the anchor assembly 15 to control the first fastener 154 of the anchor assembly 15 to rotate and / or move, so as to drive the first anchor block 151 located inside the circumferential wall 11 of the steel pipe 10 to rotate and / or move, so that the abutting end surface 1514 of the first anchor block 151 abuts against the inner wall surface of the circumferential wall 11 of the steel pipe 10;
[0042] Subsequently, the worker places the head of the first fastener 154 of the anchor assembly 15 against the outer wall surface of the circumferential wall 11 of the steel pipe 10 to fasten the anchor assembly 15 as a whole to the circumferential wall 11 of the steel pipe 10. Specifically, the gap between the first fastener 154 and the through hole 111 may be filled with a sealant, so that the inner cavity of the circumferential wall 11 of the steel pipe 10 is in a sealed state, thereby preventing the subsequent concrete 12 from overflowing at the through hole 111;
[0043] Further, the concrete 12 is filled into the circumferential wall 11 of the steel pipe 10 to restrict the first anchor block 151 whose abutting end face 1514 abuts against the inner wall surface of the circumferential wall 11 to the inside of the circumferential wall 11 of the steel pipe 10, so that the first anchor block 151 of the anchor assembly 15 is firmly embedded in the concrete 12 filled in the circumferential wall 11 of the steel pipe 10;
[0044] Afterwards, the first fastener 154 of the anchor assembly 15 is removed from the first anchor block 151 that is restrained by the concrete 12 inside the circumferential wall 11;
[0045] Then, the steel beam 13 is threadedly connected to the first threaded hole 1512 of the first anchor block 151 confined inside the circumferential wall 11 of the steel pipe 10 through the first fastener 154 or the second fastener 14 .
[0046] Therefore, the steel tube concrete column of this embodiment is pre-embedded with an anchor component 15 before pouring the inner core of the concrete 12. After the concrete 12 is filled into the circumferential wall 11 of the steel tube 10 of the steel tube concrete column, the first anchor block 151 of the pre-embedded anchor component 15 can be firmly confined inside the circumferential wall 11 of the steel tube 10, so that the first anchor block 151 of the anchor component 15 is firmly embedded in the concrete 12 filled inside the circumferential wall 11 of the steel tube 10, and the steel beam 13 can be threadedly connected with the first threaded hole 1512 of the first anchor block 151 confined inside the circumferential wall 11 of the steel tube 10 through the first fastener 154 or the second fastener 14. Among them, the abutting end face 1514 of the first anchor block 151 of the anchor assembly 15 of the present embodiment abuts against the inner wall surface of the circumferential wall 11 of the steel pipe 10, which can improve the rigidity, compressive bearing capacity and anchoring effect of the connection between the steel pipe concrete column and the steel beam 13, thereby improving the tightness, stability, structural rigidity and strength, compressive bearing capacity and earthquake resistance of the connection position between the steel pipe concrete column and the steel beam 13. Moreover, the entire construction process of the steel pipe concrete column of the present embodiment can achieve a fastened connection with the steel beam 13 without the need for workers to weld or drill holes. During the installation of the steel beam 13, it is only necessary to remove the first fastener 154 from the first anchor block 151 restricted by the concrete 12 inside the circumferential wall 11, and then the steel beam 13 can be threadedly connected to the first threaded hole 1512 of the first anchor block 151 restricted inside the circumferential wall 11 of the steel pipe 10 through the first fastener 154 or the second fastener 14. During the removal of the steel beam 13, it is only necessary to remove the first fastener 154 from the first anchor block 151 restricted by the concrete 12 inside the circumferential wall 11. After the fastener 154 or the second fastener 14 is removed, the steel beam 13 can be removed from the steel tube concrete column, and the first fastener 154 can be threadedly connected to the first threaded hole 1512 of the first anchor block 151 confined inside the circumferential wall 11 of the steel tube 10, so as to prevent dust or debris from entering the first threaded hole 1512 of the first anchor block 151 confined inside the circumferential wall 11 of the steel tube 10 and affecting subsequent reuse, so that the disassembly and assembly operation of the steel tube concrete column and the steel beam 13 is flexible and simple, thereby achieving the purpose of reuse and saving resources. Therefore, the steel tube concrete column of this embodiment improves the bearing capacity of the steel tube concrete column while also improving the convenience of construction.
[0047] Combination Figure 1 , which is an implementation method of the steel pipe 10 and the steel beam 13 of this embodiment, that is, the circumferential wall 11 of the steel pipe 10 is set as a flat wall, so that the abutting end face 1514 of the first anchor block 151 and the inner wall surface of the circumferential wall 11 are flat surfaces adapted to abut, and the connecting wall of the steel beam 13 and the outer wall surface of the circumferential wall 11 are also flat surfaces adapted to abut, so that the steel pipe 10 of this embodiment is a rectangular steel pipe 10, and correspondingly, the abutting end face 1514 of the first anchor block 151 and the flat surface of the connecting wall of the steel beam 13 are adapted.
[0048] See also Fig.15 and Fig.16, which is another implementation of the steel pipe 10' and the steel beam 13' of this embodiment, that is, the circumferential wall 11' of the steel pipe 10' is set as an arc-shaped wall, so that the abutting end face 1514 of the first anchor block 151 and the inner wall surface of the circumferential wall 11 are adapted to abut with an arc-shaped surface, and the connecting wall 131' of the steel beam 13' and the outer wall surface of the circumferential wall 11 are also adapted to abut with an arc-shaped surface, so that the steel pipe 10' of this embodiment is an arc-shaped steel pipe, and correspondingly, the abutting end face 1514 of the first anchor block 151 and the arc-shaped surface of the connecting wall 131' of the steel beam 13' are adapted.
[0049] See also Figures 17 to 19 In this embodiment, the through hole 111 of the steel pipe 10 is polygonal or elliptical, and the shape of the cross section of the first anchor block 151 perpendicular to the axial direction of the first threaded hole 1512 is adapted to the shape of the through hole 111, so that the first anchor block 151 can smoothly pass through the through hole 111 of the steel pipe 10 and be inserted into the circumferential wall 11 of the steel pipe 10. Rotating and / or moving the first anchor block 151 located inside the circumferential wall 11 can make the abutting end face 1514 of the first anchor block 151 abut against the inner wall surface of the circumferential wall 11, thereby preventing the first anchor block 151 from escaping from the through hole 111 of the steel pipe 10, and ensuring that the first anchor block 151 is firmly restricted inside the circumferential wall 11 of the steel pipe 10 when pouring concrete 12. In addition, see Fig. 20 In this embodiment, the through hole 111 of the steel pipe 10 is arranged in a circular shape, and the shape of the cross section of the first anchor block 151 perpendicular to the axial direction of the first threaded hole 1512 is adapted to the shape of the through hole 111, so that after the first anchor block 151 passes through the through hole 111 of the steel pipe 10 and is inserted into the circumferential wall 11 of the steel pipe 10, the first anchor block 151 located inside the circumferential wall 11 is moved, and the abutting end face 1514 of the first anchor block 151 can also abut against the inner wall surface of the circumferential wall 11. Therefore, the shape of the through hole 111 and the axial cross-section of the first anchor block 151 perpendicular to the first threaded hole 1512 is not restricted, as long as the first anchor block 151 can pass through the through hole 111 of the steel pipe 10 and be inserted into the circumferential wall 11 of the steel pipe 10, and the first anchor block 151 located inside the circumferential wall 11 can be rotated and / or moved so that the abutting end face 1514 of the first anchor block 151 abuts against the inner wall surface of the circumferential wall 11.
[0050] Specifically, the rod section of the first fastener 154 of this embodiment is a partial rod section of the threaded rod, and the head is a nut. The nut and the threaded rod can be detachably threaded, and the nut can abut on the outer wall surface or the connecting wall 131 of the steel beam 13; or, the first fastener 154 of this embodiment is a first bolt. And, the second fastener 14 of this embodiment is a second bolt. Further, the rod section of the first fastener 154 of this embodiment is sleeved with a first gasket 155, and the first gasket 155 abuts on the outer wall surface of the circumferential wall 11 or between the connecting wall 131 of the steel beam 13 and the head of the first fastener 154, and the rod portion of the second fastener 14 is sleeved with a second gasket 141, and the second gasket 141 abuts between the connecting wall 131 of the steel beam 13 and the shoulder of the second fastener 14, thereby improving the stability of the locking. Furthermore, the first gasket 155 and the second gasket 141 can fully cover the through hole 111 to prevent the through hole 111 from being exposed and affecting the appearance.
[0051] Combination Figures 3 to 7 In this embodiment, the anchor assembly 15 further includes a second anchor block 153 and a connecting rod 152. The first anchor block 151 is provided with a second threaded hole 1513 at a second end face that is arranged opposite to the first end face of the first anchor block 151 in the axial direction of the first threaded hole 1512. The second anchor block 153 is provided with a third threaded hole 1531 at an end face that is close to the first anchor block 151. The first threaded end of the connecting rod 152 is detachably threadedly connected to the second threaded hole 1513, and the second threaded end of the connecting rod 152 is detachably threadedly connected to the third threaded hole 1531. The second anchor block 153 and the connecting rod 1521 52 can be inserted into the interior of the circumferential wall 11 through the through hole 111, and the concrete 12 will limit the second anchor block 153 and the connecting rod 152152 inserted into the interior of the circumferential wall 11 to the interior of the circumferential wall 11, so that the first anchor block 151, the second anchor block 153 and the connecting rod 152152 of the anchor assembly 15 are all fastened and embedded in the concrete 12 filled in the circumferential wall 11 of the steel pipe 10, further improving the tightness, stability, structural stiffness and strength, compressive bearing capacity and seismic resistance of the connection position between the steel tube concrete column and the steel beam 13, thereby further improving the bearing capacity of the steel tube concrete column.
[0052] In order to further improve the tightness, stability, structural rigidity and strength, compressive bearing capacity and seismic resistance of the connection position between the steel tube concrete column and the steel beam 13, the first anchor block 151 of this embodiment is concavely provided with a first groove 1511 on the outer peripheral surface in the circumferential direction of the first threaded hole 1512, and the first groove 1511 can be filled with concrete 12, and the second anchor block 153 of this embodiment is concavely provided with a second groove (not shown) on the outer peripheral surface in the circumferential direction of the connecting rod 152, and the second groove can be filled with concrete 12. Specifically, the connecting rod 152 of this embodiment is coaxially arranged with the first threaded hole 1512. Further, the cross-section of the first anchor block 151 of this embodiment perpendicular to the axial direction of the first threaded hole 1512 is rectangular or elliptical, and the cross-section of the second anchor block 153 perpendicular to the axial direction of the first threaded hole 1512 is rectangular or elliptical, and the long axis direction of the first anchor block 151 and the long axis direction of the second anchor block 153 are arranged perpendicular to each other.
[0053] Preferably, the anchor assembly 15 of this embodiment includes a first anchor block 151, a first fastener 154, a second anchor block 153 and a connecting rod 152152, a first end surface of the first anchor block 151 is provided with a first threaded hole 1512, a threaded rod of the first fastener 154 is detachably threadedly connected to the first threaded hole 1512, a head of the first fastener 154 is provided at one end of the first fastener 154 away from the first anchor block 151, a second threaded hole 1513 is provided at a second end surface of the first anchor block 151 that is arranged opposite to the first end surface in the axial direction of the first threaded hole 1512, and a third threaded hole 1513 is provided at an end surface of the second anchor block 153 that is close to the first anchor block 151 The threaded hole 1531, the first threaded end of the connecting rod 152 is detachably threadedly connected to the second threaded hole 1513, and the second threaded end of the connecting rod 152 is detachably threadedly connected to the third threaded hole 1531, and in this embodiment, the connecting rod 152 is coaxially arranged with the first threaded hole 1512, the shape of the cross-section of the first anchor block 151 perpendicular to the axial direction of the first threaded hole 1512 is a rectangle, the shape of the cross-section of the second anchor block 153 perpendicular to the axial direction of the first threaded hole 1512 is a rectangle, and the long axis direction of the first anchor block 151 and the long axis direction of the second anchor block 153 are perpendicular to each other, and correspondingly, the through hole 111 of the steel pipe 10 is a rectangular hole.
[0054] Therefore, the construction method of the steel tube concrete column having the preferred anchor assembly 15 of this embodiment specifically includes:
[0055] First, align the second anchor block 153 of the anchor assembly 15 with the long axis and short axis of the through hole 111 on the circumferential wall 11 of the steel pipe 10, as shown in FIG. Fig. 9 As shown;
[0056] Subsequently, the second anchor block 153 of the anchor assembly 15 is inserted into the interior of the circumferential wall 11 of the steel pipe 10 through the through hole 111 of the steel pipe 10, as shown in FIG. Fig.10 and Fig.11 As shown;
[0057] Next, the first fastener 154 of the anchor assembly 15 is controlled to rotate to drive the anchor assembly 15 to rotate as a whole, so that the first anchor block 151 of the anchor assembly 15 is aligned with the long axis and the short axis of the through hole 111 of the steel pipe 10. Fig.12 As shown;
[0058] Further, the connecting rod 152 of the anchor assembly 15 is inserted into the interior of the circumferential wall 11 through the through hole 111 of the steel pipe 10;
[0059] Furthermore, the first anchor block 151 of the anchor assembly 15 is inserted into the interior of the circumferential wall 11 of the steel pipe 10 through the through hole 111 on the circumferential wall 11 of the steel pipe 10, as shown in FIG. Fig.13 As shown;
[0060] Furthermore, the first fastener 154 of the anchor assembly 15 is controlled to rotate to drive the anchor assembly 15 to rotate as a whole, so that the first anchor block 151 located inside the circumferential wall 11 rotates until the long axis direction of the first anchor block 151 is perpendicular to the long axis direction of the through hole 111, and the abutting end surface 1514 of the first anchor block 151 abuts against the inner wall surface of the circumferential wall 11, as shown in FIG. Fig.14 As shown;
[0061] Furthermore, the head of the first fastener 154 is abutted against the outer wall surface of the circumferential wall 11 to fasten the anchor assembly 15 to the circumferential wall 11. Specifically, the gap between the first fastener 154 and the through hole 111 can be filled with a sealant, so that the inner cavity of the circumferential wall 11 of the steel pipe 10 is in a sealed state, thereby preventing the subsequent concrete 12 from overflowing at the through hole 111;
[0062] Furthermore, concrete 12 is filled into the circumferential wall 11 of the steel pipe 10 to restrict the first anchor block 151, the connecting rod 152, and the second anchor block 153, whose abutting end face 1514 abuts against the inner wall surface of the circumferential wall 11, to the circumferential wall 11 of the steel pipe 10, so that the first anchor block 151, the connecting rod 152, and the second anchor block 153 of the anchor assembly 15 are fastened and embedded in the concrete 12 filled in the circumferential wall 11 of the steel pipe 10;
[0063] Afterwards, the first fastener 154 of the anchor assembly 15 is removed from the first anchor block 151 that is restrained by the concrete 12 inside the circumferential wall 11;
[0064] Then, the steel beam 13 is threadedly connected to the first threaded hole 1512 of the first anchor block 151 which is confined inside the circumferential wall 11 of the steel pipe 10 by the first fastener 154 or the second fastener 14. Figures 1 to 3 shown.
[0065] Therefore, the steel tube concrete column of this embodiment is pre-embedded with an anchor assembly 15, which can be fastened to the steel beam 13 without the need for workers to weld or drill holes, making the disassembly and assembly of the steel tube concrete column and the steel beam 13 flexible and simple, achieving the purpose of reuse and saving resources, and improving the tightness, stability, structural stiffness and strength, compressive bearing capacity and seismic resistance of the connection position between the steel tube concrete column and the steel beam 13, thereby improving the bearing capacity of the steel tube concrete column and the convenience of construction.
[0066] The above embodiments are only preferred examples of the present invention and are not intended to limit the scope of implementation of the present invention. Therefore, any equivalent changes or modifications made based on the structure, features and principles of the present invention should be included in the scope of the present invention patent application.
Claims
1. A steel tube concrete column, comprising a steel tube, characterized in that: Also included is an anchor assembly; A through hole is formed through the circumferential wall of the steel pipe, the anchor assembly comprises a first anchor block and a first fastener, a first threaded hole is formed on the first end surface of the first anchor block, and a threaded rod of the first fastener is detachably threadedly connected to the first threaded hole; The first anchor block can be inserted into the interior of the circumferential wall through the through hole, and the rod section of the first fastener is inserted into the through hole and is rotatable and / or movably arranged relative to the through hole; The first fastener can drive the first anchor block located inside the circumferential wall to rotate and / or move, so that the abutting end surface of the first end surface protruding from the first threaded hole abuts against the inner wall surface of the circumferential wall, and the head of the first fastener can abut against the outer wall surface of the circumferential wall; Concrete is filled inside the circumferential wall to confine the first anchor block with the abutting end face abutting against the inner wall surface inside the circumferential wall, and the steel beam can be detachably threadedly connected to the first threaded hole of the first anchor block confined inside the circumferential wall through the first fastener or the second fastener.
2. The steel tube concrete column according to claim 1, characterized in that: The through hole is arranged in a polygonal or elliptical shape, and the shape of the cross section of the first anchor block perpendicular to the axial direction of the first threaded hole is adapted to the shape of the through hole; And / or, the abutting end surface and the inner wall surface are arc-shaped surfaces adapted to abut against each other; And / or, the abutting end surface and the inner wall surface are flat surfaces adapted to abut against each other.
3. The steel tube concrete column according to claim 1, characterized in that: The first anchor block has a first groove formed inwardly on an outer peripheral surface in the circumferential direction of the first threaded hole, and the first groove may be filled with the concrete.
4. The steel tube concrete column according to claim 1, characterized in that: The rod segment is a partial rod segment of the threaded rod, the head is a nut, the nut is detachably threadedly connected to the threaded rod, and the nut can abut on the outer wall surface or the connecting wall of the steel beam; or, the first fastener is a first bolt; And / or, the second fastener is a second bolt.
5. The steel tube concrete column according to claim 4, characterized in that: The rod segment is sleeved with a first gasket, which abuts against the outer wall surface or between the connecting wall of the steel beam and the head; And / or, a second gasket is sleeved on the stem of the second fastener, and the second gasket abuts between the connecting wall of the steel beam and the shoulder of the second fastener.
6. The steel tube concrete column according to any one of claims 1 to 5, characterized in that: The anchor assembly further includes a second anchor block and a connecting rod, wherein the first anchor block is provided with a second threaded hole at a second end face arranged opposite to the first end face in the axial direction of the first threaded hole, and the second anchor block is provided with a third threaded hole at an end face close to the first anchor block, the first threaded end of the connecting rod is detachably threadedly connected to the second threaded hole, and the second threaded end of the connecting rod is detachably threadedly connected to the third threaded hole; The second anchor block and the connecting rod may be inserted into the interior of the circumferential wall through the through hole, and the concrete may confine the second anchor block and the connecting rod inserted into the interior of the circumferential wall inside the circumferential wall.
7. The concrete-filled steel tube column according to claim 6, characterized in that: The second anchor block is provided with a second groove on the outer peripheral surface in the circumferential direction of the connecting rod, and the second groove can be filled with the concrete; And / or, the cross-section of the first anchor block perpendicular to the axial direction of the first threaded hole is rectangular or elliptical, and the cross-section of the second anchor block perpendicular to the axial direction of the first threaded hole is rectangular or elliptical, and the long axis direction of the first anchor block and the long axis direction of the second anchor block are arranged perpendicular to each other; And / or, the connecting rod is coaxially arranged with the first threaded hole.
8. Anchor assembly, characterized in that: The invention comprises a first anchor block, a first fastener, a second anchor block and a connecting rod, wherein a first threaded hole is provided on a first end surface of the first anchor block, a threaded rod of the first fastener is detachably threadedly connected to the first threaded hole, and a head is provided on an end of the first fastener away from the first anchor block; The first anchor block has a second threaded hole formed on a second end face that is arranged opposite to the first end face in the axial direction of the first threaded hole, and the second anchor block has a third threaded hole formed on an end face that is close to the first anchor block. The first threaded end of the connecting rod is detachably threadedly connected to the second threaded hole, and the second threaded end of the connecting rod is detachably threadedly connected to the third threaded hole.