Tunnel arch supporting mechanism for tunnel construction

By designing a tunnel arch support mechanism with multiple combinations of arch support plates and support columns, the problem of insufficient stability when the tunnel arch support is fixed in the prior art is solved, the safety of construction personnel is improved, and the support range is expanded.

CN222863439UActive Publication Date: 2025-05-13BRIDGE & TUNNEL ENGINEERING COMPANY OF THE THIRD ENGINEERING GROUP CO LTD OF CHINA RAILWAY
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202422040216.2
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-08-22
Publication Date
2025-05-13
Estimated Expiration
2034-08-22

AI Technical Summary

Technical Problem

The existing tunnel arch support mechanism designs a single group of support components, resulting in insufficient stability when the tunnel arch support is fixed, which increases the risk to construction workers.

Method used

A tunnel arch support mechanism for tunnel construction is designed, and the tunnel arch is supported and fixed by providing components such as the first arch support plate, the second arch support plate, the first support column, the third arch support plate, the fourth arch support plate, the second support column, the adjustment rod, the connecting seat, the fixing seat and the cylinder, and the stability is improved through the double-layer arch support plate.

Benefits of technology

Through this design, the stability of tunnel arch support when fixing is improved, the safety of construction personnel is increased, and the support range is expanded through adjustment rods.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222863439U_ABST
    Figure CN222863439U_ABST
Patent Text Reader

Abstract

The utility model discloses a tunnel arch supporting mechanism for tunnel construction. The tunnel arch supporting mechanism comprises a first arch supporting plate, a second arch supporting plate, a first supporting column, a third arch supporting plate, a fourth arch supporting plate, a second supporting column, an adjusting rod, a connecting base, a fixing base and an air cylinder. First supporting columns are installed at the two ends of the bottom of the first arch-shaped supporting plate, and a second arch-shaped supporting plate is fixedly installed at the bottoms of the first supporting columns. According to the tunnel arch supporting device, the first arch supporting plate, the second arch supporting plate, the first supporting column, the third arch supporting plate, the fourth arch supporting plate, the second supporting column, an adjusting rod, a connecting base, a fixing base, an air cylinder and other components are arranged and used in cooperation, so that the tunnel arch is conveniently supported during construction, and in addition, the supporting effect is good. And meanwhile, through the arrangement of the double-layer arched supporting plate, the stability effect during supporting and fixing is improved conveniently, and the safety of the constructors during construction is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of tunnel construction, in particular to a tunnel arch supporting mechanism for tunnel construction. Background Art

[0002] Tunnel construction is also called tunnel engineering. Tunnel engineering is a building built underground or underwater or in a mountain to lay railways or build roads for motor vehicles to pass. According to its location, it can be divided into three categories: mountain tunnel engineering, underwater tunnel engineering and urban tunnel engineering. Mountain tunnel engineering is to pass under mountains or hills to shorten the distance and avoid steep slopes; underwater tunnel engineering is to pass under rivers or straits or under the sea; urban tunnel engineering is to pass underground in cities to meet the needs of railways passing through large cities. Among these three types of tunnel engineering, mountain tunnel engineering is the most constructed. However, when constructing tunnel arches, arch support mechanisms are needed to support and fix them in order to improve the safety of construction workers at work.

[0003] The existing arch support mechanism usually supports the tunnel arch with a single set of support components. This design easily reduces the stability of the tunnel arch support when it is fixed, and increases the danger for construction workers when working. Utility Model Content

[0004] The purpose of the utility model is to provide a tunnel arch support mechanism for tunnel construction. The utility model is to provide a first arch support plate, a second arch support plate, a first support column, a third arch support plate, a fourth arch support plate, a second support column, an adjusting rod, a connecting seat, a fixing seat and a cylinder and other components for use in combination, so as to facilitate the support and fixation of the tunnel arch. The first arch support plate, the second arch support plate, the third arch support plate and the fourth arch support plate and other components are used in combination to increase the stability of the tunnel arch support; so as to solve the problems raised in the above-mentioned background technology.

[0005] In order to achieve the above purpose, the utility model provides the following technical solutions:

[0006] A tunnel arch support mechanism for tunnel construction, comprising: a first arch support plate, a second arch support plate, a first support column, a third arch support plate, a fourth arch support plate, a second support column, an adjustment rod, a connecting seat, a fixing seat and a cylinder;

[0007] The first arched support plate is provided with first support columns at both ends of the bottom, the second arched support plate is fixedly installed at the bottom of the first support column, the second support columns are provided with second support columns at both ends of the bottom of the third arched support plate, and the fourth arched support plate is fixedly installed at the bottom of the second support column;

[0008] The two ends of the bottom of the second arched support plate and the fourth arched support plate are fixedly connected with a connecting seat, the bottom of the connecting seat is provided with a fixing seat, the bottom of the fixing seat is fixedly installed with the output end of the cylinder, and the bottom of the cylinder is fixedly installed with a base;

[0009] Wherein, adjustment rods are installed at the inner center and both ends of the third arch support plate and the fourth arch support plate, and one end of the adjustment rod is slidably installed inside the inner side of the first arch support plate and the second arch support plate.

[0010] Preferably, a column groove is provided at the bottom of the connecting seat, and a column block is clamped inside the column groove.

[0011] Preferably, the column groove and the column block are matched with each other, and the column block is fixedly installed at the top center of the fixing seat.

[0012] Preferably, an extension plate is installed at the center of the outer surface of the base, and a handle for handholding is installed at one end of the top of the extension plate.

[0013] Preferably, electric telescopic rods are installed at both ends of the top of the base, the output end of the electric telescopic rod passes through the base and is fixedly connected to a conical seat, and a positioning cone is clamped at the bottom of the conical seat.

[0014] Preferably, rollers for moving the arch support mechanism are installed at both ends of the bottom of the base.

[0015] Compared with the prior art, the beneficial effects of the utility model are:

[0016] The utility model provides a first arch support plate, a second arch support plate, a first support column, a third arch support plate, a fourth arch support plate, a second support column, an adjusting rod, a connecting seat, a fixing seat and a cylinder and other components for use in coordination, so as to facilitate the tunnel arch to play a supporting role during construction, and also improve the safety of construction personnel, and at the same time, by providing a double-layer arch support plate, it is convenient to improve the stability effect during support and fixing, and increase the safety of construction personnel during construction;

[0017] However, the first arched support plate, the second arched support plate and the third arched support plate, the fourth arched support plate are separated by adjusting the rod, so as to increase the range of the tunnel arch support and fixation. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] Figure 1 It is a schematic diagram of the structure of the utility model;

[0019] Figure 2 This is a schematic diagram of the structure of the arch support mechanism of the utility model after height adjustment;

[0020] Figure 3This is a schematic diagram of the structure of the arched support plate of the utility model in an open state;

[0021] Figure 4 This is a schematic diagram of the explosive separation structure of the arched support mechanism of the utility model;

[0022] Figure 5 for Figure 4 Schematic diagram of the structure viewed from above.

[0023] In the figure: 1. first arched support plate; 101. second arched support plate; 102. first support column; 2. third arched support plate; 201. fourth arched support plate; 202. second support column; 203. adjusting rod; 3. connecting seat; 4. column slot; 5. column block; 6. fixing seat; 7. cylinder; 8. base; 9. electric telescopic rod; 10. conical seat; 11. positioning cone; 12. extension plate; 13. handrail; 14. roller. DETAILED DESCRIPTION

[0024] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0025] See also Figures 1 to 5 , the utility model provides a technical solution:

[0026] A tunnel arch support mechanism for tunnel construction, comprising: a first arch support plate 1, a second arch support plate 101, a first support column 102, a third arch support plate 2, a fourth arch support plate 201, a second support column 202, an adjustment rod 203, a connecting seat 3, a fixing seat 6 and a cylinder 7;

[0027] The first arched support plate 1 is provided with first support columns 102 at both ends of the bottom, the second arched support plate 101 is fixedly installed at the bottom of the first support column 102, the second support columns 202 are provided at both ends of the bottom of the third arched support plate 2, and the fourth arched support plate 201 is fixedly installed at the bottom of the second support column 202;

[0028] The second arch support plate 101 and the fourth arch support plate 201 are fixedly connected with a connecting seat 3 at both ends of their bottoms, a fixing seat 6 is provided at the bottom of the connecting seat 3, an output end of a cylinder 7 is fixedly installed at the bottom of the fixing seat 6, and a base 8 is fixedly installed at the bottom of the cylinder 7; rollers 14 for moving the arch support mechanism are installed at both ends of the bottom of the base 8.

[0029] Among them, adjustment rods 203 are installed at the inner center and both ends of the third arch support plate 2 and the fourth arch support plate 201, and one end of the adjustment rod 203 is slidably installed inside the inner side of the first arch support plate 1 and the second arch support plate 101.

[0030] The utility model is provided with a first arch support plate 1, a second arch support plate 101, a first support column 102, a third arch support plate 2, a fourth arch support plate 201, a second support column 202, an adjusting rod 203, a connecting seat 3, a fixing seat 6 and a cylinder 7 and other components for use in combination, so as to facilitate the tunnel arch during construction, so as to play a supporting role for the tunnel arch, and also improve the safety of the construction personnel, and at the same time, by providing a double-layer arch support plate, it is convenient to improve the stability effect during support and fixing, and increase the safety of the construction personnel during construction;

[0031] However, the first arched support plate 1, the second arched support plate 101 and the third arched support plate 2, the fourth arched support plate 201 are separated by the adjusting rod 203, so as to increase the range of the tunnel arch support and fixation.

[0032] Furthermore, when the tunnel arch needs to be supported, the handgrip 13 is held by hand to push the support mechanism to the position in the tunnel arch that needs to be supported and fixed and then stop. At the same time, the handgrips 13 at both ends of the back of the support mechanism are held by hand to drive the first arch support plate 1 and the second arch support plate 101 to move outward through the adjustment rod 203, thereby expanding the support range of the tunnel arch;

[0033] Then, by starting the cylinder 7, its output end drives the fixed seat 6 to move upward, so that the fixed seat 6 drives the arched support plate on the connecting seat 3 to fit and support the inner top of the tunnel arch, thereby facilitating the support of the tunnel arch, thereby improving the stability of the tunnel arch support, and also reducing the safety of construction workers at work.

[0034] A column groove 4 is provided at the bottom of the connecting seat 3 , and a column block 5 is clamped inside the column groove 4 . The column groove 4 and the column block 5 are adapted to each other, and the column block 5 is fixedly installed at the top center of the fixing seat 6 .

[0035] The utility model provides the column groove 4 and the column block 5, so as to facilitate the disassembly and installation of the first arched support plate 1, the second arched support plate 101, the third arched support plate 2 and the fourth arched support plate 201.

[0036] An extension plate 12 is installed at the center of the outer surface of the base 8 to facilitate the fixed support of the handrail 13; a handrail 13 for handholding is installed at one end of the top of the extension plate 12 to facilitate the construction workers to hold the mobile arch support mechanism.

[0037] Electric telescopic rods 9 are installed at both ends of the top of the base 8. The electric telescopic rod 9 passes through the output end of the base 8 and is fixedly connected to a conical seat 10. A positioning cone 11 is clamped at the bottom of the conical seat 10.

[0038] When the arch support mechanism moves to the supporting and fixed position in the tunnel arch, the electric telescopic rod 9 is started so that its output end drives the positioning cone 11 on the bottom of the conical seat 10 to be inserted and fixed into the ground, so that the arch support mechanism is fixed, thereby facilitating the improvement of the stability of the arch support mechanism during use and facilitating its rapid disassembly and removal.

[0039] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. A tunnel arch support mechanism for tunnel construction, characterized in that: include: A first arched support plate (1), a second arched support plate (101), a first support column (102), a third arched support plate (2), a fourth arched support plate (201), a second support column (202), an adjustment rod (203), a connecting seat (3), a fixing seat (6) and a cylinder (7); The first arched support plate (1) is provided with first support columns (102) at both ends of the bottom, the second arched support plate (101) is fixedly installed at the bottom of the first support column (102), the second support columns (202) are provided with second support columns (202) at both ends of the bottom of the third arched support plate (2), and the fourth arched support plate (201) is fixedly installed at the bottom of the second support column (202); The second arched support plate (101) and the fourth arched support plate (201) are fixedly connected to a connecting seat (3) at both ends of their bottoms, a fixing seat (6) is provided at the bottom of the connecting seat (3), an output end of a cylinder (7) is fixedly mounted at the bottom of the fixing seat (6), and a base (8) is fixedly mounted at the bottom of the cylinder (7); Wherein, adjustment rods (203) are installed at the inner center and both ends of the third arched support plate (2) and the fourth arched support plate (201), and one end of the adjustment rod (203) is slidably installed inside the inner side of the first arched support plate (1) and the second arched support plate (101).

2. A tunnel arch support mechanism for tunnel construction according to claim 1, characterized in that: A column groove (4) is provided at the bottom of the connection seat (3), and a column block (5) is clamped inside the column groove (4).

3. A tunnel arch support mechanism for tunnel construction according to claim 2, characterized in that: The column slot (4) is adapted to the column block (5), and the column block (5) is fixedly mounted at the top center of the fixing seat (6).

4. The tunnel arch support mechanism for tunnel construction according to claim 1, characterized in that: An extension plate (12) is installed at the center of the outer surface of the base (8), and a handle (13) for handholding is installed at one end of the top of the extension plate (12).

5. The tunnel arch support mechanism for tunnel construction according to claim 1, characterized in that: Electric telescopic rods (9) are installed at both ends of the top of the base (8); the output end of the electric telescopic rod (9) passes through the base (8) and is fixedly connected to a conical seat (10); and a positioning cone (11) is clamped at the bottom of the conical seat (10).

6. The tunnel arch support mechanism for tunnel construction according to claim 1, characterized in that: Rollers (14) for moving the arch support mechanism are installed at both ends of the bottom of the base (8).