Aerial building-building machine for fabricated building
By designing an aerial building machine for prefabricated buildings, the problems of high labor costs, high lifting risks and low automation levels in prefabricated buildings are solved, and the automated lifting and installation of buildings are realized, and construction safety and efficiency are improved.
Patent Information
- Application Number
- CN202421761638.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-24
- Publication Date
- 2025-05-16
- Estimated Expiration
- 2034-07-24
AI Technical Summary
In the construction of prefabricated buildings, the labor cost is high and the lifting risk is high, and the automation level needs to be improved.
A sky building machine for prefabricated buildings is designed, including lifting columns, truss beams, cranes, robots and other components. Through the combination and coordinated work of these components, the automatic lifting and installation of the building is realized.
The mechanization and automation of lifting operations have been achieved, the worker has been reduced, construction safety and efficiency have been improved, and labor intensity and construction cycle have been reduced.
Smart Images

Figure CN222879251U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of building construction, and specifically discloses an aerial building construction machine used for assembled buildings. Background Art
[0002] Prefabricated buildings are a new type of building production method that is sustainable and based on the prefabrication of components in factories and on-site assembly installation. It is characterized by standardized design, factory production, assembly construction, integrated decoration and information management. It integrates various business areas such as R&D design, production and manufacturing, and on-site assembly to achieve energy conservation, environmental protection, and full-cycle value maximization of building products. The use of prefabricated buildings can optimize resource allocation, reduce resource consumption, and improve project quality, functional quality, environmental quality, and productivity. However, a large number of operators need to be trained during construction, the labor cost is high, the prefabricated parts are difficult to hoist, the hoisting risk is high, and the automation level needs to be improved. Utility Model Content
[0003] The utility model provides an aerial building construction machine for prefabricated buildings, so as to improve the technical problems of high labor cost, great hoisting risk and need to improve the automation level of prefabricated buildings.
[0004] The above-mentioned aerial building machine for prefabricated buildings includes lifting columns, truss beams, cranes, crane traveling mechanisms, crane traveling driving parts, crane moving rails, concrete vertical transportation devices, concrete placing machines and placing machine mounting beams; multiple lifting columns are arranged around preset positions of the prefabricated building, and the top ends are connected through truss beams; the crane moving rails are installed on the truss beams; a crane traveling mechanism is installed at the bottom of the crane; the crane traveling mechanism is installed on the crane moving rails and is driven by the crane traveling driving parts to travel along the crane moving rails; the concrete vertical transportation devices are arranged along the lifting columns; the placing machine mounting beam is perpendicular to the crane moving rails, and both ends are fixed on the truss beams; the placing machine is installed on the placing machine mounting beam and is connected to the concrete vertical transportation device.
[0005] In the above-mentioned aerial building machine for prefabricated buildings, multiple lifting columns are arranged in a square shape around the preset position of the prefabricated building; the truss beams include two oppositely arranged longitudinal truss beams and two transverse truss beams connecting the longitudinal truss beams; the crane moving track is installed on the two longitudinal truss beams.
[0006] The above-mentioned aerial building machine for prefabricated buildings also includes a manipulator, a manipulator walking mechanism, a manipulator walking drive and a manipulator moving track; the manipulator moving track is parallel to the crane moving track, installed on the truss beam, and staggered with the crane moving track; the bottom end of the manipulator is installed with a manipulator walking mechanism; the manipulator walking mechanism is installed on the manipulator moving track, and is driven by the manipulator walking drive to move along the manipulator moving track.
[0007] In the above-mentioned aerial building machine for prefabricated buildings, the lifting column includes a plurality of standard sections connected in sequence, and two adjacent standard sections are detachably connected; the floor height of the prefabricated building is an integer multiple of the length of the standard section; the aerial building machine also includes a lifting mechanism; the lifting mechanism includes a fixed part and a telescopic part, the fixed part is connected to the ground, and the telescopic part is connected to the standard section.
[0008] The above-mentioned aerial building machine for prefabricated buildings also includes a perimeter purlin; the perimeter purlin is located below the truss beam and is connected to the standard section.
[0009] In the above-mentioned aerial building machine for prefabricated buildings, an external rack is installed below the truss beam.
[0010] In the above-mentioned aerial building machine for prefabricated buildings, the crane is a gantry crane; the crane traveling mechanism is a crane traveling wheel installed on the gantry of the gantry crane; the crane traveling drive member is a crane traveling motor, which drives the crane traveling wheel to rotate.
[0011] In the above-mentioned aerial building machine for prefabricated buildings, the lifting mechanism is a hydraulic cylinder; the aerial building machine is also provided with a hydraulic pump station cooperating with the hydraulic cylinder.
[0012] Compared with the prior art, the utility model has the following beneficial effects.
[0013] 1. Compared with the manual construction method, the aerial building machine for prefabricated buildings provided by the utility model realizes the mechanization and automation of hoisting operations, reduces the number of operators, makes the hoisting process safer, shortens the construction period, and reduces labor intensity.
[0014] 2. The above-mentioned aerial building machine for prefabricated buildings has low cost and high degree of automation. It can adapt to different building types and sites, improve construction efficiency, have a smaller construction operation radius, and pose relatively little danger to construction personnel and objects on the ground, greatly reducing safety hazards. It is easy to operate and can better control the quality of construction. BRIEF DESCRIPTION OF THE DRAWINGS
[0015] In order to more clearly illustrate the specific implementation methods of the utility model or the technical solutions in the prior art, the drawings required for use in the specific implementation methods or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some implementation methods of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0016] Figure 1 It is a structural schematic diagram of an aerial building machine used for prefabricated buildings;
[0017] Figure 2 for Figure 1 A partial enlarged view of
[0018] Figure 3 This is a schematic diagram of the installation of the external bracket.
[0019] In the figure: 1-truss beam; 2-crane moving track; 3-concrete vertical transportation device; 4-concrete placing boom; 5-concrete placing boom mounting beam; 6-manipulator; 7-manipulator moving track; 8-standard section; 9-purlin; 10-external bracket; 11-gantry crane; 12-hydraulic cylinder. DETAILED DESCRIPTION
[0020] The technical solution of the utility model will be described clearly and completely below in conjunction with the accompanying drawings. Obviously, the described embodiments are part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments of the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0021] Example 1
[0022] The present embodiment provides an aerial building machine for prefabricated buildings, comprising a lifting column, a truss beam 1, a crane, a crane traveling mechanism, a crane traveling drive, a crane moving track 2, a concrete vertical transport device 3, a concrete placing machine 4 and a concrete placing machine mounting beam 5; a plurality of lifting columns are arranged around a preset position of the prefabricated building, and the top ends are connected through the truss beam 1; the crane moving track 2 is installed on the truss beam 1; a crane traveling mechanism is installed at the bottom end of the crane; the crane traveling mechanism is installed on the crane moving track 2, and is driven by the crane traveling drive to travel along the crane moving track 2; the concrete vertical transport device 3 is arranged along the lifting column, and is used to pump concrete from the bottom end of the lifting column to the top end; the concrete placing machine mounting beam 5 is perpendicular to the crane moving track 2, and both ends are fixed on the truss beam 1; the concrete placing machine 4 is installed on the concrete placing machine mounting beam 5 and is connected to the concrete vertical transport device 3.
[0023] In the above-mentioned aerial building machine for prefabricated buildings, a plurality of lifting columns are arranged in a square shape around the preset position of the prefabricated building; the truss beam 1 includes two longitudinal truss beams arranged opposite to each other and two transverse truss beams connecting the longitudinal truss beams; the crane moving track 2 is installed on the two longitudinal truss beams, which is more in line with construction practices. The above-mentioned aerial building machine for prefabricated buildings also includes a manipulator 6, a manipulator walking mechanism, a manipulator walking drive and a manipulator moving track 7; the manipulator moving track 7 is parallel to the crane moving track 2, installed on the truss beam 1, and staggered with the crane moving track 2; a manipulator walking mechanism is installed at the bottom end of the manipulator 6; the manipulator walking mechanism is installed on the manipulator moving track 7, and is driven by the manipulator walking drive to move along the manipulator moving track 7.
[0024] The crane moving track 2 and the manipulator moving track 7 located on the same truss beam 1 are two different tracks. The manipulator moving track 7 is located on the inner side of the truss beam 1, and the crane moving track 2 is located on the outer side of the truss beam 1. The operation of the two does not affect or conflict with each other.
[0025] In the above-mentioned aerial building machine for prefabricated buildings, the lifting column includes a plurality of standard sections 8 connected in sequence, and two adjacent standard sections 8 are detachably connected; the floor height of the prefabricated building is an integer multiple of the length of the standard section 8; the aerial building machine also includes a lifting mechanism; the lifting mechanism includes a fixed part and a telescopic part, the fixed part is connected to the ground, and the telescopic part is connected to the standard section. In order to facilitate operation, the telescopic part of the lifting mechanism is connected to the previous standard section between two adjacent standard sections 8 to attach Figure 1 Take an example to illustrate, the telescopic part of the lifting mechanism is connected to the fifth standard section. When the height of the lifting column needs to be raised, the connection between the fifth standard section and the fourth standard section is removed, the telescopic part of the lifting mechanism is extended, the fifth standard section is lifted to the height of one or several standard sections, and a new standard section is installed between the fifth and fourth standard sections; when the height of the lifting column needs to be lowered, the telescopic part of the lifting mechanism is extended, the fifth standard section is lifted, the standard section below the fifth standard section is removed, the telescopic part of the lifting mechanism is retracted, and the fifth standard section is reconnected with the first standard section.
[0026] The above-mentioned aerial building machine for prefabricated buildings also includes a perimeter purlin 9; the perimeter purlin 9 is located below the truss beam 1 and is connected to the standard section 8.
[0027] In the above-mentioned aerial building machine for prefabricated buildings, an external rack 10 is installed below the truss beam 1. The external rack 10 is an external wall construction platform for workers to perform external wall operations. The number of external racks 10 is 1-2 layers.
[0028] In the above-mentioned aerial building machine for prefabricated buildings, the crane is a gantry crane 11; the crane traveling mechanism is a crane traveling wheel installed on the gantry of the gantry crane 11; the crane traveling drive member is a crane traveling motor, which drives the crane traveling wheel to rotate.
[0029] In the above-mentioned aerial building machine for prefabricated buildings, the lifting mechanism is a hydraulic cylinder 12; the aerial building machine is also provided with a hydraulic pump station cooperating with the hydraulic cylinder.
[0030] The above-mentioned aerial building machine for prefabricated buildings is a large steel structure frame that is set outside the building and can be automatically lifted and lowered. The steel frame is highly integrated with mechanical components and multiple construction platforms with various lifting, transportation, decoration installation, and cloth functions. Through lattice steel pipe lifting columns and multiple independent horizontal purlins, it is combined into a large-scale special mechanical equipment that simulates a "mobile building factory". Artificial intelligence and 5G industrial Internet technology are used to form an automated green construction under remote control. This is a mobile building factory with a high degree of automation, which saves a lot of labor costs and only requires a small amount of manpower for auxiliary control. Compared with traditional tower crane equipment for lifting prefabricated components, the aerial building machine designed by the present invention has the advantages of stability, safety, speed, automation, etc. The manipulator 6 attached to the steel frame replaces the traditional diagonal rod support, which is more convenient, fast, and stable. Moreover, the scheme has superior practicality and wide applicability.
[0031] Example 2
[0032] The building process of the aerial building machine for prefabricated buildings described in Example 1 is described as follows.
[0033] Step 1: Use an external crane to install the six lattice lifting columns, truss beam 1, multiple horizontal steel purlins, gantry crane 11, crane moving track 2, concrete vertical transportation device 3, and concrete placing machine 4 of the aerial building machine. The six lattice lifting columns are arranged in a rectangular structure.
[0034] Step 2: Start building the first layer. The gantry crane 11 moves along the crane moving track 2 to the top of the prefabricated component, and extends the hook downward to hook up the prefabricated component.
[0035] Step three: The gantry crane 11 moves along the crane moving track 2 to a predetermined longitudinal position, and then the hook moves laterally along the gantry of the gantry crane 11 to transport the prefabricated component to the predetermined position, and then the manipulator 6 will also move along the manipulator moving track 7 to the periphery of the prefabricated component to temporarily fix the prefabricated component.
[0036] Step 4: After all vertical components are installed, start preparing the reinforcement and formwork for the vertical load-bearing columns, and then pour the concrete.
[0037] Step 5: After the construction of the vertical components is completed, start hoisting the horizontal components, and the construction of the first floor is completed.
[0038] Step 6: Through the hydraulic pump station, the telescopic rods of the six groups of hydraulic cylinders 11 are controlled to extend at the same time, and the standard section 8 connected to the telescopic rod is lifted to the preset height, and the standard section 8 is increased by horizontal advancement to complete one lifting, and the lifting is repeated until the truss beam 1, the crane moving track 2, and the manipulator moving track 7 reach the second-floor construction height.
[0039] Step 7: Repeat the construction process of the first layer to complete the construction of the second layer, and start installing the first layer of external racks under the truss beam 1. The external rack is an external wall construction platform for workers to perform external wall operations.
[0040] Step 8: Continue to lift the aerial building machine and start building the third floor, and install the second layer of racks under the first layer of racks, that is, a total of two layers of racks 10 are installed under the truss beam 1.
[0041] Step 9: So far, the installation of the aerial building machine is completed, and then the normal cycle begins, with the main components of the nth floor being hoisted and installed from the bottom to the top. The completed (n-1) floor and (n-2) floor can be used for exterior wall decoration and other construction operations through the two layers of external racks 10 under the truss beam 1, and the construction of all floors is completed in a cycle.
[0042] Step 10: After all floors are built, start to lower the height of the lifting columns, and use the hydraulic pump station to control the extension of the telescopic rods of the six groups of hydraulic cylinders 12 at the same time. The standard sections 8 connected to the telescopic rods are lifted to a preset height, and the standard sections 8 below the standard sections 8 connected to the hydraulic cylinders 12 are removed. By pushing out the standard sections 8 one by one, the height of the entire aerial building machine is gradually lowered. When it is lowered to the lowest height, the various components of the aerial building machine are removed by an external crane.
[0043] In step 2, the pre-storage position of the prefabricated components is on the ground below the narrow sides of the rectangular structure on both sides. The stacking requirements and sequence must meet the requirements of lifting to ensure smooth lifting and installation.
[0044] In step 4, the vertical load-bearing columns are cast in place and mainly bear vertical loads and certain overturning loads.
[0045] In step five, after the construction of the vertical components is completed, it means that the horizontal components can be hoisted and installed only after the strength of the cast-in-place vertical load-bearing columns reaches a certain requirement.
[0046] In step six, each lifting requires the hydraulic synchronizer to accurately and synchronously control the extension of all hydraulic cylinders 11. The lifting height, i.e., the floor height of the prefabricated building, is an integer multiple of the length of the standard section 8.
[0047] In step eight, the height of the two-layer external rack 10 is exactly the height of two floors, which allows workers to decorate the exterior walls of two floors at the same time, thereby improving construction efficiency.
[0048] In step ten, completing the construction of all floors means completing the construction, installation, and exterior wall decoration of all floors.
[0049] Finally, it should be noted that the above embodiments are only used to illustrate the technical solution of the utility model, rather than to limit it. Although the utility model has been described in detail with reference to the aforementioned embodiments, ordinary technicians in this field should understand that they can still modify the technical solutions recorded in the aforementioned embodiments, or replace some or all of the technical features therein with equivalents. However, these modifications or replacements do not make the essence of the corresponding technical solution deviate from the scope of the technical solution of the embodiments of the utility model.
Claims
1. An aerial building machine for prefabricated buildings, comprising a lifting column, a truss beam, a crane, a crane travel mechanism, a crane travel drive member, a crane moving track, a concrete vertical transport device, a placing machine and a placing machine mounting beam; It is characterized in that A plurality of lifting columns are arranged around the preset positions of the prefabricated building, and the top ends are connected by truss beams; the crane moving track is installed on the truss beams; A crane traveling mechanism is installed at the bottom end of the crane; The crane travel mechanism is installed on the crane moving track and is driven by the crane travel driving member to travel along the crane moving track; The concrete vertical transport device is arranged along the lifting column; The concrete placing machine mounting beam is perpendicular to the crane moving track, and both ends are fixed on the truss beam; The concrete placing boom is installed on a concrete placing boom installation beam and is connected to a concrete vertical transport device.
2. The aerial building machine for prefabricated buildings according to claim 1, characterized in that: Multiple lifting columns are arranged in a square shape around the preset positions of the prefabricated building; The truss beam comprises two longitudinal truss beams arranged opposite to each other and two transverse truss beams connecting the longitudinal truss beams; The crane moving rail is installed on two longitudinal truss beams.
3. The aerial building machine for prefabricated buildings according to claim 2, characterized in that: It also includes a manipulator, a manipulator walking mechanism, a manipulator walking drive member and a manipulator moving track; The manipulator moving track is parallel to the crane moving track, installed on the longitudinal truss beam, and staggered with the crane moving track; A manipulator walking mechanism is installed at the bottom end of the manipulator; The manipulator walking mechanism is installed on the manipulator moving track and is driven by the manipulator walking driving member to move along the manipulator moving track.
4. The aerial building machine for prefabricated buildings according to claim 3 is characterized in that: The lifting column comprises a plurality of standard sections connected in sequence, and two adjacent standard sections are detachably connected; The storey height of prefabricated buildings is an integer multiple of the standard section length; The aerial building machine for prefabricated buildings also includes a lifting mechanism; The lifting mechanism comprises a fixed part and a telescopic part, wherein the fixed part is connected to the ground, and the telescopic part is connected to the standard section.
5. The aerial building machine for prefabricated buildings according to claim 4 is characterized in that: It also includes perimeter purlins; The enclosure purlin is located below the truss beam and is connected to the standard section.
6. The aerial building machine for prefabricated buildings according to claim 5, characterized in that: An external rack is installed below the truss beam.
7. The aerial building machine for prefabricated buildings according to claim 1, characterized in that: The crane is a gantry crane; The crane travel mechanism is the crane travel wheel, which is installed on the gantry of the gantry crane; The crane travel drive is a crane travel motor, which drives the crane travel wheel to rotate.
8. The aerial building machine for prefabricated buildings according to claim 4, characterized in that: The lifting mechanism is a hydraulic cylinder; The aerial building construction machine for prefabricated buildings is also provided with a hydraulic pump station cooperating with the hydraulic cylinder.