Folding hanging basket for bridge wet joint construction

By designing a hanging basket for wet joint construction of bridges with adjustable height and folding and scaling, the problems of poor adaptability and insufficient construction safety of existing equipment are solved, and a more efficient and safe construction process is achieved.

CN222893500UActive Publication Date: 2025-05-23SINOCHEM COMM CONSTR GRP THIRD ENG CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420862824.9
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-04-23
Publication Date
2025-05-23
Estimated Expiration
2034-04-23

AI Technical Summary

Technical Problem

The existing bridge wet joint construction equipment has poor adaptability, cannot effectively adjust the height, and lacks a safe ladder, which affects construction safety and efficiency.

Method used

A folding hanging basket for wet joint construction of bridges is designed, including a bracket with adjustable height, a folding and scaling structure and a safety ladder to ensure that the hanging basket can adapt to prefabricated beams of different heights and sizes and provide a safe construction environment.

Benefits of technology

The height adjustment and multiple turnover of the hanging basket are realized, which improves the flexibility and safety of construction, simplifies the operation process, and improves the operation efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222893500U_ABST
    Figure CN222893500U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of bridge wet joint construction equipment, and mainly discloses a folding hanging basket for bridge wet joint construction, which comprises a first support, a second support, a first support arm, a second support arm and a base. The two ends of the base are hinged to the first support and the second support, a first supporting arm is connected to the upper end of the first support in an up-down telescopic mode, a second supporting arm is connected to the upper end of the second support in an up-down telescopic mode, and hanging basket cross arms are arranged at the upper end of the first supporting arm and the upper end of the second supporting arm and hung on the edges of the two precast beams respectively. According to the utility model, the height can be adjusted according to the size of the precast beam, and meanwhile, the structure is simple, the single-person operation can be realized, the working efficiency is improved, the folding and storage are more convenient, and the multi-time turnover can be realized.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of bridge wet joint construction equipment, in particular to a folding hanging basket for bridge wet joint construction. Background Art

[0002] Wet joints are mainly used to connect prestressed concrete beams. During the construction process, prestressed concrete beams are usually prefabricated in blocks and then cantilevered into large-span continuous beams. In order to connect these beams into a whole, cast-in-place concrete is used to fill the joints between the beams. This joint is called a wet joint in the construction industry. The diaphragm refers to a transverse member located between the main beams of the bridge. Its function is to increase the rigidity and stability of the bridge, separate the main beams of the bridge, and enable the bridge deck to withstand vehicle loads and transfer them to the main beams. The construction process of the diaphragm directly affects the safety and service life of the bridge. After the precast beams are hoisted onto the cap beams and laid, wet joints are formed between the precast beams. The diaphragms between the wet joints are located under the precast beams and need to be reinforced and installed with formwork.

[0003] The existing hanging baskets have the following technical problems: 1. Since the bridge height is relatively high and the bridge is often laid above the river and between the valleys, the ground terrain under the bridge is relatively complex. Therefore, it is not easy to set up equipment under the bridge to construct the diaphragm, and a construction equipment that can be hung between the prefabricated beams is needed. 2. The width of the wet joint is relatively narrow. After the prefabricated beams are hoisted and laid, the steel bars between the wet joints affect the bottom of the hanging basket, and the hanging basket needs to be folded and scaled before it can be lowered from between the wet joints. 3. Due to the different sizes of prefabricated beams, the height of the diaphragm from the upper surface of the beam is also different, so the hanging basket needs to be able to adjust the up and down height to meet the requirements of the diaphragm construction. The existing hanging basket has poor adaptability and cannot achieve multiple turnovers. At the same time, there is no safety ladder, which makes it inconvenient for workers to go up and down, and the construction safety cannot be guaranteed. Utility Model Content

[0004] The utility model aims to provide a folding hanging basket for bridge wet joint construction, which solves the technical problems existing in the prior art. The hanging basket can adjust the height, can be folded and scaled, and can ensure construction safety.

[0005] The technical solution of the utility model to achieve the above-mentioned purpose is a folding hanging basket for bridge wet joint construction, comprising a first bracket, a second bracket, a first support arm, a second support arm and a base. The two ends of the base are hinged with the first bracket and the second bracket through a pin shaft, the upper end of the first bracket is telescopically connected to the first support arm and fixed by bolts, the upper end of the second bracket is telescopically connected to the second support arm and fixed by bolts, a number of threaded holes are arranged at equal intervals on the first bracket and the second bracket, and corresponding threaded holes are also arranged on the first support arm and the second support arm, and the bolts are passed through the corresponding threaded holes on the first bracket and the first support arm and the second bracket and the second support arm, and then fixed by nuts. Ladder rods are arranged at equal intervals from top to bottom on the first support arm and / or the second support arm, and the upper ends of the first support arm and the second support arm are provided with hanging basket cross arms, and the two hanging basket cross arms are respectively hung on the edges of the two prefabricated beams and extend in the direction away from the center of the expansion joint. The upper ends of the first bracket and the second bracket are both provided with a safety rope, one end of the safety rope is connected to the first bracket and the second bracket, and the other end of the safety rope is provided with a rope buckle. The safety rope is stretched upward so that the rope buckle is hung on the steel bars on the surface of the prefabricated beam and fixed.

[0006] A further solution of the utility model is that support rods are provided on the two hanging basket cross arms. The support rods, firstly, provide extended support arms when the wet joint is wider and the distance between the two hanging basket cross arms is smaller, so as to prevent the hanging basket from falling; secondly, increase the length of the force arm and improve the supporting area of ​​the hanging basket cross arm, so as to make the supporting strength of the hanging basket higher, prevent the hanging basket from shaking, and improve safety.

[0007] A further solution of the utility model is that cross bars are arranged at equal intervals at the lower parts of the first bracket and the second bracket, and the cross bars are used as side fences and improve the strength of the first bracket and the second bracket.

[0008] A further solution of the utility model is that hinged connecting rods are evenly spaced on both sides of the lower part between the first bracket and the second bracket, and the connecting rods are also used as side fences and improve the strength between the first bracket and the second bracket.

[0009] A further solution of the utility model is that the two ends of the base are connected to the first bracket and the second bracket through a pin shaft, and the two ends of the connecting rod are hinged to the first bracket and the second bracket through a pin shaft.

[0010] A further solution of the utility model is that a patterned plate is provided on the upper surface of the base to increase friction and prevent workers from slipping.

[0011] According to the above technical solution, the first support arm and the first bracket, the second support arm and the second bracket are first adjusted to the same height, and then fixed with bolts. Then, the hanging basket is folded and scaled, and the width between the first bracket and the second bracket, the first support arm and the second support arm is shortened by lifting the first bracket or the second bracket. Next, the folded hanging basket is lowered to the bottom of the prefabricated beam through the expansion joint, and then the rope buckle of the wire rope is held by hand. After opening the hanging basket, the rope buckle is hung on the embedded steel bars on the upper surface of the prefabricated beam.

[0012] Compared with the prior art, the beneficial effects of the utility model are:

[0013] The hanging basket of the utility model can realize the safe up and down of personnel, adjust the height according to the size of the prefabricated beam, complete the operations such as tying the reinforcement of the transverse partition and installing the template, and has the advantages of being simple and flexible, safe and reliable, practical and highly applicable. At the same time, the structure is simple, and it can be operated by one person, which greatly improves the work efficiency; it is more convenient to fold and put away, and it can realize multiple turnovers and realize the standardization of work. BRIEF DESCRIPTION OF THE DRAWINGS

[0014] In order to more clearly illustrate the embodiments of the utility model or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0015] Figure 1 This is a schematic diagram of the overall structure of the hanging basket in Example 1 of the utility model;

[0016] Figure 2 This is a schematic diagram of the folded state of the hanging basket in Example 1 of the utility model.

[0017] In the figure: 1. first bracket, 2. second bracket, 3. first support arm, 4. second support arm, 5. base, 6. connecting rod, 7. support rod, 8. safety rope, 9. cross bar, 10. hanging basket cross arm, 11. ladder rod, 12. threaded hole 12, 13. bolt, 14. pin. DETAILED DESCRIPTION

[0018] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0019] In the present invention, "upper" and "lower" only represent relative positional relationships. When the absolute position of the described object changes, the relative positional relationship may also change accordingly.

[0020] Example 1

[0021] like Figure 1-2 As shown, a folding hanging basket for bridge wet joint construction includes a first bracket 1, a second bracket 2, a first support arm 3, a second support arm 4 and a base 5. The first bracket 1 is equal to the second bracket 2 in height, and the first support arm 3 is equal to the second support arm 4 in height.

[0022] The two ends of the base 5 are hinged to the lower ends of the first bracket 1 and the second bracket 2 respectively. The base 5 is a rectangular frame formed by welding four steel pipes, and the steel pipes are square pipes. The upper surface of the rectangular frame of the base 5 is provided with a patterned plate to increase friction and prevent workers from slipping.

[0023] The first bracket 1 and the second bracket 2 have exactly the same structure, specifically, two steel pipes are used as columns, and cross bars 9 are welded at equal intervals between the lower parts of the two steel pipes. There are at least two cross bars 9. The steel pipes and cross bars 9 of the first bracket 1 are both square pipes. The upper parts of the two steel pipes extend upward, and the extended parts are provided with threaded holes 12 at equal intervals. The cross bars 9 are used as side fences and to improve the strength of the first bracket 1 and the second bracket 2. The two ends of the two square pipes of the rectangular frame of the base 5 are respectively hinged to the bottom of the two vertical steel pipes of the first bracket 1 and the second bracket 2 through pins 14.

[0024] The upper end of the first bracket 1 is telescopically connected to the first support arm 3 and fixed by bolts 13. The upper end of the second bracket 2 is telescopically connected to the second support arm 4 and fixed by bolts 13. The first support arm 3 and / or the second support arm 4 are evenly spaced from top to bottom. Ladder rods 11 are evenly spaced and arranged on the first bracket 1 and the second bracket 2. Corresponding threaded holes 12 are also arranged on the first support arm 3 and the second support arm 4. Specifically, the first support arm 3 and the second support arm 4 have the same structure, specifically two steel pipes as columns, and the ladder rods 11 are evenly spaced and welded between the upper parts of the two steel pipes. There are at least three ladder rods 11. The lower parts of the two steel pipes extend downward, and the extended parts are evenly spaced and arranged with threaded holes 12 corresponding to the first bracket 1 and the second bracket 2. When fixed, there are at least two butt-jointed threaded holes 12. After the bolts 13 pass through the corresponding threaded holes 12 on the first bracket 1 and the first support arm 3 and the second bracket 2 and the second support arm 4, they are fixed by nuts.

[0025] The upper ends of the first support arm 3 and the second support arm 4 are both provided with a hanging basket cross arm 10. The two hanging basket cross arms 10 are respectively hung on the edges of the two prefabricated beams and extend in a direction away from the center of the expansion joint. The hanging basket cross arm 10 is a rectangular frame welded by four steel pipes. A further solution of the utility model is that the two hanging basket cross arms 10 are provided with a support rod 7, the length of which is greater than the distance between the two ends of the two hanging basket cross arms 10. The support rod 7 is a round steel pipe, and the two support rods 7 pass through the side steel pipes of the two hanging basket cross arms 10. The support rod 7 firstly provides an extended support arm when the wet joint is wide and the distance between the two hanging basket cross arms 10 is small, so as to prevent the hanging basket from falling; secondly, it increases the length of the force arm and improves the support area of ​​the hanging basket cross arm 10, so as to make the support strength of the hanging basket higher, prevent the hanging basket from shaking, and improve safety.

[0026] The upper ends of the first bracket 1 and the second bracket 2 are both provided with a safety rope 8, one end of the safety rope 8 is connected to the four upper ends of the columns of the first bracket 1 and the second bracket 2, and the other end of the safety rope 8 is provided with a rope buckle. The safety rope 8 is stretched upward so that the rope buckle is hung on the steel bars on the surface of the prefabricated beam and fixed.

[0027] A further solution of the utility model is that hinged connecting rods 6 are evenly spaced on both sides of the lower part between the first bracket 1 and the second bracket 2, and there are at least two connecting rods 6, which are also used as side fences and improve the strength between the first bracket 1 and the second bracket 2. The two ends of the connecting rod 6 are hinged to the columns of the first bracket 1 and the second bracket 2 through a pin 14.

[0028] Directions:

[0029] First, adjust the first support arm 3 and the first bracket 1, the second support arm 4 and the second bracket 2 to the same appropriate height according to the size of the prefabricated beam, and then fix them with bolts 13. Then, fold and scale the hanging basket, and shorten the width between the first bracket 1 and the second bracket 2, the first support arm 3 and the second support arm 4 by lifting the first bracket 1 or the second bracket 2. Next, lower the folded hanging basket to the bottom of the prefabricated beam through the expansion joint, and then hold the rope buckle of the wire rope by hand. After opening the hanging basket, hang the rope buckle on the embedded steel bars on the upper surface of the prefabricated beam, and the two hanging basket cross arms 10 are respectively hung on the prefabricated beams on both sides of the wet joint. Further, two support rods 7 are inserted into the steel pipes on both sides of the two hanging basket cross arms 10. Finally, the construction personnel enter the top of the base 5 from the ladder rod 11 on the first support arm 3 or the second support arm 4 to carry out the construction of the diaphragm. After the construction is completed, climb out through the ladder rod 11, pull out the support rod 7, fold the hanging basket, pull out the folded hanging basket, and carry out the construction of the next position.

[0030] It is obvious to those skilled in the art that the present invention is not limited to the details of the exemplary embodiments described above, and that the present invention can be implemented in other specific forms without departing from the spirit or essential features of the present invention. Therefore, the embodiments should be regarded as exemplary and non-limiting from any point of view, and the scope of the present invention is defined by the appended claims rather than the above description, and it is intended that all changes falling within the meaning and scope of the equivalent elements of the claims are included in the present invention. Any reference numeral in a claim should not be regarded as limiting the claim to which it relates.

Claims

1. A folding hanging basket for bridge wet joint construction, characterized in that: The invention comprises a first bracket (1), a second bracket (2), a first support arm (3), a second support arm (4) and a base (5); the two ends of the base (5) are respectively hinged to the first bracket (1) and the second bracket (2); the upper end of the first bracket (1) is telescopically connected to the first support arm (3) and fixed by bolts (13); the upper end of the second bracket (2) is telescopically connected to the second support arm (4) and fixed by bolts (13); ladder rods (11) are arranged at equal intervals from top to bottom on the first support arm (3) and / or the second support arm (4); the upper ends of the first support arm (3) and the second support arm (4) are provided with hanging basket cross arms (10); and the upper ends of the first bracket (1) and the second bracket (2) are provided with safety ropes (8).

2. A foldable hanging basket for bridge wet joint construction according to claim 1, characterized in that: Cross bars (9) are arranged at equal intervals at the lower parts of the first bracket (1) and the second bracket (2).

3. A foldable hanging basket for bridge wet joint construction according to claim 2, characterized in that: Articulated connecting rods (6) are arranged at equal intervals on both sides of the lower part between the first bracket (1) and the second bracket (2).

4. The foldable hanging basket for bridge wet joint construction according to claim 3, characterized in that: The two ends of the base (5) are connected to the first bracket (1) and the second bracket via a pin shaft (14), and the two ends of the connecting rod (6) are hinged to the first bracket (1) and the second bracket (2) via a pin shaft (14).

5. A foldable hanging basket for bridge wet joint construction according to claim 4, characterized in that: The upper surface of the base (5) is provided with a patterned plate.

6. A foldable hanging basket for bridge wet joint construction according to any one of claims 1 to 5, characterized in that: A support rod (7) is arranged on the hanging basket cross arm (10).