Reinforcement cage protection structure for over-pouring of concrete pile
By designing the steel cage protection structure and using the combination of the protective cylinder and the anti-cage cylinder, the problem of the difficult concrete being removed after the concrete piles are overfilled is solved, achieving efficient project progress and reducing manpower and material investment.
Patent Information
- Application Number
- CN202422042069.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-22
- Publication Date
- 2025-06-06
- Estimated Expiration
- 2034-08-22
AI Technical Summary
During the construction of concrete piles, the overfilled concrete is difficult to remove, resulting in the impact of the project progress and large manpower and material investment.
A steel cage protection structure is designed, including a protective cylinder and a spill-proof cylinder. By setting a protective cylinder on the top of the steel cage and spraying foam material to seal it, forming a casting channel to pour in concrete. After solidification, the protective structure can be removed by removing the concrete.
It effectively solved the problem that concrete is difficult to remove after concrete piles are overfilled, reduced manpower and material investment, and improved project progress.
Smart Images

Figure CN222948985U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to a steel cage protection structure for a concrete pile, in particular to a steel cage protection structure for over-pouring of a concrete pile. Background Art
[0002] When making concrete piles, in order to ensure the concrete strength of the top of the concrete piles and the quality of the project, in the actual construction process of concrete piles, over-pouring is required to achieve the floating of floating objects mixed in the concrete, debris that has not been cleaned up in the foundation pit, silt at the bottom of the hole that is difficult to completely remove in the foundation pit, and bubbles mixed in the concrete. The over-pouring part is the part mixed with these impurities; after the concrete piles solidify, the over-pouring part of the concrete needs to be removed. The common method is to use a hammer to make this part of the concrete fall off, and then clean the remaining concrete on the steel cage while ensuring that the steel cage is not excessively deformed. This approach not only requires a lot of manpower and material resources, but also seriously affects the progress of the project. Utility Model Content
[0003] The utility model aims to solve the existing deficiencies and discloses a steel cage protection structure for over-pouring of concrete piles. The steel cage protection tube fully covers the upper part of the steel cage, which can solve the problem of difficult removal of concrete after solidification when pouring concrete.
[0004] In order to achieve the purpose of the utility model, the present application discloses the following technical solutions:
[0005] A steel cage protection structure for over-pouring of concrete piles comprises a protection tube and an anti-overflow tube, the anti-overflow tube is sleeved on the outside of the protection tube, an annular cavity is formed between the anti-overflow tube and the protection tube, the protection tube comprises an outer tube, an outer tube cavity is arranged in the outer tube, an inner tube cavity is arranged in the outer tube, an inner tube cavity is arranged in the inner tube, an annular plate is arranged between the top of the outer tube and the top of the inner tube, two hanging rings and two through holes are arranged at intervals on the annular plate, covers are arranged on the tops of the two through holes, and foaming material is arranged between the bottom of the outer tube and the bottom of the inner tube.
[0006] The steel cage protection structure used for overfilling of concrete piles has two handles arranged opposite to each other on the upper part of the outer wall of the anti-overflow cylinder.
[0007] The steel cage protection structure used for over-pouring of concrete piles is provided with a handle on the top of the cover and a rubber plug post is provided on the bottom of the cover, and the rubber plug post is inserted into the through hole.
[0008] The foaming material of the steel cage protection structure used for over-pouring of concrete piles is a heat-insulating foaming agent.
[0009] Through the above disclosure, the beneficial effects of the present disclosure are:
[0010] The steel cage protection structure for over-pouring of concrete piles described in the utility model has the following advantages: after the steel cage is placed in the excavated foundation pit, the protection tube is covered on the top of the steel cage by using the outer tube cavity between the outer tube and the inner tube, and then the foaming material is sprayed at the lower opening between the inner tube and the outer tube for sealing. After the outer anti-overflow tube is placed at the mouth of the foundation pit outside the protection tube, the inner tube cavity can be used to form a pouring channel to pour concrete into the steel cage. After the concrete solidifies, the protection tube and the outer anti-overflow tube are removed, and the concrete shell and the over-pouring concrete column can be smashed with tools, thereby solving the original problem that the concrete on the upper part of the steel cage needs to be cleared; the utility model effectively solves the problem that the solidified concrete is difficult to clear after over-pouring of concrete in the steel cage in the prior art. BRIEF DESCRIPTION OF THE DRAWINGS
[0011] Figure 1 is a schematic diagram of the structure of the present disclosure;
[0012] Figure 2 It is a three-dimensional structural schematic diagram of the protective tube disclosed in the present invention;
[0013] Figure 3 is a schematic diagram of the three-dimensional structure of the protective tube disclosed in another perspective;
[0014] Figure 4 It is a schematic diagram of the three-dimensional structure of the anti-overflow cylinder disclosed in the present invention;
[0015] Figure 5 It is a structural schematic diagram of the over-pouring part of the concrete pile after pouring of the present invention.
[0016] In the figure: 1. lifting ring; 2. handle; 3. cover; 4. ring plate; 5. rubber plug; 6. inner tube; 7. outer tube; 8. handle; 9. anti-overflow tube; 10. inner tube cavity; 11. foam material; 12. base surface; 13. steel cage; 14. cage cavity; 15. ring cavity; 16. soil layer; 17. foundation pit; 18. perforation; 19. outer tube cavity; 20. gap; 21. concrete over-filling column; 22. concrete shell; 23. concrete pile. DETAILED DESCRIPTION
[0017] The preferred embodiments of the present invention will be described in detail below in conjunction with the accompanying drawings so as to more clearly understand the invention objectives, features and advantages of the present invention. It should be understood that the embodiments shown in the accompanying drawings are not intended to limit the scope of the present invention, but are only intended to explain that the technical solution of the present invention is not limited to one implementation method.
[0018] Combined with Figures 1 to 4The steel cage protection structure for over-pouring of concrete piles comprises a protection tube and an anti-overflow tube 9, the anti-overflow tube 9 is sleeved on the outside of the protection tube, two handles 8 are arranged opposite to each other on the upper part of the outer wall of the anti-overflow tube 9, an annular cavity 15 is formed between the anti-overflow tube 9 and the protection tube, the protection tube comprises an outer tube 7, an outer tube cavity 19 is arranged in the outer tube 7, an inner tube 6 is arranged in the outer tube cavity 19, an inner tube cavity 10 is arranged in the inner tube 6, an annular plate 4 is arranged between the top of the outer tube 7 and the top of the inner tube 6, two hanging rings 1 and two through holes 18 are arranged on the annular plate 4 at intervals, a cover 3 is arranged at the top of the two through holes 18, a handle 2 is arranged at the top of the cover 3, a rubber plug 5 is arranged at the bottom of the cover 3, the rubber plug 5 is inserted in the through hole 18, a foaming material 11 is arranged between the bottom of the outer tube 7 and the bottom of the inner tube 6, and the foaming material 11 is a thermal insulation foaming agent.
[0019] The steel cage protection structure for overfilling concrete piles is implemented in combination with the attached Figures 1 to 5 The specific construction of the present disclosure is further explained; after the steel cage 13 is placed in the excavated foundation pit, the steel cage 13 is positioned so that the steel cage 13 is centered in the foundation pit 17, and the protective tube and the outer anti-overflow tube 9 are soaked or sprayed in all directions with a cement release agent, and then the protective tube is covered on the top of the steel cage 13 using the outer tube cavity 19 between the outer tube 7 and the inner tube 6, so that the top of the steel cage 13 is in contact with the bottom of the ring plate 4, and the inner tube 6 is placed in the cage cavity 14 provided in the steel cage 13, and the foaming material 11 is sprayed at the lower opening between the inner tube 6 and the outer tube 7 for sealing, and the sealing of the foaming material 11 plays a role in fixing the protective tube on the top of the steel cage 13. The anti-overflow tube 9 is placed on the pit mouth of the foundation pit 17 of the base surface 12, so that the lower part of the outer wall of the anti-overflow tube 9 is in contact with the soil layer 16, and the inner tube cavity 10 is used to form a pouring channel to pour concrete into the steel cage 13. After the concrete solidifies, the cover 3 is removed. At this time, the outer tube cavity 19 between the outer tube 7 and the inner tube 6 is connected to the external environment. The protective tube loses negative pressure and can be removed by lifting the lifting ring 1 through the lifting device (although the foaming material 11 has a certain strength, it is insignificant compared with the weight of the steel cage 13 after the concrete is poured, and the cement release agent also has a lubricating effect). Then the anti-overflow tube 9 is removed to form a combined attachment Figure 5 The structure is as follows: the steel cage 13 in the foundation pit 17 forms a concrete pile 23, the concrete located inside the inner cylinder cavity 10 forms a concrete super-filling column 21, the annular cavity 15 between the anti-overflow cylinder 9 and the protection cylinder forms a concrete shell 22, and the space between the concrete super-filling column 21 and the concrete shell 22 forms a gap 20. Use tools to smash the concrete shell 22 and the concrete super-filling column 21 on the upper part of the concrete pile 23, and remove the foaming material 11 at the lower part of the gap 20.
[0020] The preferred embodiments of the present disclosure have been described in detail above, but it should be understood that after reading the above teachings of the present disclosure, those skilled in the art may make various changes or modifications within the scope of protection of the present disclosure. These equivalent forms also fall within the scope defined by the claims attached to this application.
[0021] The parts not described in detail in this utility model are prior art.
Claims
1. A steel cage protection structure for overfilling of concrete piles, characterized by: The invention comprises a protective tube and an anti-overflow tube (9), wherein the anti-overflow tube (9) is sleeved on the outside of the protective tube, and an annular cavity (15) is formed between the anti-overflow tube (9) and the protective tube. The protective tube comprises an outer tube (7), an outer tube cavity (19) is provided in the outer tube (7), an inner tube (6) is provided in the outer tube cavity (19), an inner tube cavity (10) is provided in the inner tube (6), an annular plate (4) is provided between the top of the outer tube (7) and the top of the inner tube (6), two suspension rings (1) and two through holes (18) are provided on the annular plate (4) at intervals, and a cover (3) is provided at the top of each of the two through holes (18), and a foaming material (11) is provided between the bottom of the outer tube (7) and the bottom of the inner tube (6).
2. The steel cage protection structure for concrete pile overfilling according to claim 1 is characterized in that: Two handles (8) are arranged opposite to each other on the upper part of the outer wall of the overflow prevention cylinder (9).
3. The steel cage protection structure for concrete pile overfilling according to claim 1 is characterized by: A handle (2) is provided on the top of the cover (3), and a rubber plug post (5) is provided on the bottom of the cover (3), wherein the rubber plug post (5) is inserted into the through hole (18).
4. The steel cage protection structure for concrete pile overfilling according to claim 1 is characterized in that: The foaming material (11) is a heat-insulating foaming agent.