Permanent and temporary combined construction road structure
By designing the construction road structure that combines Yonglin, the problem that temporary roads cannot meet the requirements of permanent roads is solved, the effective utilization of materials and human resources is achieved, and the construction efficiency is improved.
Patent Information
- Application Number
- CN202422166013.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-04
- Publication Date
- 2025-06-10
- Estimated Expiration
- 2034-09-04
AI Technical Summary
In construction projects, temporary roads at the construction site cannot meet the design slope and bearing capacity requirements of the permanent road after construction is completed, resulting in the need to be broken down and waste of materials and human resources.
A construction road structure that combines Yonglin is designed, including the foundation concrete layer and ash soil layer. The foundation concrete layer reserves expansion joints and fills asphalt rubber. Pipes are embedded below the ash soil layer, and wells are set up in the road to facilitate the later laying of asphalt concrete.
This structure can be used as a temporary road, and can also be transformed into a permanent road after construction is completed, avoiding the waste of materials and human resources, and meeting the foundation bearing capacity requirements for heavy vehicles passing through the construction stage.
Smart Images

Figure CN222961842U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of road construction, and particularly relates to a construction road structure combining temporary and permanent roads. Background Technique
[0002] At present, in construction projects, the dust control of construction sites by various government functional departments is becoming increasingly severe. It is required that the temporary roads on construction sites must be hardened and sprinkled and wetted for 24 hours. In the early stage of project construction, due to the tight construction period and heavy tasks, various pipelines below the temporary roads have not been constructed. When landscaping construction is carried out later, the concrete temporary roads are demolished, and the concrete blocks are transported out, and the field pipelines and formal roads are constructed again, resulting in waste of materials and human resources. Therefore, in the early stage of construction, how to reasonably plan the temporary roads and insert the construction of various pipelines in advance to make them the permanent road base to avoid waste of materials and human resources is an urgent problem to be solved by those skilled in the art. Content of the Utility Model
[0003] The utility model relates to the construction road of the main roads in the newly-built public buildings and residential building areas, mainly solves the problem of the combination of the temporary roads and the permanent roads required during the construction of the newly-built buildings, and avoids the technical problems such as the demolition of the temporary roads due to the non-compliance with the design gradient and bearing capacity requirements during the construction of the permanent roads, resulting in material waste and cost increase, and provides a construction road structure combining temporary and permanent roads.
[0004] The technical solution of the utility model to solve the above technical problems is as follows: a construction road structure combining temporary and permanent roads, which includes a base concrete layer and a lime soil layer arranged in sequence from top to bottom. The base concrete layer includes multiple sections of base concrete segments, and a expansion joint is reserved between adjacent two sections of base concrete segments. The expansion joint is filled with asphalt rubber; pipelines are embedded in the plain soil compaction foundation below the lime soil layer, and multiple water wells are also arranged in the base concrete layer and the lime soil layer. The upper ends of the water wells are located on the upper surface of the base concrete layer, and the multiple water wells are communicated with each other through the pipelines;
[0005] The width of the lime soil layer is greater than the width of the base concrete layer, and curb stones made of multiple concrete blocks are respectively arranged on both sides of the base concrete layer in the width direction.
[0006] The beneficial effects of the present utility model are as follows: For the construction road structure with the combination of temporary and permanent use of the present utility model, by embedding pipelines and setting up water wells, this construction road structure can be used as a temporary road for building construction, and after the building construction is completed, asphalt concrete can be laid as a permanent road structure without damaging the temporary road structure; it can not only meet the requirements of the design drawings but also meet the requirements of the bearing capacity of the foundation when various heavy vehicles pass during the construction stage, solving problems such as the need to break the temporary concrete road, transport the concrete fragments out of the site, and re-construct the field pipe network and the formal road during the later garden construction, resulting in waste of materials and human resources.
[0007] On the basis of the above technical solution, the present utility model can also be improved as follows.
[0008] Further, the curb is located on the lime soil layer, and both sides of the lime soil layer exceed the width of the two curbs by a certain part, and the widths of the parts exceeding the two curbs on both sides of the lime soil layer are equal.
[0009] Further, lime soil piles are provided on the widths of the parts where both sides of the lime soil layer exceed the two curbs, and the lime soil piles are piled on the outer side walls of the curbs.
[0010] Further, an AC-20C asphalt concrete layer is also provided on the foundation concrete layer, an AC-13 asphalt concrete layer is provided on the AC-20C asphalt concrete layer, and the widths of the AC-20C asphalt concrete layer and the AC-13 asphalt concrete layer are both equal to the width of the foundation concrete layer; the upper end of the water well extends to the upper surface of the AC-13 asphalt concrete layer.
[0011] Further, the thickness of the AC-13 asphalt concrete layer is 30 - 50 mm, and the thickness of the AC-20C asphalt concrete layer is 50 mm - 70 mm.
[0012] Further, the thickness of the AC-13 asphalt concrete layer is 40 mm, and the thickness of the AC-20C asphalt concrete layer is 60 mm.
[0013] Further, the foundation concrete layer is a C30 concrete layer.
[0014] Further, the thickness of the foundation concrete layer is 150 mm - 250 mm.
[0015] Further, the thickness of the lime soil layer is 200 mm - 300 mm; the width of the expansion joint is 8 mm - 12 mm.
[0016] Further, the water well includes a rainwater well and a sewage well, the pipeline includes a rainwater pipe and a sewage pipe, and the lower ends of adjacent rainwater wells are connected through the rainwater pipe, and the lower ends of adjacent sewage wells are connected through the sewage pipe. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] Figure 1 It is a plan view of the permanent and temporary construction road structure of the utility model;
[0018] Figure 2 The cross-sectional structure diagram of the permanent and temporary construction road structure of the utility model is shown in FIG. Figure 1 ;
[0019] Figure 3 The cross-sectional structure diagram of the permanent and temporary construction road structure of the utility model is shown in FIG. Figure 2 .
[0020] In the accompanying drawings, the components represented by the reference numerals are listed as follows:
[0021] 1. Foundation concrete layer; 11. Foundation concrete section; 12. Expansion joint;
[0022] 2. Curb; 21. Concrete block; 22. Ash pile;
[0023] 3. AC-13 asphalt concrete layer; 31. AC-20C asphalt concrete layer;
[0024] 4. Lime soil layer; 5. Ram the foundation with plain soil;
[0025] 6. Sewage well; 61. Sewage pipe; 7. Rainwater well; 71. Rainwater pipe. DETAILED DESCRIPTION
[0026] The principles and features of the present invention are described below in conjunction with the accompanying drawings. The examples given are only used to explain the present invention and are not used to limit the scope of the present invention.
[0027] like Figures 1 to 3 As shown, a permanent and temporary construction road structure of the present embodiment comprises a foundation concrete layer 1 and a lime soil layer 4 arranged in sequence from top to bottom, wherein the foundation concrete layer 1 comprises a plurality of foundation concrete segments 11, and an expansion joint 12 is reserved between two adjacent foundation concrete segments 11, and the expansion joint 12 is filled with asphalt rubber; a pipeline is pre-buried in the rammed earth foundation 5 below the lime soil layer 4, and a plurality of water wells are further arranged in the foundation concrete layer 1 and the lime soil layer 4, and the upper ends of the water wells are located on the upper surface of the foundation concrete layer 1, and the plurality of water wells are interconnected through the pipelines;
[0028] The width of the ash soil layer 4 is greater than the width of the base concrete layer 1 , and the base concrete layer 1 is provided with curbs 2 made of a plurality of concrete blocks 21 on both sides in the width direction.
[0029] like Figure 2As shown, the curb 2 of this embodiment is located on the lime soil layer 4. The two sides of the lime soil layer 4 respectively extend beyond the two curbs 2 by a partial width, and the partial widths by which the two sides of the lime soil layer 4 extend beyond the two curbs 2 are equal.
[0030] As Figure 2 shown, on the partial widths by which the two sides of the lime soil layer 4 of this embodiment respectively extend beyond the two curbs 2, there are lime soil piles 22, and the lime soil piles 22 are piled on the outer side walls of the curbs 2.
[0031] When the asphalt concrete layer is arranged on the upper part of the basic concrete layer 1 of this embodiment, a manhole cover can be covered on the water well, and it can be used as a temporary road.
[0032] As Figure 2 shown, an AC-20C asphalt concrete layer 31 is further arranged on the basic concrete layer 1 of this embodiment. An AC-13 asphalt concrete layer 3 is arranged on the AC-20C asphalt concrete layer 31. The widths of the AC-20C asphalt concrete layer 31 and the AC-13 asphalt concrete layer 3 are both equal to the width of the basic concrete layer 1; the upper end of the water well extends to the upper surface of the AC-13 asphalt concrete layer 3. After the asphalt concrete layer is laid, it can be used as a formal road.
[0033] Optionally, the thickness of the AC-13 asphalt concrete layer 3 of this embodiment is 30 - 50 mm, and the thickness of the AC-20C asphalt concrete layer 31 is 50 mm - 70 mm.
[0034] Preferably, the thickness of the AC-13 asphalt concrete layer 3 is 40 mm, and the thickness of the AC-20C asphalt concrete layer 31 is 60 mm.
[0035] Optionally, the basic concrete layer 1 is a C30 concrete layer.
[0036] Optionally, the thickness of the basic concrete layer 1 is 150 mm - 250 mm.
[0037] Optionally, the thickness of the lime soil layer 4 is 200 mm - 300 mm, preferably 250 mm, the lime-soil ratio is 3:7, and the compaction coefficient ≥ 0.97; the width of the expansion joint 12 is 8 mm - 12 mm. The lime soil layer is arranged on a rammed plain soil foundation, and the compaction coefficient of the rammed plain soil foundation ≥ 0.94.
[0038] Specifically, as Figure 1 shown, the water well includes a rainwater well 7 and a sewage well 6. The pipelines include a rainwater pipe 71 and a sewage pipe 61. The lower ends between adjacent rainwater wells 7 are communicated through the rainwater pipe 71, and the lower ends between adjacent sewage wells 6 are communicated through the sewage pipe 61.
[0039] In the construction preparation stage of the temporary and permanent combined construction road structure of this embodiment, construction drawings of outdoor pipe networks, construction roads, and landscape gardens are obtained. Plan layout drawings for each stage are drawn based on the construction drawings. Design optimization is carried out according to the plan layout drawings in combination with the construction drawings of outdoor pipe networks, construction roads, and landscape gardens, and the design unit is communicated with for drawing change adjustment. The outdoor pipe network is constructed first, and temporary sleeves are arranged in advance at positions where pipelines cannot be embedded temporarily. The underground pipe network, the compaction of the original soil subgrade of the road surface, the construction of the 3:7 lime soil base layer of the road surface, and the construction of the concrete base layer of the road surface are constructed in sequence according to the adjusted plan layout drawings, and the asphalt mixture surface layer is reserved for construction in the landscape garden stage. Specifically, a 200-mm-thick C30 concrete base layer is poured on the lime soil layer first, and this base layer serves as the temporary road surface layer. A 10-mm-wide expansion joint is set every 6 m on the road, and the expansion joint is treated with asphalt rubber caulking. After the construction of the temporary road is completed and after it is used as a temporary road, the concrete base layer can be cleaned, and a 60-mm-thick AC-20C ordinary asphalt concrete surface layer is paved. After the maintenance period ends, a 40-mm-thick AC-13 ordinary asphalt concrete is continued to be paved as the final surface layer.
[0040] For the temporary and permanent combined construction road structure of this embodiment, by embedding pipelines and setting up water wells, this construction road structure can be used as a temporary road for building construction, and after the building construction is completed, asphalt concrete can be laid as a permanent road structure without damaging the temporary road structure; it can not only meet the requirements of the design drawings but also meet the foundation bearing capacity requirements when various heavy vehicles pass during the construction stage, solving problems such as the need to break the concrete temporary road and transport the concrete fragments out of the site and re-construct the field pipe network and the formal road during later garden construction, resulting in waste of materials and human resources. Through the practice of combining temporary and permanent construction roads, not only is the construction procedure simplified, the construction time in the landscape garden stage is shortened, but also the construction investment is reduced, greatly improving the outdoor construction efficiency, having a positive impact on the overall project, shortening the construction period at the same time, enabling the construction unit to put it into use and operation in advance, and maximizing the benefits.
[0041] In the description of the present invention, it should be understood that the orientation or positional relationship indicated by the terms "center", "longitudinal", "transverse", "length", "width", "thickness", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outer", "clockwise", "counterclockwise", "axial", "radial", "circumferential", etc. is based on the orientation or positional relationship shown in the drawings, and is only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation of the present invention.
[0042] In addition, the terms "first" and "second" are for descriptive purposes only and should not be construed as indicating or implying relative importance or implicitly specifying the quantity of the indicated technical features. Thus, features defined with "first" and "second" may explicitly or implicitly include at least one such feature. In the description of the present utility model, "a plurality of" means at least two, such as two, three, etc., unless otherwise specifically defined.
[0043] In the present utility model, unless otherwise clearly defined and limited, the terms such as "mounted", "connected", "connected to", "fixed", etc. shall be construed in a broad sense. For example, it may be a fixed connection, a detachable connection, or integrated; it may be a mechanical connection or an electrical connection; it may be directly connected or indirectly connected through an intermediate medium, and it may be the internal communication of two elements or the interaction relationship between two elements, unless otherwise clearly limited. For those of ordinary skill in the art, the specific meanings of the above terms in the present utility model can be understood according to specific circumstances.
[0044] In the present utility model, unless otherwise clearly defined and limited, the first feature being "on" or "under" the second feature may be that the first and second features are in direct contact, or the first and second features are indirectly in contact through an intermediate medium. Moreover, the first feature being "above", "over" and "on top of" the second feature may be that the first feature is directly above or obliquely above the second feature, or merely indicates that the first feature has a higher horizontal height than the second feature. The first feature being "under", "beneath" and "underneath" the second feature may be that the first feature is directly below or obliquely below the second feature, or merely indicates that the first feature has a lower horizontal height than the second feature.
[0045] In the description of this specification, the descriptions with reference to terms such as "one embodiment", "some embodiments", "example", "specific example", or "some examples" etc. mean that the specific features, structures, materials or characteristics described in connection with the embodiment or example are included in at least one embodiment or example of the present utility model. In this specification, the schematic descriptions of the above terms do not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described can be combined in a suitable manner in any one or more embodiments or examples. In addition, without contradiction, those skilled in the art can combine and combine the different embodiments or examples described in this specification and the features of different embodiments or examples.
[0046] Although the embodiments of the present utility model have been shown and described above, it can be understood that the above embodiments are exemplary and should not be construed as limiting the present utility model. Those of ordinary skill in the art can make changes, modifications, substitutions and variations to the above embodiments within the scope of the present utility model.
Claims
1. A permanent and temporary construction road structure, characterized in that: It includes a foundation concrete layer and a lime soil layer arranged in sequence from top to bottom, the foundation concrete layer includes multiple foundation concrete segments, expansion joints are reserved between two adjacent foundation concrete segments, and the expansion joints are filled with asphalt rubber; a pipeline is pre-buried in the rammed soil foundation below the lime soil layer, and multiple water wells are also arranged in the foundation concrete layer and the lime soil layer, the upper ends of the water wells are located on the upper surface of the foundation concrete layer, and the multiple water wells are interconnected through the pipelines; The width of the ash soil layer is greater than the width of the foundation concrete layer, and the foundation concrete layer is provided with curbs made of a plurality of concrete blocks on both sides in the width direction.
2. According to claim 1, a permanent and temporary construction road structure is characterized in that: The curb is located on the ash soil layer, and the widths of the parts on both sides of the ash soil layer respectively exceed the two curbs, and the widths of the parts on both sides of the ash soil layer respectively exceed the two curbs are equal.
3. According to claim 2, a permanent and temporary construction road structure is characterized in that: Ash soil piles are arranged on the widths of the parts of the ash soil layer that respectively exceed the two curbs on both sides, and the ash soil piles are arranged on the outer side walls of the curbs.
4. According to claim 1, a permanent and temporary construction road structure is characterized in that: An AC-20C asphalt concrete layer is also provided on the base concrete layer, and an AC-13 asphalt concrete layer is provided on the AC-20C asphalt concrete layer. The widths of the AC-20C asphalt concrete layer and the AC-13 asphalt concrete layer are both equal to the width of the base concrete layer; the upper end of the water well extends to the upper surface of the AC-13 asphalt concrete layer.
5. According to claim 4, a permanent and temporary construction road structure is characterized in that: The thickness of the AC-13 asphalt concrete layer is 30-50 mm, and the thickness of the AC-20C asphalt concrete layer is 50 mm-70 mm.
6. A permanent and temporary construction road structure according to claim 5, characterized in that: The thickness of the AC-13 asphalt concrete layer is 40 mm, and the thickness of the AC-20C asphalt concrete layer is 60 mm.
7. The permanent and temporary construction road structure according to claim 1 is characterized in that: The base concrete layer is a C30 concrete layer.
8. The permanent and temporary construction road structure according to claim 7 is characterized in that: The thickness of the foundation concrete layer is 150 mm to 250 mm.
9. The permanent and temporary construction road structure according to claim 1, characterized in that: The thickness of the ash soil layer is 200 mm to 300 mm; the width of the expansion joint is 8 mm to 12 mm.
10. The permanent and temporary construction road structure according to claim 1, characterized in that: The water wells include rainwater wells and sewage wells, the pipelines include rainwater pipes and sewage pipes, the lower ends of adjacent rainwater wells are connected through rainwater pipes, and the lower ends of adjacent sewage wells are connected through sewage pipes.