Movable storage hopper for concrete side ditch pouring

By designing the storage hopper used for casting of movable concrete side ditches, the problems of cumbersome crane operation and high sliding form construction cost in the existing technology are solved, and efficient casting of concrete side ditches is achieved, saving construction time and cost.

CN222961846UActive Publication Date: 2025-06-10宁夏交通建设股份有限公司
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421603957.0
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-07-09
Publication Date
2025-06-10
Estimated Expiration
2034-07-09

AI Technical Summary

Technical Problem

In the existing concrete side ditch pouring technology, crane operation is cumbersome and wastes time, sliding form construction costs are high and greatly affected by geographical location, making it difficult to effectively solve the problems of construction efficiency and cost.

Method used

A storage hopper for casting movable concrete side ditch is designed, including the storage hopper body, material port, support plate, roller, first and second discharge adjustment components. The storage hopper is driven to move through the roller, and combined with the adjustable baffle and discharge adjustment components, the efficient casting of concrete is achieved.

Benefits of technology

It reduces the investment in cranes, saves construction time, reduces mechanical investment costs, improves construction efficiency, and is suitable for cast-in-place edge ditches of various widths, effectively ensuring the applicability of the storage hopper.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222961846U_ABST
    Figure CN222961846U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of concrete construction, in particular to a movable storage hopper for concrete side ditch pouring, which comprises a storage hopper body. Material openings are formed in the left side and the right side of the bottom of the storage hopper body correspondingly, first baffles are arranged on the outer sides of the lower ends of the material openings correspondingly, and first discharging adjusting assemblies are arranged below the first baffles correspondingly. Second baffles are arranged on the inner sides of the lower ends of the material ports. A second discharging adjusting assembly is arranged in the middle of the lower end of the storage hopper body. Supporting plates are fixed to the left and right sides of the lower end of the storage hopper body; rollers are rotationally connected to the front and rear parts of the lower ends of the supporting plates; according to the concrete storage hopper, concrete is added into the storage hopper body, discharging can be directly carried out through the material opening, investment of a crane is reduced, construction time is saved, the storage hopper is easy to manufacture and not affected by geographic positions, excessive machines do not need to be input, and input cost is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of concrete construction, in particular to a movable storage hopper for concrete side ditch pouring. Background Art

[0002] Concrete refers to the general term for engineering composite materials in which aggregate is cemented into a whole by cementitious materials. Usually, the term concrete refers to cement concrete, which uses cement as the cementitious material, sand and stone as the aggregate; it is mixed with water (which may contain additives and admixtures) in a certain proportion and obtained by stirring, also known as ordinary concrete, and it is widely used in civil engineering.

[0003] In the prior art, there are usually two methods for concrete pouring construction of cast-in-place side ditches. The first is a crane for concrete hoisting and pouring construction. During the construction, the position of the crane needs to be frequently moved, and the operation sequence of concrete hoisting is relatively cumbersome, wasting effective construction time. The second is slip form construction, which is greatly affected by geographical location and requires more machinery, so the cost is relatively high. Therefore, for the prior art, how to solve the above problems is particularly crucial. Summary of the Utility Model

[0004] In view of the deficiencies of the prior art, the utility model provides a movable storage hopper for concrete side ditch pouring to solve the problems such as cumbersome, time-consuming and high cost.

[0005] To achieve the above object, the utility model is realized through the following technical solutions: A movable storage hopper for concrete side ditch pouring, including a storage hopper body;

[0006] On both the left and right sides of the bottom of the storage hopper body, there are material openings, and on the outer sides of the lower ends of the material openings, there are first baffles, and below the first baffles, there are first blanking adjustment components;

[0007] On the inner sides of the lower ends of the material openings, there are second baffles, and in the middle of the lower end of the storage hopper body, there is a second blanking adjustment component;

[0008] On both the left and right sides of the lower end of the storage hopper body, there are support plates fixed, and at the front and rear parts of the lower ends of the support plates, there are rollers rotatably connected.

[0009] Preferably, in the middle of the inner bottom end of the storage hopper body, there is a V-shaped protrusion, and the V-shaped protrusion is located between the two material openings.

[0010] Preferably, each of the first blanking adjustment components includes a first guide rod, a first adjusting plate and a threaded adjusting rod. The first guide rods are all fixed on the inner sides of the support plates, and the first adjusting plates are all slidably sleeved on the peripheries of the first guide rods, and the first adjusting plates are all fixed to the lower ends of the first baffles.

[0011] Preferably, the threaded adjusting rods all rotatably penetrate through adjacent support plates, and the first adjusting plates are all threadedly sleeved on the threaded adjusting rods.

[0012] Preferably, the second blanking adjustment assembly includes a fixed plate, a bidirectional lead screw, second adjusting plates and second guide rods. The fixed plate is fixed to the middle of the lower end of the storage hopper body. The bidirectional lead screw rotatably penetrates through the fixed plate. There are two second adjusting plates, which are respectively fixed to the lower ends of the two second baffles, and the second adjusting plates are all threadedly sleeved on the bidirectional lead screw.

[0013] Preferably, the second guide rods are all fixed to the left and right ends of the fixed plate, and the second adjusting plates are all slidably sleeved on the second guide rods on the same side.

[0014] The utility model provides a movable storage hopper for concrete side ditch pouring, which has the following beneficial effects:

[0015] By adding concrete into the storage hopper body, discharging can be directly carried out through the material outlet, reducing the investment in cranes, thus saving construction time. Moreover, the storage hopper is simple to manufacture, not affected by geographical location, and does not require too much machinery, which is beneficial to reducing the input cost. And through the rollers, the storage hopper body can be conveniently driven to move and be used, which is convenient and fast to use and beneficial to improving work efficiency. Also, by setting the first baffle and the second baffle whose positions can be adjusted, it is beneficial to change the blanking amount of the material outlet according to the pouring requirements. Therefore, it is beneficial to carry out pouring construction for various widths of cast-in-place side ditches, reducing the cost of additional manufacturing and effectively ensuring the applicability of the storage hopper. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] Figure 1 is a schematic diagram of the overall structure of the utility model;

[0017] Figure 2 is a front view plane structure schematic diagram of the overall structure of the utility model;

[0018] Figure 3 is a bottom plane structure schematic diagram of the overall structure of the utility model.

[0019] Figures 1-3 In the figure: storage hopper body 1, material outlet 2, support plate 3, roller 4, V-shaped protrusion 5, first baffle 6, first adjusting plate 7, first guide rod 8, threaded adjusting rod 9, fixed plate 10, second baffle 11, second adjusting plate 12, second guide rod 13, bidirectional lead screw 14. DETAILED DESCRIPTION OF THE EMBODIMENTS

[0020] Next, the technical solutions in the embodiments of the present invention will be clearly and completely described in conjunction with the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only a part of the embodiments of the present invention, rather than all the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without creative efforts shall fall within the protection scope of the present invention.

[0021] Please refer to Figures 1-3 , the present invention provides a technical solution: a movable storage hopper for concrete side ditch pouring, including a storage hopper body 1. Both the left and right sides of the bottom of the storage hopper body 1 are provided with material openings 2. Both the left and right sides of the lower end of the storage hopper body 1 are fixed with support plates 3. The front and rear parts of the lower end of the support plate 3 are rotatably connected with rollers 4.

[0022] By adding concrete into the storage hopper body 1, and then combining with manual use of a shovel to push the concrete into the material opening 2, the concrete can be directly unloaded and poured through the material opening 2, reducing the investment in cranes, thus saving construction time. Moreover, the storage hopper is simple to manufacture, not affected by geographical location, and does not require excessive machinery, which is conducive to reducing the input cost. And through the rollers 4, the storage hopper body 1 can be conveniently driven to move and be used, which is convenient and fast to use and conducive to improving work efficiency.

[0023] In this embodiment, a V-shaped protrusion 5 is provided in the middle of the inner bottom end of the storage hopper body 1, and the V-shaped protrusion 5 is located between the two material openings 2.

[0024] By providing the V-shaped protrusion 5 at the inner bottom end of the storage hopper body 1, when the concrete is added into the storage hopper body 1, the concrete will slide along the inclined surface of the V-shaped protrusion 5 into the material opening 2 for blanking and pouring, which is conducive to reducing the work force when manually using a shovel to push the concrete into the material opening 2, making the pouring process more labor-saving and convenient.

[0025] In this embodiment, first baffles 6 are provided on the outer sides of the lower ends of the material inlets 2. First blanking adjustment assemblies are provided below the first baffles 6. Each of the first blanking adjustment assemblies includes a first guide rod 8, a first adjusting plate 7, and a threaded adjusting rod 9. The first guide rods 8 are fixed to the inner sides of the support plates 3. The first adjusting plates 7 are slidably sleeved around the first guide rods 8, and the first adjusting plates 7 are fixed to the lower ends of the first baffles 6. The threaded adjusting rods 9 rotatably penetrate through the adjacent support plates 3, and the first adjusting plates 7 are threadedly sleeved on the threaded adjusting rods 9. Second baffles 11 are provided on the inner sides of the lower ends of the material inlets 2. A second blanking adjustment assembly is provided in the middle of the lower end of the storage hopper body 1. The second blanking adjustment assembly includes a fixing plate 10, a bidirectional lead screw 14, a second adjusting plate 12, and a second guide rod 13. The fixing plate 10 is fixed to the middle of the lower end of the storage hopper body 1. The bidirectional lead screw 14 rotatably penetrates through the fixing plate 10. Two second adjusting plates 12 are provided and are respectively fixed to the lower ends of the two second baffles 11, and the second adjusting plates 12 are threadedly sleeved on the bidirectional lead screw 14. The second guide rods 13 are fixed to the left and right ends of the fixing plate 10, and the second adjusting plates 12 are slidably sleeved on the second guide rods 13 on the same side.

[0026] Moreover, according to the width of the cast-in-place side ditch, then turn the threaded adjusting rod 9 to drive the first adjusting plate 7 to slide along the first guide rod 8. The first adjusting plate 7 will drive the first baffle 6 to move together, so as to facilitate adjusting the position and size of the first baffle 6 blocking the material inlet 2. And by turning the bidirectional lead screw 14 to drive the second adjusting plate 12 to slide along the second guide rod 13, the second adjusting plate 12 will drive the second baffle 11 to move together, so as to facilitate adjusting the position and size of the second baffle 11 blocking the material inlet 2. Therefore, by providing the first baffle 6 and the second baffle 11 whose positions can be adjusted, it is beneficial to change the blanking amount of the material inlet 2 according to the pouring requirements. Thus, it is beneficial to carry out pouring construction for cast-in-place side ditches of various widths, reducing the cost of additional manufacturing and effectively ensuring the applicability of the storage hopper.

[0027] Working principle:

[0028] By adding concrete into the storage hopper body 1, and then manually pushing the concrete into the material inlet 2 with a shovel, discharging and pouring can be directly carried out through the material inlet 2. Moreover, the storage hopper body 1 can be conveniently driven to move by the rollers 4. By turning the threaded adjusting rod 9, the first adjusting plate 7 slides along the first guide rod 8, and the first adjusting plate 7 drives the first baffle 6 to move together, so as to facilitate adjusting the position and size of the first baffle 6 blocking the material inlet 2. By turning the bidirectional lead screw 14, the second adjusting plate 12 slides along the second guide rod 13, and the second adjusting plate 12 drives the second baffle 11 to move together, so as to facilitate adjusting the position and size of the second baffle 11 blocking the material inlet 2. Therefore, by setting the first baffle 6 and the second baffle 11 whose positions can be adjusted, it is beneficial to change the discharging amount of the material inlet 2 according to the pouring requirements.

[0029] Although the embodiments of the present invention have been shown and described, for those of ordinary skill in the art, it can be understood that various changes, modifications, substitutions and variations can be made to these embodiments without departing from the principle and spirit of the present invention. The scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. A movable concrete ditch pouring storage hopper, comprising a storage hopper body (1), characterized in that: The left and right sides of the bottom of the storage hopper body (1) are both provided with material openings (2), the outer sides of the lower ends of the material openings (2) are both provided with first baffles (6), and a first material discharge adjustment component is provided below the first baffles (6); A second baffle (11) is provided on the inner side of the lower end of the material opening (2), and a second material discharge adjustment component is provided in the middle of the lower end of the storage hopper body (1); Support plates (3) are fixed on both left and right sides of the lower end of the storage hopper body (1), and rollers (4) are rotatably connected to the front and rear parts of the lower end of the support plate (3).

2. A movable concrete ditch pouring storage hopper according to claim 1, characterized in that: A V-shaped protrusion (5) is provided in the middle of the bottom end of the storage hopper body (1), and the V-shaped protrusion (5) is located between the two material openings (2).

3. A movable concrete ditch pouring storage hopper according to claim 1, characterized in that: The first material discharge adjustment assembly comprises a first guide rod (8), a first adjustment plate (7) and a threaded adjustment rod (9); the first guide rod (8) is fixed to the inner side of the support plate (3); the first adjustment plate (7) is slidably sleeved on the outer periphery of the first guide rod (8); and the first adjustment plate (7) is fixed to the lower end of the first baffle (6).

4. A movable concrete ditch pouring storage hopper according to claim 3, characterized in that: The threaded adjustment rods (9) are all rotated to pass through the adjacent support plates (3), and the first adjustment plates (7) are all threadedly sleeved with the threaded adjustment rods (9).

5. The movable concrete ditch pouring storage hopper according to claim 1 is characterized in that: The second material discharge adjustment assembly comprises a fixed plate (10), a bidirectional screw rod (14), a second adjustment plate (12) and a second guide rod (13); the fixed plate (10) is fixed to the middle part of the lower end of the storage hopper body (1); the bidirectional screw rod (14) rotates and passes through the fixed plate (10); the second adjustment plate (12) is provided with two pieces and is fixed one by one to the lower ends of the two second baffles (11); and the second adjustment plates (12) are both threadedly sleeved with the bidirectional screw rod (14).

6. A movable concrete ditch pouring storage hopper according to claim 5, characterized in that: The second guide rods (13) are fixed to the left and right ends of the fixed plate (10), and the second adjustment plates (12) are slidably sleeved with the second guide rods (13) on the same side.