Construction hoist rail quick-mounting module in hoistway and construction hoist
By designing the speed installation module of construction elevator tracks in the shaft, the problem of the installation of construction elevator tracks in the shaft in the existing technology requires workers to carefully install them, achieving a more efficient and accurate installation process, reducing work difficulty and cost.
Patent Information
- Application Number
- CN202421543148.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-02
- Publication Date
- 2025-06-24
- Estimated Expiration
- 2034-07-02
AI Technical Summary
The installation of existing construction lift tracks in the shaft requires workers to carefully install them, resulting in large workloads and dependent on workers' experience. The frequent transition of shaft lifts increases work difficulty and cost.
A speed-installation module for construction elevators in the shaft is designed. By connecting multiple tracks outside the shaft to form an integral module, it is directly placed into the shaft to install, reducing the installation workload of workers in the shaft and improving the installation accuracy.
Through the design and installation method of the overall module, the installation speed and accuracy are significantly improved, manpower and material investment are reduced, and the quality of installation work and the overall performance of the elevator are improved.
Smart Images

Figure CN223016187U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of rapid installation of construction elevator tracks, in particular to a rapid installation module for construction elevator tracks in a shaft and a construction elevator. Background Technique
[0002] There are two template scaffolds, upper and lower ones, which are welded with 4# angle steel according to the shaft size and the structure of the construction elevator, and then placed at the top and bottom of the shaft respectively, and fixed to the elevator shaft wall by electric welding. The elevator has two main rails and two counterweight rails, and these four rails are installed in sequence according to the setting-out position of the template scaffold. The length of the main rail is 2.5 meters, and 8 M12 bolts and splints are used for connection during connection. The counterweight rail is a 5-meter hollow rail, and 8 M12 bolts and splints are also used for connection. All the existing construction elevator tracks need to be installed by workers in the shaft. Generally, the space in the shaft is very narrow, and the installation is very inconvenient. Especially, there are a large number of bolts during the installation process, and the on-site workload is very large. The car (cage) and the counterweight move up and down along the two main rails and two counterweight rails respectively, and the installation accuracy of the rails is directly related to the operation quality of the elevator.
[0003] The installation and adjustment of the existing rails need to be very careful, the workload of the installation workers is very large, and the quality requirements for the workers are very high. At the same time, the shaft elevator is transferred frequently, which further increases the work difficulty and cost. Content of the Utility Model
[0004] The purpose of the utility model is to provide a rapid installation module for construction elevator tracks in a shaft and a construction elevator, so as to solve the problems raised in the above background technique that the installation and adjustment of the existing rails need to be very careful, the workload of the installation workers is very large, the quality requirements for the workers are very high, and at the same time, the shaft elevator is transferred frequently, which further increases the work difficulty and cost.
[0005] To solve the above technical problems, the utility model is realized through the following technical solutions:
[0006] A rapid installation module for construction elevator tracks in a shaft includes: a main body component and a plurality of rails, and the plurality of rails are arranged on the main body component at intervals, wherein the plurality of rails are arranged parallel to each other.
[0007] Furthermore, the main body component includes an upper beam and a lower beam, the upper beam and the lower beam are arranged at intervals and parallel to each other; wherein, the rails are perpendicular to the upper beam and the lower beam.
[0008] Furthermore, the plurality of rails include a first rail, a second rail and a third rail, the second rail and the third rail are arranged on the same side of the main body component, and / or the first rail is arranged on the side of the main body component opposite to the second rail.
[0009] Further, the main body assembly further includes side beam structures, the extending direction of the side beam structures is perpendicular to the upper beam and the track, and the track is fixed to the upper beam and the lower beam through the side beam structures.
[0010] Further, the multiple tracks include a second track and a third track, and the side beam structures include: two first side beams respectively arranged at two ends of the lower beam, one end of the second track and one end of the third track are respectively connected to the two first side beams and fixed to the lower beam, and / or two second side beams respectively arranged at two ends of the upper beam, the other end of the second track and the other end of the third track are respectively connected to the two second side beams and fixed to the upper beam.
[0011] Further, the multiple tracks further include a first track, the two first side beams and the lower beam enclose a trough-shaped structure, the second track and the third track are arranged inside the trough-shaped structure, and the first track is fixed to the lower beam and located outside the trough-shaped structure; the two second side beams and the upper beam also enclose a trough-shaped structure, the second track and the third track are arranged inside the trough-shaped structure, and the first track is fixed to the upper beam and located outside the trough-shaped structure.
[0012] Further, the main body assembly further includes a middle beam, the upper beam, the middle beam and the lower beam are sequentially arranged at intervals along the extending direction of the track, the side beam structures further include two middle side beams respectively arranged at two ends of the middle beam and respectively connected to the second track and the third track; the main body assembly further includes a support structure which is respectively connected to the upper beam, the middle beam and the lower beam to form an integral structure.
[0013] Further, the multiple tracks include a first track, a second track and a third track, wherein the second track and the third track are respectively located at opposite ends of the main body assembly, and the first track is arranged on one side of the main body assembly close to the second track or close to the third track.
[0014] Further, there are at least 2 tracks, and / or the number of tracks is odd.
[0015] The utility model further provides a construction elevator in a hoistway, which includes a plurality of the above-mentioned track quick-installation modules, and the plurality of track quick-installation modules are sequentially threadedly connected or plugged and connected in the vertical direction. The multiple tracks in the track quick-installation module include a first track, a second track and a third track. The elevator further includes: a counterweight movably arranged between the second track and the third track to move along the extending direction of the track; a car movably arranged on the first track and moving along the extending direction of the track, wherein the counterweight and the car are respectively arranged on two sides of the main body assembly of the track quick-installation module.
[0016] According to another embodiment of the present utility model, a rapid installation module for a construction elevator track in a hoistway is provided, including: a main body assembly, the main body assembly includes a middle side beam, a first side beam, an upper beam, a middle beam, a lower beam, a second side beam, diagonal web members, a first track, a second track, and a third track; the first side beam is arranged directly below the middle side beam, the second side beam is arranged directly above the middle side beam, the upper beam is fixed on one side of the outer surface of the second side beam, the middle beam is fixed on one side of the outer surface of the middle side beam, the lower beam is fixed on one side of the outer surface of the first side beam, the diagonal web members penetrate through the middle of the middle beam, the first track is installed on one side of the outer surface of the upper beam, the second track is fixed on one side of the outer surface of a group of middle side beams, and the third track is fixed on one side of the outer surface of another group of middle side beams.
[0017] Further, there are two middle side beams, which are respectively fixed on both sides of the outer surface of the middle beam, there are two first side beams, which are respectively fixed on both sides of the outer surface of the lower beam, and there are two second side beams, which are respectively fixed on both sides of the outer surface of the upper beam.
[0018] Further, the middle side beam, the first side beam and the second side beam are set as a group, and a total of two groups are set.
[0019] Further, a second guide shoe is fixed on the outer surface of the second track, a second counterweight frame is fixed on the outer surface of the second guide shoe, a first guide shoe is fixed on the outer surface of the third track, a first counterweight frame is connected to the outer surface of the first guide shoe, a counterweight is arranged in the middle of the first counterweight frame and the second counterweight frame, and a car is arranged outside the main body assembly.
[0020] Further, the second track and the third track are counterweight tracks, the first track is the main track, and the three track models are the same.
[0021] Compared with the prior art, the advantages of the present utility model are as follows:
[0022] First, in the present utility model, a plurality of tracks are connected into an integral module by arranging the main body assembly outside the hoistway. During construction, the track rapid installation module is directly placed into the hoistway as a whole, reducing the installation workload of workers in the hoistway. At the same time, the installation accuracy of the integral module is higher, and it no longer overly relies on the on-site construction experience of workers, improving the quality and ensuring safety.
[0023] II. In the present utility model, by providing a middle side beam, a first side beam, an upper beam, a middle beam, a lower beam, a second side beam, diagonal web members, a first guide rail, a second guide rail, a third guide rail, a first guide shoe, a first counterweight frame, a second guide shoe, a second counterweight frame, a counterweight, and a car, two counterweight rails and one main rail are fixed in a steel structure module. The three guide rails in the module are of the same type. The height of the module is 2 meters, the length is 0.82 meters, and the width is 0.22 meters. The above components are assembled and welded into an integral whole on a process jig, having relatively high strength and stiffness. The two modules are connected by 4 M20 high-strength bolts. There are steel structure support rods between the module and the hoistway wall. By increasing or decreasing the number of modules, the purpose of increasing or decreasing the height of the lift in the hoistway is achieved. Since the three guide rails are connected into an integral module, when setting out the line, only a rough measurement of the size of the hoistway is required. Taking any one of the guide rails in the module as a reference to set a plumb line, the relative positions of other components can be determined quickly and very accurately. There is no need to make a line-setting mold. At the same time, after the position of the module is determined, the position and verticality of the other main rail can also be quickly determined. The installation speed is fast. The guide rails no longer need to be transported, transferred, measured, positioned, reinforced, and adjusted one by one. By adopting the design and installation method of the integral module, not only can the installation speed and accuracy be significantly improved, but also the quality of the installation work and the overall performance of the lift can be enhanced while saving manpower and material resources. BRIEF DESCRIPTION OF THE DRAWINGS
[0024] In order to more clearly illustrate the technical solutions of the embodiments of the present utility model, the drawings required for describing the embodiments will be briefly introduced below. Obviously, the drawings in the following description are only some embodiments of the present utility model. For those of ordinary skill in the art, without creative efforts, other drawings can also be obtained based on these drawings.
[0025] Figure 1 Schematic diagram of the main components of the present utility model;
[0026] Figure 2 Second perspective schematic diagram of the main components of the present utility model;
[0027] Figure 3 Third perspective schematic diagram of the main components of the present utility model;
[0028] Figure 4 Structural diagram of the track quick-installation module of the present utility model.
[0029] In the drawings, the list of components represented by each reference numeral is as follows:
[0030] 1. Middle side beam; 2. First side beam; 3. Upper beam; 4. Middle beam; 5. Lower beam; 6. Second side beam; 7. Diagonal web member; 8. First track; 9. Second track; 10. Third track; 11. First guide shoe; 111. First counterweight frame; 12. Second guide shoe; 121. Second counterweight frame; 13. Counterweight; 14. Carriage. Detailed implementation manner
[0031] To make the above objects, features, and advantages of the present utility model more obvious and understandable, the following will describe in detail the specific implementation manners of the present utility model with reference to the accompanying drawings.
[0032] In the following description, many specific details are set forth to fully understand the present utility model. However, the present utility model can also be implemented in other ways different from those described herein. Those skilled in the art can make similar extensions without departing from the connotation of the present utility model. Therefore, the present utility model is not limited by the specific implementation manners disclosed below.
[0033] Secondly, the present utility model will be described in detail with reference to the schematic diagrams. When detailing the implementation manners of the present utility model, for the convenience of explanation, the cross-sectional views showing the device structure will be enlarged locally in a non-general proportion, and the schematic diagrams are only examples and should not limit the protection scope of the present utility model herein. In addition, in actual production, three-dimensional spatial dimensions including length, width, and depth should be included.
[0034] To make the purpose, technical solution, and advantages of the present utility model clearer, the following will further describe in detail the implementation manners of the present utility model with reference to the accompanying drawings.
[0035] Please refer to Figures 1 to 4 As shown, the present utility model provides a track quick-installation module for a construction elevator in a shaft, including: a main body assembly and a plurality of tracks. The plurality of tracks are arranged on the main body assembly at intervals, and among them, the plurality of tracks are arranged parallel to each other. According to one embodiment, there are at least 2 tracks and the number of tracks is odd. Preferably, the number of tracks is 3.
[0036] The present utility model connects a plurality of tracks into an integral module by setting the main body assembly outside the shaft. During construction, the track quick-installation module is directly placed into the shaft as a whole, reducing the installation workload of workers in the shaft. At the same time, the installation accuracy of the integral module is higher, and it no longer overly relies on the on-site construction experience of workers, improving the quality and ensuring safety.
[0037] The main body assembly includes an upper beam 3 and a lower beam 5. The upper beam 3 and the lower beam 5 are arranged at intervals and parallel to each other; among them, the tracks are perpendicular to the upper beam 3 and the lower beam 5. The upper beam and the lower beam are respectively arranged at the upper and lower ends of the tracks and are fixed to each track by bolts.
[0038] Multiple rails include a first rail 8, a second rail 9, and a third rail 10. The second rail 9 and the third rail 10 are arranged on the same side of the main body assembly. At the same time, the first rail 8 is arranged on the side of the main body assembly opposite to the second rail 9. Specifically, the second rail and the third rail are respectively connected to the same side of the upper beam and the lower beam by bolts, and the first rail is connected to the other side of the upper beam and the lower beam, so that the first rail is not in the same plane as the second rail and the third rail. The spacing distance between the plane formed by the first rail and the planes formed by the second rail and the third rail is determined according to the space of the hoistway or the cross-sectional dimensions of the construction elevator. According to a more inferior embodiment, the first rail 8, the second rail 9, and the third rail 10 can also be arranged on the same side of the main body assembly.
[0039] In order to ensure the distance between the first rail and the planes formed by the second rail and the third rail, the main body assembly of the present utility model is further provided with a side beam structure. The extending direction of the side beam structure is perpendicular to the upper beam 3 and the rails, and the rails are fixed on the upper beam 3 and the lower beam 5 through the side beam structure.
[0040] Specifically, multiple rails include a second rail 9 and a third rail 10. The side beam structure includes two first side beams 2 and two second side beams 6. The two first side beams 2 are respectively arranged at both ends of the lower beam 5. One end of the second rail 9 and one end of the third rail 10 are respectively connected to the two first side beams 2 and fixed to the lower beam 5. The two second side beams 6 are respectively arranged at both ends of the upper beam 3. The other end of the second rail 9 and the other end of the third rail 10 are respectively connected to the two second side beams 6 and fixed to the upper beam 3.
[0041] According to an embodiment, multiple rails further include a first rail 8. The two first side beams 2 and the lower beam 5 enclose a trough-shaped structure, which can refer to the shape of channel steel or a groove shape. The second rail 9 and the third rail 10 are arranged inside the trough-shaped structure, that is, in the semi-closed space enclosed by the trough-shaped structure. The first rail 8 is fixed on the lower beam 5 and located outside the trough-shaped structure, that is, on the side opposite to the semi-closed space. Similarly, the two second side beams 6 and the upper beam 3 also enclose a trough-shaped structure. The second rail 9 and the third rail 10 are arranged inside the trough-shaped structure, and the first rail 8 is fixed on the upper beam 3 and located outside the trough-shaped structure.
[0042] The main body assembly further includes a middle beam 4. The upper beam 3, the middle beam 4, and the lower beam 5 are sequentially arranged at intervals along the extending direction of the rails, that is, arranged at equal intervals from top to bottom in the vertical direction.
[0043] The side beam structure further includes two middle side beams 1. The two middle side beams 1 are respectively arranged at both ends of the middle beam 4 and are respectively connected to the second rail 9 and the third rail 10, increasing the strength and stability of the main body assembly.
[0044] In addition, the main body component further includes a support structure which is respectively connected to the upper beam 3, the middle beam 4 and the lower beam 5 to form an integral structure. The support structure includes a plurality of diagonal web members 7, such as Figure 1 or Figure 2 As shown, according to an embodiment, there are 2 diagonal web members arranged between the upper beam and the middle beam in a V shape, and 2 diagonal web members arranged between the middle beam and the lower beam in an inverted V shape. The 2 diagonal web members between the upper beam and the middle beam are symmetrically arranged with the 2 diagonal web members between the middle beam and the lower beam.
[0045] The plurality of tracks include a first track 8, a second track 9 and a third track 10. Among them, the second track 9 and the third track 10 are respectively located at opposite ends of the main body component. The first track 8 is arranged on one side of the main body component close to the second track 9 or close to the third track 10, that is, although the first track is arranged between the second track and the third track, it is not in the middle position (its position is determined by the relative positions of the traction machine overhead beam and the counterweight wheel), or in other words, the first track is not arranged at the middle position of the upper beam or the lower beam. The first track is either closer to the second track or closer to the third track. The second track 9 and the third track 10 are used to install the counterweight, and the first track is used to install the car.
[0046] According to the second embodiment of the present invention, there is also provided a construction elevator in a hoistway, which includes a plurality of the above-mentioned track quick-installation modules. The plurality of track quick-installation modules are sequentially threadedly connected or plug-connected in the vertical direction. The threaded connection can be achieved by screws or bolts. The plug connection includes connections through inserted pins, etc. The plurality of tracks in the track quick-installation module include a first track 8, a second track 9 and a third track 10. The elevator further includes: a fourth track, a counterweight 13 and a car 14. The fourth track is symmetrically arranged with the first track (8). Specifically, the fourth track can be selectively connected to the upper beam, the middle beam and the lower beam. The fourth track and the first track are located on the same side of the main body component. The counterweight and the car are respectively arranged on both sides of the main body component. The counterweight 13 is movably arranged between the second track 9 and the third track 10 to move along the extending direction of the track; the car 14 is movably arranged between the first track 8 and the fourth track and moves along the extending direction of the track.
[0047] Specifically, a second guide shoe 12 is fixed to the outer surface of the second track 9, and a second counterweight frame 121 is fixed to the outer surface of the second guide shoe 12. A first guide shoe 11 is fixed to the outer surface of the third track 10, and a first counterweight frame 111 is connected to the outer surface of the first guide shoe 11. A counterweight 13 is arranged in the middle of the first counterweight frame 111 and the second counterweight frame 121, and a car 14 is arranged outside the main body assembly. The second guide shoe 12 fixed to the outer surface of the second track 9 and the first guide shoe 11 fixed to the outer surface of the third track 10 are respectively connected to the second counterweight frame 121 and the first counterweight frame 111. This configuration ensures the stability of the counterweight system during the lifting process of the elevator, thereby improving energy efficiency and reducing energy consumption.
[0048] This embodiment is a track quick-installation module for a construction hoist in a hoistway, including:
[0049] A main body assembly, which includes a middle side beam 1, a first side beam track 2, an upper beam 3, a middle beam 4, a lower beam 5, and a second side beam 6;
[0050] The first side beam 2 is arranged directly below the middle side beam 1, the second side beam 6 is arranged directly above the middle side beam 1, the upper beam 3 is fixed to one side of the outer surface of the second side beam 6, the middle beam 4 is fixed to one side of the outer surface of the middle side beam 1, and the lower beam 5 is fixed to one side of the outer surface of the first side beam 2;
[0051] The upper beam 3 is fixed to the outer side surface of the second side beam 6, and the middle beam 4 and the lower beam 5 respectively extend outward and are fixed on the outer side surface of the first side beam 2. This layout enhances the lateral stability of the entire guide rail system and provides a solid foundation for the installation of the guide rails;
[0052] A diagonal web member 7 passes through the middle of the middle beam 4, a first track 8 is fixedly installed on one side of the outer surface of the upper beam 3, a second track 9 is fixed to one side of the outer surface of a group of middle side beams 1, and a third track 10 is fixed to one side of the outer surface of another group of middle side beams 1;
[0053] A diagonal web member 7 passes through the middle of the middle beam 4. This design is to increase the mechanical stability of the entire structure and prevent deformation caused by load changes;
[0054] Working principle:
[0055] The three guide rails, namely the first track 8, the second track 9, and the third track 10, are processed to the same length on a special machine tool and then connected to other components on a process jig to form a cuboid module. Among them, the second track 9 and the third track 10 are counterweight rails, and the first track 8 is the main track for the car 14 to run. The relative positions of the three tracks are fixed and the models are the same. Once the position of any one of them is determined, the positions of the other two can be determined.
[0056] The above three tracks are connected into an integral module through the main body component. Therefore, during wire laying, it is only necessary to roughly measure the size of the hoistway, hang a plumb line with any one of the tracks in the module as a reference, and the relative positions of other components can be determined quickly and very accurately without making a wire laying module.
[0057] Meanwhile, after the position of the module is determined, the position and verticality of the other main track can also be determined quickly. The installation speed is fast, and there is no need to transport, transfer, measure, position, reinforce, and adjust the tracks one by one.
[0058] By adopting the design and installation method of the integral module for this step, it can not only significantly improve the installation speed and accuracy, but also save manpower and material resources while improving the quality of the installation work and the overall performance of the elevator.
[0059] In the description of the present utility model, it should also be noted that unless otherwise clearly specified and defined, the terms "set", "install", "connect", and "couple" should be understood in a broad sense. For example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be directly connected or indirectly connected through an intermediate medium, and it can be the communication inside two components. For those of ordinary skill in the art, the specific meanings of the above terms in the present utility model can be understood according to specific situations.
[0060] Finally, it should be noted that the above are only the preferred embodiments of the present utility model and are not used to limit the present utility model. Although the present utility model has been described in detail with reference to the foregoing embodiments, for those skilled in the art, they can still modify the technical solutions described in the foregoing embodiments, or perform equivalent replacements for some of the technical features. Any modifications, equivalent replacements, improvements, etc. made within the spirit and principle of the present utility model shall be included in the protection scope of the present utility model.
Claims
1. A rail quick-installation module for a construction elevator in a hoistway, characterized in that: include: Main body components; A plurality of rails are arranged on the main body component at intervals, wherein the plurality of rails are arranged parallel to each other.
2. A rail quick-installation module for hoistway construction according to claim 1, characterized in that: The main body assembly comprises an upper beam (3) and a lower beam (5), wherein the upper beam (3) and the lower beam (5) are arranged at intervals and are parallel to each other; Wherein, the track is perpendicular to the upper beam (3) and the lower beam (5).
3. A rail quick-installation module for a hoistway construction machine according to claim 2, characterized in that: The plurality of rails include a first rail (8), a second rail (9) and a third rail (10), The second rail (9) and the third rail (10) are arranged on the same side of the main body component, and / or the first rail (8) is arranged on a side of the main body component opposite to the second rail (9).
4. The rail quick-installation module for hoistway construction according to claim 2, characterized in that: The main body component also includes a side beam structure, the extension direction of the side beam structure is perpendicular to the upper beam (3) and the track, and the track is fixed to the upper beam (3) and the lower beam (5) through the side beam structure.
5. The rail quick-installation module for hoistway construction according to claim 4 is characterized in that: The plurality of rails include a second rail (9) and a third rail (10), and the side beam structure includes: two first side beams (2), the two first side beams (2) being respectively arranged at two ends of the lower beam (5), one end of the second track (9) and one end of the third track (10) being respectively connected to the two first side beams (2) and fixed to the lower beam (5), and / or Two second side beams (6), the two second side beams (6) are respectively arranged at two ends of the upper beam (3), and the other end of the second track (9) and the other end of the third track (10) are respectively connected to the two second side beams (6) and fixed to the upper beam (3).
6. A rail quick-installation module for hoistway construction according to claim 5, characterized in that: The plurality of rails also include a first rail (8), The two first side beams (2) and the lower beam (5) form a trough-shaped structure, the second track (9) and the third track (10) are arranged on the inner side of the trough-shaped structure, and the first track (8) is fixed on the lower beam (5) and is located on the outer side of the trough-shaped structure; The two second side beams (6) and the upper beam (3) also form a trough-shaped structure, the second track (9) and the third track (10) are arranged on the inner side of the trough-shaped structure, and the first track (8) is fixed on the upper beam (3) and is located on the outer side of the trough-shaped structure.
7. The rail quick-installation module for hoistway construction according to claim 5, characterized in that: The main body assembly further comprises a middle beam (4), the upper beam (3), the middle beam (4) and the lower beam (5) being arranged in sequence and spaced apart along the extension direction of the track. The side beam structure further comprises two middle side beams (1), the two middle side beams (1) being respectively arranged at two ends of the middle beam (4) and respectively connected to the second rail (9) and the third rail (10); The main body component also includes a supporting structure, wherein the supporting structure is respectively connected to the upper beam (3), the middle beam (4) and the lower beam (5) to form an integral structure.
8. The rail quick-installation module for hoistway construction according to claim 2, characterized in that: The plurality of rails include a first rail (8), a second rail (9) and a third rail (10), The second rail (9) and the third rail (10) are respectively located at two opposite ends of the main body component, and the first rail (8) is arranged on a side of the main body component close to the second rail (9) or close to the third rail (10).
9. The rail quick-installation module for hoistway construction according to claim 1, characterized in that: The number of the rails is at least 2, and / or the number of the rails is an odd number.
10. A hoist for construction in a hoistway, characterized in that: The elevator comprises a plurality of track quick-assembly modules according to any one of claims 1 to 9, wherein the plurality of track quick-assembly modules are sequentially threaded or plug-connected in a vertical direction, wherein the plurality of rails in the track quick-assembly modules comprise a first rail (8), a second rail (9) and a third rail (10), and the elevator further comprises: a fourth track, the fourth track being arranged symmetrically with the first track (8); a counterweight (13), the counterweight (13) being movably arranged between the second rail (9) and the third rail (10) so as to move along an extension direction of the rails; A car (14), the car (14) being movably arranged between the first rail (8) and the fourth rail and moving along the extension direction of the rail; The counterweight (13) and the car (14) are respectively arranged on both sides of the main body component of the track quick assembly module.