Construction device for through arch bridge
By designing a device for the construction of lower bearing arch bridges, the efficient construction and dismantling of the bridges is achieved by using the cooperation of door machines and hanging beams, solving the problems of high cost and low efficiency of traditional construction methods, saving materials and manpower, and improving construction efficiency.
Patent Information
- Application Number
- CN202422252001.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-13
- Publication Date
- 2025-06-27
- Estimated Expiration
- 2034-09-13
AI Technical Summary
The traditional lower bearing arch bridge construction method is costly and has low construction efficiency. The lifting process of middle beams and arch rib brackets is time-consuming and labor-intensive, and a lot of manpower and material resources are wasted.
A device for the construction of lower bearing arch bridges is designed, including two rows of side beam frames and two rows of bottom beam frames. Through the cooperation of door machines and hanging beams, the erection and disassembly of side beam frames and bottom beam frames, and the lifting and flip of middle beams and arch rib brackets are avoided, thus avoiding the erection and disassembly of steel trestles.
It realizes efficient construction and dismantling of bridges, saves materials and manpower, reduces construction costs, improves construction efficiency, and avoids waste of steel trestles and complex construction processes.
Smart Images

Figure CN223033859U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the field of arch bridge construction, in particular to a construction device for a through arch bridge. Background Art
[0002] Arch bridges are one of the most widely used bridge structures. When constructing an arch bridge and installing the middle cross beam and arch rib support, a steel trestle is mostly built on one side of the bridge, and then a floating crane, crawler crane or truck crane is used to hoist the middle cross beam or arch rib support. The traditional construction method is to build a steel trestle and then the crane goes onto the steel trestle for construction. The width of the steel trestle must meet the requirements of the crane, wasting a large amount of materials. This construction method has a high cost and low construction efficiency. A floating crane usually requires a ship and is usually used for water construction, relying on buoyancy to support the equipment, with low construction efficiency and high construction cost. Crawler cranes and truck cranes are restricted under poor ground conditions and may not be applicable in all construction environments. At the same time, the temporary steel trestle built after the traditional through arch bridge construction is relatively difficult to disassemble, time-consuming and laborious. It is also relatively difficult to hoist the middle cross beam and arch rib support during the hoisting process, wasting a lot of manpower and material resources. For this reason, we propose a construction device for a through arch bridge to solve the above problems. Content of the Utility Model
[0003] The utility model provides a construction device for a through arch bridge, which solves the problems that when using a floating crane, crawler crane or truck crane to hoist the middle cross beam or arch rib support to build an arch bridge, it is necessary to build and disassemble a steel trestle, with a high construction cost, low construction efficiency, and time-consuming and laborious during the hoisting process of the middle cross beam and arch rib support.
[0004] To solve the above technical problems, the technical solution adopted by the utility model is: a construction device for a through arch bridge, including two rows of side beam frames and two rows of bottom beam frames. The side beam frames are located outside the bottom beam frames. A connecting beam system is provided between the side beam frames and the bottom beam frames. Two moving gantry cranes are provided on the side beam frames. A traveling lifting beam is provided on the gantry cranes. A plurality of sliding lifting blocks are provided on the lifting beam;
[0005] Both sides of the bottom beam frames are used to install the middle cross beam and arch rib support;
[0006] On one side of the end side beam frame, a transport vehicle is provided, and the transport vehicle is used to transport the middle cross beam, arch rib support, side beam frame and bottom beam frame;
[0007] Tracks are provided on the top of the side beam frames, and electrical systems are provided at the bottoms on both sides of the gantry cranes.
[0008] In a preferred solution, the two ends of the gantry crane abut against the tracks and slide, a horizontally moving crane is provided on the gantry crane, and side hoisting winches are provided on both sides of the gantry crane.
[0009] In the preferred solution, a pile cap, a main cross beam, a main longitudinal beam, and a distribution beam are successively arranged on the top of the side beam frame and the bottom beam frame. The track is arranged on the distribution beam of the side beam frame. The bottom beam frame includes a plurality of second pile foundations. Top lifting lugs, a plurality of side lifting lugs, and a plurality of bottom lifting lugs are arranged on the bottom beam frame. A wire pulley is arranged on one side of the distribution beam at the top of the side beam frame.
[0010] In the preferred solution, the lifting beam includes main beams on both sides. The main beams are connected to the crane. A plurality of sliding lifting blocks are arranged on the main beams. Electric hoists are arranged at the bottoms of the lifting blocks. Positioning grooves are arranged on the main beams. A lead screw is arranged between the two main beams, and a motor is arranged at the end of the lead screw.
[0011] In the preferred solution, a hydraulic cylinder is arranged on the lifting block. A bearing bush is arranged at the top of the hydraulic cylinder. The bearing bush is connected to the lead screw. Telescopic second hydraulic cylinders are arranged on both sides of the lifting block. The second hydraulic cylinders abut against the positioning grooves on the main beam.
[0012] In the preferred solution, the connecting beam system includes a plurality of hoops installed on the first pile foundation and a plurality of ring frames installed on the second pile foundation. Connecting tie rods are arranged between the hoops and the ring frames at the horizontal position. A rotating device is arranged on the hoops at the horizontal position.
[0013] In the preferred solution, the rotating device includes a turntable rotatably connected to the hoop. A plurality of grooves are arranged on the hoop. Supports are arranged on both sides of the turntable. A rotating locking rod is arranged on the support. A locking block is arranged at one end of the locking rod. A hinged cylinder is arranged at the other end of the locking rod. The cylinder is installed on the hoop.
[0014] In the preferred solution, a connecting column is arranged on the ring frame. The connecting tie rod includes a first connecting rod and a second connecting rod. A bidirectional screw is arranged between the first connecting rod and the second connecting rod. The first connecting rod is connected to the turntable. A plurality of rotatably connected clamps are arranged at one end of the second connecting rod. The clamps are clamped on the connecting column. Both ends of the connecting column are connected to the ring frame through nuts.
[0015] The beneficial effects of the present utility model are as follows: Through the cooperation of the gantry crane and the lifting beam, the side beam frame and the bottom beam frame are successively erected to form a support platform from both ends of the river. The side beam frame and the bottom beam frame are connected by a connecting beam system. Similarly, the middle cross beam is hoisted from both ends of the river to the center by the gantry crane to build the bridge deck on the support platform. After the bridge deck is built, the arch rib support is hoisted through the cooperation of the gantry crane and the lifting beam until the entire bridge is built. Then, in the reverse order, through the cooperation of the gantry crane and the lifting beam, the side beam frame, the bottom beam frame, and the arch rib support are successively disassembled and hoisted from the middle to both ends of the river. The whole device does not require a steel trestle during the process of building the arch bridge, and at the same time, it does not require floating cranes, crawler cranes, or truck cranes to complete the hoisting. The gantry crane and the lifting beam can complete the whole process from installation and construction to disassembly, with high use efficiency, greatly reducing the construction cost, avoiding the process of temporarily building and disassembling the steel trestle, saving time and effort, and greatly saving materials.
[0016] The side hoists on both sides of the gantry crane and the crane and lifting beam at the top cooperate with each other, enabling the lifting of the bottom beam support installed at the bottom of the bridge to the top of the bridge. Then, through coordinated operation, the bottom beam support can be flipped, turning the vertically placed bottom beam support to a horizontal state. Subsequently, it is moved to the transport vehicle by the gantry crane, completing the process of lifting the bottom beam support installed at the bottom of the bridge to the top of the bridge, avoiding the complex construction of using a floating crane with a floating ship to lift the bottom beam support, and greatly saving costs. Similarly, the gantry crane and the lifting beam cooperate with each other, enabling the in-air flipping of the side beam support and the arch rib support, lifting the vertically placed lifted object to a horizontal state, greatly facilitating the lifting process, and enabling the direct lifting and unloading of the lifted object from the transport vehicle, avoiding the process of using other equipment for flipping operations in the middle and accelerating the construction efficiency.
[0017] The overall device has high safety, replacing the traditional process that requires a crane on a steel trestle; it is highly efficient in construction. Since the gantry crane and the lifting beam have a flipping function, the transport vehicle directly transports the relevant structure to the bottom on one side of the bridge, and the gantry crane can directly lift and install the relevant structure from the bottom of the bridge; it has good economic benefits, saves materials, and is fast and efficient in construction. At the same time, it avoids the phenomenon of wasting materials in the traditional construction method of building a steel trestle.
[0018] The connection beam system can be connected and disassembled quickly. By rotating the bidirectional screw, the connecting tie rod can be telescopically tightened, and the hoop can be quickly installed and removed on the side beam support. The fixture at the end of the connecting tie rod can be quickly installed and removed on the bottom beam support. The connecting tie rod can adapt to different distances between the side beam support and the bottom beam support. At the same time, when the bottom beam support and the side beam support are being installed, due to inevitable factors such as the river or the uneven bottom of the riverbed causing deflection and inclination, the rotating device on the hoop can rotate and lock, enabling the connection beam system to connect two relatively inclined supports, so that the side beam support, the bottom beam support, and the connection beam system are connected into a whole, making the overall structure stable, capable of withstanding the impact of the river water, facilitating the installation and construction of the bridge deck, and having great popularization value. Description of the Drawings
[0019] The following further describes the present utility model in conjunction with the drawings and embodiments;
[0020] Figure 1 is the front view of the overall structure of the present utility model;
[0021] Figure 2 is the front view of the partial structure of the present utility model;
[0022] Figure 3 is the side view of the middle beam during the lifting of the overall structure of the present utility model;
[0023] Figure 4 is the side view of the arch rib support during the lifting of the overall structure of the present utility model;
[0024] Figure 5 It is a side view of the hoisting bottom beam frame of the overall structure of the utility model;
[0025] Figure 6 It is a front view of the hoisting beam turning bottom beam frame of the utility model;
[0026] Figure 7 It is a front view of the hoisting middle cross beam of the utility model;
[0027] Figure 8 It is a side view of the hoisting beam of the utility model;
[0028] Figure 9 It is a front view of the partial structure of the utility model;
[0029] Figure 10 It is a top view of the partial structure of the utility model;
[0030] Figure 11 It is the utility model Figure 10 An enlarged view of A;
[0031] Figure 12 It is an axonometric view of the hoop of the utility model;
[0032] Figure 13 It is the utility model Figure 12 An enlarged view of B;
[0033] Figure 14 It is an axonometric view of the hoop of the utility model from another perspective;
[0034] Figure 15 It is an axonometric view of the ring frame of the utility model;
[0035] Figure 16 It is an axonometric view of the second connecting rod and the fixture of the utility model;
[0036] In the figure: gantry crane 1; crane 101; side winch 102; track 2; electrical system 3; side beam frame 4; first pile foundation 401; bottom beam frame 5; second pile foundation 501; bottom lifting lug 502; top lifting lug 503; side lifting lug 504; connecting beam system 6; hoop 601; ring frame 602; connecting column 6021; connecting tie rod 603; first connecting rod 6031; bidirectional screw 6032; second connecting rod 6033; rotating device 604; turntable 6041; support 6042; locking rod 6043; locking block 6044; cylinder 6045; fixture 605; hoisting beam 7; sliding lifting block 701; lead screw 702; hydraulic cylinder 703; bearing bush 704; main beam 705; motor 706; roller 707; second hydraulic cylinder 708; middle cross beam 8; arch rib support 9; transport vehicle 10; wire pulley 11. Specific implementation manners
[0037] Example 1:
[0038] As Figure 1-16 shown in the figure, the construction device for a through arch bridge includes two rows of side beam frames 4 and two rows of bottom beam frames 5. The side beam frames 4 are located outside the bottom beam frames 5. A connecting beam system 6 is provided between the side beam frames 4 and the bottom beam frames 5. Two moving gantry cranes 1 are provided on the side beam frames 4. A traveling hanging beam 7 is provided on the gantry crane 1. A plurality of sliding hanging blocks 701 are provided on the hanging beam 7;
[0039] The two side bottom beam frames 5 are used to install the middle cross beam 8 and the arch rib support 9;
[0040] A transport vehicle 10 is provided on one side of the end side beam frame 4. The transport vehicle 10 is used to transport the middle cross beam 8, the arch rib support 9, the side beam frame 4 and the bottom beam frame 5;
[0041] Tracks 2 are provided on the top of the side beam frame 4. Electrical systems 3 are provided at the bottom of both sides of the gantry crane 1. With this structure, through the cooperation of the gantry crane 1 and the hanging beam 7, the side beam frame 4 and the bottom beam frame 5 are sequentially erected on the support platforms from both ends of the river. They are connected by the connecting beam system 6 between the side beam frame 4 and the bottom beam frame 5. Similarly, the middle cross beam 8 is hoisted from both ends of the river to the center by the gantry crane 1 to build the bridge deck on the support platform. After the bridge deck is built, the arch rib support 9 is hoisted by the cooperation of the gantry crane 1 and the hanging beam 7 until the entire bridge is built. Then, in the reverse order, through the cooperation of the gantry crane 1 and the hanging beam 7, the side beam frame 4, the bottom beam frame 5 and the arch rib support 9 are sequentially disassembled and hoisted from the middle to both ends of the river. The overall device does not require a steel trestle during the process of building the arch bridge, and at the same time, it does not require floating cranes, crawler cranes or truck cranes to complete the hoisting. The gantry crane 1 and the hanging beam 7 can complete the whole process from installation and construction to disassembly, with high use efficiency, greatly reducing the construction cost, avoiding the process of temporarily building and disassembling the steel trestle, saving time and effort, and greatly saving materials.
[0042] The side winches 102 on both sides of the gantry crane 1, the crane 101 on the top and the hanging beam 7 cooperate with each other, and can hoist the bottom beam frame 5 installed at the bottom of the bridge to the top of the bridge. Then, through the coordinated operation, the bottom beam frame 5 can be flipped, and the vertically placed bottom beam frame 5 can be flipped to the horizontal state. Then, it is moved to the transport vehicle 10 by the gantry crane 1, realizing the process of hoisting the bottom beam frame 5 installed at the bottom of the bridge to the top of the bridge, avoiding the complex construction of hoisting the bottom beam frame 5 using a floating ship with a floating crane, and greatly saving the cost. Similarly, the gantry crane 1 and the hanging beam 7 cooperate with each other, and can flip the side beam frame 4 and the arch rib support 9 in the air, and can hoist the vertically placed hoisted object to the horizontal state, greatly facilitating the hoisting process, and can directly lift and unload the hoisted object from the transport vehicle 10, avoiding the process of using other equipment for flipping operations in the middle, and accelerating the construction efficiency.
[0043] The overall device has high safety, replacing the traditional process that requires a crane to access the steel trestle; it is highly efficient in construction. Since the gantry crane 1 and the hanging beam 7 have a flipping function, the transport vehicle 10 can directly transport the relevant structures to the bottom of one side of the bridge, and the gantry crane 1 can directly hoist and install the relevant structures from the bottom of the bridge; it has good economic benefits, saves materials, and is fast and efficient in construction. At the same time, it avoids the phenomenon of wasting materials in the traditional construction method of building a steel trestle.
[0044] The connection beam system 6 can be connected and disassembled quickly. By rotating the bidirectional screw 6032, the connecting tie rod 603 can be telescopically tightened. The hoop 601 can be quickly installed and removed on the side beam frame 4. The clamp 605 at the end of the connecting tie rod 603 can be quickly installed and removed on the bottom beam frame 5. The connecting tie rod 603 can adapt to different distances between the side beam frame 4 and the bottom beam frame 5. At the same time, when the bottom beam frame 5 and the side beam frame 4 are being installed, and inevitably deflect and tilt due to factors such as the river or the uneven bottom of the riverbed, the rotating device 604 on the hoop 601 can rotate and lock, so that the connection beam system 6 can connect two relatively inclined supports, so that the side beam frame 4, the bottom beam frame 5 and the connection beam system 6 are connected into a whole, so that the overall structure is stable and can withstand the impact of the river water, facilitating the installation and construction of the bridge deck.
[0045] In the preferred solution, both ends of the gantry crane 1 rest on the track 2 and slide. A horizontally moving crane 101 is provided on the gantry crane 1, and side winches 102 are provided on both sides of the gantry crane 1. With this structure, through the cooperation of the gantry crane 1 and the hanging beam 7, support platforms are erected from both ends of the river for the side beam frame 4 and the bottom beam frame 5 in sequence, and they are connected by the connection beam system 6 between the side beam frame 4 and the bottom beam frame 5. Similarly, the middle cross beam 8 is hoisted from both ends of the river to the center by the gantry crane 1 to build the bridge deck on the support platform. After the bridge deck is built, the arch rib support 9 is hoisted through the cooperation of the gantry crane 1 and the hanging beam 7 until the entire bridge is completed.
[0046] The steel cables of the two side winches 102 rest on the wire wheels 11. One end of the steel cables of the two side winches 102 is respectively connected to the side lifting lugs 504 of the bottom beam frame 5. One of the sliding lifting blocks 701 of the hanging beam 7 is connected to the top lifting lug 503 of the bottom beam frame 5. One side winch 102 extends and the other side winch 102 contracts to achieve the horizontal movement of the bottom beam frame 5.
[0047] In a preferred embodiment, a pile cap, a main cross beam, a main longitudinal beam, and a distribution beam are sequentially provided on the top of the side beam frame 4 and the bottom beam frame 5. The track 2 is arranged on the distribution beam of the side beam frame 4. The bottom beam frame 5 includes a plurality of second pile foundations 501. A top lifting lug 503, a plurality of side lifting lugs 504, and a plurality of bottom lifting lugs 502 are provided on the bottom beam frame 5. A wire wheel 11 is provided on one side of the distribution beam at the top of the side beam frame 4. With this structure, when the bottom beam frame 5 moves horizontally: the steel cables of the two side winches 102 abut against the wire wheel 11. One end of the steel cables of the two side winches 102 is respectively connected to the side lifting lugs 504 of the bottom beam frame 5. One of the sliding lifting blocks 701 of the lifting beam 7 is connected to the top lifting lug 503 of the bottom beam frame 5. One side winch 102 extends, and the other side winch 102 contracts to achieve the horizontal movement of the bottom beam frame 5.
[0048] When the bottom beam frame 5 is flipped in the air, the connection between the side lifting lug 504 and the side winch 102 is disconnected. The other sliding lifting block 701 of the lifting beam 7 is connected to the bottom lifting lug 502. At the same time, when the electric hoist at the bottom of the sliding lifting block 701 is retracted, the position of the sliding lifting block 701 connected to the bottom lifting lug 502 is moved, and the electric hoist on the bottom lifting lug 502 is tightened to flip the bottom beam frame 5 in the air. Similarly, bottom lifting lugs, top lifting lugs, and side lifting lugs in the same positions as those of the bottom beam frame 5 are provided on both the side beam frame 4 and the arch rib support 9. The flipping processes of the side beam frame 4 and the arch rib support 9 are the same as that of the bottom beam frame 5.
[0049] In a preferred embodiment, the lifting beam 7 includes main beams 705 on both sides. The main beams 705 are connected to the crane 101. A plurality of sliding lifting blocks 701 are provided on the main beams 705. An electric hoist is provided at the bottom of the sliding lifting block 701. A positioning groove is provided on the main beams 705. A lead screw 702 is provided between the two main beams 705. A motor 706 is provided at the end of the lead screw 702. With this structure, the second hydraulic cylinders 708 on both sides of the sliding lifting block 701 are retracted, the motor 706 is driven to rotate the lead screw 702, and the hydraulic cylinder 703 is driven to make the bearing bush 704 abut against the lead screw 702 to move the sliding lifting block 701. When the movement is in place, the bearing bush 704 is disconnected, and the second hydraulic cylinder 708 is extended to position the sliding lifting block 701. The lifting beam 7 can adjust the positions of a plurality of sliding lifting blocks 701 so that when different sliding lifting blocks 701 are connected to the suspended object, the suspended object can be flipped.
[0050] In a preferred embodiment, a hydraulic cylinder 703 is provided on the sliding lifting block 701. A bearing bush 704 is provided at the top of the hydraulic cylinder 703. The bearing bush 704 is connected to the lead screw 702. Telescopic second hydraulic cylinders 708 are provided on both sides of the sliding lifting block 701. The second hydraulic cylinders 708 abut against the positioning grooves on the main beams 705. With this structure, rollers 707 are provided at the bottoms of both ends of the sliding lifting block 701. The rollers 707 abut against the main beams 705 and slide.
[0051] In a preferred embodiment, the connecting beam system 6 includes a plurality of hoop fasteners 601 mounted on the first pile foundation 401 and a plurality of ring frames 602 mounted on the second pile foundation 501. A connecting tie rod 603 is provided between the hoop fasteners 601 and the ring frames 602 at the horizontal position, and a rotating device 604 is provided on the hoop fasteners 601 at the horizontal position. With this structure, the connecting beam system 6 can be connected and disassembled quickly. By rotating the double-headed screw 6032, the connecting tie rod 603 can be telescopically tightened. The hoop fastener 601 can be quickly installed and removed on the side beam frame 4. The clamp 605 at the end of the connecting tie rod 603 can be quickly installed and removed on the bottom beam frame 5. The connecting tie rod 603 can adapt to different distances between the side beam frame 4 and the bottom beam frame 5. At the same time, when the bottom beam frame 5 and the side beam frame 4 are being installed, and inevitably deflect and tilt due to factors such as rivers or uneven riverbeds, the rotating device 604 on the hoop fastener 601 can rotate and lock, so that the connecting beam system 6 can connect two relatively inclined brackets, so that the side beam frame 4, the bottom beam frame 5 and the connecting beam system 6 are connected into a whole, so that the overall structure is stable, can withstand the impact of river water, and is convenient for installing and constructing the bridge deck.
[0052] In a preferred embodiment, the rotating device 604 includes a turntable 6041 rotatably connected to the hoop fastener 601. A plurality of grooves are provided on the hoop fastener 601. Support seats 6042 are provided on both sides of the turntable 6041. A rotatable locking rod 6043 is provided on the support seats 6042. A locking block 6044 is provided at one end of the locking rod 6043, and a hinged cylinder 6045 is provided at the other end of the locking rod 6043. The cylinder 6045 is installed on the hoop fastener 601. With this structure, when the side beam frame 4 and the bottom beam frame 5 are relatively inclined, the cylinder 6045 is driven so that the end of the locking rod 6043 is away from the turntable 6041, and the connecting tie rod 603 is rotated so that the axis line of the clamp 605 is flush with the axis line of the ring frame 602. Stop rotating, drive the cylinder 6045 so that the locking block 6044 is stuck in the groove of the turntable 6041, so that the rotating device 604 is locked.
[0053] In a preferred embodiment, a connecting column 6021 is provided on the ring frame 602. The connecting tie rod 603 includes a first connecting rod 6031 and a second connecting rod 6033. A double-headed screw 6032 is provided between the first connecting rod 6031 and the second connecting rod 6033. The first connecting rod 6031 is connected to the turntable 6041. A plurality of rotatably connected clamps 605 are provided at one end of the second connecting rod 6033. The clamps 605 are clamped on the connecting column 6021. Both ends of the connecting column 6021 are connected to the ring frame 602 through nuts. With this structure, the clamp 605 includes a second hoop fastener. A locking nut and a locking handle are provided on the second hoop fastener. A gasket is provided between the second hoop fastener and the locking handle. The second hoop fastener is rotatably connected to the second connecting rod 6033.
[0054] Embodiment 2: Further explanation in combination with Embodiment 1:
[0055] A construction method for a construction device of a through arch bridge, characterized in that side beam frames 4 and bottom beam frames 5 are erected from both ends of the river, and other structures except the middle cross beam and the arch rib are erected at the ends. A gantry crane 1 is installed on the track 2;
[0056] The side beam frames 4 and the bottom beam frames 5 are hoisted at both ends of the two gantry cranes 1: When hoisting the side beam frames 4 and the bottom beam frames 5, the side beam frames 4 and the bottom beam frames 5 are turned and installed in the air by using the lifting beam 7 and the gantry crane 1;
[0057] The side beam frames 4 and the bottom beam frames 5 are installed at the bottom of the riverbed, and a connecting beam system 6 is installed between the side beam frames 4 and the bottom beam frames 5;
[0058] Repeat steps S2 to S3 in sequence, and the two gantry cranes 1 complete the erection of the bottom support from both ends to the middle;
[0059] The two gantry cranes 1 hoist multiple middle cross beams 8 from both ends to the middle in sequence and install them on the top of the bottom beam frame 5 to construct the bridge deck;
[0060] The gantry crane 1 hoists the arch rib supports 9 from both ends to the middle in sequence: The arch rib supports 9 are hoisted from the transport vehicle 10 and turned in the air by using the lifting beam 7;
[0061] The arch rib segments are installed on the arch rib supports 9 through the gantry crane 1, and the arch rib segments are grouted;
[0062] The two gantry cranes 1 are used to hoist and disassemble from the middle to both ends in sequence: The connecting beam system 6 is disassembled, and the side beam frames 4, the bottom beam frames 5, the middle cross beams 8 and the arch rib supports 9 are all hoisted and transported to the transport vehicle 10 through the gantry crane 1;
[0063] The side beam frames 4, the bottom beam frames 5 and the arch rib supports 9 are all turned in the air by using the gantry crane 1 and the lifting beam 7, and are turned from the vertical position to the horizontal position.
[0064] The above embodiments are only the preferred technical solutions of the present invention and should not be regarded as limitations on the present invention. The protection scope of the present invention should be the technical solutions recorded in the claims, including equivalent replacement solutions of the technical features in the technical solutions recorded in the claims. That is, equivalent replacement improvements within this scope are also within the protection scope of the present invention.
Claims
1. A construction device for a through-type arch bridge, characterized by: The invention comprises two rows of side beam frames (4) and two rows of bottom beam frames (5), the side beam frames (4) are located outside the bottom beam frames (5), a connecting beam system (6) is provided between the side beam frames (4) and the bottom beam frames (5), two movable gantry cranes (1) are provided on the side beam frames (4), a walking hanging beam (7) is provided on the gantry crane (1), and a plurality of sliding sliding blocks (701) are provided on the hanging beam (7); The bottom beam frames (5) on both sides are used to install the middle cross beam (8) and the arch rib bracket (9); A transport vehicle (10) is provided on one side of the side beam frame (4) at the end, and the transport vehicle (10) is used to transport the middle cross beam (8), the arch rib bracket (9), the side beam frame (4) and the bottom beam frame (5); A track (2) is provided on the top of the side beam frame (4), and an electrical system (3) is provided on the bottom of both sides of the door machine (1).
2. The construction device for a through arch bridge according to claim 1 is characterized in that: Both ends of the gantry machine (1) slide against the rails (2), a horizontally movable crane (101) is provided on the gantry machine (1), and side winches (102) are provided on both sides of the gantry machine (1).
3. The construction device for a through arch bridge according to claim 1 is characterized in that: The tops of the side beam frame (4) and the bottom beam frame (5) are provided with pile caps, main cross beams, main longitudinal beams and distribution beams in sequence, the track (2) is arranged on the distribution beam of the side beam frame (4), the bottom beam frame (5) includes a plurality of second pile foundations (501), the bottom beam frame (5) is provided with a top lifting lug (503), a plurality of side lifting lugs (504) and a plurality of bottom lifting lugs (502), and a guide wheel (11) is provided on one side of the distribution beam at the top of the side beam frame (4).
4. The construction device for a through arch bridge according to claim 1 is characterized in that: The hanging beam (7) comprises main beams (705) on both sides, the main beams (705) are connected to the crane (101), a plurality of sliding lifting blocks (701) are provided on the main beams (705), an electric hoist is provided at the bottom of the sliding lifting blocks (701), a positioning groove is provided on the main beam (705), a screw rod (702) is provided between the two main beams (705), and a motor (706) is provided at the end of the screw rod (702).
5. The construction device for a through arch bridge according to claim 1 is characterized in that: A hydraulic cylinder (703) is provided on the sliding block (701), a bearing bush (704) is provided on the top of the hydraulic cylinder (703), the bearing bush (704) is connected to the screw rod (702), and telescopic second hydraulic cylinders (708) are provided on both sides of the sliding block (701), and the second hydraulic cylinders (708) are against the positioning groove of the main beam (705).
6. The construction device for a through arch bridge according to claim 1 is characterized in that: The connecting beam system (6) comprises a plurality of hoops (601) installed on the first pile foundation (401) and a plurality of ring frames (602) installed on the second pile foundation (501), a connecting tie rod (603) is provided between the hoops (601) in a horizontal position and the ring frames (602), and a rotating device (604) is provided on the hoops (601) in a horizontal position.
7. The construction device for a through arch bridge according to claim 1 is characterized in that: The rotating device (604) comprises a rotating disk (6041) rotatably connected to the clamp (601); the clamp (601) is provided with a plurality of grooves; supports (6042) are provided on both sides of the rotating disk (6041); a rotating locking rod (6043) is provided on the supports (6042); a locking block (6044) is provided at one end of the locking rod (6043); a hinged cylinder (6045) is provided at the other end of the locking rod (6043); and the cylinder (6045) is mounted on the clamp (601).
8. The construction device for a through arch bridge according to claim 1 is characterized in that: A connecting column (6021) is provided on the ring frame (602), and the connecting tie rod (603) comprises a first connecting rod (6031) and a second connecting rod (6033). A bidirectional screw rod (6032) is provided between the first connecting rod (6031) and the second connecting rod (6033). The first connecting rod (6031) is connected to a rotating disk (6041). One end of the second connecting rod (6033) is provided with a plurality of rotatably linked clamps (605), and the clamps (605) are clamped on the connecting column (6021). Both ends of the connecting column (6021) are connected to the ring frame (602) via nuts.