Prefabricated wallboard component

By integrating prefabricated production of prefabricated wall panel components for lightweight wall panels and concrete frames in the factory, the problems of low integration and low construction efficiency of existing lightweight wall panels are solved, and efficient wall panel installation and material utilization are achieved.

CN223048250UActive Publication Date: 2025-07-01安徽海龙建筑工业有限公司 +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202422118845.2
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-08-30
Publication Date
2025-07-01
Estimated Expiration
2034-08-30

AI Technical Summary

Technical Problem

Existing lightweight wall panels have low integration in non-load-bearing wall applications and require multiple assembly and cutting, resulting in low construction efficiency and waste of materials.

Method used

Prefabricated wall panel components, including lightweight wall panels and a concrete frame surrounding them, are adopted to improve the integrity and integration of wall panels through integrated prefabricated production in the factory, and to embed wire boxes and wire pipes on the wall panels to reduce the process of installing equipment pipelines on site.

Benefits of technology

It realizes efficient prefabrication and rapid installation of wall panels, reduces the number of on-site assembly and adjustment, improves construction efficiency, and reduces material waste and construction difficulty.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN223048250U_ABST
    Figure CN223048250U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of fabricated buildings, in particular to a prefabricated wallboard component which comprises a light wallboard and a concrete frame which surrounds the light wallboard, is attached to the edge of the light wallboard and is connected with the light wallboard. The light wallboard is formed by splicing at least two light battens; the concrete frame comprises two constructional columns located on the left side and the right side of the light wallboard and two ring beams located on the upper side and the lower side of the light wallboard, and the light wallboard is connected with the constructional columns through first connecting pieces and connected with the ring beams through second connecting pieces; a mounting groove is formed in the side surface of the concrete frame and is used for placing a connecting component for connecting the prefabricated wallboard component with a building main body structure. The concrete frame and the batten are integrally prefabricated in a factory, so that the wallboard component is better in integrality, one wall body only needs to be mounted once, the problems that an existing light batten needs to be spliced for multiple times, and the mounting efficiency is low are solved, and construction procedures are reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of prefabricated buildings, in particular to a precast wall panel component. Background Art

[0002] A prefabricated building refers to a concrete structure building that is prefabricated in a factory and then assembled and connected at the construction site.

[0003] At present, light panels are generally used as materials for non-load-bearing walls in prefabricated buildings, which play a role in enclosing and separating spaces. Light panels are usually standard-width boards (the width generally does not exceed 600 mm), and have advantages such as good sound insulation, strong fire resistance, and low cost.

[0004] However, in the application of existing light panels in non-load-bearing walls, there are disadvantages such as small plate width dimensions requiring multiple assemblies, low wall panel integration, and the need for on-site chiseling, which affect the on-site construction progress and reduce work efficiency. Specifically, due to the small width of existing light panels, on-site construction usually requires assembling multiple light panels, and the levelness and verticality need to be adjusted repeatedly during the assembly process, affecting the on-site construction progress; since light panels are standard-width boards, in order to meet the width dimensions of non-load-bearing walls, when installing the last board, it is usually necessary to cut the light panel, resulting in waste; at the same time, the integration of light panels is relatively low, and on-site chiseling of installation equipment pipelines is required at the construction site, increasing construction procedures, generating construction waste, and it is difficult to control the on-site chiseling quality.

[0005] Building by using precast wall panels for assembly can effectively reduce on-site wet operations, save on-site labor requirements, and at the same time, prefabricating and producing in the factory in advance can shorten the construction period of the building. Therefore, there is an urgent need for a precast wall panel component to solve the problems of low integration of existing light wall panels, multiple on-site assemblies and cuts required for continuous installation of light wall panels, and cumbersome procedures for installing equipment pipelines. Summary of the Utility Model

[0006] (I) Technical Problems to be Solved

[0007] In view of the above-mentioned shortcomings and deficiencies of the prior art, the utility model provides a precast wall panel component, which solves the technical problems of low integration of existing light wall panels, multiple on-site assemblies and cuts required for continuous installation of light wall panels, and cumbersome procedures for installing equipment pipelines.

[0008] (II) Technical Solutions

[0009] In order to achieve the above object, the main technical solutions adopted by the utility model include:

[0010] A precast wall panel component, comprising a lightweight wall panel, and a concrete frame surrounding the lightweight wall panel and connected to the edge of the lightweight wall panel in a fitting manner;

[0011] The lightweight wall panel is formed by splicing at least two lightweight strip panels;

[0012] The concrete frame includes two construction columns located on the left and right sides of the lightweight wall panel, and two ring beams located on the upper and lower sides of the lightweight wall panel. The lightweight wall panel is connected to the construction columns through a first connecting member, and the lightweight wall panel is connected to the ring beams through a second connecting member;

[0013] An installation groove is provided on the side surface of the concrete frame, and the installation groove is used for placing a connecting member for connecting the precast wall panel component to the building main structure.

[0014] The first connecting member is a first connecting steel bar embedded in the lightweight wall panel. A construction column steel reinforcement cage is provided inside the construction column, and the first connecting steel bar is fixedly connected to the construction column steel reinforcement cage;

[0015] The second connecting member is a second connecting steel bar embedded in the lightweight wall panel. A ring beam steel reinforcement cage is provided inside the ring beam, and the second connecting steel bar is fixedly connected to the ring beam steel reinforcement cage.

[0016] The first connecting steel bar is tied or welded to the construction column steel reinforcement cage, and the second connecting steel bar is tied or welded to the ring beam steel reinforcement cage.

[0017] In the lightweight wall panel, the joint between two adjacent lightweight strip panels is sealed and connected by mortar.

[0018] A wire box groove and a wire pipe groove communicating with the wire box groove are provided on the surface of the precast wall panel component. A pre-embedded wire box is installed in the wire box groove, a pre-embedded wire pipe is installed in the wire pipe groove, and the pre-embedded wire box is connected to the pre-embedded wire pipe.

[0019] The wire box groove is provided on the lightweight wall panel. The wire pipe groove includes a main groove section and a connecting groove section. The main groove section is provided on the concrete frame, the first end of the connecting groove section communicates with the wire box groove, and the second end of the connecting groove section communicates with the main groove section.

[0020] The pre-embedded wire pipe has a wiring end extending out of the precast wall panel component, and a wire pipe connecting comb joint is provided at the wiring end.

[0021] The two ring beams are respectively a lower ring beam located below the lightweight wall panel and an upper ring beam located above the lightweight wall panel. A lifting hook for lifting the precast wall panel component is provided at the top of the upper ring beam.

[0022] The lightweight wall panel is formed by sequentially splicing an integer number of lightweight strip panels with the same size in the left-right direction.

[0023] (III) Beneficial effects

[0024] The beneficial effects of the present utility model are as follows: The present utility model provides a precast wall panel component, in which the concrete frame and the lightweight slab are integrally precast in the factory. The wall panel component has better integrity and a larger width dimension, enabling a wall to be installed only once, overcoming the problem of low installation efficiency caused by multiple assemblies and repeated adjustments of the horizontal and vertical levels during on-site installation of existing lightweight slabs, and reducing the construction procedures. At the same time, the number of lightweight slabs and the width of the construction columns can be adjusted according to design requirements, avoiding material waste caused by cutting.

[0025] By providing embedded wire boxes and embedded conduits on the slab, the integration degree of the wall is improved, and no manual chiseling is required during on-site installation, with high construction and installation efficiency and reliable quality.

[0026] Since the main material of the wall panel component is the lightweight slab, the weight of the wall panel component is less than that of ordinary concrete wall panel components and conventional lightweight concrete wall panel components of the same size, reducing the construction hoisting and installation difficulties. BRIEF DESCRIPTION OF THE DRAWINGS

[0027] Figure 1 It is the first structural schematic diagram of the precast wall panel component of the present utility model;

[0028] Figure 2 It is the second structural schematic diagram of the precast wall panel component of the present utility model;

[0029] Figure 3 It is the partial structural connection schematic diagram of the lightweight slab and the concrete structure of the present utility model;

[0030] Figure 4 It is the structural connection schematic diagram of the precast wall panel component of the present utility model and the building main structure.

[0031]

DESCRIPTION OF THE REFERENCE NUMERALS

[0032] 1: Construction column;

[0033] 2: Ring beam;

[0034] 3: Lightweight slab;

[0035] 4: Hoisting hook;

[0036] 5: Embedded wire box;

[0037] 6: Embedded conduit;

[0038] 7: Conduit connection comb joint;

[0039] 8: First connecting steel bar;

[0040] 9: Drilling hole;

[0041] 10: Second connecting steel bar;

[0042] 11: Main structure floor slab;

[0043] 12: Bolt;

[0044] 13: Nut;

[0045] 14: Connecting member;

[0046] 15: Bedding mortar;

[0047] 16: Installation groove. Detailed implementation manner

[0048] For better explaining the present utility model for easy understanding, the present utility model will be described in detail below in conjunction with the attached drawings through specific implementation manners. Among them, the orientation nouns such as "upper", "lower", etc. mentioned in this article are based on Figure 1 the orientation of

[0049] For better understanding the above technical solution, the exemplary embodiments of the present utility model will be described in more detail below with reference to the attached drawings. Although the exemplary embodiments of the present utility model are shown in the drawings, it should be understood that the present utility model can be implemented in various forms and should not be limited by the embodiments described herein. On the contrary, these embodiments are provided to enable a clearer and more thorough understanding of the present utility model and to be able to convey the scope of the present utility model completely to those skilled in the art.

[0050] The present utility model provides a precast wall panel member, including a lightweight wall panel, and a concrete frame that surrounds the lightweight wall panel and is connected to the lightweight wall panel by fitting to the edge of the lightweight wall panel. The lightweight wall panel is formed by splicing at least two lightweight strips 3 of the same size in the left - right direction in sequence. The concrete frame and the lightweight strip 3 are integrally manufactured in the factory. A lifting hook 4 for hoisting is provided at the top of the concrete frame. Embedded wire boxes 5 and embedded wire pipes 6 connected to the embedded wire boxes 5 are provided on the lightweight strip 3. Through the wall panel member precast integrally with the lightweight strip 3 and the concrete frame, the wall panel member has good integrity and a relatively large width dimension, and it can realize that only one installation is required for one wall, solving the problems of complex processes and low construction efficiency caused by the relatively small width of the existing lightweight strip 3, multiple assemblies and repeated adjustments during installation.

[0051] The concrete frame includes two construction columns 1 located on the left and right sides of the lightweight wall panel, and two ring beams 2 located on the upper and lower sides of the lightweight wall panel. The lightweight wall panel is connected to the construction column 1 through a first connecting member, and the lightweight wall panel is connected to the ring beam 2 through a second connecting member. The two ring beams 2 are respectively a lower ring beam located below the lightweight wall panel and an upper ring beam located above the lightweight wall panel. A lifting hook 4 for hoisting the precast wall panel member is provided at the top of the upper ring beam.

[0052] The upper and lower sides of the concrete frame are provided with installation grooves 16, and the installation grooves 16 are used to place the connecting members 14 that connect the precast wall panel components to the main building structure, so as to keep the wall surface flat. The connecting member 14 has a bend, and the bend is arranged at a right angle, that is, the connecting member 14 has a first end arranged along the vertical direction and a second end arranged along the horizontal direction, and the first end is perpendicular to the second end.

[0053] In this embodiment, the connecting member 1 is made of a connecting steel plate, and the size of the connecting steel plate is matched with the installation groove 16.

[0054] The first connecting member is the first connecting steel bar 8 embedded in the lightweight wall panel. The construction column 1 has a construction column steel reinforcement cage inside, and the first connecting steel bar 8 is fixedly connected to the construction column steel reinforcement cage. The second connecting member is the second connecting steel bar 10 embedded in the lightweight wall panel. The ring beam 2 has a ring beam steel reinforcement cage inside, and the second connecting steel bar 10 is fixedly connected to the ring beam steel reinforcement cage. The first connecting steel bar 8 is tied or welded to the construction column steel reinforcement cage, and the second connecting steel bar 10 is tied or welded to the ring beam steel reinforcement cage.

[0055] Conventional non-integrated prefabricated and post-installed lightweight wall panels usually use pipe clamps and U-shaped card connectors to connect the lightweight slats 3 to the construction column 1 or the ring beam 2. This application can also use pipe clamps and U-shaped card connectors for connection.

[0056] The end of the lightweight slat 3 connected to the concrete frame is provided with a drilling hole 9, and the drilling hole 9 is used to insert the first connecting steel bar 8 and the second connecting steel bar 10. After the connecting steel bars are placed in the drilling hole 9, the drilling hole 9 is filled with grouting material to fix the connecting steel bars in the drilling hole 9.

[0057] The joints between two adjacent lightweight slats 3 are sealed and connected by mortar. Multiple lightweight slats 3 are continuously fixed on the concrete frame to form precast wall panel components. The number of lightweight slats 3 is selected according to the wall design requirements. At the same time, the width of the construction column 1 can also be adjusted according to the wall size requirements. By integrally prefabricating the concrete frame and the lightweight slats 3 in the factory, the problems of low installation efficiency caused by multiple assemblies and repeated adjustments of the horizontal and vertical degrees during the on-site installation of the existing lightweight slats 3 are overcome. At the same time, the number of lightweight slats 3 and the width of the construction column 1 can be adjusted according to the design requirements, avoiding waste of plates caused by cutting.

[0058] The surface of the lightweight panel 3 is provided with a wire box groove and a wire pipe groove communicating with the wire box groove. The embedded wire box 5 is installed in the wire box groove, and the embedded wire pipe 6 is installed in the wire pipe groove. The embedded wire box 5 is connected to the embedded wire pipe 6. The wire box groove is opened on the lightweight wall panel. The wire pipe groove includes a main groove section and a connecting groove section. The main groove section is opened on the concrete frame, and the first end of the connecting groove section communicates with the wire box groove, and the second end of the connecting groove section communicates with the main groove section. The embedded wire pipe 6 extends from the lightweight panel 3 to the concrete frame along the position of the wire pipe groove, facilitating the subsequent installation of equipment pipelines. The embedded wire pipe 6 has a wiring end extending out of the precast wall panel member, and a wire pipe connecting comb joint 7 is arranged at the wiring end. By arranging the embedded wire box 5 and the embedded wire pipe 6 on the lightweight panel 3, the integration degree of the wall is improved, and the problem of chiseling on-site for installing equipment pipelines is avoided.

[0059] The present utility model further includes a preparation method for precast wall panel members, comprising the following steps:

[0060] Step 1: Design and manufacture a wall panel mold according to the size of the non-load-bearing wall panel, and determine the number of lightweight panels 3.

[0061] Since each lightweight panel 3 adopts a standard width size, the width of the construction column 1 outside the lightweight panel 3 can be adjusted to ensure that the number of lightweight panels 3 is an integer, without the need to cut the lightweight panels 3.

[0062] Step 2: Set reserved drill holes 9 on the upper and lower sides of the lightweight panel 3 and on the side in contact with the construction column 1. After placing the connecting steel bars 8 in the drill holes 9, fill the drill holes 9 with grouting material.

[0063] Step 3: Groove the lightweight panel 3 according to the design requirements for setting equipment pipelines.

[0064] Step 4: Assemble the processed lightweight panels 3 on the mold table, and seal the joints between the lightweight panels 3 with special mortar.

[0065] Step 5: After the lightweight panels 3 are assembled, start hoisting and placing the steel reinforcement cage, and bind and connect the connecting steel bars of the lightweight panels 3 with the steel reinforcement cage.

[0066] Among them, the steel reinforcement cage includes a construction column steel reinforcement cage and a ring beam steel reinforcement cage. The connecting steel bars of the lightweight panel 3 include a first connecting steel bar 8 and a second connecting steel bar 10 embedded in the lightweight panel 3. The first connecting steel bar 8 is fixedly connected to the construction column steel reinforcement cage, and the second connecting steel bar 10 is fixedly connected to the ring beam steel reinforcement cage.

[0067] Step 6: Arrange the embedded wire box 5 and the embedded wire pipe 6 at the preset positions of the lightweight panel 3 and the concrete frame according to the design requirements, and embed bolts 12 on the upper and lower sides and the left and right sides of the precast wall panel member.

[0068] Step 7: Pour the concrete frame around the lightweight slab 3. After pouring, cover it with a film for curing.

[0069] Among them, the concrete frame includes two construction columns 1 on the left and right sides of the lightweight slab 3, and two ring beams 2 on the upper and lower sides of the lightweight slab 3. When the width dimension of the required wall panel component is large, multiple construction columns 1 can be set.

[0070] Step 8: After curing, start demolding. Transfer the demolded precast wall panel component to the designated location for storage.

[0071] The present utility model also includes a construction method for precast wall panel components, which includes the following steps:

[0072] Step 1: Prepare precast wall panel components and construction and installation tools.

[0073] Before construction, prepare the precast wall panel components to be installed and the supporting installation tools and materials, including crowbars, wooden wedges, and fixing steel clips.

[0074] Step 2: Clean the construction working surface of the main structure floor 11 and determine the installation positioning line of the precast wall panel component.

[0075] Step 3: Lift and transfer the precast wall panel component to the installation position, hoist it to 600 mm above the working layer. The installer uses two towing ropes to hold the slab and slowly lower the precast wall panel component.

[0076] Step 4: Manually straighten the precast wall panel component, place it in place according to the preset installation positioning line, and install diagonal braces for temporary fixation to adjust the verticality of the wall panel.

[0077] Step 5: After the precast wall panel component is installed in place, fix and connect the lower part of the precast wall panel component to the main structure floor 11 through the reserved bolts 12, nuts 13, and connecting steel plates.

[0078] Among them, a bedding mortar 15 is filled between the bottom surface of the precast wall panel component and the main structure floor 11. The bedding mortar 15 is used to fill the gap between the precast wall panel component and the main structure floor 11.

[0079] Step 6: After the concrete of the vertical and horizontal components of the current layer of the main structure is poured and cured and the formwork is removed, fix and connect the upper part, left and right sides of the precast wall panel component to the concrete components of the building main structure through the reserved bolts 12, nuts 13, and connecting steel plates.

[0080] The precast wall panel component provided by the utility model prefabricates the concrete frame and the lightweight panel 3 integrally in the factory, overcoming the problem that the existing lightweight panel 3 needs to be assembled multiple times on site and the levelness and perpendicularity need to be adjusted repeatedly, resulting in low installation efficiency, and reducing the construction procedures. At the same time, the number of lightweight panels 3 and the width of the construction column 1 can be adjusted according to the design requirements, avoiding material waste caused by cutting.

[0081] By providing a buried wire box 5 and a buried wire pipe 6 on the lightweight panel 3, the integration degree of the wall is improved, and manual chiseling is no longer required during on-site installation, with high construction and installation efficiency and reliable quality.

[0082] Installation grooves 16 are provided at the upper and lower parts of the precast wall panel component for placing the connecting component 14 that connects the precast wall panel component to the building main structure, and can keep the wall surface flat after the precast wall panel component is connected to the building main structure. Connecting bolts 12 are buried at the lower part of the precast wall panel component, which is convenient for subsequent fixed connection with the connecting component 14.

[0083] The wall panel component prefabricated integrally by the lightweight panel 3 and the concrete frame has better integrity and a larger width dimension, and can realize that only one installation is required for one wall surface, solving the problems of complex procedures and low construction efficiency caused by the small width of the existing lightweight panel 3 and the need for multiple assemblies and repeated adjustments during installation.

[0084] Since the main material of the wall panel component is the lightweight panel 3, the weight of the wall panel component is less than that of the ordinary concrete wall panel component and the conventional lightweight concrete wall panel component of the same size, reducing the construction hoisting and installation difficulty.

[0085] The construction method of the precast wall panel component provided by the utility model hoists the integrally precast wall panel component to the installation position, and only needs to fix the end of the precast wall panel component to the building main structure to complete the installation of the precast wall panel component. The installation process is fast and convenient, improving the construction efficiency and saving labor costs.

[0086] In the description of the present utility model, it should be understood that the terms "first" and "second" are only used for descriptive purposes and cannot be understood as indicating or implying relative importance or implicitly indicating the quantity of the indicated technical features. Thus, the features defined with "first" and "second" may explicitly or implicitly include one or more of such features. In the description of the present utility model, "a plurality" means two or more, unless otherwise specifically defined.

[0087] In the present utility model, unless otherwise clearly defined and limited, terms such as "installation", "connection", "attachment", "fixation", etc. shall be understood in a broad sense. For example, it can be a fixed connection, a detachable connection, or an integral one; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium; it can be the communication inside two elements or the interaction relationship between two elements. For those of ordinary skill in the art, the specific meanings of the above terms in the present utility model can be understood according to specific circumstances.

[0088] In the present utility model, unless otherwise clearly defined and limited, when the first feature is "on" or "under" the second feature, it can be that the first and second features are in direct contact, or the first and second features are in indirect contact through an intermediate medium. Moreover, when the first feature is "above", "over" and "on top of" the second feature, it can be that the first feature is directly above or obliquely above the second feature, or merely indicates that the horizontal height of the first feature is higher than that of the second feature. When the first feature is "under", "beneath" and "underneath" the second feature, it can be that the first feature is directly below or obliquely below the second feature, or merely indicates that the horizontal height of the first feature is lower than that of the second feature.

[0089] In the description of this specification, the description of terms such as "one embodiment", "some embodiments", "embodiment", "example", "specific example" or "some examples", etc. means that the specific features, structures, materials or characteristics described in connection with the embodiment or example are included in at least one embodiment or example of the present utility model. In this specification, the schematic descriptions of the above terms do not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described can be combined in a suitable manner in any one or more embodiments or examples. In addition, without contradiction, those skilled in the art can combine and combine the different embodiments or examples described in this specification and the features of different embodiments or examples.

[0090] Although the embodiments of the present utility model have been shown and described above, it can be understood that the above embodiments are exemplary and should not be construed as limiting the present utility model. Those of ordinary skill in the art can make changes, modifications, substitutions and variations to the above embodiments within the scope of the present utility model.

Claims

1. A prefabricated wall panel component, characterized in that: It includes a lightweight wall panel, and a concrete frame surrounding the lightweight wall panel and fitting the edges of the lightweight wall panel and connected to the lightweight wall panel; The lightweight wall panel is formed by splicing at least two lightweight strips (3); The concrete frame comprises two structural columns (1) located on the left and right sides of the lightweight wall panel, and two ring beams (2) located on the upper and lower sides of the lightweight wall panel, the lightweight wall panel is connected to the structural columns (1) via a first connecting member, and the lightweight wall panel is connected to the ring beam (2) via a second connecting member; A mounting groove (16) is provided on the side of the concrete frame, and the mounting groove (16) is used to place a connecting component (14) connecting the prefabricated wall panel component and the main structure of the building.

2. The prefabricated wall panel component according to claim 1, characterized in that: The first connecting member is a first connecting steel bar (8) pre-buried in the lightweight wall panel, a structural column steel bar cage is provided inside the structural column (1), and the first connecting steel bar (8) is fixedly connected to the structural column steel bar cage; The second connecting member is a second connecting steel bar (10) pre-buried in the lightweight wall panel, a ring beam steel bar cage is provided inside the ring beam (2), and the second connecting steel bar (10) is fixedly connected to the ring beam steel bar cage.

3. The prefabricated wall panel component according to claim 2, characterized in that: The first connecting steel bar (8) is connected to or welded to the structural column steel cage by binding, and the second connecting steel bar (10) is connected to or welded to the ring beam steel cage by binding.

4. The prefabricated wall panel component according to claim 1, characterized in that: In the lightweight wallboard, the joints between two adjacent lightweight strip boards (3) are sealed and connected by mortar.

5. The prefabricated wall panel component according to claim 1, characterized in that: A wire box groove and a wire tube groove communicating with the wire box groove are provided on the surface of the prefabricated wall panel component; a pre-buried wire box (5) is installed in the wire box groove; a pre-buried wire tube (6) is installed in the wire tube groove; and the pre-buried wire box (5) is connected to the pre-buried wire tube (6).

6. The prefabricated wall panel component according to claim 5, characterized in that: The wire box slot is opened on the lightweight wall panel, and the wire tube slot includes a main slot section and a connecting slot section. The main slot section is opened on the concrete frame, the first end of the connecting slot section is connected to the wire box slot, and the second end of the connecting slot section is connected to the main slot section.

7. The prefabricated wall panel component according to claim 5, characterized in that: The pre-buried wire tube (6) has a wiring terminal extending out of the prefabricated wall panel component, and the wiring terminal is provided with a wire tube connecting comb section (7).

8. The prefabricated wall panel component according to claim 1, characterized in that: The two ring beams (2) are respectively a lower ring beam located below the lightweight wall panel and an upper ring beam located above the lightweight wall panel, and a hook (4) for hoisting the prefabricated wall panel component is provided on the top of the upper ring beam.

9. The prefabricated wall panel component according to claim 1, characterized in that: The lightweight wall panel is formed by splicing an integer number of lightweight strips (3) with the same size in sequence along the left-right direction.