Power construction platform for cement pole
A modular electric power construction platform for cement poles addresses the challenge of bulkiness and weight by using detachable components for easy transport and stable assembly, enhancing usability and safety.
Patent Information
- Application Number
- CN202422252669.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-14
- Publication Date
- 2025-07-15
- Estimated Expiration
- 2034-09-14
AI Technical Summary
The existing power construction platform is large in size and heavy in weight, so it is not easy to get on and off the vehicle during outdoor power construction.
A power construction platform for cement poles is designed, including a workbench, a support arm and an electric reverse chain. The support arm is removably fixed to the cement pole. The electric reverse chain is used for lifting and lowering of the workbench and further fixed by a clasp and a connecting seat.
It realizes lightweight and separate portability of the equipment, which is easy to carry to the maintenance site, is fast to install, and ensures the stability and safety of the workbench during operation.
Smart Images

Figure CN223104097U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the field of electric power construction, and particularly relates to an electric power construction platform for cement poles. Background Technique
[0002] Cement poles are important components of electric power facilities, mainly used for fixing electric wires, installing insulators, connecting cables, etc. During the electric power construction process, by climbing the poles, electric power construction workers can check the status of these devices to ensure their stability and safety.
[0003] For example, Chinese Patent CN116654841B discloses an electric power construction operation platform, including an electric power construction platform. An auxiliary frame is arranged inside the top of the electric power construction platform. Limit lock plates are arranged on both the upper and lower sides of the middle part of the electric power construction platform. An anti-slip frame is arranged at the bottom of the electric power construction platform; the electric power construction platform is used to assist workers in working at heights.
[0004] Since the electric power construction operation platform is large in volume and heavy in weight, it is not easy to get on and off the vehicle for carrying during outdoor electric power construction.
[0005] Therefore, we propose an electric power construction platform for cement poles to solve the above problems. Content of the Utility Model
[0006] Aiming at the problem that the electric power construction operation platform is large in volume and heavy in weight, and it is not easy to get on and off the vehicle for carrying during outdoor electric power construction, the utility model provides an electric power construction platform for cement poles.
[0007] The solution adopted by the utility model to solve its technical problems is: an electric power construction platform for cement poles, including a workbench, a support arm, and at least one electric chain hoist. One end of the support arm is detachably and fixedly connected to the cement pole through a middle hoop;
[0008] The electric chain hoist is detachably installed on the support arm;
[0009] The workbench is located below the electric chain hoist, and a guardrail is installed on its top. The guardrail is connected to the rope of the electric chain hoist;
[0010] A connecting seat is installed on one side of the workbench. At least one lower hoop is installed on the side of the connecting seat close to the cement pole. The lower hoop is detachably installed on the cement pole and is used to fix the workbench after reaching the predetermined height.
[0011] Preferably, the number of the electric chain hoists is two, and the number of the lower hoops is two.
[0012] Preferably, two hanging rings are installed at the bottom of the support arm, and the hooks of the electric chain hoists are hung in the hanging rings.
[0013] Preferably, a plurality of rib plates are installed between the connecting seat and the workbench.
[0014] Preferably, it further includes an upper hoop and a pulling rope. The upper hoop is detachably installed on the cement pole and is located above the middle hoop. An upper fixing ring is installed on the side of the upper hoop, a lower fixing ring is installed on the top of the support arm, and the pulling rope is installed between the upper fixing ring and the lower fixing ring.
[0015] Compared with the prior art, the beneficial effects of the present utility model are as follows:
[0016] 1. The overall weight of the support arm and the workbench of the present utility model is relatively light, and they can be carried separately, reducing the volume and weight of the overall equipment, facilitating the maintenance personnel to carry it to the maintenance site, and the support arm and the workbench can be installed one by one, with convenient and fast installation, saving time and effort.
[0017] 2. The present utility model fixes the middle hoop at a suitable height on the cement pole, and then supports and fixes the support arm. By controlling the two electric chain hoists to wind the ropes, the workbench moves smoothly upward along the cement pole. After the workbench rises to a suitable height, it is connected to the cement pole through the lower hoop to further fix the workbench to ensure the stability and safety of the workbench during operation.
[0018] 3. By setting the upper hoop and the pulling rope to pull the support arm, the present utility model can effectively increase the structural stability, prevent the support arm from bending or breaking due to external forces, and improve the bearing capacity of the support arm. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] Figure 1 It is a front view structural schematic diagram of the present utility model;
[0020] Figure 2 It is a top view sectional structural schematic diagram of the lifting platform of the present utility model.
[0021] In the figure: 11 workbench, 12 lower hoop, 13 connecting seat, 14 rib plate, 2 guardrail, 3 electric chain hoist, 41 middle hoop, 42 support arm, 43 hanging ring, 51 upper hoop, 52 upper fixing ring, 53 pulling rope, 54 lower fixing ring. DETAILED DESCRIPTION OF THE EMBODIMENTS
[0022] The present utility model will be further described below with reference to the drawings and embodiments.
[0023] Please refer to Figure 1-2 , the present utility model provides a technical solution for a power construction platform for cement poles:
[0024] Embodiment 1:
[0025] According toFigure 1 and Figure 2 As shown in Figure 2 , it includes a workbench 11, a support arm 42, and at least one electric chain hoist 3. One end of the support arm 42 is detachably and fixedly connected to a cement pole through a middle hoop 41, and two hanging rings 43 are installed at the bottom of the support arm 42.
[0026] In this embodiment, there are two electric chain hoists 3. The hooks of the electric chain hoists 3 are hung in the hanging rings 43, so that the electric chain hoists 3 are easy to separate from the hanging rings 43 for disassembly, so as to facilitate the separate carrying of the electric chain hoists 3 and the support arm 42.
[0027] The workbench 11 is located below the electric chain hoists 3, and a guardrail 2 is installed on its top. The guardrail 2 is connected to the ropes of the electric chain hoists 3. By controlling the ropes of the two electric chain hoists 3 to be retracted and released, the workbench 11 moves smoothly up and down along the cement pole.
[0028] A connecting seat 13 is installed on one side of the workbench 11. At least one lower hoop 12 is installed on the side of the connecting seat 13 close to the cement pole. In this embodiment, the number of the lower hoops 12 is two. The lower hoops 12 are detachably installed on the cement pole. After the workbench 11 rises to a suitable height, it is connected to the cement pole through the lower hoops 12 to further fix the workbench 11 to ensure the stability and safety of the workbench 11 during operation.
[0029] The overall weight of the support arm 42 and the workbench 11 of the present utility model is relatively light, and they can be carried separately, reducing the volume and weight of the overall equipment, facilitating the maintenance personnel to carry them to the maintenance site, and the support arm 42 and the workbench 11 can be installed one by one, with convenient, fast, time-saving and labor-saving installation.
[0030] When in specific use, a power construction platform for a cement pole of the present utility model, first, the worker carries the support arm 42 to climb the cement pole. After climbing to a suitable height, the middle hoop 41 is fixed at a suitable height on the cement pole to support and fix the support arm 42. Then, the hooks of the two electric chain hoists 3 are respectively hung in the hanging rings 43, and the ground staff connects the ropes of the electric chain hoists 3 to the guardrail 2. Then, control the two electric chain hoists 3 to wind up the ropes, so that the workbench 11 moves smoothly upward along the cement pole. Finally, after the workbench 11 rises to a suitable height, it is connected to the cement pole through the lower hoops 12 to further fix the workbench 11.
[0031] Embodiment Two:
[0032] On the basis of Embodiment One, as Figure 1 and Figure 2 shown, multiple rib plates 14 are installed between the connecting seat 13 and the workbench 11 to increase the connection strength between the connecting seat 13 and the workbench 11 and improve the stability.
[0033] Embodiment 3:
[0034] Based on Embodiment 1, as Figure 1 shown, it further includes an upper hoop 51 and a pulling rope 53. The upper hoop 51 is detachably installed on the cement pole and is located above the middle hoop 41. An upper fixing ring 52 is installed on the side of the upper hoop 51, and a lower fixing ring 54 is installed at the top of the support arm 42. The pulling rope 53 is installed between the upper fixing ring 52 and the lower fixing ring 54. By setting the upper hoop 51 and the pulling rope 53 to pull the support arm 42, the stability of the structure can be effectively increased, preventing the support arm 42 from bending or breaking due to external forces and improving the load-bearing capacity of the support arm 42.
Claims
1. An electric power construction platform for cement poles, characterized in that: It includes a workbench, a support arm and at least one electric chain hoist. One end of the support arm is detachably and fixedly connected to a cement pole through a middle hoop. The electric chain hoist is detachably installed on the support arm. The workbench is located below the electric chain hoist, and a guardrail is installed on its top. The guardrail is connected to the rope of the electric chain hoist. A connecting seat is installed on one side of the workbench. At least one lower hoop is installed on the side of the connecting seat close to the cement pole. The lower hoop is detachably installed on the cement pole and is used to fix the workbench after it reaches the predetermined height.
2. The electric power construction platform for cement poles according to claim 1, wherein: The number of the electric chain hoists is two, and the number of the lower hoops is two.
3. The electric power construction platform for cement poles according to claim 2, wherein: Two hanging rings are installed at the bottom of the support arm, and the hooks of the electric chain hoist are hung in the hanging rings.
4. The electric power construction platform for cement utility poles according to claim 1, wherein: Multiple rib plates are installed between the connecting seat and the workbench.
5. The electric power construction platform for cement poles according to claim 1, characterized in that: It also includes an upper hoop and a pulling rope. The upper hoop is detachably installed on the cement pole and is located above the middle hoop. An upper fixing ring is installed on the side of the upper hoop, and a lower fixing ring is installed at the top of the support arm. The pulling rope is installed between the upper fixing ring and the lower fixing ring.
Citation Information
Patent Citations
A power construction operation platform
CN116654841B