Water interception protection structure of rock slope

By setting up fixed bases, water interception walls and passive net protection structures on steep rocky slopes, combined with mortar anchors and anchor rods to fix them, the problem of high construction difficulty is solved, and simplified construction and effective protection effects are achieved.

CN223119198UActive Publication Date: 2025-07-18POWERCHINA HUADONG ENG CORP LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202422216556.6
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-09-10
Publication Date
2025-07-18
Estimated Expiration
2034-09-10

AI Technical Summary

Technical Problem

The construction of sluice ditches and passive protective nets on steep rocky slopes is difficult, it is difficult to dig troughs on site, and the construction takes a long time.

Method used

The fixed base, water intercept wall and passive protective mesh structure are adopted, combined with mortar anchors and anchor rods to fix it, and the natural steep rocky slope is used to reduce the excavation amount, and a protective mesh is formed with support columns and rope mesh. The anchor rods are fixed on the slope.

Benefits of technology

It reduces the construction difficulty and excavation volume, simplifies the construction process, effectively guides falling rocks and slags, and improves construction efficiency and safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN223119198U_ABST
    Figure CN223119198U_ABST
Patent Text Reader

Abstract

The utility model provides a rock slope water interception protection structure which comprises a fixed base arranged on one side of the bottom of a steep rock slope, the fixed base comprises a foundation section fixed base, a plurality of expansion section fixed bases are arranged on the side, away from the steep rock slope, of the foundation section fixed base, a water interception wall is arranged on the foundation section fixed base, and a plurality of expansion section fixed bases are arranged on the water interception wall. A passive protection net structure is connected to the upper face of each expanded section fixing base, the structure is simple, construction is convenient, compared with a traditional intercepting ditch, a natural steep rock slope is utilized, groove digging does not need to be conducted on the intercepting ditch, excessive digging of the rock slope can be avoided when the intercepting ditch is built, the digging amount is reduced, and the construction difficulty is lowered; and meanwhile, the cutoff wall is combined with the passive protective net structure, so that the construction land and the construction difficulty are reduced, and falling stones and disintegrating slag can be dredged by utilizing the cutoff wall.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of civil engineering, in particular to a water intercepting and protecting structure for a rocky slope. Background Art

[0002] In water conservancy and hydropower projects, it is usually necessary to arrange water intercepting ditches on the back slopes of water retaining buildings, power generation buildings, slag (material) yards, etc., to reduce the adverse effects of rainwater and accumulated water on the slopes or buildings. At the same time, it is also necessary to arrange passive protection nets to form surface protection for the protection area above the water intercepting ditches, so as to prevent the falling of collapsed rock masses and play a role in slope protection. For steep rocky slopes, the construction of both water intercepting ditches and passive protection nets is relatively difficult, the on-site trenching difficulty is high, and anchoring facilities need to be arranged, resulting in a large construction time consumption. Content of the Utility Model

[0003] The purpose of the utility model is to overcome the above-mentioned deficiencies of the prior art and provide a water intercepting and protecting structure for a rocky slope, which can solve the problems that the construction of both water intercepting ditches and passive protection nets on steep rocky slopes is relatively difficult and the on-site trenching difficulty is high.

[0004] To this end, the utility model adopts the following technical solutions:

[0005] A water intercepting and protecting structure for a rocky slope includes a fixed base arranged on one side of the bottom of a steep rocky slope. The fixed base includes a base section fixed base, and a plurality of enlarged section fixed bases are arranged on the side of the base section fixed base away from the steep rocky slope. A water intercepting wall is arranged on the upper surface of the base section fixed base, and a passive protection net structure is connected to the upper surface of each enlarged section fixed base.

[0006] On the basis of adopting the above technical solutions, the utility model can also adopt the following further technical solutions, or use a combination of these further technical solutions:

[0007] The distance between two adjacent enlarged section fixed bases is 5m to 10m.

[0008] The passive protection net structure includes a structure base fixed on the enlarged section fixed base. The structure base is connected with support columns, the upper ends of the support columns are connected with a wire mesh, and the lower parts of the wire mesh are respectively connected with the structure base and the upper part of the water intercepting wall.

[0009] The upper end of the support column is also connected with a tension anchor rope, the end of the tension anchor rope is connected with an anchor rod, and the anchor rod is fixed on the steep rocky slope.

[0010] The height of the anchor rod is higher than the height of the water intercepting wall.

[0011] The said structural foundation is anchored to the fixed base of the enlarged section through anchor bolts for foundation bolts.

[0012] There are at least two rows of mortar anchor bolts arranged in the fixed base of the foundation section. The lower part of the mortar anchor bolts extends into the steep rocky slope. At least one row of the mortar anchor bolts is arranged throughout the water cut-off wall.

[0013] There is at least one row of the said mortar anchor bolts arranged in the fixed base of the enlarged section.

[0014] The cross-section of the water cut-off wall is a right trapezoid with a narrower upper part and a wider lower part. The inclined surface of the water cut-off wall faces the side of the steep rocky slope.

[0015] Compared with the prior art, the utility model has the following advantages and beneficial effects: the structure is simple and the construction is convenient. Compared with the traditional intercepting ditch, the natural steep rocky slope is utilized, and it is not necessary to carry out trench excavation for the intercepting ditch, which can avoid excessive excavation of the rocky slope during the construction of the intercepting ditch, reduce the excavation volume and lower the construction difficulty; at the same time, the combination of the water cut-off wall and the passive protection net structure reduces the construction land and construction difficulty, and the water cut-off wall can be used to guide the falling rocks and debris. Description of the Drawings

[0016] Figure 1 It is a sectional view of the utility model with the fixed base of the enlarged section set.

[0017] Figure 2 It is a sectional view of the utility model with the fixed base of the foundation section set.

[0018] Figure 3 It is an elevation view of the utility model. Detailed Embodiment

[0019] In order to enable those skilled in the art to better understand the technical solution of the utility model, the preferred implementation scheme of the utility model will be described below in combination with specific embodiments. The examples of the embodiments are shown in the drawings, in which the same or similar reference numerals represent the same or similar functional elements from beginning to end. However, it should be understood that the drawings are only for illustrative purposes and cannot be construed as a limitation to the utility model; in order to better illustrate this embodiment, some components in the drawings will be omitted, enlarged or reduced, and do not represent the size of the actual product; for those skilled in the art, it is understandable that some well-known structures and their descriptions in the drawings may be omitted. The positional relationships described in the drawings are only for illustrative purposes and cannot be construed as a limitation to the utility model.

[0020] The utility model will be further described below in combination with the drawings and embodiments, but it shall not be used as the basis for limiting the utility model.

[0021] A water intercepting and protecting structure for a rocky slope provided by the utility model comprises a fixed base 2 arranged on one side of the bottom of a steep rocky slope 1. The fixed base 2 comprises a basic section fixed base 21. A plurality of enlarged section fixed bases 22 are arranged on the side of the basic section fixed base 21 away from the steep rocky slope 1. A water intercepting wall 3 is arranged on the upper surface of the basic section fixed base 21. A passive protection net structure 4 is connected to the upper surface of each enlarged section fixed base 22.

[0022] The distance between two adjacent enlarged section fixed bases 22 is 5m to 10m.

[0023] The passive protection net structure 4 comprises a structure foundation 41 fixed on the enlarged section fixed base 22. The structure foundation 41 is connected with support columns 42. The upper ends of the support columns 42 are connected with a rope net 43. The lower parts of the rope net 43 are respectively connected with the structure foundation 41 and the upper part of the water intercepting wall 3.

[0024] The upper ends of the support columns 42 are also connected with tension anchor ropes 44. The ends of the tension anchor ropes 44 are connected with anchor bolts 5. The anchor bolts 5 are fixed on the steep rocky slope 1.

[0025] The height of the anchor bolts 5 is higher than the height of the water intercepting wall 3.

[0026] The structure foundation 41 is anchored on the enlarged section fixed base 22 through anchor bolts.

[0027] At least two rows of mortar anchor bolts 6 are arranged in the basic section fixed base 21. The lower parts of the mortar anchor bolts 6 extend into the interior of the steep rocky slope 1. At least one row of mortar anchor bolts 6 is arranged throughout the water intercepting wall 3.

[0028] In this embodiment, two rows of mortar anchor bolts 6 are arranged in the basic section fixed base 21. One row of mortar anchor bolts 6 is arranged throughout the water intercepting wall 3.

[0029] At least one row of mortar anchor bolts 6 is arranged in the enlarged section fixed base 22.

[0030] In this embodiment, one row of mortar anchor bolts 6 is arranged in the enlarged section fixed base 22.

[0031] The cross section of the water intercepting wall 3 is a right trapezoid with a narrow upper part and a wide lower part. The inclined surface of the water intercepting wall 3 faces the side of the steep rocky slope 1.

[0032] Before the construction of the utility model, the smooth rock mass of the steep rocky slope 1 is roughened or the broken rock mass is removed outside the slope opening line. Three rows (two rows) of mortar anchor bolts 6 are arranged in the fixed base 2. One end of the mortar anchor bolts 6 is exposed. Among them, the mortar anchor bolts 6 in the part of the water intercepting wall 3 need to be arranged throughout. With the structural steel bars of the water intercepting wall 3, the fixed base 2 and the water intercepting wall 3 are fixed by pouring concrete with the mortar anchor bolts 6 exposed on the steep rocky slope 1 as the inserted steel bars.

[0033] The water cutoff wall 3 mainly undertakes the functions of intercepting water on the slope and retaining falling rocks and slag, and the passive protection net structure 4 can also intercept the crushed stones rolling down from a high place.

[0034] Based on the description and drawings of the present utility model, those skilled in the art can easily manufacture or use a water cutoff and protection structure for a rocky slope of the present utility model and can achieve the positive effects recorded in the present utility model.

[0035] It should be noted that the terms "including" and "having" in the description, claims and the above-mentioned drawings of the present utility model and any variations thereof are intended to cover non-exclusive inclusion. The terms "installed", "set up", "provided with", "connected", "linked" and "socketed" should be understood in a broad sense. For example, it can be a fixed connection, a detachable connection or an integral structure; it can be a mechanical connection or an electrical connection; it can be directly connected, or indirectly connected through an intermediate medium, or there can be internal communication between two mechanisms, components or parts. For those of ordinary skill in the art, the specific meanings of the above terms in the present utility model can be understood according to specific circumstances.

[0036] In the description of the present utility model, it should be understood that the orientation or positional relationships indicated by the terms "one end", "the other end", "outer side", "inner side", "horizontal", "end part", "length", "outer end", "left", "right", etc. are based on the orientation or positional relationships shown in the drawings, and are only for the convenience of describing the present utility model and simplifying the description, rather than indicating or implying that the indicated mechanism or component must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be construed as a limitation to the present utility model. The terms "first" and "second" are only used for simplicity in description and do not indicate or imply relative importance.

[0037] In addition, when practicing the claims of the present utility model, through the study of the drawings, the disclosure and the appended claims, those skilled in the art can understand and affect the variations of the disclosed embodiments. In addition, in the claims and the description, words such as "including" and "containing" do not exclude other elements or steps, and non-plural nouns do not exclude their plural forms.

[0038] The above are only the preferred embodiments of the present utility model and are not used to limit the scope of implementation of the present utility model. That is, all equal changes and modifications made in accordance with the present utility model are covered by the scope of the claims of the present utility model, and no further examples will be given here.

Claims

1. A water interception and protection structure for a rocky slope, characterized in that It includes a fixed base (2) arranged on one side at the bottom of a steep rocky slope (1). The fixed base (2) includes a base section fixed base (21). On the side of the base section fixed base (21) away from the steep rocky slope (1), there are a number of enlarged section fixed bases (22). A water interception wall (3) is arranged on the upper surface of the base section fixed base (21). A passive protection net structure (4) is connected to the upper surface of each enlarged section fixed base (22).

2. The water intercepting and protecting structure for a rocky slope according to claim 1, characterized in that, The distance between two adjacent enlarged section fixed bases (22) is 5m to 10m.

3. The water intercepting and protecting structure for a rocky slope according to claim 1, characterized in that The passive protection net structure (4) includes a structure foundation (41) fixed on the enlarged section fixed base (22). The structure foundation (41) is connected to support columns (42). The upper ends of the support columns (42) are connected to a rope net (43). The lower parts of the rope net (43) are respectively connected to the structure foundation (41) and the upper part of the water interception wall (3).

4. The water intercepting and protecting structure for a rocky slope according to claim 3, characterized in that, The upper ends of the support columns (42) are also connected to anchor ropes (44). The ends of the anchor ropes (44) are connected to anchor rods (5). The anchor rods (5) are fixed on the steep rocky slope (1).

5. The water intercepting and protecting structure for a rocky slope according to claim 4, characterized in that, The height of the anchor rod (5) is higher than the height of the water interception wall (3).

6. The water intercepting and protecting structure for a rocky slope according to claim 3, characterized in that The structure foundation (41) is anchored to the enlarged section fixed base (22) through anchor bolts.

7. The water interception and protection structure for a rocky slope according to claim 1, characterized in that, At least two rows of mortar anchor rods (6) are arranged in the base section fixed base (21). The lower parts of the mortar anchor rods (6) extend into the interior of the steep rocky slope (1). At least one row of the mortar anchor rods (6) is arranged throughout the water interception wall (3).

8. The water intercepting and protecting structure for a rocky slope according to claim 7, characterized in that, At least one row of the mortar anchor rods (6) is arranged in the enlarged section fixed base (22).

9. The water intercepting and protecting structure for a rocky slope according to claim 1, characterized in that, The cross-section of the water interception wall (3) is a right trapezoid with a narrower upper part and a wider lower part. The inclined surface of the water interception wall (3) faces the side of the steep rocky slope (1).