Hanging basket middle landing platform device

By setting up a flooring platform device in the middle of the hanging basket on the middle floor of a high-rise building, and fixing the hanging basket with vertical keels and reinforcements of the curtain wall, the problem of inconvenience in landing the hanging basket is solved, safety is improved and construction costs are reduced.

CN223119479UActive Publication Date: 2025-07-18CHINA CONSTR EIGHTH ENG DIV CORP LTD ZHEJIANG CONSTR CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202422399872.1
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-09-29
Publication Date
2025-07-18
Estimated Expiration
2034-09-29

AI Technical Summary

Technical Problem

It is inconvenient to land and handle when it is not in use, resulting in inconvenient construction and safety hazards.

Method used

A middle flooring platform device for hanging basket is designed, and the hanging basket is fixed to the intermediate layer using vertical keels and reinforcements of the curtain wall, and the docking of the hanging basket is achieved through the support beams and platform plates, and protective rods and intercept cables are provided to improve safety.

Benefits of technology

It effectively solves the problem of docking of hanging baskets, improves construction safety, reduces accident rates, and reduces construction costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN223119479U_ABST
    Figure CN223119479U_ABST
Patent Text Reader

Abstract

The utility model discloses a hanging basket middle landing platform device which comprises a plurality of curtain wall vertical keels installed on the outer vertical face of a high-rise building. One end of the reinforcing part is connected to the upper end of the curtain wall vertical keel, and the other end of the reinforcing part is connected to the middle layer of the high-rise building through an embedded part; each supporting beam is provided with a fixed end and an overhanging end, the middles of the supporting beams are installed on the curtain wall vertical keels, the fixed ends are in lap joint with the middle layer, and the overhanging ends extend to the outer side of the high-rise building; the platform plate is used for a hanging basket to stop, the platform plate is laid on the multiple bearing beams, the reinforcing piece is provided with a supporting column, and the supporting column is supported on the platform plate; and the protection rods are vertically arranged at the cantilever ends, and the protection rods on the multiple supporting beams are connected with interception inhaul cables. The hanging basket solves the problem that the hanging basket for mounting the curtain wall of the high-rise building is inconvenient to stop on the ground.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of building construction, in particular to a hanging basket intermediate landing platform device. Background Technique

[0002] At present, many frame-core tube structures are high-rise buildings, and the curtain wall installation method mostly uses the hanging basket installation method. When the hanging basket is not in use, it needs to land, but considering the high number of floors, the construction is relatively inconvenient. Content of the Utility Model

[0003] In order to overcome the defects existing in the prior art, a hanging basket intermediate landing platform device is provided at present to solve the problem that it is inconvenient for the hanging basket used for curtain wall installation of high-rise buildings to land and dock.

[0004] To achieve the above object, a hanging basket intermediate landing platform device is provided, including:

[0005] Multiple vertical curtain wall keels, installed on the outer facade of a high-rise building;

[0006] A reinforcement member, one end of the reinforcement member is connected to the upper end of the vertical curtain wall keel, and the other end of the reinforcement member is connected to the intermediate layer of the high-rise building through an embedded part;

[0007] Multiple support beams, the support beam has a fixed end and a cantilever end, the middle part of the support beam is installed on the multiple vertical curtain wall keels, the fixed end is lapped on the intermediate layer, and the cantilever end extends to the outside of the high-rise building;

[0008] A platform board for the hanging basket to dock, laid on the multiple support beams, a support column is installed on the reinforcement member, and the support column supports the platform board;

[0009] A protective rod, vertically arranged at the cantilever end, and an interception cable is connected to the protective rods on the multiple support beams.

[0010] Further, the number of the reinforcement members is two. One reinforcement member is connected to the floor slab of the intermediate layer, the support column is arranged on the one reinforcement member, and the other reinforcement member is connected to the structural beam of the intermediate layer.

[0011] Further, the reinforcement member includes:

[0012] Two connecting beams, one ends of the two connecting beams are connected to the embedded part, and the vertical curtain wall keel is embedded between the other ends of the two connecting beams;

[0013] A locking member for locking the vertical curtain wall keel, installed on the connecting beam.

[0014] Further, the embedded part includes:

[0015] An embedded plate is embedded in the side of the floor slab or the structural beam, and the end of the connecting beam is fixedly connected to the embedded plate;

[0016] Anchor rods are connected to the embedded plate and embedded in the floor slab or the structural beam.

[0017] Furthermore, a protective net is installed outside the plurality of protective rods.

[0018] The beneficial effect of the utility model is that the middle landing platform device of the hanging basket of the utility model is reinforced by the original vertical keel of the curtain wall, the vertical keel of the curtain wall is fixed by the reinforcement piece, the reinforcement piece is implanted into the structural beam of the middle layer through the embedded plate and tied with the structural beam (or tied with the floor slab in the floor slab), and a supporting beam is arranged on the upper part, the supporting beam and the vertical keel of the curtain wall are fixed with bolts, and a protective rod is arranged on the upper part of the supporting beam, the two are fixed by welding, and an intercepting cable is arranged, and finally a platform board is laid at the bottom. After the setting is completed, the hanging basket can be docked on the platform board and enter and exit through the middle floor slab.

[0019] The utility model discloses a hanging basket middle landing platform device which uses a glass curtain wall keel and a reinforcement piece to set a platform for docking the hanging basket at the middle layer, thereby effectively solving the docking problem of the hanging basket and effectively improving the safety. BRIEF DESCRIPTION OF THE DRAWINGS

[0020] Other features, objects and advantages of the present application will become more apparent by reading the detailed description of non-limiting embodiments made with reference to the following drawings:

[0021] Figure 1 It is a structural schematic diagram of the intermediate landing platform device of the hanging basket according to an embodiment of the utility model.

[0022] Figure 2 It is a schematic structural diagram of the bottom of the hanging basket middle landing platform device according to an embodiment of the utility model.

[0023] Figure 3 It is a front view of the middle landing platform device of the hanging basket according to an embodiment of the utility model.

[0024] Figure 4 It is a structural schematic diagram of the cantilevered end of the supporting beam according to an embodiment of the utility model. DETAILED DESCRIPTION

[0025] The present application is further described in detail below in conjunction with the accompanying drawings and embodiments. It is to be understood that the specific embodiments described herein are only used to explain the relevant utility model, rather than to limit the utility model. It is also necessary to explain that, for ease of description, only the parts related to the utility model are shown in the accompanying drawings.

[0026] It should be noted that, without conflict, the embodiments in the present application and the features in the embodiments can be combined with each other. The present application will be described in detail below with reference to the drawings and in combination with the embodiments.

[0027] Referring to Figures 1 to 4 As shown, the utility model provides a middle landing platform device for a hanging basket, including: a curtain wall vertical keel 1, a support beam 3, a platform plate 4, and a guardrail 5.

[0028] Among them, a curtain wall structure is installed on the outer facade of a high-rise building. The curtain wall structure includes curtain wall glass and curtain wall vertical keels. The number of curtain wall vertical keels is multiple. The multiple curtain wall vertical keels 1 are arranged at intervals along the circumferential direction of the high-rise building. The curtain wall vertical keels are installed on the outer facade of the high-rise building.

[0029] In this embodiment, the curtain wall structure forms a fault at the middle layer of the high-rise building.

[0030] The reinforcement member 2 is used to reinforce the multiple curtain wall vertical keels. Specifically, one end of the reinforcement member 2 is connected to the upper end of the curtain wall vertical keel 1. The other end of the reinforcement member 2 is connected to the middle layer of the high-rise building through the embedded part 23.

[0031] As a preferred embodiment, the number of the reinforcement members 2 is two. The two reinforcement members are arranged up and down.

[0032] Specifically, in this embodiment, the middle layer includes a floor slab and a structural beam. The floor slab and the structural beam are integrally cast. Among them, one reinforcement member 2 is connected to the floor slab 6 of the middle layer. The other reinforcement member 2 is connected to the structural beam 7 of the middle layer.

[0033] The support column 24 is arranged on one of the reinforcement members 2. The support column is arranged on one of the upper reinforcement members.

[0034] In this embodiment, referring to Figure 4 As shown, the reinforcement member 2 includes: a connecting beam 21 and a locking member 22.

[0035] Each reinforcement member includes two connecting beams 21. One end of the two connecting beams 21 is connected to the embedded part 23. The curtain wall vertical keel 1 is embedded between the other ends of the two connecting beams 21. The locking member 22 is installed on the connecting beam 21.

[0036] The locking member 22 is used to lock the curtain wall vertical keel 1. Specifically, through holes are respectively formed at the upper end of the curtain wall vertical keel and the end of the connecting beam. The locking member 22 passes through the through holes at the upper end of the curtain wall vertical keel and the end of the connecting beam. Pressing nuts are respectively installed at both ends of the locking member. The two pressing nuts respectively press against the opposite sides of the two connecting beams.

[0037] Continuing to refer to Figure 3 andFigure 4 As shown, the embedded part 23 includes an embedded plate and an anchor rod.

[0038] The embedded plate is embedded in the side of the floor slab 6 or the structural beam 7. The end of the connecting beam 21 is fixedly connected to the embedded plate. The anchor rod is connected to the embedded plate. The anchor rod is embedded in the floor slab 6 or the structural beam 7.

[0039] There are multiple supporting beams 3. The supporting beams 3 have a fixed end and a cantilevered end. The middle of the supporting beam 3 is installed on multiple curtain wall vertical keels 1. The fixed end is overlapped on the middle layer. The cantilevered end extends to the outside of the high-rise building.

[0040] The platform plate 4 is laid on a plurality of supporting beams 3. The reinforcing member 2 is provided with a supporting column 24. The supporting column 24 is supported on the platform plate 4. The platform plate 4 is provided for the hanging basket 8 to dock.

[0041] The protection rod 5 is vertically arranged at the cantilever end. The protection rods 5 on the multiple supporting beams 3 are connected with interception cables. The exterior of the multiple protection rods 5 is equipped with a protection net.

[0042] The utility model discloses a hanging basket intermediate landing platform device, which is reinforced by utilizing the original vertical keel of the curtain wall, and fixes the vertical keel of the curtain wall by means of reinforcement pieces, which are implanted into the structural beam of the intermediate layer through the embedded plate and tied to the structural beam (or tied to the floor slab in the floor slab), and a supporting beam is arranged at the upper part, and the supporting beam and the vertical keel of the curtain wall are fixed by bolts, and a protective rod is arranged at the upper part of the supporting beam, and the two are fixed by welding, and an intercepting cable is arranged, and finally a layer of platform board is laid at the bottom, and after the arrangement is completed, the hanging basket can be docked on the platform board and enter and exit through the intermediate floor slab.

[0043] The utility model discloses a hanging basket middle landing platform device which uses a glass curtain wall keel and a reinforcement piece to set a platform for docking the hanging basket at the middle layer, thereby effectively solving the docking problem of the hanging basket and effectively improving the safety.

[0044] The utility model provides a landing platform device in the middle of the hanging basket, which prevents workers from entering a floor directly by crossing the hanging basket without stopping on the ground for convenience, thereby significantly reducing the occurrence rate of accidents.

[0045] The utility model discloses a hanging basket middle landing platform device, which sets the platform through the original curtain wall keel, thereby greatly reducing the construction cost.

[0046] The above description is only a preferred embodiment of the present application and an explanation of the technical principles applied. Those skilled in the art should understand that the scope of the utility model involved in the present application is not limited to the technical solutions formed by the specific combination of the above technical features, and should also cover other technical solutions formed by any combination of the above technical features or their equivalent features without departing from the inventive concept of the utility model. For example, the technical solutions formed by mutually replacing the above features with (but not limited to) the technical features with similar functions disclosed in the present application.

Claims

1. A middle landing platform device for a hanging basket, characterized in that, Including: Multiple vertical curtain wall keels, installed on the outer facade of a high-rise building; Reinforcement members, one end of the reinforcement members is connected to the upper end of the vertical curtain wall keels, and the other end of the reinforcement members is connected to the middle layer of the high-rise building through embedded parts; Multiple support beams, the support beams have a fixed end and a cantilever end, the middle parts of the support beams are installed on the multiple vertical curtain wall keels, the fixed ends are lapped on the middle layer, and the cantilever ends extend to the outside of the high-rise building; Platform plates for the hanging basket to dock, laid on the multiple support beams, support columns are installed on the reinforcement members, and the support columns support the platform plates; Guardrails, erected on the cantilever ends, and intercepting cables are connected to the guardrails on the multiple support beams.

2. The intermediate landing platform device for the hanging basket according to claim 1, characterized in that, The number of the reinforcement members is two. One reinforcement member is connected to the floor slab of the middle layer, the support column is arranged on the one reinforcement member, and the other reinforcement member is connected to the structural beam of the middle layer.

3. The hanging basket intermediate landing platform device according to claim 2, characterized in that, The reinforcement members include: Two connecting beams, one end of the two connecting beams is connected to the embedded parts, and the vertical curtain wall keels are embedded between the other ends of the two connecting beams; Locking members for locking the vertical curtain wall keels, installed on the connecting beams.

4. The hanging basket intermediate landing platform device according to claim 3, characterized in that, The embedded parts include: Embedded plates, embedded on the side of the floor slab or the structural beam, and the ends of the connecting beams are fixedly connected to the embedded plates; Anchoring rods, connected to the embedded plates and embedded in the floor slab or the structural beam.

5. The intermediate landing platform device of the hanging basket according to claim 1, characterized in that, A protective net is installed outside the multiple guardrails.