Modularized integrated building concrete module hoisting structure
Through the design of vertical telescopic rods and clamping mechanisms, the problem that the existing lifting structure cannot be adapted to concrete modules of different sizes is solved, and flexible adaptation and convenient operation of the lifting structure are achieved.
Patent Information
- Application Number
- CN202422355321.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-26
- Publication Date
- 2025-07-22
- Estimated Expiration
- 2034-09-26
AI Technical Summary
The existing lifting structure is difficult to adapt according to the different sizes of the concrete module, resulting in the inability to effectively clamp or clamp the fixture.
The vertical telescopic rod and clamping mechanism are adopted to clamp the concrete module by moving the support rod, and the spacing of the connecting beams is adjusted by adjusting the bracket and tightening rope to accommodate concrete modules of different sizes.
The lifting structure can be adapted to concrete modules of different sizes, making it easy to clamp and lower the concrete modules, and can quickly adjust the spacing of the connecting beams.
Smart Images

Figure CN223133889U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the field of building construction, in particular to a hoisting structure for modular integrated building concrete modules. Background Technique
[0002] During the building construction process, construction workers may use modular integrated building concrete modules for building construction. The modular integrated building concrete modules are generally pre-produced by customization in a factory and then transported to the construction site for rapid erection. During the on-site construction process, the modular integrated building concrete modules need to be hoisted.
[0003] The hoisting of the prior art is generally carried out by a crane. A hoisting fixture is installed on the hook of the crane. After the hoisting fixture receives an upward pulling force from the crane, the lower end of the fixture clamps inward, thereby clamping the building concrete module. However, the sizes and dimensions of the concrete modules are different. If the size of the fixture is larger than the concrete module, it is easy to cause that the concrete module cannot be clamped after the lower end of the fixture tightens. If the size of the fixture is smaller than the concrete module, the concrete module cannot be clamped at the clamping position of the fixture. The hoisting structure in the prior art is difficult to adjust the size, resulting in its inability to adapt to the size of the concrete module. Content of the Utility Model
[0004] In order to solve the problem that the hoisting structure in the background technique is difficult to adjust the size, the utility model provides a hoisting structure for modular integrated building concrete modules.
[0005] The technical solution of the utility model is: including a vertical telescopic rod;
[0006] The vertical telescopic rod extends in the up and down direction, and a self-locking mechanism is arranged inside the vertical telescopic rod. The upper end of the vertical telescopic rod is fixedly connected with a support cross beam extending in the left and right direction, and a connecting frame is fixedly connected to the upper surface of the support cross beam;
[0007] The lower end of the vertical telescopic rod is detachably connected with an installation cross beam. A clamping mechanism is arranged on the installation cross beam. The clamping mechanism includes a left fixture and a right fixture. Both the left fixture and the right fixture are slidably arranged on the installation cross beam, and the distance between the left fixture and the right fixture is adjustable. Both the left fixture and the right fixture can swing left and right;
[0008] Both the left and right sides of the middle part of the vertical telescopic rod are fixedly connected with rope connecting frames. The positions of the two rope connecting frames correspond to each other left and right. The opposite ends of the two rope connecting frames are both fixedly connected with ropes. Installation avoidance grooves are respectively arranged on the left and right sides of the connecting frame. A lockable rope winding drum is rotatably arranged in each installation avoidance groove. One end of the rope far away from the rope connecting frame is fixedly connected to the rope winding drum. The rope winding drum is used to adjust the tension of the rope;
[0009] The upper ends of the left clamp and the right clamp are both connected to the middle ends of the corresponding ropes. When the ropes are tightened upward, the left clamp and the right clamp are driven to swing in opposite directions.
[0010] Preferably, the clamping mechanism includes two brackets extending in the front-back direction. A left-right through chute is provided in each bracket. The brackets are movably sleeved on the mounting cross beam through the chutes. A locking member is provided on the brackets for locking the positions of the brackets on the mounting cross beam.
[0011] The left clamp includes a bracket on the left side and a left clamping frame. The left clamping frames are hinged to the front and rear sides of the bracket on the left side.
[0012] The right clamp includes a bracket on the right side and a right clamping frame. Padding plates are fixedly connected to the front and rear sides of the bracket on the right side. The thickness of the padding plates is equal to the thickness of the left clamping frame. The right clamping frame is hinged to the padding plates. The right clamping frame and the left clamping frame are corresponding to each other in the left-right position.
[0013] The tops of the right clamping frame and the left clamping frame are both connected to the ropes.
[0014] Preferably, the left clamping frame and the right clamping frame both extend vertically. Inclined connecting support plates are fixedly connected to the upper ends of the left clamping frame and the right clamping frame.
[0015] The upper parts of the connecting support plates corresponding to each other in the left-right position are staggered and crossed in the front-back direction to form an X structure. The crossing points of the two connecting support plates correspond to the position of the vertical telescopic rod in the front-back direction.
[0016] A support column extending in the front-back direction is fixedly connected between the upper ends of the connecting support plates corresponding to each other in the front-back position. The support column is located below the rope connecting frame on the same side. The ropes extending from the rope connecting frame bypass below the support column and then extend upward and are fixedly connected to the rope winding drum on the same side.
[0017] Preferably, a connecting beam extending in the front-back direction is fixedly connected between the lower ends of the two left clamping frames and between the lower ends of the two right clamping frames. Friction pads are fixedly connected to the opposite surfaces of the two connecting beams.
[0018] Preferably, the vertical telescopic rod includes a guiding frame which extends vertically. A chute extending in the up-down direction is provided in the guiding frame. The chute has an open upper end and a closed lower end structure. A support rod is slidably provided in the chute. The upper end of the support rod is fixedly connected with a support cross beam.
[0019] Rope connecting frames are fixedly connected to the upper parts of the left and right sides of the guiding frame.
[0020] The bottom wall of the guide frame is fixedly connected with a fixing block. There is a gap between the fixing block and the support rod. A locking rod extending in the vertical direction is hinged on the fixing block. A locking groove is formed in the lower part of the support rod. The upper end of the locking rod is fixedly connected with a limiting rod extending in the front-rear direction. The limiting rod is slidably arranged inside the locking groove.
[0021] The lower end of the guide frame is fixedly connected with a mounting frame. The mounting frame is detachably connected with the mounting cross beam.
[0022] The locking groove can lock the locking rod.
[0023] Preferably, the locking groove includes a vertical sliding groove and a locking block. The vertical sliding groove is formed in the lower part of the front side of the support rod. A vertically extending locking block is fixedly connected inside the vertical sliding groove. The gap between the inner wall of the vertical sliding groove and the outer side of the locking block forms a loop-shaped sliding groove. The limiting rod can slide in the loop-shaped sliding groove.
[0024] The top wall of the vertical sliding groove extends downward to form a V-shaped protrusion. The top of the locking block is provided with a V-shaped notch. The position of the V-shaped notch corresponds to the position of the V-shaped protrusion up and down. The gap between the position of the V-shaped notch and the V-shaped protrusion forms a V-shaped sliding groove.
[0025] When the limiting rod is at the lowest position in the V-shaped sliding groove, the locking rod locks the support rod.
[0026] Preferably, through holes penetrating up and down are formed in the left and right side surfaces of the support cross beam. A support pillar extending in the front-rear direction is fixedly connected inside the through hole. The outer surface of the support pillar contacts the rope.
[0027] Preferably, the locking member includes a locking hole. A plurality of locking holes arranged in the left-right direction are formed in the upper surface of the mounting cross beam. A locking socket is formed on the bracket. A locking bolt is inserted between the locking socket and the corresponding locking hole. A nut is threadedly connected to the locking bolt.
[0028] Preferably, a hook connecting frame adapted to the hook is provided on the connecting frame.
[0029] The advantages of the present utility model are as follows: The clamping mechanism can be driven to clamp by the movement of the support rod, and the concrete module can be quickly lowered by locking the support rod. The distance between the connecting beams can be adjusted by moving the bracket and tightening the rope, so that the hoisting structure can be adapted to concrete modules of different sizes. Description of the Drawings
[0030] To more clearly illustrate the technical solutions in the embodiments of the present invention or the prior art, the following will briefly introduce the drawings required for the description of the embodiments or the prior art. Obviously, the drawings in the following description are only some embodiments of the present invention. For those of ordinary skill in the art, without creative efforts, other drawings can also be obtained based on these drawings.
[0031] Figure 1 It is a schematic diagram of the main structure of Embodiment 1;
[0032] Figure 2 It is Figure 1 a schematic diagram of the vertical telescopic rod structure;
[0033] Figure 3 It is Figure 1 a schematic diagram of the right view structure;
[0034] Figure 4 It is Figure 1 a schematic diagram of the clamping mechanism structure;
[0035] Figure 5 It is Figure 1 a schematic diagram of the partial structure of the vertical telescopic rod.
[0036] In the figure, 1 is the vertical telescopic rod, 101 is the guide frame, 102 is the support rod, 103 is the fixed block, 104 is the locking rod, 105 is the locking groove, 106 is the mounting frame; 2 is the support cross beam, 201 is the avoidance groove, 3 is the connecting frame, 301 is the rope winding drum, 4 is the rope connecting frame, 5 is the mounting cross beam, 501 is the locking hole, 502 is the locking bolt, 6 is the clamping mechanism, 601 is the bracket, 602 is the left clamping frame, 603 is the connecting beam, 604 is the support column, 605 is the backing plate, 606 is the right clamping frame, 7 is the friction pad, 8 is the hook connecting frame. Specific embodiments
[0037] The following will clearly and completely describe the technical solutions in the embodiments of the present invention in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only some embodiments of the present invention, rather than all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without creative efforts belong to the scope of protection of the present invention.
[0038] Embodiment 1: The purpose of this embodiment is to propose a modular integrated building concrete module hoisting structure.
[0039] According to Figures 1 to 4 , it includes a vertical telescopic rod 1;
[0040] The vertical telescopic rod 1 extends in the up and down direction. The vertical telescopic rod 1 includes a guide frame 101 which extends vertically. A chute extending in the up and down direction is formed on the guide frame 101. The chute has an open upper end and a closed lower end structure, and a support rod 102 is slidably arranged in the chute.
[0041] A fixed block 103 is fixedly connected to the bottom wall of the guide frame 101. There is a gap between the fixed block 103 and the support rod 102. A locking rod 104 extending in the up and down direction is hinged on the fixed block 103. A locking groove 105 is formed in the lower part of the support rod 102. The upper end of the locking rod 104 is fixedly connected with a limiting rod extending in the front and back directions, and the limiting rod is slidably arranged inside the locking groove 105.
[0042] The locking groove 105 includes a vertical chute and a locking block. The vertical chute is formed in the lower part of the front side of the support rod 102. A vertically extending locking block is fixedly connected in the vertical chute. The gap between the inner wall of the vertical chute and the outer side of the locking block forms a loop-shaped chute, and the limiting rod can slide in the loop-shaped chute.
[0043] The top wall of the vertical chute extends downward to form a V-shaped protrusion. The top of the locking block is provided with a V-shaped notch. The position of the V-shaped notch corresponds to the position of the V-shaped protrusion up and down. The gap between the position of the V-shaped notch and the V-shaped protrusion forms a V-shaped chute. When the limiting rod is at the lowest position in the V-shaped chute, the locking rod 104 locks the support rod 102.
[0044] The lower end of the guide frame 101 is fixedly connected with a mounting frame 106, and the mounting frame 106 is connected to the mounting cross beam 5 through mounting bolts.
[0045] A clamping mechanism 6 is arranged on the mounting cross beam 5. The clamping mechanism 6 includes two brackets 601 extending in the front and back directions. A chute that is transparent from left to right is formed in the bracket 601. The bracket 601 is movably sleeved on the mounting cross beam 5 through the chute. A locking member is arranged on the bracket 601. The locking member includes a locking hole 501. A plurality of locking holes 501 arranged in the left and right directions are formed on the upper surface of the mounting cross beam 5. A locking socket is formed on the bracket 601. A locking bolt 502 is inserted between the locking socket and the corresponding locking hole 501, and a nut is threadedly connected to the locking bolt 502.
[0046] Left clamping frames 602 are hinged on the front and back sides of the left bracket 601.
[0047] Padding plates 605 are fixedly connected to the front and back sides of the right bracket 601. The thickness of the padding plate 605 is equal to the thickness of the left clamping frame 602. Right clamping frames 606 are hinged on the padding plates 605. The right clamping frames 606 and the left clamping frames 602 are corresponding to each other left and right. The left clamping frames 602 and the right clamping frames 606 both extend vertically. The upper ends of the left clamping frames 602 and the right clamping frames 606 are fixedly connected with inclined connecting support plates.
[0048] The upper parts of the connecting support plates corresponding to each other left and right are staggered and crossed front and back to form an X structure, and the crossing points of the two connecting support plates correspond to the position of the vertical telescopic rod 1 front and back. A support column 604 extending in the front-back direction is fixedly connected between the upper ends of the connecting support plates corresponding to each other front and back. The support column 604 is located below the rope connecting frame 4 on the same side. The ropes extending from the rope connecting frame 4 bypass below the support column 604 and then extend upward and are fixedly connected to the rope winding drum 301 on the same side.
[0049] A connecting beam 603 extending in the front-back direction is fixedly connected between the lower ends of the two left clamping frames 602 and between the lower ends of the two right clamping frames 606. Friction pads 7 are fixedly connected to the opposite surfaces of the two connecting beams 603. The friction pads 7 can be made of rubber material.
[0050] The upper end of the support rod 102 is fixedly connected to a support cross beam 2. A connecting frame 3 is fixedly connected to the upper surface of the support cross beam 2. A hook connecting frame 8 adapted to the hook is provided on the connecting frame 3.
[0051] Rope connecting frames 4 are fixedly connected to the upper parts of the left and right side surfaces of the guide frame 101. The positions of the two rope connecting frames 4 correspond to each other left and right, and ropes are fixedly connected to the opposite ends of the two rope connecting frames 4. Installation avoidance grooves are formed on the left and right sides of the connecting frame 3. Rotatable lockable rope winding drums 301 are provided in the installation avoidance grooves. The ends of the ropes far from the rope connecting frames 4 are fixedly connected to the rope winding drums 301. The rope winding drums 301 are used to adjust the tension of the ropes. The rotation of the rope winding drums 301 can be locked by using a pin-type locking method for the rope winding drums 301.
[0052] Avoidance grooves 201 that are vertically penetrating are formed on the left and right side surfaces of the support cross beam 2. A support column extending in the front-back direction is fixedly connected in the avoidance grooves 201. The outer surface of the support column contacts the rope.
[0053] Working principle: Before construction, first connect the hook connecting frame 8 with the hook of the crane for installation. Then, apply a downward pressure to the support rod 102. When the support rod 102 is stressed, the V-shaped chute contacts the limit rod. The V-shaped protrusion on the vertical chute guides the limit rod to slide left and right downward to both sides, thereby driving the locking rod 104 to swing left and right until the limit rod slides out of the V-shaped chute, so that the support rod 102 is unlocked. Then, apply an upward pulling force to the hook connecting frame 8 through the crane, thereby driving the connecting frame 3 upward. The upward movement of the connecting frame 3 drives the support rod 102 upward. The upward movement of the support rod 102 causes the limit rod to continue to slide downward in the locking groove 105. During this process, the upward movement of the support rod 102 drives the support crossbeam 2 upward, thereby tightening the rope. The tightened rope drives the support column 604 upward, so that both the right clamping frame 606 and the left clamping frame 602 swing in opposite directions with the connection point with the bracket 601 as the center, thereby reducing the distance between the two connecting beams 603, and thus clamping the concrete module.
[0054] After the concrete module is clamped, the right clamping frame 606 and the left clamping frame 602 stop swinging, so that the movement of the support column 604 is limited, and the rope applies a pulling force to the support crossbeam 2, so that the movement of the support rod 102 stops.
[0055] When the crane hoists the concrete module to the designated position, the hook of the crane moves downward, so that the support rod 102 resets, so that the limit rod slides back into the V-shaped chute, and the limit rod falls back to the V-shaped notch, so that the limit rod is locked again. The reset of the support rod 102 causes the distance between the connecting beams 603 to reset, and the concrete module disengages from the contact with the connecting beams 603. The crane hoists the lifting structure again. During the hoisting process, since the limit rod is locked, the movement of the support rod 102 is also locked, and the concrete module is lowered.
[0056] When adjusting the size, remove the locking bolt 502 to release the lock of the bracket 601 on the installation crossbeam 5, and at the same time release the lock of the rope winding drum 301. Then move the bracket 601 to adjust the gap between the two connecting beams 603. When the gap reaches the appropriate distance, reinsert the locking bolt 502 between the locking socket and the corresponding locking hole 501, and then screw on the nut to lock it.
[0057] When expanding the distance between the connecting beams 603, during the movement of the bracket 601, the rope winding drum 301 rotates, and the length of the rope is extended.
[0058] When reducing the distance between the connecting beams 603, after the bracket 601 completes the movement, rotate the rope winding drum 301 to shorten the length of the rope.
[0059] After the adjustment is completed, lock the rope winding drum 301 again.
[0060] Thus, the hoisting structure can be conveniently installed on the crane. At the same time, the clamping of the hoisting structure and the lowering of the concrete module are relatively convenient. Moreover, the distance between the connecting beams 603 can be adjusted by moving the support 601 and tightening the ropes, so that the hoisting structure can be adapted to concrete modules of different sizes.
[0061] For those skilled in the art, it is obvious that the present utility model is not limited to the details of the above exemplary embodiments, and the present utility model can be implemented in other specific forms without departing from the spirit or basic characteristics of the present utility model. Therefore, from any point of view, the embodiments should be regarded as exemplary and non-restrictive. The scope of the present utility model is defined by the appended claims rather than the above description. Therefore, all changes falling within the meaning and scope of the equivalent elements of the claims are intended to be embraced within the present utility model. Any reference signs in the claims should not be construed as limiting the claims involved.
Claims
1. The hoisting structure of the concrete module of the modular integrated building is characterized in that: Comprising a vertical telescopic rod (1); The vertical telescopic rod (1) extends in the up and down direction, and a self-locking mechanism is provided inside the vertical telescopic rod (1). The upper end of the vertical telescopic rod (1) is fixedly connected to a support cross beam (2) extending in the left and right direction, and a connecting frame (3) is fixedly connected to the upper surface of the support cross beam (2); The lower end of the vertical telescopic rod (1) is detachably connected to an installation cross beam (5). A clamping mechanism (6) is provided on the installation cross beam (5). The clamping mechanism (6) includes a left clamp and a right clamp. Both the left clamp and the right clamp are slidably arranged on the installation cross beam (5), and the distance between the left clamp and the right clamp is adjustable. Both the left clamp and the right clamp can swing left and right; On the left and right sides of the middle part of the vertical telescopic rod (1), a rope connecting frame (4) is fixedly connected to each side. The positions of the two rope connecting frames (4) correspond to each other left and right. Ropes are fixedly connected to the opposite ends of the two rope connecting frames (4). Installation avoidance grooves are provided on the left and right sides of the connecting frame (3). A lockable rope winding drum (301) is rotatably arranged in each installation avoidance groove. One end of the rope far from the rope connecting frame (4) is fixedly connected to the rope winding drum (301). The rope winding drum (301) is used to adjust the tension of the rope; The upper ends of the left clamp and the right clamp are both connected to the middle ends of the corresponding ropes. When the ropes are tightened upwards, the left clamp and the right clamp are driven to swing in opposite directions.
2. The hoisting structure of the concrete module of the modular integrated building according to claim 1, characterized in that: The clamping mechanism (6) includes two brackets (601) extending in the front and back direction. A left-right through chute is provided inside the bracket (601). The bracket (601) is movably sleeved on the installation cross beam (5) through the chute. A locking member is provided on the bracket (601) to lock the position of the bracket (601) on the installation cross beam (5); The left clamp includes the bracket (601) on the left side and a left clamping frame (602). The left clamping frame (602) is hinged to the front and back sides of the bracket (601) on the left side; The right clamp includes the bracket (601) on the right side and a right clamping frame (606). Padding plates (605) are fixedly connected to the front and back sides of the bracket (601) on the right side. The thickness of the padding plate (605) is equal to the thickness of the left clamping frame (602). The right clamping frame (606) is hinged to the padding plate (605). The right clamping frame (606) and the left clamping frame (602) are in corresponding positions left and right; The tops of the right clamping frame (606) and the left clamping frame (602) are both connected to the ropes.
3. The hoisting structure of the concrete module of the modular integrated building according to claim 2, characterized in that: Both the left clamping frame (602) and the right clamping frame (606) extend vertically. Inclined connecting support plates are fixedly connected to the upper ends of the left clamping frame (602) and the right clamping frame (606); The upper parts of the connecting support plates corresponding to each other left and right are staggered and crossed front and back to form an X structure, and the intersection point of the two connecting support plates corresponds to the position of the vertical telescopic rod (1) front and back; A support column (604) extending in the front and back direction is fixedly connected between the upper ends of the connecting support plates corresponding to each other front and back. The support column (604) is located below the rope connecting frame (4) on the same side. The rope extending from the rope connecting frame (4) bypasses below the support column (604) and then extends upwards and is fixedly connected to the rope winding drum (301) on the same side.
4. The hoisting structure of the concrete module of the modular integrated building according to claim 3, characterized in that: A connecting beam (603) extending in the front-rear direction is fixedly connected between the lower ends of the two left clamping frames (602) and between the lower ends of the two right clamping frames (606), and friction pads (7) are fixedly connected to the opposite surfaces of the two connecting beams (603).
5. The hoisting structure of the modular integrated building concrete module according to claim 1, characterized in that: The vertical telescopic rod (1) includes a guide frame (101) which extends vertically. A chute extending in the up-down direction is formed on the guide frame (101). The chute has an open upper end and a closed lower end. A support rod (102) is slidably arranged in the chute, and the upper end of the support rod (102) is fixedly connected with a support cross beam (2). Rope connecting frames (4) are fixedly connected to the upper parts of the left and right side surfaces of the guide frame (101). A fixed block (103) is fixedly connected to the bottom wall of the guide frame (101). There is a gap between the fixed block (103) and the support rod (102). A locking rod (104) extending in the up-down direction is hinged to the fixed block (103). A locking groove (105) is formed in the lower part of the support rod (102). The upper end of the locking rod (104) is fixedly connected with a limiting rod extending in the front-rear direction, and the limiting rod is slidably arranged inside the locking groove (105). The lower end of the guide frame (101) is fixedly connected with a mounting frame (106), and the mounting frame (106) is detachably connected with a mounting cross beam (5). The locking groove (105) can lock the locking rod (104).
6. The hoisting structure of the concrete module of the modular integrated building according to claim 5, characterized in that: The locking groove (105) includes a vertical chute and a locking block. The vertical chute is formed in the lower part of the front side surface of the support rod (102). A vertically extending locking block is fixedly connected in the vertical chute. The gap between the inner wall of the vertical chute and the outer side surface of the locking block forms a return chute, and the limiting rod can slide in the return chute. The top wall of the vertical chute extends downward to form a V-shaped protrusion, and the top of the locking block is provided with a V-shaped notch. The position of the V-shaped notch corresponds to the position of the V-shaped protrusion up and down. The gap between the position of the V-shaped notch and the V-shaped protrusion forms a V-shaped chute. When the limiting rod is at the lowest position in the V-shaped chute, the locking rod (104) locks the support rod (102).
7. The hoisting structure of the concrete module of the modular integrated building according to claim 1, characterized in that: Avoidance grooves (201) penetrating up and down are formed on the left and right side surfaces of the support cross beam (2). Pillars extending in the front-rear direction are fixedly connected in the avoidance grooves (201), and the outer surface of the pillars contacts the rope.
8. The modular integrated building concrete module hoisting structure according to claim 2, characterized in that: The locking member includes a locking hole (501). A plurality of locking holes (501) arranged in the left-right direction are formed on the upper surface of the mounting cross beam (5). A locking socket is formed on the bracket (601). A locking bolt (502) is inserted between the locking socket and the corresponding locking hole (501), and a nut is threadedly connected to the locking bolt (502).
9. The hoisting structure of the concrete module of the modular integrated building according to claim 1, wherein: A hook connecting frame (8) adapted to the hook is arranged on the connecting frame (3).