Steel pipe conveying device for deep foundation pit steel pipe well construction

The transportation device composed of a tripod and universal wheels solves the problem of low efficiency in steel pipe transportation during the construction of deep foundation pit steel pipe shafts, and realizes fast and labor-saving steel pipe transportation. It is suitable for the transportation of steel pipes of different diameters and lengths.

CN223327550UActive Publication Date: 2025-09-12CHINA CONSTRUCTION SIXTH ENGINEERING DIVISION CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202422676138.5
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-11-04
Publication Date
2025-09-12
Estimated Expiration
2034-11-04

AI Technical Summary

Technical Problem

In the existing technology, during the construction of deep foundation pit steel pipe shafts, the transportation and installation of steel pipes mainly rely on manual handling or transport vehicles, resulting in large manpower input and low efficiency.

Method used

A transport device consisting of a tripod and universal wheels is used to fix the steel pipe through a clamping structure, and two mobile frames are connected by ropes to achieve flexible transportation of the steel pipe.

Benefits of technology

It realizes the fast and labor-saving transportation of steel pipes, reduces manpower input, is suitable for the transportation of steel pipes of different diameters and lengths, and improves construction efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN223327550U_ABST
    Figure CN223327550U_ABST
Patent Text Reader

Abstract

The utility model belongs to the field of buildings, and particularly relates to a steel pipe conveying device for deep foundation pit steel pipe well construction, which comprises two moving frames symmetrically arranged front and back and a connecting rope for connecting the two moving frames, the movable frame comprises a triangular frame, a steel pipe clamping structure arranged on the triangular frame and universal wheels arranged below the movable frame. According to the steel pipe conveying device for deep foundation pit steel pipe well construction, the steel pipes are fixed through the clamping structures, the steel pipes are conveyed through the triangular frame composed of angle steel and the universal wheels below the triangular frame, time and labor are saved, rapid and flexible in-field conveying is achieved, and manpower input is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the field of construction, and in particular relates to a steel pipe transportation device for the construction of a deep foundation pit steel pipe well. Background Art

[0002] With the increase in underground space engineering construction in my country, underground engineering represented by subways will develop faster and faster, especially deep foundation pit support and excavation dewatering engineering construction technology represented by soft soil and water-rich areas have been rapidly and widely used. Especially for areas with abundant groundwater, deep foundation pit dewatering technology is crucial to foundation pit excavation. It can effectively lower the water level, ensure normal excavation of earthwork, lower the water level to the base without sudden surge, and ensure the normal construction of the station floor project.

[0003] Quality control of the dewatering well construction process is crucial for subway station foundation pit dewatering projects. The welding, installation, and lowering of the steel pipes after completion are particularly crucial. The steel pipes used in deep foundation pit dewatering wells require transportation and installation. This process typically involves manual handling or transport by truck, a labor-intensive and inefficient method. Utility Model Content

[0004] The purpose of the utility model is to overcome the defects in the prior art and provide a steel pipe transportation device for the construction of a deep foundation pit steel pipe well.

[0005] In order to achieve the above-mentioned purpose, the present invention adopts the following technical solutions:

[0006] A steel pipe transportation device for the construction of a deep foundation pit steel pipe shaft comprises two mobile frames symmetrically arranged front and back and a connecting rope connecting the two mobile frames; the mobile frames comprise a tripod, a steel pipe holding structure arranged on the tripod and a universal wheel arranged below the mobile frames.

[0007] The tripod is formed by connecting three angle steels, and every two adjacent angle steels are connected by using a triangular connecting steel plate.

[0008] Two bolt holes are respectively provided at the front and rear ends of each angle steel; corresponding mounting holes are provided on the triangular connecting steel plate; bolts are used to connect the bolt holes and the mounting holes to connect and fix the triangular connecting steel plate and the angle steel.

[0009] The angle steel of the tripod perpendicular to the transport direction is the first angle steel, and the others connected to the first angle steel are the second angle steel and the third angle steel; the clamping structure includes a connecting frame connecting the second angle steel and the third angle steel and two fixed clamping wheels arranged on the connecting piece.

[0010] A fixed clamping wheel is also provided on the first angle steel at a position corresponding to the fixed clamping wheel.

[0011] Rope connecting rings are provided on the first angle steel and the connecting frame.

[0012] The triangular connecting steel plate is provided with a connecting hole for connecting the universal wheel; the universal wheel includes a rotating shaft connected to the connecting hole, a mounting frame connected to the rotating shaft, a mounting shaft arranged on the mounting frame, and a wheel arranged on the mounting shaft.

[0013] Compared with the prior art, the beneficial effects of the present invention are:

[0014] The utility model of the steel pipe transportation device for deep foundation pit steel pipe well construction adopts a clamping structure to fix the steel pipe, and adopts a tripod composed of angle steel and universal wheels under the tripod to transport the steel pipe, which saves time and labor and realizes fast and flexible on-site transportation: reducing manpower input; as a preferred form, each mobile frame is provided with 4 fixed clamping wheels to fix the front and rear ends of the steel pipe, making transportation convenient, fast and labor-saving. At the same time, the front and rear two mobile frames can be adjusted according to the length of the steel pipe by ropes. The steel pipe and the rope combine the two mobile frames into a whole, and can be rotated in any direction by universal wheels to meet the transportation requirements within the construction site. The utility model of the steel pipe transportation device for deep foundation pit steel pipe well construction is more suitable for the transportation of steel pipe well pipes of different diameters and long-sized steel pipe well pipes, and has a wide range of applications. BRIEF DESCRIPTION OF THE DRAWINGS

[0015] Figure 1 This is a schematic diagram of the structure of the steel pipe transportation device for deep foundation pit steel pipe well construction of the utility model;

[0016] Figure 2-3 It is a side view and a front view of the steel pipe transportation device for the construction of a deep foundation pit steel pipe well according to the present invention. DETAILED DESCRIPTION

[0017] In order to enable those skilled in the art to better understand the technical solution of the present invention, the present invention will be further described in detail below with reference to the accompanying drawings and the best embodiment.

[0018] Figure 1-3 A steel pipe transportation device for deep foundation pit steel pipe well construction is shown, including two mobile frames arranged symmetrically in front and back and a connecting rope 7 (hereinafter referred to as the rope) connecting the two mobile frames; the mobile frame includes a tripod, a steel pipe holding structure arranged on the tripod and a universal wheel arranged under the mobile frame.

[0019] The tripod is made up of three angle steels 1 connected together, with each pair of adjacent angle steels connected by triangular connecting steel plates 2. Each angle steel has two bolt holes at its front and rear ends, respectively; the triangular connecting steel plates have corresponding mounting holes. Bolts 5 are used to connect the bolt holes and mounting holes to secure the triangular connecting steel plates and the angle steels.

[0020] In this application, a 40*40*5mm angle steel with a length of 40cm is used as an illustrative example. The triangular angle steel formed as a whole has better stability and does not deform during use.

[0021] The angle steel of the tripod perpendicular to the transport direction is the first angle steel, and the others connected to the first angle steel are the second angle steel and the third angle steel; the clamping structure includes a connecting frame connecting the second angle steel and the third angle steel and two fixed clamping wheels 4 arranged on the connecting piece.

[0022] The first angle steel is also provided with a fixed card wheel 4 at a position corresponding to the fixed card wheel. The fixed card wheels are symmetrically arranged in two groups of four along the central axis of the tripod, which can effectively fix the steel pipes placed on the tripod so that they do not move during transportation and effectively play a fixing role.

[0023] The first angle steel and the connecting frame are equipped with a rope connection ring 6. This U-shaped connection ring 6 connects the two mobile frames, forming a complete steel pipe transport device through the use of a connecting rope 7. The connecting rope 7 is pulled and moved by a handheld traction rope ring 11. The connecting rope has a diameter of no less than 10 mm, and its length can be adjusted to the length of the transported steel pipe. The traction rope is arranged in a circular ring, forming the traction rope ring 11, which further facilitates steel pipe transportation.

[0024] The triangular connecting steel plate is provided with a connecting hole for connecting the universal wheel; the universal wheel includes a rotating shaft 3 connected to the connecting hole, a mounting frame 9 connected to the rotating shaft, a mounting shaft 9 set on the mounting frame and a wheel 10 set on the mounting shaft. The rotating shaft 3 can rotate freely in the connecting hole to realize the rotation of the universal wheel in different directions.

[0025] From the above, it can be seen that the steel pipe transportation device for deep foundation pit steel pipe well construction of the present invention adopts a clamping structure to fix the steel pipe, and adopts a tripod composed of angle steel and universal wheels under the tripod to transport the steel pipe, which saves time and effort and realizes fast and flexible on-site transportation: reducing manpower input; as a preferred form, each mobile frame is provided with 4 fixed clamping wheels to fix the front and rear ends of the steel pipe, making transportation convenient, fast and labor-saving. At the same time, the front and rear two mobile frames can be adjusted according to the length of the steel pipe by ropes. The steel pipe and the rope combine the two mobile frames into a whole, and can be rotated in any direction by universal wheels to meet the transportation requirements within the construction site. The steel pipe transportation device for deep foundation pit steel pipe well construction of the present invention is more suitable for the transportation of steel pipe well pipes of different diameters and long-sized steel pipe well pipes, and has a wide range of applications.

[0026] The above contents are only preferred embodiments of the present invention. For ordinary technicians in this field, according to the concept of the present invention, there may be changes in the specific implementation methods and application scope. The content of this specification should not be understood as limiting the present invention.

Claims

1. A steel pipe transportation device for deep foundation pit steel pipe well construction, characterized in that: The mobile frame comprises two front-to-back symmetrically arranged mobile frames and a connecting rope connecting the two mobile frames; the mobile frame comprises a tripod, a steel pipe holding structure arranged on the tripod and a universal wheel arranged below the mobile frame.

2. The steel pipe transportation device for deep foundation pit steel pipe well construction according to claim 1 is characterized in that: The tripod is formed by connecting three angle steels, and every two adjacent angle steels are connected by using a triangular connecting steel plate.

3. The steel pipe transportation device for deep foundation pit steel pipe well construction according to claim 2, characterized in that: Two bolt holes are respectively provided at the front and rear ends of each angle steel; corresponding mounting holes are provided on the triangular connecting steel plate; bolts are used to connect the bolt holes and the mounting holes to connect and fix the triangular connecting steel plate and the angle steel.

4. The steel pipe transportation device for deep foundation pit steel pipe well construction according to claim 2, characterized in that: The angle steel of the tripod perpendicular to the transport direction is the first angle steel, and the others connected to the first angle steel are the second angle steel and the third angle steel; the clamping structure includes a connecting frame connecting the second angle steel and the third angle steel and two fixed clamping wheels arranged on the connecting frame.

5. The steel pipe transportation device for deep foundation pit steel pipe well construction according to claim 4, characterized in that: A fixed clamping wheel is also provided on the first angle steel at a position corresponding to the fixed clamping wheel.

6. The steel pipe transportation device for deep foundation pit steel pipe well construction according to claim 5, characterized in that: Rope connecting rings are provided on the first angle steel and the connecting frame.

7. The steel pipe transportation device for deep foundation pit steel pipe well construction according to claim 2, characterized in that: The triangular connecting steel plate is provided with a connecting hole for connecting the universal wheel; the universal wheel includes a rotating shaft connected to the connecting hole, a mounting frame connected to the rotating shaft, a mounting shaft arranged on the mounting frame, and a wheel arranged on the mounting shaft.