Pressing device capable of rapidly adjusting pressure supply
Through the cooperation of high-pressure plunger pump and electric ball valve, the problem of long time consumption in adjusting pressure supply of existing pressure-generating device is solved, fast and accurate pressure adjustment is achieved, and testing efficiency and equipment adaptability are improved.
Patent Information
- Application Number
- CN202422675576.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-11-04
- Publication Date
- 2025-09-12
- Estimated Expiration
- 2034-11-04
AI Technical Summary
Existing pressure-testing devices take a long time to quickly adjust the supply pressure, and the pressure changes are not precise and smooth enough, which may affect the accuracy of the test results and cause damage to the tested object.
A high-pressure plunger pump is used to provide high-pressure supply pressure, and the electric ball valve and pressure relief valve are used to quickly adjust the supply pressure. The design of sliding plates and elastic tubes can adapt to different equipment lengths to ensure the connectivity and adaptability of the device.
It achieves fast and precise adjustment of supply pressure, shortens the test cycle, improves test accuracy and equipment adaptability, and ensures project progress.
Smart Images

Figure CN223332564U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of regulating supply pressure, in particular to a pressure-pressing device capable of quickly regulating supply pressure. Background Art
[0002] A pressure test device is a device used to perform pressure tests on various containers, piping systems or equipment. The device mainly uses a power source (such as an electric pump or a pneumatic pump) to generate liquid (such as water, oil) or gas (such as nitrogen, compressed air) at a certain pressure. These media are driven by the device and transported into the target object to be tested. Its purpose is to verify the strength and sealing of the target object.
[0003] The adjustment mechanism of the pressure test device is relatively complicated. When the supply pressure needs to be changed in a short period of time, such as adjusting from a lower pressure to a higher pressure to test the performance of pipelines or containers under different pressure environments, it is often necessary to manually operate multiple valves or go through complex program settings. This process is time-consuming. In addition, when adjusting the supply pressure, some pressure test devices do not change the pressure accurately and smoothly, and the pressure may be instantly too high or too low. This not only affects the accuracy of the test results, but may even cause damage to the tested object.
[0004] Therefore, in order to address the problem that the above-mentioned existing pressure-pressing device cannot quickly adjust the supply pressure, a pressure-pressing device that can quickly adjust the supply pressure can be designed. The high-pressure plunger pump provides high pressure to the equipment to be pressure tested and the electric ball valve is opened to gradually release the pressure in the pressure relief valve, thereby achieving rapid adjustment of the supply pressure. Utility Model Content
[0005] In order to overcome the problem that the existing pressure-pressing device cannot quickly adjust the supply pressure.
[0006] The technical solution of the present utility model is: a pressure-beating device capable of quickly adjusting the supply pressure, comprising a workbench, a water tank being installed at the upper end of the workbench, a control valve 1 being installed at the right end of the water tank, a check valve 1 being installed at the right end of the control valve 1, a water supply pump being installed at the right end of the check valve 1, a safety filter being installed at the right end of the water supply pump, a support platform 1 being installed at the right side of the upper end of the workbench, a high-pressure plunger pump being installed at the upper end of the support platform 1, a check valve 2 being installed at the left end of the high-pressure plunger pump, a control valve 2 being installed at the lower end on the left side of the check valve 2, a check valve 3 being installed at the left end of the check valve 2, a pressure sensor being installed at the left side of the check valve 3, a support platform 2 being installed at the left end of the workbench, a sliding plate being installed at the upper end of the support platform 2, an electric ball valve being installed at the upper end of the sliding plate, and a pressure relief valve being installed at the left end of the electric ball valve.
[0007] Preferably, a high pressure plunger pump is used to provide high pressure to the equipment to be pressure tested. The outlet of the high pressure plunger pump is divided into two paths, one path enters the equipment to be pressure tested, and the other path connects to the regulating valve and returns to the water tank. Before the pressure test, the electric ball valve at the front end of the pressure relief valve is closed, and the water supply pump and the high-pressure plunger pump are started. By slowly closing the control valve 2 at the outlet of the high-pressure plunger pump, the outlet pressure of the high-pressure pump is continuously increased until the required test pressure is reached. After the pressure test is completed, the electric ball valve is opened and the pressure is gradually released through the pressure relief valve, so as to facilitate rapid pressure changes. By pulling the sliding plate left and right, the electric ball valve and the pressure relief valve are moved accordingly, and the corresponding positions of the four flange interfaces are changed. The connectivity of the device is ensured by the extension of the elastic tube, which is convenient for adjustment according to the length of the equipment to be pressure tested, thereby improving the adaptability of the device.
[0008] Preferably, the water supply pump and the lower end of the safety filter are connected through flange 1, and the upper end of the safety filter is provided with a flange interface 1.
[0009] Preferably, flange interface 2 is provided on both sides of the high-pressure plunger pump, and flange interface 2 and flange interface 1 are connected through a pipeline.
[0010] Preferably, a water outlet pipe is provided at the lower end of the second control valve, and the lower end of the water outlet pipe extends to the inner side of the water tank.
[0011] Preferably, the left end of the check valve three is installed with a control valve three, the upper end of the control valve three and the pressure sensor, and the left end of the control valve three is installed with a flange interface three.
[0012] Preferably, a slide groove is provided at the upper end of the support platform 2, a slider is provided at the lower end of the sliding plate, the slide groove and the slider are slidably connected, and a flange interface 4 is installed at the right end of the electric ball valve.
[0013] Preferably, a transfer box 1 is installed at the left end of the pressure relief valve, an elastic tube is installed at the lower end of the transfer box 1, a transfer box 2 is installed at the lower end of the elastic tube, the transfer box 2 is fixedly connected to the workbench, a drain pipe is provided at the right end of the transfer box 2, and the right end of the drain pipe extends to the inside of the water tank.
[0014] Beneficial effects of the utility model:
[0015] 1. This pressure device, which can quickly adjust the supply pressure, provides high pressure to the equipment to be pressure tested through a high-pressure plunger pump. The outlet of the high-pressure plunger pump is divided into two paths, one for the equipment to be pressure tested, and the other connected to the regulating valve and returned to the water tank. Before the pressure test, the electric ball valve in front of the pressure relief valve is closed, and the water pump and the high-pressure plunger pump are started. By slowly closing the second control valve at the outlet of the high-pressure plunger pump, the outlet pressure of the high-pressure pump is continuously increased until the required test pressure is reached. After the pressure test is completed, the electric ball valve is opened and the pressure is gradually released through the pressure relief valve, which facilitates the rapid change of pressure and can efficiently detect the pressure resistance and sealing of pipelines under different pressure conditions, greatly shortening the test cycle and improving the project progress.
[0016] 2. This pressure device, which can quickly adjust the supply pressure, moves the electric ball valve and the pressure relief valve by pulling the sliding plate left and right, changing the corresponding positions of the four flange interfaces. The connection of the device is ensured by the extension of the elastic tube, which is convenient for adjustment according to the length of the equipment to be pressure tested, thereby improving the adaptability of the device. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] Figure 1 The figure shows the overall structure of the pressure device that can quickly adjust the supply pressure of the utility model. Figure 1 ;
[0018] Figure 2 The figure shows the overall structure of the pressure device that can quickly adjust the supply pressure of the utility model. Figure 2 ;
[0019] Figure 3 Shown is a schematic diagram of the structure of a safety filter with a pressure relief device capable of quickly adjusting the supply pressure of the present invention;
[0020] Figure 4 Shown is a schematic diagram of the structure of the second support platform of the pressing device of the present invention that can quickly adjust the pressure supply.
[0021] Explanation of the accompanying symbols: 1. Workbench; 2. Water tank; 3. Control valve 1; 4. Check valve 1; 5. Water pump; 6. Safety filter; 61. Flange 1; 62. Flange interface 1; 7. Support platform 1; 71. High-pressure plunger pump; 72. Flange interface 2; 8. Check valve 2; 9. Control valve 2; 91. Water outlet pipe; 10. Check valve 3; 11. Pressure sensor; 111. Control valve 3; 112. Flange interface 3; 12. Support platform 2; 121. Slide; 13. Sliding plate; 131. Sliding block; 14. Electric ball valve; 141. Flange interface 4; 15. Pressure relief valve; 151. Adapter box 1; 152. Elastic tube; 153. Adapter box 2; 154. Drain pipe. DETAILED DESCRIPTION
[0022] The present invention will be further described below with reference to the accompanying drawings and embodiments.
[0023] See also Figure 1-Figure 4The utility model provides an embodiment: a pressure device capable of quickly adjusting the supply pressure, comprising a workbench 1, a water tank 2 is installed on the upper end of the workbench 1, a control valve 3 is installed on the right end of the water tank 2, a check valve 4 is installed on the right end of the control valve 3, a water supply pump 5 is installed on the right end of the check valve 4, a safety filter 6 is installed on the right end of the water supply pump 5, a support platform 7 is installed on the right side of the upper end of the workbench 1, a high-pressure plunger pump 71 is installed on the upper end of the support platform 7, a check valve 2 8 is installed on the left end of the high-pressure plunger pump 71, a control valve 2 9 is installed on the lower end of the left side of the check valve 2 8, a check valve 3 10 is installed on the left end of the check valve 3 10, and a pressure filter 6 is installed on the left side of the check valve 3 10. Force sensor 11, support platform 2 12 is installed on the left end of the workbench 1, and a sliding plate 13 is installed on the upper end of support platform 2 12, and an electric ball valve 14 is installed on the upper end of the sliding plate 13. A pressure relief valve 15 is installed on the left end of the electric ball valve 14. First, inject the test solution into the water tank 2, adjust the sliding plate 13 according to the size of the device to be pressurized, and then fix the device to be pressurized, open the control valve 1 3, and then start the water pump 5. The test solution is injected into the pipe inside the device and the device to be pressurized through the safety filter 6, and then close the control valve 2 9 and the electric ball valve 14, and use the high-pressure plunger pump 71 to provide pressure to the liquid. The pressure is displayed by the pressure sensor 11.
[0024] See also Figure 1 , Figure 2 and Figure 3 In this embodiment, the water supply pump 5 and the lower end of the safety filter 6 are connected by a flange 1 61, the upper end of the safety filter 6 is provided with a flange interface 1 62, and flange interfaces 2 72 are provided on both sides of the high-pressure plunger pump 71. The flange interface 2 72 and the flange interface 1 62 are connected through a pipeline. The lower end of the control valve 2 9 is provided with a water outlet pipe 91. The lower end of the water outlet pipe 91 extends to the inner side of the water tank 2. The high-pressure plunger pump 71 provides high pressure to the equipment to be pressure tested. The outlet of the high-pressure plunger pump 71 is divided into two ways, one of which enters the equipment to be pressure tested. , connect the regulating valve all the way back to the water tank 2, close the electric ball valve 14 at the front end of the pressure relief valve 15 before the pressure test, start the water pump 5 and the high-pressure plunger pump 71, and slowly close the control valve 2 9 at the outlet of the high-pressure plunger pump 71 to make the high-pressure pump outlet pressure continue to rise until the required test pressure. After the pressure test is completed, open the electric ball valve 14 and gradually release the pressure through the pressure relief valve 15, which is convenient for realizing rapid pressure change. It can efficiently detect the pressure resistance and sealing of the pipeline under different pressure conditions, greatly shorten the test cycle, and improve the project progress.
[0025] See also Figure 1 , Figure 2 and Figure 4The left end of the check valve 10 is equipped with a control valve 3 111, the upper end of the control valve 3 111 and the pressure sensor 11, the left end of the control valve 3 111 is equipped with a flange interface 3 112, the upper end of the support platform 2 12 is provided with a slide groove 121, the lower end of the sliding plate 13 is provided with a slider 131, the slide groove 121 and the slider 131 are slidably connected, the right end of the electric ball valve 14 is equipped with a flange interface 4 141, the left end of the pressure relief valve 15 is equipped with an adapter box 151, the lower end of the adapter box 151 is equipped with an elastic tube 152, the elastic tube A second adapter box 153 is installed at the lower end of 152, and the second adapter box 153 is fixedly connected to the workbench 1. A drain pipe 154 is provided at the right end of the second adapter box 153, and the right end of the drain pipe 154 extends to the inner side of the water tank 2. When fixing the equipment to be pressure tested, the sliding plate 13 is pulled left and right to make the electric ball valve 14 and the pressure relief valve 15 move accordingly, changing the corresponding position of the flange interface four 141, and ensuring the connectivity of the device through the extension of the elastic tube 152, which is convenient for adjustment according to the length of the equipment to be pressure tested, thereby improving the adaptability of the device.
[0026] When working, first inject the test solution into the water tank 2, adjust the sliding plate 13 according to the size of the device to be pressurized, and move the sliding plate 13 left and right to move the electric ball valve 14 and the pressure relief valve 15 accordingly, changing the corresponding position of the flange interface 4 141. The connection of the device is ensured by the extension of the elastic tube 152, and then fix the device to be pressurized, open the control valve 1 3, and then start the water pump 5. The test solution is injected into the pipeline inside the device and the device to be pressurized through the security filter 6, and then close the control valve 2 9 and the electric ball valve 14. Use the high-pressure plunger pump 71 to provide pressure to the liquid, and the pressure is displayed by the pressure sensor 11. As shown, the high-pressure plunger pump 71 provides high pressure to the equipment to be pressure tested. The outlet of the high-pressure plunger pump 71 is divided into two paths, one path enters the equipment to be pressure tested, and the other path connects to the regulating valve and returns to the water tank 2. Before the pressure test, the electric ball valve 14 at the front end of the pressure relief valve 15 is closed, and the water supply pump 5 and the high-pressure plunger pump 71 are started. By slowly closing the control valve 29 at the outlet of the high-pressure plunger pump 71, the outlet pressure of the high-pressure pump is continuously increased until the required test pressure is reached. After the pressure test is completed, the electric ball valve 14 is opened and the pressure is gradually released through the pressure relief valve 15, which facilitates the rapid change of pressure and can efficiently detect the pressure resistance and sealing of the pipeline under different pressure conditions, greatly shortening the test cycle and improving the project progress.
[0027] Through the above steps, the high-pressure plunger pump 71 provides high pressure to the equipment to be pressure tested. Before the pressure test, the electric ball valve 14 at the front end of the pressure relief valve 15 is closed, the water pump 5 and the high-pressure plunger pump 71 are started, and the control valve 2 9 at the outlet of the high-pressure plunger pump 71 is slowly closed to make the outlet pressure of the high-pressure pump continue to rise until the required test pressure. After the pressure test is completed, the electric ball valve 14 is opened and the pressure is gradually released through the pressure relief valve 15, so as to facilitate the rapid change of pressure and efficiently detect the pressure resistance and sealing of the pipeline under different pressure conditions, so as to solve the problem that the existing pressure testing device cannot quickly adjust the supply pressure.
Claims
1. A pressing device capable of quickly adjusting the supply pressure, comprising a workbench (1), characterized in that: A water tank (2) is installed at the upper end of the workbench (1), a control valve (3) is installed at the right end of the water tank (2), a check valve (4) is installed at the right end of the control valve (3), a water supply pump (5) is installed at the right end of the check valve (4), a safety filter (6) is installed at the right end of the water supply pump (5), a support platform (7) is installed at the right end of the upper end of the workbench (1), a high-pressure plunger pump (71) is installed at the upper end of the support platform (7), and a check valve (7) is installed at the left end of the high-pressure plunger pump (71). Valve 2 (8), the lower end of the left side of check valve 2 (8) is installed with control valve 2 (9), the left end of check valve 2 (8) is installed with check valve 3 (10), the left side of check valve 3 (10) is installed with pressure sensor (11), the left end of workbench (1) is installed with support platform 2 (12), the upper end of support platform 2 (12) is installed with sliding plate (13), the upper end of sliding plate (13) is installed with electric ball valve (14), and the left end of electric ball valve (14) is installed with pressure relief valve (15).
2. The pressure-suppressing device capable of rapidly adjusting the supply pressure according to claim 1, characterized in that: The water supply pump (5) and the lower end of the safety filter (6) are connected through a flange 1 (61), and the upper end of the safety filter (6) is provided with a flange interface 1 (62).
3. The pressure-suppressing device capable of rapidly adjusting the supply pressure according to claim 1, characterized in that: Flange interface 2 (72) is provided on both sides of the high-pressure plunger pump (71), and flange interface 2 (72) and flange interface 1 (62) are communicated through a pipeline.
4. The pressure-suppressing device capable of rapidly adjusting the supply pressure according to claim 1, characterized in that: A water outlet pipe (91) is provided at the lower end of the second control valve (9), and the lower end of the water outlet pipe (91) extends to the inner side of the water tank (2).
5. The pressure-suppressing device capable of rapidly adjusting the supply pressure according to claim 1, characterized in that: The left end of the check valve three (10) is equipped with a control valve three (111), the upper end of the control valve three (111) and the pressure sensor (11), and the left end of the control valve three (111) is equipped with a flange interface three (112).
6. The pressure-suppressing device capable of rapidly adjusting the supply pressure according to claim 1, characterized in that: A chute (121) is provided at the upper end of the supporting platform (12), a slider (131) is provided at the lower end of the sliding plate (13), the chute (121) and the slider (131) are slidably connected, and a flange interface (141) is installed at the right end of the electric ball valve (14).
7. The pressing device capable of rapidly adjusting the supply pressure according to claim 1, characterized in that: The left end of the pressure relief valve (15) is provided with a first adapter box (151), the lower end of the first adapter box (151) is provided with an elastic tube (152), the lower end of the elastic tube (152) is provided with a second adapter box (153), the second adapter box (153) is fixedly connected to the workbench (1), the right end of the second adapter box (153) is provided with a drain pipe (154), and the right end of the drain pipe (154) extends to the inner side of the water tank (2).