Detachable support hanger suitable for vertical pipeline of steel structure factory building
By designing detachable supports and hangers, fixing steel clamps to steel column flanges with bolts, and combining angle steels and clips for connection, the problems of inconvenient installation and component damage of existing supports and hangers are solved, efficient installation and convenient maintenance are achieved, and the utilization efficiency and life of vertical pipelines in steel structure workshops are improved.
Patent Information
- Application Number
- CN202423064664.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-12-12
- Publication Date
- 2025-09-26
- Estimated Expiration
- 2034-12-12
AI Technical Summary
Existing supports and hangers are inconvenient to install in steel structure workshops and may have adverse effects on component performance, especially welded and threaded connections, which lead to complex construction and damage to components.
Bolts are used to fix the steel clamp block and the steel column flange, and the angle steel and the clamp are connected by bolts. It is designed as a detachable support bracket, including components such as the first clip, right-angle support block, L-shaped extension block and nut, to achieve flexible adjustment and installation.
It improves installation efficiency and convenience of subsequent maintenance, reduces maintenance costs, and ensures the stability and service life of components.
Smart Images

Figure CN223388157U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of steel structure buildings, in particular to a detachable support and hanger suitable for vertical pipelines in steel structure workshops. Background Art
[0002] Energy conservation and emission reduction in the construction industry is crucial to the realization of my country's "dual carbon" goals. The natural advantages of steel structure buildings, such as short construction period, good seismic resistance, and green environmental protection, will be further highlighted. Among them, the number of factory buildings accounts for the largest proportion. Due to the high height of steel structure factory buildings, it brings difficulties to the installation and subsequent maintenance of vertical pipelines. At present, most of the pipeline supports and hangers are welded and threaded connections. On the one hand, it will increase the workload and make construction inconvenient. On the other hand, it will have an adverse effect on the local performance of components such as steel columns.
[0003] Traditional connection forms between supports and hangers and components such as steel columns are mostly weld connections and threaded connections, which will have an adverse effect on the local performance of the components. To address this problem, a new connection method is proposed, which uses bolts to compress and fix the steel clamps to the left and right flanges of the steel columns. The bolts only stay on the surface of the steel column flanges and will not damage the flanges. The supporting parts at both ends are welded to the clamp steels on both sides by angle steel, and the upper horizontal angle steel and the clamps for fixing the vertical pipes are bolted, which is convenient for installation and subsequent maintenance. Summary of the Invention
[0004] The technical problem to be solved by the present invention is that: the existing technology has the disadvantage that the existing fixed type of support and hanger is not convenient for installation. For this reason, we propose a detachable support and hanger suitable for vertical pipelines in steel structure workshops.
[0005] In order to achieve the above-mentioned purpose, the present application adopts the following technical solution: a detachable support bracket suitable for vertical pipes in steel structure factories, comprising a steel structure body, wherein first clips are installed at both ends of the top of the steel structure body, the inner wall of one side of the first clip is connected to a first bolt through a thread, and the other side of the first clip is fixedly connected to a right-angle support block, a first L-shaped extension block is installed on one side of the right-angle support block, and a second bolt is connected to the bottom of the right-angle support block through a thread, and one end of the second bolt passes through one side of the first L-shaped extension block and is connected to a first nut through a thread.
[0006] Preferably, a first sliding groove is provided on one side of the inner wall of the first L-shaped extension block, and the surface of the second bolt is slidably connected to the inner wall of the first sliding groove.
[0007] Preferably, one side of the inner wall of the first L-shaped extension block is connected to a third bolt via a thread, and one end of the third bolt is connected to the first clamp via a thread.
[0008] Preferably, the first buckle is U-shaped.
[0009] Preferably, the first buckle is made of alloy material.
[0010] Preferably, a first protective pad is installed on one side of the inner wall of the first buckle.
[0011] Preferably, the surface of the first clamping member is provided with first anti-slip grooves.
[0012] Technical effects and advantages of this utility model:
[0013] In the present utility model, the utility model relates to the technical field of steel structure construction, and discloses a detachable support and hanger suitable for vertical pipes in steel structure factories, including a steel structure body, and first clips are installed at both ends of the top of the steel structure body. The detachable support and hanger suitable for vertical pipes in steel structure factories, the user fixes the position of the bracket on the surface of the steel structure body, and by adjusting the tightness of the first bolt, can easily and accurately adjust and move the position of the steel structure body. This adjustment method allows the equipment to flexibly adapt to different installation requirements, thereby improving the overall use efficiency. After the device is put into use, the subsequent maintenance of the equipment also becomes very convenient and quick. The user can quickly carry out necessary inspections and maintenance work to ensure the stable operation of the equipment. This design not only improves work efficiency, but also reduces maintenance costs, making it easier for users to operate the device. BRIEF DESCRIPTION OF THE DRAWINGS
[0014] Figure 1 This is a schematic diagram of the main structure of the utility model;
[0015] Figure 2 This is a vertical cross-sectional view of the first L-shaped extension block of the present invention;
[0016] Figure 3 This is a top view of the first L-shaped extension block of the present invention;
[0017] Figure 4 This is a bottom view of the first buckle of the present utility model;
[0018] Figure 5 This is a bottom-view internal cross-sectional view of the first buckle of the present invention.
[0019] Legend: 1. Steel structure body; 2. First clip; 3. First bolt; 4. Right-angle support block; 5. First L-shaped extension block; 6. Second bolt; 7. First nut; 8. First slide groove; 9. Third bolt; 10. First clamp; 11. First protective pad; 12. First anti-slip pattern. DETAILED DESCRIPTION
[0020] The present invention will now be described in further detail with reference to the accompanying drawings and preferred embodiments. These drawings are simplified schematic diagrams that only illustrate the basic structure of the present invention in a schematic manner, and therefore only show components related to the present invention.
[0021] Reference Figure 1 - Figure 5As shown, the utility model provides a technical solution: a detachable support and hanger suitable for vertical pipes in steel structure factories, including a steel structure body 1, first clips 2 are installed at both ends of the top of the steel structure body 1, the inner wall of one side of the first clip 2 is connected to a first bolt 3 through a thread, the other side of the first clip 2 is fixedly connected to a right-angle support block 4, one side of the right-angle support block 4 is installed with a first L-shaped extension block 5, the bottom of the right-angle support block 4 is connected to a second bolt 6 through a thread, one end of the second bolt 6 passes through one side of the first L-shaped extension block 5 and is connected to a first nut 7 through a thread, when the user places the first bolts 3 at both ends at the specified positions of the steel structure body 1 through the first L-shaped extension block 5, and tightens the first bolt 3 to make one side of the first clip 2 The first bolt 3 is gradually moved inwards, so that the first bolt 3 clamps the steel structure body 1 on the inner wall of the first clip 2, so that the position of the bracket on the surface of the steel structure body 1 is fixed. By adjusting the tightness of the first bolt 3, the position of the steel structure body 1 can be easily and accurately adjusted and moved. This adjustment method allows the equipment to flexibly adapt to different installation requirements, thereby improving the overall use efficiency. This adjustment mechanism allows the user to directly replace the original support bracket without the need for a complicated installation process, which greatly simplifies the operation steps. After the device is put into use, the subsequent maintenance of the equipment also becomes very convenient and quick. The user can quickly carry out necessary inspections and maintenance work to ensure the stable operation of the equipment. This design not only improves work efficiency, but also reduces maintenance costs. The first L-shaped extension block 5 is provided with a first slide groove 8 on one side of the inner wall of the first L-shaped extension block 5, and the surface of the second bolt 6 is slidably connected to the inner wall of the first slide groove 8. By loosening the second bolt 6, the spacing between the right-angle support blocks 4 at both ends can be adjusted through the first slide groove 8 to correspond to the steel structure bodies 1 of different specifications for installation. By adjusting the first L-shaped extension block 5, the support and hanger can adapt to steel structure bodies 1 of different specifications, so that the adaptability of the device is improved. One side of the inner wall of the first L-shaped extension block 5 is connected to the third bolt 9 by a thread, and one end of the third bolt 9 is connected to the first clamping member 10 by a thread. The user installs the first clamping member 10 through the third bolt 9 on one side of the first L-shaped extension block 5, so that the user can The position of the bracket can be precisely adjusted by the first clamp 10, and the position of the bolt hole between the third bolt 9 and the first clamp 10 can be moved and adjusted to meet the needs of vertical pipes with different diameters. The shape of the first clamp 2 is U-shaped. When the user installs the first clamp 2 into the two ends of the steel structure body 1, the U-shape of the first clamp 2 is pressed and fixed to the left and right flanges of the steel structure body 1, and will not cause local damage to the flanges of the steel structure body 1. The material of the first clamp 2 is alloy material. The material of the first clamp 2 adopts high-quality alloy material. This material has extremely high strength and durability. After the first clamp 2 is installed on the steel structure body 1, the first clamp 2 can maintain its structural integrity and stability during long-term use.This effectively increases the lifespan of the device. A first protective pad 11 is installed on one side of the inner wall of the first clip 2. When the user installs the first bolt 3 at both ends of the steel structure body 1, the first protective pad 11 installed on the inner wall of the first clip 2 forms a barrier between the inner wall of the first clip 2 and the surface of the steel structure body 1, preventing the first clip 2 from abrading the surface of the steel structure body 1 during movement. The surface of the first clamp 10 is provided with a first anti-slip groove 12. By installing the first anti-slip groove 12 on the first slide 8, the user can adjust the position of the support bracket without any accidents while holding the first slide 8, thereby improving the safety of the device during use.
[0022] Working principle:
[0023] In step one, the user installs the first clip 2 on both ends of the steel structure body 1, and uses its U-shaped structure to press and fix it with the left and right flanges of the steel structure body 1 without causing local damage. Then, the first bolts 3 at both ends are placed in the specified position through the first L-shaped extension block 5, and the first bolt 3 is tightened so that the first clip 2 clamps the steel structure body 1, thereby fixing the bracket position. When the support bracket position needs to be adjusted, the second bolt 6 is loosened, and the distance between the right-angle support blocks 4 at both ends is adjusted through the first slide groove 8 to adapt to steel structure bodies 1 of different specifications. When adjusting the bracket position, the third bolt 9 and the first clip 10 are used for fine-tuning to meet the needs of vertical pipes of different diameters. The design of the first protective pad 11 and the first anti-slip groove 12 ensures the safety of the user when installing the equipment and the protection of the steel structure body 1, thereby improving the service life of the device and the convenience of operation.
[0024] Finally, it should be noted that the above is only a preferred embodiment of the present invention and is not intended to limit the present invention. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art can still modify the technical solutions described in the aforementioned embodiments or make equivalent replacements for some of the technical features therein. Any modifications, equivalent replacements, improvements, etc. made within the spirit and principles of the present invention should be included in the scope of protection of the present invention.
Claims
1. A detachable support and hanger for vertical pipes in a steel structure factory building, comprising a steel structure body (1), characterized in that: Both ends of the top of the steel structure body (1) are equipped with first clips (2), the inner wall of one side of the first clip (2) is connected to a first bolt (3) through a thread, the other side of the first clip (2) is fixedly connected to a right-angle support block (4), one side of the right-angle support block (4) is equipped with a first L-shaped extension block (5), the bottom of the right-angle support block (4) is connected to a second bolt (6) through a thread, and one end of the second bolt (6) passes through one side of the first L-shaped extension block (5) and is connected to a first nut (7) through a thread.
2. The detachable support and hanger for vertical pipes in steel structure workshops according to claim 1 is characterized in that: A first sliding groove (8) is provided on one side of the inner wall of the first L-shaped extension block (5), and the surface of the second bolt (6) is slidably connected to the inner wall of the first sliding groove (8).
3. The detachable support and hanger for vertical pipes in steel structure workshops according to claim 1 is characterized in that: One side of the inner wall of the first L-shaped extension block (5) is connected to a third bolt (9) via a thread, and one end of the third bolt (9) is connected to a first clamping member (10) via a thread.
4. The detachable support and hanger for vertical pipes in steel structure workshops according to claim 1 is characterized in that: The first buckle (2) is U-shaped.
5. The detachable support and hanger for vertical pipes in steel structure workshops according to claim 1 is characterized in that: The first buckle (2) is made of alloy material.
6. The detachable support and hanger for vertical pipes in steel structure workshops according to claim 1 is characterized by: A first protective pad (11) is installed on one side of the inner wall of the first buckle (2).
7. The detachable support and hanger for vertical pipes in steel structure workshops according to claim 3 is characterized by: A first anti-slip pattern (12) is provided on the surface of the first clamping member (10).