Pipe cutting equipment for constructional engineering installation

By designing pipe cutting equipment with automatic feeding and fixing mechanisms, the problem of low efficiency in manual material handling and feeding has been solved, realizing the automation and efficient cutting of pipe processing.

CN223670294UActive Publication Date: 2025-12-16GANSU THIRD CONSTR GROUP CORP
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202520068649.0
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-01-13
Publication Date
2025-12-16
Estimated Expiration
2035-01-13

AI Technical Summary

Technical Problem

The existing pipe processing requires manual handling and loading, which increases labor costs and reduces work efficiency.

Method used

Design a pipe cutting device, including a feeding mechanism and a pipe cutting mechanism. The device uses a cylinder to drive a piston rod to move a rocker block and a partition plate to achieve automatic pipe feeding. The device uses an electric push rod and a compression ring to fix the pipe and then cuts it in conjunction with the pipe cutting assembly.

Benefits of technology

It enables automatic pipe feeding, reduces labor requirements, improves work efficiency, and enhances the stability and precision of cutting.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN223670294U_ABST
    Figure CN223670294U_ABST
Patent Text Reader

Abstract

The utility model discloses a pipe cutting device for constructional engineering installation, and relates to the technical field of constructional engineering, the pipe cutting device comprises a pipe cutting device body, the pipe cutting device body comprises a processing table, the left side of the top of the processing table is fixedly provided with a bearing plate, and the top of the processing table is provided with a pipeline body. The air cylinder is arranged to drive the piston rod to stretch out and draw back and push the swing block to swing left and right, so that the first partition plate and the second partition plate move up and down in a staggered mode, and when the first partition plate moves downwards, a pipeline can be conveniently retained at the top of the machining table; when the second partition plate moves downwards, the second partition plate can be inserted between the last but one pipeline and the last but one pipeline, the last but one pipeline and the pipeline in front of the second partition plate can be conveniently retained on the machining table, at the moment, the first partition plate moves upwards, the last pipeline loses blocking, then the last pipeline rolls rightwards along the inclination angle of the machining table, and the feeding purpose is achieved. Labor force can be reduced, and working efficiency is further improved.
Need to check novelty before this filing date? Find Prior Art

Description

TECHNICAL FIELD

[0001] The utility model relates to the technical field of building engineering, specifically relates to a pipe cutting equipment for building engineering installation. BACKGROUND

[0002] Building engineering refers to people's production, residence, study, public activities and so on, constructs all kinds of housing construction and its auxiliary facilities, and the installation of line, pipeline, equipment matched therewith. Among them, pipeline is one of the most common materials in building engineering, before installing and laying pipeline, needs to utilize pipe cutting equipment to process it.

[0003] The existing pipeline needs manual feeding when processing and cutting, which is inconvenient, increases labor and reduces work efficiency. Therefore, we provide a pipe cutting equipment for building engineering installation. UTILITY MODEL CONTENT

[0004] The utility model is to provide a pipe cutting equipment for building engineering installation to solve the problems in the above background technology.

[0005] To solve the above technical problems, the utility model adopts the technical scheme of:

[0006] A pipe cutting equipment for building engineering installation, comprising a pipe cutting equipment body, the pipe cutting equipment body comprises a processing table, a bearing plate is fixedly installed on the top left side of the processing table, and a pipeline body is arranged on the top of the processing table.

[0007] The top of the processing table is provided with a feeding mechanism, and the right side of the processing table is provided with a pipe cutting mechanism.

[0008] The feeding mechanism comprises a support bracket fixedly installed on the top of the processing table and located on the right side of the bearing plate.

[0009] Further improvement of the utility model technical scheme is that limit grooves are formed on the front end of the support bracket, a connecting plate is rotatably installed on the top of the bearing plate, a gas cylinder is fixedly installed on the right side of the connecting plate, and the limit grooves can limit the up-down movement of the two groups of partition plates.

[0010] Further improvement of the utility model technical scheme is that a piston rod is arranged on the output end of the gas cylinder, and a rotating shaft is fixedly installed on the other end of the piston rod.

[0011] Further improvement of the utility model technical scheme is that a swing block is rotatably connected to the inner shaft of the rotating shaft, and a partition plate one is movably connected to the right side of the swing block.

[0012] The further improvement in the utility model technical scheme lies in that: the left side interior of the swing block is movably connected with a partition plate two, and the other end of the partition plate one and the partition plate two all penetrates through the limiting groove and extends at the right side top of the processing table.

[0013] The further improvement in the utility model technical scheme lies in that: the pipe cutting mechanism comprises a placing groove arranged at one end of the right side of the processing table, limiting vertical rods are fixedly installed on the two sides of the right end of the processing table, a pipe cutting assembly is arranged on the top of the limiting vertical rod, and the placing groove can clasp and roll the pipeline.

[0014] The further improvement in the utility model technical scheme lies in that: an electric push rod is fixedly sleeved on the outer surface of the limiting vertical rod, an extrusion ring is fixedly connected to the other end of the electric push rod, the two groups of extrusion rings are convenient to abut on the top of the two ends of the pipeline to be cut, can extrude and fix the pipeline, promote cutting stability, further improve cutting accuracy, and reduce the waste rate.

[0015] Due to the adoption of the above technical scheme, the utility model has the following technical progress compared with the prior art:

[0016] 1. The pipe cutting equipment for building engineering installation is provided, the piston rod is driven to extend and retract by the cylinder, the swing block is pushed left and right to swing, the partition plate one and the partition plate two are moved up and down, the two plate bodies are moved staggeredly, the pipeline is retained on the top of the processing table when the partition plate one moves down, the partition plate two moves up at this time, the partition plate two is inserted between the penultimate pipeline and the last pipeline when the partition plate two moves down, the penultimate pipeline and the pipeline in front are retained on the processing table, the last pipeline loses the block and rolls to the right side along the inclination angle of the processing table when the partition plate one moves up, the purpose of feeding is achieved, the labor can be reduced, and the work efficiency is further improved.

[0017] 2. The pipe cutting equipment for building engineering installation is provided, the pipeline is clamped and rolled by the placing groove, the extrusion ring is abutted at the two ends of the pipeline by the starting of the two groups of electric push rods, the pipeline is fixed, the cutting stability is promoted, and the cutting accuracy rate is further promoted. BRIEF DESCRIPTION OF DRAWINGS

[0018] Figure 1 It is a structural schematic view of the utility model;

[0019] Figure 2 It is a processing table structural schematic view of the utility model;

[0020] Figure 3 It is a supporting bracket structural schematic view of the utility model;

[0021] Figure 4The placing groove structure schematic view of the utility model discloses.

[0022] Figure 5 The utility model discloses Figure 4 A enlarged structure schematic view.

[0023] In the drawing: 1, cutting pipe equipment ontology;2, processing platform;21, placing groove;22, limit vertical rod;23, cutting pipe assembly;24, electric push rod;25, extrusion ring;3, bearing plate;31, support support;32, limit groove;33, connecting plate;34, air cylinder;35, piston rod;36, rotating shaft;37, swing block;38, partition board one;39, partition board two;4, pipe ontology. Specific embodiments

[0024] The technical scheme in the embodiments of the utility model will be described clearly and completely below in conjunction with the drawings in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by those skilled in the art without creative labor fall within the scope of the utility model.

[0025] Embodiment 1

[0026] As Figures 1-5 The utility model provides a cutting pipe equipment for building engineering installation, including cutting pipe equipment ontology 1, cutting pipe equipment ontology 1 includes processing platform 2, and the top left side of processing platform 2 is fixedly installed with bearing plate 3, and the top of processing platform 2 is provided with pipe ontology 4, and the top of processing platform 2 is provided with feeding mechanism, and the right side one end of processing platform 2 is provided with cutting pipe mechanism, and cutting pipe mechanism includes placing groove 21 set up in the right side one end of processing platform 2, and the right end both sides of processing platform 2 are all fixedly installed with limit vertical rod 22, and the top of limit vertical rod 22 is provided with cutting pipe assembly 23, and the outer surface of limit vertical rod 22 is fixedly sleeved with electric push rod 24, and the other end of electric push rod 24 is fixedly connected with extrusion ring 25.

[0027] Further, the pipe enters the inside of placing groove 21, is urged extrusion ring 25 to contact at both ends of the pipe by the start of two groups of electric push rod 24, fixes, and cooperates cutting pipe assembly 23 and carries out cutting processing to the pipe.

[0028] Embodiment 2

[0029] As Figures 1-5As shown, on the basis of embodiment 1, the utility model provides a technical scheme: preferably, the feeding mechanism includes the support support 31 that is fixedly installed on the top of processing table 2 and is located on the right side of bearing plate 3, the front end both sides of support support 31 are all provided with the limiting slot 32, the top of bearing plate 3 is rotatably installed with the connecting plate 33, the right side of connecting plate 33 is fixedly installed with the pneumatic cylinder 34, the output end of pneumatic cylinder 34 is provided with the piston rod 35, the other end of piston rod 35 is fixedly installed with the pivot 36, the inside axle of pivot 36 is rotatably connected with the swing block 37, the right side inside of swing block 37 is movably connected with the partition plate one 38, the left side inside of swing block 37 is movably connected with the partition plate two 39, and the other end of partition plate one 38 and partition plate two 39 all penetrates limiting slot 32 and extends in the right side top of processing table 2.

[0030] Further, the output end of pneumatic cylinder 34 drives piston rod 35 to stretch and retract, piston rod 35 stretches and retracts and pushes swing block 37 to swing left and right, further drives partition plate one 38 and partition plate two 39 to move up and down, the two plate bodies stagger, when partition plate one 38 moves down, it is convenient to retain the pipeline on the top of processing table 2, at this time, partition plate two 39 moves up, when partition plate two 39 moves down, it is inserted between the penultimate pipeline and the last pipeline, it is convenient to retain the penultimate pipeline and the front pipeline on processing table 2, at this time, partition plate one 38 moves up, and the last pipeline loses the block, and then rolls to the right side along the inclination angle of processing table 2.

[0031] Now, the working principle of the pipe cutting device for building engineering installation will be described in detail.

[0032] As shown, Figures 1-5 When in use, the pipelines are arranged and placed on the top of processing table 2 in sequence, the output end of pneumatic cylinder 34 drives piston rod 35 to stretch and retract, piston rod 35 stretches and retracts and pushes swing block 37 to swing left and right, further drives partition plate one 38 and partition plate two 39 to move up and down, the two plate bodies stagger, when partition plate one 38 moves down, it is convenient to retain the pipeline on the top of processing table 2, at this time, partition plate two 39 moves up, when partition plate two 39 moves down, it is inserted between the penultimate pipeline and the last pipeline, it is convenient to retain the penultimate pipeline and the front pipeline on processing table 2, at this time, partition plate one 38 moves up, and the last pipeline loses the block, and then rolls to the right side along the inclination angle of processing table 2, and enters the inside of placing groove 21, and then the starting of two groups of electric push rods 24 makes extrusion ring 25 abut on both ends of the pipeline, fixes the pipeline, and cooperates with pipe cutting assembly 23 to cut the pipeline.

[0033] The utility model has made the detailed description to the utility model generally above, but can make some modification or improvement to it on the basis of the utility model, this is obvious to the general skilled person in the technical field. Therefore, the modification or improvement without departing from the utility model thought spirit, all are within the protection scope of the utility model.

Claims

1. A pipe cutting apparatus for use in building engineering installations, comprising a pipe cutting apparatus body (1), characterised in that: The pipe cutting device body (1) comprises a machining table (2), a bearing plate (3) is fixedly installed on the top left side of the machining table (2), and a pipe body (4) is arranged on the top of the machining table (2); The machining table (2) is provided with a feeding mechanism, and a pipe cutting mechanism is arranged at one end of the right side of the machining table (2); The feeding mechanism comprises a supporting bracket (31) fixedly installed on the top of the machining table (2) and located on the right side of the bearing plate (3).

2. A pipe cutting apparatus for use in building construction installations according to claim 1 wherein: The front end of the supporting bracket (31) is provided with a limiting groove (32) on both sides, the top of the bearing plate (3) is rotatably provided with a connecting plate (33), and the right side of the connecting plate (33) is fixedly provided with a gas cylinder (34).

3. A pipe cutting apparatus for use in building construction installations according to claim 2 wherein: The output end of the gas cylinder (34) is provided with a piston rod (35), and the other end of the piston rod (35) is fixedly provided with a rotating shaft (36).

4. A pipe cutting apparatus for use in building construction installations according to claim 3 wherein: The rotating shaft (36) is rotatably connected with a swing block (37) at the inner shaft of the rotating shaft (36), and the right side of the swing block (37) is movably connected with a partition plate one (38).

5. A pipe cutting apparatus for use in building construction installations according to claim 4 wherein: The left side of the swing block (37) is movably connected with a partition plate two (39), and the other end of the partition plate one (38) and the partition plate two (39) extends to the right top of the machining table (2) through the limiting groove (32).

6. A pipe cutting apparatus for use in building construction installations as claimed in claim 1 wherein: The pipe cutting mechanism comprises a placing groove (21) arranged at one end of the right side of the machining table (2), a limiting vertical rod (22) is fixedly installed on both sides of the right end of the machining table (2), and the top of the limiting vertical rod (22) is provided with a pipe cutting assembly (23).

7. A pipe cutting apparatus for use in building construction installations according to claim 6 wherein: The outer surface of the limiting vertical rod (22) is fixedly sleeved with an electric push rod (24), and the other end of the electric push rod (24) is fixedly connected with an extrusion ring (25).