Basement post-cast strip cover plate and mold

By using prefabricated basement post-pouring strip cover plates and molds, the problems of extended construction period and water seepage were solved, and the post-pouring strip was quickly sealed, improving construction efficiency and quality.

CN223738620UActive Publication Date: 2025-12-30ANHUI WATER CONSERVANCY DEV CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202422884942.2
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-11-26
Publication Date
2025-12-30
Estimated Expiration
2034-11-26

AI Technical Summary

Technical Problem

Traditional construction of post-cast strips for basement roof slabs suffers from extended construction periods, safety hazards, quality problems, and water seepage risks. Furthermore, the failure to seal the post-cast strips in a timely manner affects the construction progress.

Method used

The prefabricated basement post-cast strip cover plate and mold are used, which includes a rectangular plate, cross-fixed transverse and longitudinal steel bars, and a pre-reserved pouring hole in the center. Combined with steel pipe and protective plate structure, it is used to strengthen the support and concrete pouring, and shorten the construction period.

Benefits of technology

Effectively sealing the post-pouring strip reduces leakage, shortens the construction period by 2 months, reduces the leakage rate by 5%, and improves construction efficiency and quality.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN223738620U_ABST
    Figure CN223738620U_ABST
Patent Text Reader

Abstract

The basement post-cast strip cover plate comprises a plate body formed by concrete pouring, the plate body is of a rectangular structure, transverse reinforcing steel bars and longitudinal reinforcing steel bars are embedded in the plate body, and the corresponding intersection points of the transverse reinforcing steel bars and the longitudinal reinforcing steel bars are fixed in a twisted mode through binding wires. Extending sections are arranged on two end sides, corresponding to the plate body, of the longitudinal steel bars; a pouring hole used for pouring is reserved in the center of the plate body. The basement top plate and the side wall post-cast strip are sealed in advance through the prefabricated plates, basement top plate waterproof construction and earthwork backfilling work are conducted alternately, and the problem that the post-cast strip cannot be sealed for a long time is solved. Powerful guarantee is provided for accelerating the engineering construction progress, and meanwhile, the leakage condition of the post-cast strip is reduced. The construction period is shortened, the construction period is saved by two months, and the leakage rate is reduced by 5%.
Need to check novelty before this filing date? Find Prior Art

Description

TECHNICAL FIELD

[0001] The utility model belongs to the technical field of building construction equipment, and particularly relates to a basement post-cast strip cover plate and mold. BACKGROUND

[0002] The traditional basement roof post-cast strip will reserve the position of the post-cast strip when pouring concrete, and the formwork can be removed only after the post-cast strip period. During the cleaning of the post-cast strip, the original concrete chiseling on both sides of the post-cast strip is often improper, there is a lot of construction waste, the reinforcement is bent, and the concrete pouring is often not proper, which often leads to an extension of the construction period, difficulties in on-site management, and safety hazards. There may also be a possibility of water stop steel plate falling off, water stop steel plate not being connected, improper pouring, and not being vibrated, which leads to quality problems such as the appearance of dark water after the post-cast strip roof is formed. The basement roof post-cast strip pre-sealing technology can effectively reduce the occurrence of water seepage and does not delay the development and construction of the next process, thereby saving time for the total construction period.

[0003] The basement roof post-cast strip pre-sealing is completed by covering a prefabricated cover plate on the upper side of the post-cast strip. The cover plate has a pouring hole in the center and a steel reinforcement frame embedded inside to improve the support strength. The concrete strength grade of the cover plate should be no less than C30, and the thickness should not be less than 100 mm. UTILITY MODEL CONTENTS

[0004] The utility model aims to provide a basement post-cast strip cover plate and mold for shortening the construction period and improving the construction effect.

[0005] To solve the above technical problems, the utility model is implemented by the following technical scheme:

[0006] A basement post-cast strip cover plate includes a plate body formed by pouring concrete. The plate body is of a rectangular structure. A horizontal steel reinforcement and a vertical steel reinforcement are embedded inside the plate body. The horizontal steel reinforcement and the vertical steel reinforcement are fixed by twisting at the corresponding intersection points by means of a wire. The vertical steel reinforcement has an extension section at each end of the plate body.

[0007] A pouring hole for pouring is reserved in the center of the plate body.

[0008] Further, a steel pipe is embedded in the inner side wall of the pouring hole. The steel pipe penetrates the plate body. A steel reinforcement groove is formed in the side wall of the steel pipe to accommodate the horizontal steel reinforcement and the vertical steel reinforcement on the side.

[0009] A mold for a basement post-cast strip cover plate includes a first guard plate at both ends of the vertical steel reinforcement. The first guard plate has a positioning groove to accommodate and support the end of the vertical steel reinforcement.

[0010] A second guard plate is located at the end of the horizontal steel reinforcement. After the second guard plate is spliced with the first guard plate, a frame is formed on the side of the enclosed plate body.

[0011] The first guard plate bottom is provided with a plurality of clamping grooves for clamping and slidingly fitting the upper side of the second guard plate.

[0012] The basement top plate waterproof construction and earthwork backfill work are carried out in the basement top plate waterproof construction and earthwork backfill work, and the problem of long-term non-closure of the post-pouring belt is solved.

[0013] In the process of building construction, the basement structure is applied more and more widely, and the construction process of prefabricated reinforced concrete plate is adopted in the construction process of post-pouring belt. BRIEF DESCRIPTION OF DRAWINGS

[0014] In order to more clearly illustrate the technical scheme of the embodiment of the utility model, the following will introduce the drawings needed to be used in the embodiment of the embodiment.

[0015] Fig. 1 The utility model discloses a plate body demolding structure schematic diagram.

[0016] Fig. 2 The utility model discloses a steel bar arrangement structure schematic diagram.

[0017] Fig. 3 The utility model discloses a plate body pouring state structure schematic diagram.

[0018] In the drawings, the component list represented by each sign is as follows: plate body 1, horizontal steel bar 11, vertical steel bar 12, steel pipe 2, steel bar groove 21, first guard plate 3, positioning groove 31, second guard plate 4, clamping groove 32, folding plate 41. DETAILED DESCRIPTION

[0019] The technical scheme in the embodiment of the utility model will be described clearly and completely in combination with the drawings in the embodiment of the utility model.

[0020] As Figs. 1-3The utility model provides a basement post-cast strip cover plate, including the plate body 1 formed by concrete pouring, the plate body 1 is rectangular structure, the plate body 1 inside is embedded with transverse reinforcement 11 and longitudinal reinforcement 12, and transverse reinforcement 11 and longitudinal reinforcement 12 are fixed by twisting through lashing corresponding intersection points, and longitudinal reinforcement 12 corresponds the extension section of both ends side of plate body 1,

[0021] Plate body 1 central reservation has the pouring hole for pouring, and the corresponding concrete strength grade of plate body should not be less than C30, and the thickness should not be less than 100mm. After the arrangement of transverse reinforcement and longitudinal reinforcement, a grid structure is formed, and the extension section of the part of longitudinal reinforcement corresponding to the end side of the plate body is used for pouring and reinforcing the adjacent interval cover plate.

[0022] As Fig. 2 The inner side wall of pouring hole is embedded with steel pipe 2, steel pipe 2 penetrates plate body 1, steel pipe 2 side wall is provided with reinforcing bar slot 21 for accommodating side transverse reinforcement 11 and longitudinal reinforcement 12. The reinforcing bar slot is formed by grinding the corresponding steel pipe side wall through an angle grinder.

[0023] As Fig. 2 A mold of a basement post-cast strip cover plate, including the first guard plate 3 at both ends of longitudinal reinforcement 12, the first guard plate 3 has the positioning groove 31 for accommodating and supporting the end of longitudinal reinforcement 12, and the first guard plate is a column structure.

[0024] Including the second guard plate 4 at the end position of transverse reinforcement 11, the second guard plate 4 is spliced with the first guard plate 3 to form the frame of the surrounding plate side. The corresponding inner side of the frame is a pouring groove for pouring concrete, which becomes a plate body after solidification. Before pouring, a layer of snake bag is laid on the ground, and then the first guard plate and the second guard plate are laid. After pouring is completed, demolding is carried out.

[0025] The bottom of the first guard plate 3 is provided with a plurality of clamping grooves 32 for clamping the upper side of the second guard plate 4 and sliding fit. The spacing between the two first guard plates and the two second guard plates on both sides can be adjusted according to the size of the poured plate body. The excess clamping grooves are also used to drain excess water in the concrete during pouring. The second guard plate 4 has a folding plate 41 at the bottom, which is integrally arranged with the bottom of the second guard plate 4. The folding plate is used to support the ground to improve the support stability of the second guard plate.

[0026] The embodiments are selected and specifically described in the specification in order to better explain the principles and practical applications of the utility model, so that the persons skilled in the art can well understand and utilize the utility model.

Claims

1. A basement post-cast strip cover plate, characterized by: The utility model provides a kind of concrete pouring slab (1) formed, the slab (1) is rectangular structure, the slab (1) is embedded with transverse reinforcement (11) and longitudinal reinforcement (12), the transverse reinforcement (11) and longitudinal reinforcement (12) are fixed by twisting corresponding intersection point by lashing, the longitudinal reinforcement (12) corresponding slab (1) both ends side has extension section; The slab (1) is centrally reserved for pouring pouring hole.

2. The basement post-cast strip cover plate according to claim 1, characterized in that: The inner wall of the pouring hole is embedded with a steel pipe (2), the steel pipe (2) penetrates the slab (1), and a steel bar groove (21) is formed on the side wall of the steel pipe (2) to accommodate the lateral transverse reinforcement (11) and longitudinal reinforcement (12).

3. A mold for a basement post-cast strip cover plate, characterized by: It includes a first guard plate (3) located at both ends of the longitudinal reinforcement (12), and the first guard plate (3) has a positioning groove (31) for accommodating and supporting the end of the longitudinal reinforcement (12). It includes a second guard plate (4) located at the end of the transverse reinforcement (11), and the second guard plate (4) forms a frame surrounding the side of the slab after splicing with the first guard plate (3).

4. The mold for basement post-cast strip cover plate according to claim 3, characterized in that: The first guard plate (3) is provided with a plurality of clamping grooves (32) at the bottom, which are used for clamping and slidingly engaging the upper side of the second guard plate (4).