Plane floor slab forming structure adopting hoisting transition
By adopting a suspended transition planar floor slab forming structure and utilizing the design of formwork and transition suspension beams, the problems of low efficiency of full-span scaffolding and waste of steel truss materials were solved, achieving efficient and low-cost formwork installation and construction.
Patent Information
- Application Number
- CN202520163938.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-01-24
- Publication Date
- 2026-01-09
- Estimated Expiration
- 2035-01-24
AI Technical Summary
In existing technologies, the installation efficiency of using full-span scaffolding is low, and the use of embedded steel trusses will result in material waste.
The planar floor slab forming structure adopts hoisting transition, including formwork, transition suspension beam and support components. The formwork has hoisting grooves and connection holes on the side, and transition support is provided by the transition suspension beam. The support components are used for edge or corner support of the formwork array. The formwork does not require perforation during installation, and the height is adjusted by using movable parts and nuts.
It improves the efficiency of formwork installation, reduces the waste of steel reinforcement materials, lowers construction costs, and allows the formwork and support components to be reused, thus improving construction efficiency and safety.
Smart Images

Figure CN223781149U_ABST
Abstract
Description
TECHNICAL FIELD
[0001] The utility model relates to building template technical field, concretely relates to a plane floor forming structure of hoisting transition. BACKGROUND
[0002] The traditional template is generally used for non-assembled building, and its whole construction process is carried out on the construction site, usually, a full scaffold is first built below the construction surface as a foundation support, then the installation of the support, the installation of the main and secondary batten, the adjustment of the plane floor bottom elevation and the arch, the installation of the template are successively carried out, and finally the plane floor construction is completed through the concrete pouring, which belongs to the typical non-assembled building construction process.
[0003] When the full scaffold is set up, the width of the template needs to be considered, the wood mold above the scaffold needs to accurately support the edge or corner of the template, and the height of the top wood mold needs to be considered, so the set-up of the scaffold is required to be high, the set-up efficiency of the scaffold is delayed, the overall installation efficiency is reduced, and in the prior art, a prefabricated steel bar truss is directly hoisted to install the template without the bottom support, but when the method is used, the selection of the steel bar truss is necessarily larger than that of the steel bar with the bottom support, the steel bar truss is not removed and is embedded in the concrete as a part of the steel cage, so that the waste of consumable materials is caused. UTILITARIAN CONTENT
[0004] The utility model solves the problem in the prior art that the direct installation of the full scaffold is low in efficiency and the embedded steel bar truss causes material waste, and provides a low-cost and high-efficiency plane floor forming structure with hoisting transition.
[0005] The utility model is realized through the following technical scheme, a plane floor forming structure with hoisting transition, comprising a plurality of templates, a transition suspension beam and a support assembly.
[0006] The template comprises a template top surface, the template top surface is rectangular, a circle of template side surfaces extending downward is connected around the template top surface, the template side surfaces are perpendicular to the template top surface, a cavity is formed between the template top surface and the inner side of the template side surfaces surrounding the template top surface, the template side surfaces are provided with connecting holes, the connecting holes are horizontally arranged and pass through the cavity to the template side surfaces, the template side surfaces are provided with hoisting grooves, the hoisting grooves are located on the template side surfaces and pass through the bottom of the template top surface and the template side surfaces, and the hoisting grooves and the connecting holes are staggered.
[0007] The template sides of a plurality of templates are attached to each other to form a rectangular template array with multiple rows and multiple columns, the lower bottom surfaces of all the templates are coplanar, the connecting holes on the template sides of two adjacent templates are in the same position and are fastened and connected by penetrating the connecting holes with fasteners, the hoisting grooves on the adjacent templates are symmetrical along the template sides, and the two hoisting grooves can be combined to form a hoisting hole penetrating the upper and lower surfaces of the template.
[0008] The transition suspension beam is used for transitionally supporting the template array, and comprises a beam body, support parts, movable parts, a supporting plate and nuts.
[0009] The support assembly comprises a plurality of vertical rods, horizontal rods and top supports, and is used for supporting the edges or corners of the template array.
[0010] Further, the movable parts are fixedly provided with annular parts at the top, and the beam body is provided with a plurality of horizontal rods at the bottom.
[0011] Further, the supporting plate is rectangular.
[0012] Further, the beam body is one of a profile steel, a steel bar truss and a steel truss.
[0013] Further, the support parts adopt a height-adjustable structure.
[0014] Further, the number of hoisting grooves on a single template side is one or more.
[0015] Further, the template top surface and the template side surface are internally provided with grid-shaped reinforcing ribs.
[0016] The utility model discloses beneficial effects are:
[0017] 1. The transition suspension beam is prefabricated in the factory, can be directly installed after transportation to the construction site, the formwork can be directly laid on the side mold of the main beam or the supporting plate of the transition suspension beam, the formwork laying is very convenient, the overall installation height of the formwork is controlled by the cross beam body and the nut, the adjustment is relatively convenient, finally the support assembly is erected at the bottom of the formwork array, the bottom support of the formwork is realized, and finally the transition suspension beam is removed. Compared with directly installing the scaffold first and then laying the formwork, only one process of installing and removing the transition suspension beam is added, but the formwork installation is faster, and the erection of the support assembly does not need to worry about the problem of inaccurate jacking position, and directly uses the steel bar truss, and the steel bar truss is buried in the concrete as the steel bar, so the specification selection of the steel bar truss will be larger than that of the steel bar tied in the construction site, therefore, the scheme will not cause waste of steel bar materials.
[0018] 2. The formwork side of the utility model is provided with a hoisting groove, two or four hoisting grooves of the formwork can be spliced into a hoisting hole, the rod part of the movable part is embedded into the hoisting groove during installation, without the need of perforation installation, the installation efficiency is improved. And two formworks share one hoisting hole, reducing the opening of holes on the formwork.
[0019] 3. The movable part of the transition suspension beam can move horizontally along the direction perpendicular to the length direction of the steel bar truss, the horizontal movement is to facilitate installation, and interference of the lower supporting plate on the formwork installation can be avoided. BRIEF DESCRIPTION OF DRAWINGS
[0020] Figure 1 It is a top view three-dimensional view of the formwork in embodiment one;
[0021] Figure 2 It is a bottom view three-dimensional view of the formwork in embodiment one;
[0022] Figure 3 It is a structure schematic view of the transition suspension beam in embodiment one;
[0023] Figure 4 It is a partial enlarged view in Figure 3
[0024] Figure 5 It is a left view of the transition suspension beam;
[0025] Figure 6 It is a simple view of the support assembly;
[0026] Figure 7 It is a schematic view of the support assembly after installation, and the transition suspension beam has not been removed;
[0027] Figure 8 It is a construction process of embodiment one Figure 1 ;
[0028] Figure 9 Construction process of Example One Figure 2
[0029] Figure 10 Close-up view of Figure 9 ;
[0030] Figure 11 Close-up view of Figure 10 ;
[0031] Figure 12 Construction process of Example One Figure 3 ;
[0032] Figure 13 Construction process of Example One Figure 4 ;
[0033] Figure 14 Construction process of Example One Figure 5 ;
[0034] Figure 15 Schematic view of Example Two
[0035] Figure 16 Structural schematic view of the formwork in other examples.
[0036] In the drawings:
[0037] 10 formwork; 11 formwork top surface; 12 formwork side surface; 13 cavity; 14 connecting hole; 15 hoisting slot;
[0038] 20 transition suspension beam; 21 beam main body; 22 movable piece; 23 supporting plate; 24 nut; 25 supporting portion;
[0039] 30 supporting assembly; 31 vertical rod; 32 horizontal rod; 33 top support;
[0040] 41 main beam formwork; 42 main beam side form; 43 main beam scaffold;
[0041] 6 wall. DETAILED DESCRIPTION
[0042] The technical solutions in the embodiments of the present application will be clearly and completely described below with reference to the drawings in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, rather than all the embodiments of the present application. Based on the embodiments in the present application, all other embodiments obtained by those of ordinary skill in the art without creative labor fall within the scope of protection of the present application.
[0043] Example One
[0044] A flat floor forming structure with hoisting transition, comprising a plurality of formworks 10, a transition suspension beam 20, a support assembly 30,
[0045] The formwork comprises a formwork top surface 11, which is rectangular, and a formwork side surface 12 extending downward around the periphery of the formwork top surface 11, the formwork side surface 12 being perpendicular to the formwork top surface 11, the formwork top surface 11 and the inner side of the formwork side surface 12 surrounding it forming a cavity 13, the formwork side surface 12 being provided with a connecting hole 14, the connecting hole 14 being horizontally arranged and extending through the cavity 13 to the formwork side surface 12, the formwork side surface 12 being provided with a hoisting groove 15, the hoisting groove 15 being located on the formwork side surface 12 and extending through the formwork top surface 11 and the bottom of the formwork side surface 12, the hoisting groove 15 and the connecting hole 14 being staggered;
[0046] The formwork side surfaces 12 of the plurality of formworks 10 are adhered to each other to form a rectangular formwork array in multiple rows and columns, the lower bottom surfaces of all the formworks 10 are coplanar, the connecting holes 13 on the formwork side surfaces 12 of adjacent two formworks 10 are located at the same position and are fastened and connected by fasteners penetrating through the connecting holes 13, the hoisting grooves 17 on adjacent formworks 10 are symmetrical along the formwork side surface 15, and two hoisting grooves 17 can be combined to form a hoisting hole extending through the upper and lower surfaces of the formwork 10;
[0047] As shown in the drawings, Figures 1-2 In the present scheme, the specification of a single formwork is 800mm×2400mm, two semicircular hoisting grooves 15 and three connecting holes 14 are arranged on each of the two formwork side surfaces 12 of 800mm, five connecting holes 14 are arranged on each of the two formwork side surfaces 12 of 2400mm, there are twenty-seven formworks 10, which are arranged in a 9×3 array and spliced into a 7200mm×7200mm formwork array, adjacent two formworks 10 are fastened and connected by fasteners penetrating through the connecting holes 13, and four hoisting grooves 15 of the short edges of the two formworks 10 are spliced into two hoisting holes, the entire formwork array has a total of two rows, and each row has eighteen hoisting holes.
[0048] The transition suspension beam 20 is used to transitionally support the formwork 10 array, as Figures 3-5As shown, the transition suspension beam 20 comprises a beam body 21, a support part 25, a movable part 22, a supporting plate 23, and a nut 24, the length of the beam body 21 is greater than the span of the floor system, the support part 25 is located at both ends of the beam body 21 for supporting the beam body 21, the movable part 22 is movably arranged at the bottom of the beam body 21 and can move horizontally in the direction perpendicular to the length of the beam body 21, the screw rod structure is arranged below the movable part 22, the supporting plate 23 is provided with a through hole in the middle, the supporting plate 23 can support two formworks 10 at the same time when in use, the movable part 22 penetrates through the supporting plate 23 and the nut 24, and the nut 24 is connected to the supporting plate 23, and the height of the supporting plate 23 can be adjusted by rotating the nut 24, the movable part 22, the supporting plate 23, and the nut 24 are arranged in several groups and are arranged at intervals along the length direction of the beam body 21.
[0049] As shown in the drawings, Figure 13 In this scheme, the transition suspension beam 20 is provided with two sets, and each set of the transition suspension beam 20 is provided with 18 groups of the movable part 22, the supporting plate 23, and the nut 24, each transition suspension beam 20 simultaneously supports two rows of formworks 10 in the formwork 10 array, the movable part 22 is threadedly connected to the nut 24 after penetrating through the supporting plate 23 and the hoisting hole, and the supporting plate 23 supports the bottom surface of the formwork 10.
[0050] As shown in the drawings, Figures 6-7 The support assembly 30 comprises a plurality of vertical rods 31, horizontal rods 32, and top supports 33 for supporting the edges or corners of the formwork 10 array.
[0051] The specific construction method of this scheme is as follows:
[0052] Preparation before construction: prefabricate the formwork 10, the transition suspension beam 20, and the fastener according to the construction requirements;
[0053] Construction process:
[0054] Install the suspension beam, and erect two sets of transition suspension beams 20 according to the requirements in the drawings, the support part 25 is placed on the wall body 6, as shown in the drawings, there are two transition suspension beams 20, which are hoisted to the wall body 6 by a tower crane or other hoisting tools, are arranged in parallel, and are positioned on site; Figure 8
[0055] Install the edge support assembly 3 for supporting the outer edges of the formwork 10 array.
[0056] The template 10 is installed, starting from one corner of the wall body 6, along one side of the main beam, and then along the template 10 that has been installed, the remaining templates 10 are installed in sequence until the installation of all templates 10 is completed, the adjacent templates 10 are fastened and connected through the first fastener penetrating the connecting hole 14, and the installed template 10 is pulled tight in time, which can improve the installation accuracy and avoid the problem of mispositioning of the hoisting groove 15 and the rod of the movable piece 21 of the subsequent template 10 due to accumulated errors, the two hoisting grooves 15 are spliced into a hoisting hole, the rod of the movable piece 21 is located in the hoisting hole, and each supporting plate 23 simultaneously supports the two templates 10; the specific steps of installing the template 10 include:
[0057] Installing the first template 10: before installing the first template 10, the movable piece 22 is moved to the side away from the first template 10, when installing the first template 10, the template 10 is arranged against the wall and placed on the edge of the supporting assembly 3, the movable piece 22 is moved, and the rod of the movable piece 21 is embedded into the hoisting groove 15 of the template 10, at this time, the supporting plate 23 supports the edge of the template 10, as shown in Figures 9-11 , which is the installed state of the first template 10;
[0058] Installing the first row of remaining templates 10: the first row of templates 10 is installed along the length direction of the transition suspension beam 20, the installation method is consistent with that of installing the first template 10, and starting from the second template 10, when installing each template 10, the template side surface 12 of the newly installed template 10 is tightly arranged against the template side surface 12 of the installed template 10, and the two templates 10 are fastened and connected through the fastener penetrating the connecting hole 14; as shown in Figure 12 , which is the installed state of the first row of templates 10;
[0059] Install the second row of formwork 10: move the movable part 22 of the second transition suspension beam 20 away from one side of the second row of formwork 10, tilt the formwork 10 from bottom to top, place one side of the formwork 10 on the supporting plate 23 of the first transition suspension beam 20, align the lifting grooves 15 of the second row of formwork 10 with the lifting grooves 15 of the first row of formwork 10, then lift the other side of the second row of formwork 10 until it is horizontal, move the movable part 22 of the second transition suspension beam 20 so that the rod part 24 of the movable part is embedded in the lifting groove 15 of the second row of formwork 10, at this time the supporting plate 23 of the second transition suspension beam 20 supports the second row of formwork 10; during this process, when one formwork 10 is installed, the newly installed formwork 10 is tightly attached to the side of the already installed formwork 10, and the two formworks 10 are fastened and connected through the fastening member penetrating the connecting hole 14, the lifting grooves 15 of the first row of formwork 10 and the second row of formwork 10 are spliced into a lifting hole, the rod part 24 of the movable part penetrates the lifting hole, and the supporting plate 23 simultaneously supports the two rows of formwork 10. The movable part 22 of the transition suspension beam 20 can move horizontally along the direction perpendicular to the length of the steel bar truss 21, which facilitates installation and avoids interference of the supporting plate 23 below with the installation of the formwork 10.
[0060] Install the third row of formwork 10: the installation method is the same as that of installing the second row of formwork 10, and all formworks 10 are installed as shown in Figure 13 .
[0061] Then install the support assembly 30, as shown in Figures 6-7 , the support assembly 30 includes a plurality of vertical rods 31, horizontal rods 32, and top supports 33, the top supports 33 support the edges and corners of the formwork array; the vertical rods 31 are connected by the horizontal rods 32, and the vertical rods 31 and the main beam scaffold 43 are also connected as a whole by the horizontal rods 32, which improves the overall stability of the support assembly 30, and according to actual needs, diagonal braces can be added, during installation, rotate the adjusting nuts to adjust the height of the top supports 33 so that the top supports 33 just abut the bottom surface of the formwork 10, as shown in Figure 13 , the state of all support assemblies 30 after installation.
[0062] Finally, remove the transition suspension beam 20; rotate the nuts 24, remove all nuts 24 and supporting plates 23 from below, and remove the horizontal beam body 21 and the supporting part 25 from above, which are all recycled, Figure 14 , the state of the transition suspension beam 20 after removal.
[0063] Bind the steel bars, including horizontal and vertical plane floor steel bars and surface steel bars above the formwork;
[0064] Pour concrete and maintain;
[0065] After curing and forming, the support assembly 30, the first fastener, and the formwork 10 are removed for reuse.
[0066] In this scheme, the floor support plate is not needed, the formwork 10 is suspended by the transition suspension beam 20 for transitional hoisting, the use of consumable materials is reduced, and the cost is reduced. The transition suspension beam 20 is prefabricated in the factory and can be directly installed after being transported to the construction site. The formwork 10 can be directly laid on the main beam side form 42 or the supporting plate 23 of the transition suspension beam 20. The formwork 10 is very convenient to lay. The overall installation height of the formwork 10 is controlled by the cross beam body 21 and the nut 24. The adjustment is relatively convenient. Finally, the support assembly 30 is erected at the bottom of the formwork array to support the bottom of the formwork 10. Finally, the transition suspension beam 20 is removed. Compared with directly installing the scaffold first and then laying the formwork 10, only one process of installing and removing the transition suspension beam 20 is added. However, the formwork 10 is installed more quickly, and the erection of the support assembly 30 does not need to worry about the problem of inaccurate jacking position. Compared with directly using the steel bar truss, and the steel bar truss is embedded in the concrete as a steel bar, the specification selection of the steel bar truss will be larger than that of the steel bar tied in the construction site. Therefore, this scheme will not cause waste of steel bar materials. In this scheme, the transition suspension beam 20, the formwork 10, and the support assembly 30 can be reused, thereby reducing the cost.
[0067] In actual application, the supporting plate 23 is rectangular. Before the formwork 10 is installed, the supporting plate 23 is rotated so that the long side of the supporting plate 23 is perpendicular to the formwork 10 to be installed. After the formwork 10 is installed, the supporting plate 23 is rotated so that the short side of the supporting plate 23 is perpendicular to the installed formwork 10, thereby reducing the interference of the supporting plate 23 on the installation of the formwork 10, as shown in Figure 12 .
[0068] Embodiment Two
[0069] As shown in Figure 15 , the four edges of the formwork array are erected on the main beam side form. The support part of the transition suspension beam is placed on the main beam formwork. The support assembly is connected with the main beam scaffold by the cross bar to form a whole. The remaining construction process is similar to that of Embodiment One, which meets the construction needs of different scenes.
[0070] In other embodiments, as shown in Figure 16 , the hoisting groove 15 can be located on the long side of the formwork 10. For example, in Embodiment One, eight transition suspension beams 20 can be used to hoist the long side of the formwork 10, which can also meet the construction needs.
[0071] In other embodiments, the jacking 33 can only support on the edge of the formwork 10.
[0072] In other embodiments, the number, position and shape of the connecting holes 14 and the lifting grooves 15 can be adjusted according to actual conditions to meet the lifting requirements,
[0073] In other embodiments, the movable part 22 can also adopt other structures, such as a sleeve, a slider, etc., as long as the movable part 22 can move horizontally along the length direction perpendicular to the beam body 21.
[0074] In other embodiments, the beam body 21 can also adopt other section steels, such as an I-beam, an H-beam, a square tube, etc., or adopt one of a steel bar truss and a steel truss, as long as the large-span support can be met.
[0075] In other embodiments, the support part 25 adopts a height-adjustable structure, and the height of the beam body 21 can be adjusted as a whole.
[0076] In actual application, the construction of the self-propelled hydraulic lifting vehicle 5 is very convenient, and no full-frame scaffold is needed, workers can stand on the self-propelled hydraulic lifting vehicle 5 to perform installation work, the installation efficiency of the installation workers can be improved, and the workers do not need to climb the scaffold, so the safety is improved.
[0077] In actual application, as shown in Figure 16 The template top surface 11 and the template side surface 12 are internally provided with grid-shaped reinforcing ribs.
[0078] The plane floor forming structure adopting the lifting transition can provide transitional lifting for the formwork, improve the erection speed of the scaffold, and improve the construction efficiency.
[0079] The basic principle, main features and advantages of the utility model are shown and described above. The skilled in the art should understand that the above-mentioned embodiments are only for illustrating the technical concept and characteristics of the utility model, and the purpose is to enable the person skilled in the art to understand the content of the utility model and implement it, and it cannot limit the protection scope of the utility model, and any equivalent changes or modifications according to the spirit and essence of the utility model should be covered in the protection scope of the utility model.
Claims
1. A planar floor slab forming structure using hoisting transition, characterized in that: Includes several templates (10), transition suspension beams (20), and support components (30); The template (10) includes a template top surface (11), which is rectangular. A template side surface (12) extending downwards is connected around the top surface (11). The template side surface (12) is perpendicular to the template top surface (11). The template top surface (11) and the inner side of the template side surface (12) forming a cavity (13) are formed. The template side surface (12) is provided with a connecting hole (14), which is horizontally set and extends from the cavity (13) to the template side surface (12). The template side surface (12) is provided with a lifting groove (15), which is located on the template side surface (12) and extends through the bottom of the template top surface (11) and the template side surface (12). The lifting groove (15) and the connecting hole (14) are staggered. The template sides (12) of several templates (10) are attached in pairs to form a rectangular template (10) array with multiple rows and columns. The bottom surfaces of all templates (10) are coplanar. The connecting holes (14) on the template sides (12) of two adjacent templates (10) are in the same position and are fastened together by fasteners through the connecting holes (14). The lifting slots (15) on adjacent templates (10) are symmetrical along the template sides (12). The two lifting slots (15) can be combined to form a lifting hole that runs through the upper and lower surfaces of the template (10). The transition suspension beam (20) is used to provide transitional support for the formwork array. It includes a beam body (21), a support (25), a movable part (22), a support plate (23), and a nut (24). The length of the beam body (21) is greater than the span of the floor slab. The support (25) is located at both ends of the beam body (21) and is used to support the beam body (21). The movable part (22) is movably disposed at the bottom of the beam body (21) and can be moved at least along the length perpendicular to the beam body (21). The movable part (22) moves horizontally in the direction of degree. The lower part of the movable part (22) is a screw structure. The middle part of the support plate (23) is provided with a through hole. When the support plate (23) is working, it can support two templates (10) at the same time. The movable part (22) passes through the support plate (23) and is connected to the nut (24). Rotating the nut (24) can adjust the height of the support plate (23). Several sets of movable parts (22), support plates (23) and nuts (24) are provided and are spaced apart along the length of the main body of the crossbeam (21). The support assembly (30) includes several uprights (31), crossbars (32), and top supports (33) for supporting the sides or corners of the template (10) array.
2. The planar floor slab forming structure using hoisting transition according to claim 1, characterized in that: The movable part (22) is fixedly provided with a ring-shaped part at the top, and the main body of the crossbeam (21) is provided with several crossbars (32) at the bottom. The ring-shaped part is sleeved on the crossbars (32).
3. The planar floor slab forming structure using hoisting transition according to claim 1, characterized in that: The tray (23) is rectangular.
4. A planar floor slab forming structure using hoisting transition as described in claim 1, characterized in that: The main body of the crossbeam (21) is one of the following: steel profile, steel truss, or steel truss.
5. A planar floor slab forming structure using hoisting transition as described in claim 1, characterized in that: The support part (25) adopts a height-adjustable structure.
6. A planar floor slab forming structure using hoisting transition as described in claim 1, characterized in that: The number of lifting slots (15) on a single template side (12) is one or more. When there is only one lifting slot (15) on a single template side (12), the lifting slot (15) is located in the middle of the template side (12). When there are multiple lifting slots (15) on a single template side (12), the lifting slots (15) are symmetrically arranged along the length of the template side (12).
7. A planar floor slab forming structure using hoisting transition as described in claim 1, characterized in that: The top surface (11) and side surface (12) of the template are provided with grid-like reinforcing ribs.