Safety protection lifting system for building construction
By improving the column unit structure, power mechanism, and fixing method, the instability and safety hazards of traditional lifting systems have been solved, resulting in a highly efficient and safe construction lifting system.
Patent Information
- Application Number
- CN202520407670.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-03-10
- Publication Date
- 2026-01-30
- Estimated Expiration
- 2035-03-10
AI Technical Summary
Traditional construction safety lifting systems have defects in structural design, power transmission, fixing methods, and safety protection, resulting in system instability, low efficiency, inability to adapt to complex building structures and construction environments, and potential safety hazards.
The system employs multiple vertically overlapping column units, combined with a U-shaped metal frame and connecting reinforcing ribs. The power mechanism uses two sets of motors and a reduction mechanism. The limiting channel steel works in conjunction with the limiting wheel. The protective fixing bracket is connected by bolts. The rational design of the movable door and inspection hole improves the stability, power transmission efficiency and safety of the system.
It significantly improves the structural stability, power transmission efficiency, and safety of the lifting system, enabling it to adapt to different building structures, reduce swaying, and ensure smooth operation and personnel safety during construction.
Smart Images

Figure CN223853801U_ABST
Abstract
Description
TECHNICAL FIELD
[0001] The utility model relates to the field of building construction, and specifically relates to a building construction safety protection lifting system. BACKGROUND
[0002] In the building construction scene, construction safety is always the top priority. With the continuous expansion of building project scale and the continuous rise of building height, the performance and reliability of construction safety protection equipment are increasingly demanding. Especially in the vertical transportation of personnel and materials, the safety and reliability of the safety protection lifting system directly affect the smooth progress of construction and the safety of personnel and property. Reviewing the traditional building construction safety protection lifting system, it has significant defects in many key aspects. In terms of structural design, the column unit usually adopts a simple and single structure, lacking a stable combined structure. For example, the traditional column unit is usually a single or a small number of steel pipes simply spliced, which has poor integrity. When facing long-term and high-intensity construction use, it is prone to deformation and shaking, which not only seriously interferes with the stable operation of the lifting system, but also may cause safety accidents and endanger the lives of construction personnel. In terms of power transmission, the connection between the power mechanism and the lifting cage in the traditional system is very rough. The power mechanism is usually a simple single motor drive, and the connection with the lifting cage lacks precise transmission design, resulting in large power transmission loss, low efficiency, and unstable lifting process. At the same time, due to the lack of effective limiting and stabilizing devices, the lifting cage shakes obviously during lifting, further increasing the safety risk and reducing the reliability of the system.
[0003] Furthermore, in the fixed link with the construction building, the traditional protective fixed support has poor design flexibility and is difficult to adapt to complex and diverse building structures and construction environments. Whether it is faced with special needs in different construction stages or special-shaped building structures, the traditional support cannot ensure that the column unit and the building main body are connected stably and reliably, which undoubtedly poses a safety hazard to the entire lifting system. In addition, the safety cage and the lifting cage also have deficiencies in protection facilities. The movable door design is usually a simple opening and closing structure, which is inconvenient to operate and has a simple safety locking mechanism, and is prone to accidental opening during construction. The top of the lifting cage often does not have a reasonable access hole, making equipment maintenance and repair work difficult, which is not conducive to timely detection and elimination of potential faults. SUMMARY
[0004] Therefore, in order to solve the above-mentioned deficiencies, the utility model provides a kind of building construction safety protection lifting system.Compared with the prior art, the building construction safety protection lifting system is comprehensively optimized by innovative design.The column unit is vertically overlapped and connected by multiple column segments, each segment is connected by four groups of steel pipe columns, and is connected with the I-shaped metal frame and the connecting reinforcing rib to form a stable three-dimensional structure, which greatly improves the overall stability.Meanwhile, vertical racks are arranged on both sides of the column unit, and two groups of motors and reduction mechanisms drive the transmission gears to realize efficient and stable power transmission.The channel steel frame is tightly matched with the steel pipe column through the limiting channel steel and the limiting wheel, which significantly reduces the shaking of the lifting cage.The front and rear support bolts of the protection fixing support are connected, and the positioning seat and the metal frame are respectively and stably connected with the construction building and the column unit, which enhances the connection reliability of the system and the building.The reasonable design of the movable door and the access hole further improves the safety and maintainability of the system.
[0005] The utility model is implemented as follows: a building construction safety protection lifting system is constructed, characterized in that:
[0006] The utility model relates to a building construction safety protection lifting system, which comprises a foundation body arranged at the bottom of a construction building,
[0007] The bottom safety cage is fixedly installed on the foundation body,
[0008] The column unit is fixedly installed at the lower end of the foundation body,
[0009] The lifting cage is arranged on the column unit and can be lifted up and down along the column unit under the driving of the power mechanism, which facilitates the vertical lifting construction requirement,
[0010] The protection fixing support is used to fix the column unit and the construction building,
[0011] Each side of the column unit is fixed with a vertical rack, so that each side of the column unit can be arranged with a group of lifting cages, and the lifting cage and the channel steel frame are fixed as a whole, and the left and right ends of the channel steel frame are limiting channel steels,
[0012] The column unit is vertically overlapped and fixedly connected by multiple column segments, which facilitates the adjustment of the height of the column unit according to the height of the construction building, each column segment has four groups of steel pipe columns, the top of each group of steel pipe columns is a protruding butt joint end, which facilitates the butt joint and fixation of the upper and lower segments, the steel pipe columns of the same segment are further fixed by multiple metal frames, the metal frame is welded by L-shaped steel and has an overall I-shaped structure, the I-shaped metal frame can directly connect the four groups of steel pipe columns as a whole, thereby enhancing the stability of the whole, and the connecting reinforcing rib is further fixed between the upper and lower metal frames;
[0013] The channel steel frame is limited outside the corresponding steel pipe column by the limiting channel steel at both ends,
[0014] The side surface of the limiting channel steel is fixed with a triangular fixing seat, the triangular fixing seat is fixedly connected with a support through a bolt, and two groups of limiting wheels are installed on the support, so that the limiting wheels are tightly attached to the outside of the corresponding steel pipe column, so that the overall stability of the channel steel frame and the lifting cage is improved.
[0015] According to the building construction safety protection lifting system, the power mechanism comprises two groups of motors and reduction mechanisms arranged in a vertical direction, the motors and the reduction mechanisms are located at the top of the lifting cage, and are fixedly installed on the channel steel frame, and the output end of the reduction mechanism is provided with a transmission gear which is engaged with the vertical rack.
[0016] According to the building construction safety protection lifting system, the protection fixing support comprises a front support and a rear support, the front support and the rear support are connected through bolts, the front end of the front support is provided with a positioning seat used for being connected with the construction building, and the rear end of the rear support is fixedly connected with the metal frame in the corresponding column segment through bolts, so that the fixing between the column unit and the construction building is achieved.
[0017] According to the building construction safety protection lifting system, the side surface of the bottom safety cage and the lifting cage 4 is respectively provided with an openable movable door, and the top of the lifting cage is provided with an inspection hole.
[0018] The building construction safety protection lifting system has the following advantages: the building construction safety protection lifting system is designed in a series of innovations, and has remarkable patent beneficial effects in many key aspects, specifically,
[0019] I. The structural stability is improved: the column unit is formed by vertically overlapping and fixedly connecting a plurality of column segments, each column segment comprises four steel pipe columns, and the steel pipe columns are connected through the L-shaped metal frame and the connecting reinforcing ribs to form a very stable three-dimensional structure. Compared with the traditional single-structure column, the design greatly enhances the integrity of the column unit, effectively resists various stresses in the construction process, greatly reduces the deformation and shaking risk, provides a solid foundation for the stable operation of the entire lifting system, and effectively protects the life safety of construction personnel.
[0020] The channel steel frame is limited outside the steel pipe column by the limiting channel steel at both ends, and the overall stability of the channel steel frame and the lifting cage is significantly improved by means of the triangular fixing seat, the support and the limiting wheel. In the lifting process, the shaking can be effectively reduced, and the stability and safety of the system operation are further improved.
[0021] II. Efficient and smooth power transmission: The power mechanism adopts two groups of motors and reduction mechanisms arranged in an upper-lower manner, which are installed on the top of the lifting cage and fixed with the channel steel frame. The transmission gear at the output end of the reduction mechanism engages with the vertical racks on both sides of the column unit, achieving efficient power transmission. Compared with the traditional single-motor drive system with rough connection method, the power transmission efficiency of this design is greatly improved, the lifting process is more stable, the power transmission loss is effectively reduced, and the smoothness and safety of personnel and material transportation are ensured.
[0022] III. Flexible and reliable fixing method: The protective fixing support is composed of a front support and a rear support connected by bolts. The positioning seat at the front end of the front support is used to connect with the construction building, and the rear end of the rear support is fixed with the metal frame in the column segment. This design can well adapt to the needs of different building structures and construction environments, ensuring firm connection between the column unit and the construction building, greatly enhancing the stability and reliability of the entire lifting system in the construction site.
[0023] IV. Enhanced safety performance: The bottom safety cage and the side of the lifting cage are provided with openable doors, which are convenient for personnel and materials to enter and exit. The design fully considers the convenience and safety, effectively prevents accidental opening, and provides reliable safety protection for construction personnel. The top of the lifting cage is provided with a maintenance hole, which provides a convenient access for equipment maintenance and repair, facilitates timely detection and elimination of potential faults, ensures long-term stable operation of the system, and further enhances the safety performance.
[0024] In summary, the building construction safety protection lifting system realizes overall optimization in structure, power, fixation, and safety protection through innovative design, significantly improves the safety, stability, and efficiency of the system, and effectively meets the stringent needs of modern building construction. BRIEF DESCRIPTION OF DRAWINGS
[0025] Figures 1-2 is the overall implementation schematic diagram of the present application;
[0026] Figures 3-4 is the schematic diagram of a column segment and a lifting cage in the present application;
[0027] Figure 5 is the top view of Figure 3 in the present application;
[0028] Figure 6 is the limiting wheel part schematic diagram in the present application;
[0029] Figure 7 is the protective fixing support schematic diagram in the present application.
[0030] The components include: 1. Base structure; 2. Bottom safety cage; 3. Column unit; 4. Lifting cage; 5. Protective fixing bracket; 6. Vertical rack; 7. Channel steel frame; 7-1. Limiting channel steel; 7-2. Triangular fixing seat; 7-3. Support; 7-4. Limiting wheel; 8. Column segment; 8-1. Steel pipe column; 8-2. Protruding butt joint end; 8-3. Metal frame; 8-4. Connecting reinforcing rib; 9. Motor and reduction mechanism; 10. Transmission gear; 11. Movable door; 12. Inspection hole. Detailed Implementation
[0031] The following will be combined with the appendix Figures 1-7 This utility model will be described in detail, and the technical solutions in the embodiments of this utility model will be clearly and completely described. Obviously, the described embodiments are only some embodiments of this utility model, and not all embodiments. Based on the embodiments of this utility model, all other embodiments obtained by those of ordinary skill in the art without creative effort are within the protection scope of this utility model.
[0032] This utility model provides an improved construction safety protection lifting system, such as... Figures 1-7 As shown, it can be implemented in the following manner;
[0033] Includes foundation 1, located at the bottom of the building under construction;
[0034] The bottom safety cage 2 is fixedly installed on the foundation 1.
[0035] Column unit 3 is fixedly installed in the foundation 1 at its lower end;
[0036] The lifting cage 4 is installed on the column unit 3 and can be raised and lowered along the column unit 3 under the drive of the power mechanism, which facilitates the construction requirements of vertical lifting.
[0037] The protective fixing bracket 5 is used to fix the column unit 3 to the construction building (floor slab or wall);
[0038] A vertical rack 6 is fixed on each side of the column unit 3, so that a set of lifting cages 4 can be set on each side of the column unit 3. The lifting cages 4 are fixed to the channel steel frame 7 as a whole. The left and right ends of the channel steel frame 7 are limiting channel steels 7-1.
[0039] The column unit 3 is fixed and connected by vertically overlapping a plurality of column segments 8, which facilitates adjusting the height of the column unit 3 according to the height of the construction building, each column segment 8 has four groups of steel pipe columns 8-1, the top of each group of steel pipe columns 8-1 is a protruding butt joint end 8-2, which facilitates the butt joint and fixation of the upper and lower segments, the steel pipe columns 8-1 of the same segment are further fixed by a plurality of metal frames 8-3, the metal frame 8-3 is welded by an L-shaped steel and has an overall mouth-shaped type, the mouth-shaped metal frame 8-3 can directly connect the four groups of steel pipe columns 8-1 as a whole, thereby enhancing the stability of the whole, and the upper and lower metal frames 8-3 are further fixed with connecting reinforcing ribs 8-4;
[0040] The channel steel frame 7 is limited outside the corresponding steel pipe column 8-1 by the limiting channel steel 7-1 at both ends;
[0041] The side surface of the limiting channel steel 7-1 is fixed with a triangular-shaped fixing seat 7-2, the triangular-shaped fixing seat 7-2 is fixed and connected by a bolt with a support 7-3, two groups of limiting wheels 7-4 are installed at the support 7-3, so that the limiting wheels 7-4 tightly adhere to the outside of the corresponding steel pipe column 8-1; so that the whole of the channel steel frame 7 and the lifting cage 4 obtains better stability, and reduces the shaking of the lifting cage 4 during lifting;
[0042] The power mechanism includes two groups of motors and reduction mechanisms 9 arranged in upper and lower rows, the motors and reduction mechanisms 9 are located at the top of the lifting cage 4 as a whole, and are fixed and installed on the channel steel frame 7, the output end of the reduction mechanism is provided with a transmission gear 10, which is engaged with the vertical rack 6;
[0043] The protective fixing support 5 includes a front support 5-1 and a rear support 5-2 as a whole, the front support 5-1 and the rear support 5-2 are connected by bolts, the front end of the front support 5-1 is provided with a positioning seat 5-3 for connecting with the construction building, the rear end of the rear support 5-2 is fixed and connected with the metal frame 8-3 in the corresponding column segment 8 by a bolt, so as to achieve the fixation between the column unit 3 and the construction building;
[0044] The bottom safety enclosure 2 and the side surface of the lifting cage 4 are respectively provided with openable movable doors 11, and the top of the lifting cage 4 is provided with an inspection hole 12.
[0045] The specific installation and implementation process of the building construction safety protection lifting system of the present application will be described below;
[0046] Foundation body and bottom safety enclosure installation: Select an appropriate position at the bottom of the construction building, and construct the foundation body 1 according to the design requirements. The foundation body needs to have sufficient strength and stability to bear the entire lifting system and various loads during operation. After construction is completed, ensure that the surface of the foundation body is flat and that the positions of the various embedded components are accurate. Hoist the bottom safety enclosure 2 above the foundation body 1, and according to the preset installation position, firmly fix the bottom safety enclosure 2 on the foundation body 1 by means of bolts or welding, etc. Check whether the connection parts of the enclosure are tight to ensure that the overall structure of the enclosure is stable and plays the expected safety protection role.
[0047] Column unit construction: According to the expected height of the construction building, prepare the corresponding number of column segments 8. Hoist the first column segment 8 to the installation slot of the foundation body 1, so that the lower end of the column segment 8 is accurately connected with the reserved fixing structure in the foundation body 1, and the column segment 8 is firmly fixed in the foundation body 1 by means of bolt fastening or welding, etc. Hoist the next column segment 8, so that the protruding butt joint end 8-2 of the steel pipe column 8-1 in the upper column segment 8 is accurately aligned with the corresponding connection part of the steel pipe column 8-1 in the lower column segment 8. Use high-strength bolts to pass through the reserved holes in the butt joint parts, and tighten them one by one to realize the reliable connection of the upper and lower column segments 8. In this process, the verticality of the column segment is monitored in real time using measuring tools to ensure that the entire column unit 3 is perpendicular to the foundation body 1. After completing the connection of each column segment 8, install a metal frame 8-3 between the four groups of steel pipe columns 8-1 in the same segment. Fix the L-shaped metal frame 8-3 with the steel pipe column 8-1 by welding, etc. to connect the four groups of steel pipe columns 8-1 as a whole, thereby enhancing the structural stability of the segment. Then, install a connecting reinforcing rib 8-4 between the adjacent metal frames 8-3 to further improve the overall strength of the column unit 3. Repeat the above steps to continuously construct the column unit 3 until the required height of the construction building is reached. After the construction of the column unit is completed, the column unit 3 is comprehensively checked to ensure that the connection parts are firm and reliable, and the overall structure is stable.
[0048] Channel steel frame and lifting cage installation: Assemble the channel steel frame 7 and the lifting cage 4 in advance, and ensure that they are connected firmly and integrally. Align the limiting channel steel 7-1 at both ends of the channel steel frame 7 with the outer side of the corresponding steel pipe column 8-1 in the column unit 3, and slowly lower it, so that the limiting channel steel 7-1 slides along the outer side of the steel pipe column 8-1 until the channel steel frame 7 and the lifting cage 4 reach the predetermined installation position. Install a triangular fixing seat 7-2 on the side of the limiting channel steel 7-1, and fasten and connect the triangular fixing seat 7-2 with the limiting channel steel 7-1 through bolts. Then, connect the support 7-3 with the triangular fixing seat 7-2 through bolts, and install two sets of limiting wheels 7-4 at the support 7-3. Adjust the position of the limiting wheels 7-4 so that they are tightly attached to the outer side of the corresponding steel pipe column 8-1, complete the installation and limiting structure setting of the channel steel frame 7 and the lifting cage 4, and ensure the stability of the lifting cage 4 in the subsequent operation process.
[0049] Protective fixed support installation: Preliminarily connect the front support 5-1 and the rear support 5-2 through bolts to form the protective fixed support 5. Hoist the protective fixed support 5 to the position of the corresponding column segment 8, align the bolt hole at the rear end of the rear support 5-2 with the reserved installation hole on the metal frame 8-3 in the column segment 8, and fasten and connect the rear support 5-2 with the metal frame 8-3 through bolts. Adjust the position of the front end positioning seat 5-3 of the front support 5-1 so that it accurately fits the connection part of the construction building, and firmly connect the positioning seat 5-3 with the construction building using expansion bolts or other reliable connection methods, complete the installation of the protective fixed support 5, and realize the stable fixation between the column unit 3 and the construction building.
[0050] Movable door and manhole setting: Install openable movable doors 11 (for relevant personnel to enter and exit) on the side of the bottom safety cage 2 and the lifting cage 4 according to the design requirements. Debug the opening and closing functions of the movable doors 11 to ensure smooth and flexible operation, and check whether the door lock device is reliable and can effectively prevent accidental opening. Open manholes 12 (for convenient use during maintenance) on the top of the lifting cage 4, and install corresponding manhole covers. Ensure that the manhole covers are tightly connected with the top of the lifting cage 4, and can be conveniently and quickly opened and closed when equipment maintenance is needed.
[0051] System debugging and running: after the installation of the above-mentioned corresponding parts is completed (the installation order of each part can be adjusted according to the specific situation), the entire building construction safety protection lifting system is comprehensively checked to ensure that each part is installed correctly and connected firmly. The power supply of the power mechanism is connected, the motor and the speed reduction mechanism 9 are started, the lifting cage 4 on the stand column unit 3 is tested for lifting function by controlling the forward and reverse rotation of the motor, and the lifting process is observed to determine whether the lifting cage 4 runs smoothly, whether there is any shaking or jamming phenomenon, and whether the meshing of the transmission gear 10 and the vertical rack 6 is normal. The safety protection devices of the system are tested, such as the door lock function of the movable door 11 and the limiting effect of the limiting wheel 7-4. It is ensured that each safety protection device of the system can work normally during the operation process, effectively protecting the safety of the construction personnel and materials. After the system debugging is qualified, the system can be formally put into use for building construction. During the use process, the system is regularly maintained and repaired, the wear and tear of each part is checked, damaged parts are replaced in time, and the long-term stable and safe operation of the system is ensured.
[0052] The above description of the disclosed embodiments enables one skilled in the art to make or use the present application. Various modifications to these embodiments will be apparent to those skilled in the art, and the generic principles defined herein can be applied to other embodiments without departing from the spirit or scope of the present application. Thus, the present application is not to be limited to the embodiments shown herein but is to be accorded the widest scope consistent with the principles and novel features disclosed herein.
Claims
1. A construction safety guard hoist system, characterized by ; The base body is arranged at the bottom of the construction building; The bottom safety cage is fixedly arranged on the base body, The column unit is fixedly arranged at the lower end of the base body; The lifting cage is arranged on the column unit and can be lifted up and down along the column unit under the driving of the power mechanism, so as to facilitate the vertical lifting construction requirement; The protective fixing support is used to fix the column unit and the construction building; The two side surfaces of the column unit are respectively fixed with a vertical rack, so that a group of lifting cages can be arranged on each side surface of the column unit, the lifting cage and the channel steel frame are fixed as a whole, and the left and right ends of the channel steel frame are limit channel steels, The column unit is vertically overlapped and fixedly connected by a plurality of column segments, so as to adjust the height of the column unit according to the height of the construction building, each column segment has four groups of steel pipe columns, the top of each group of steel pipe columns is a protruding butt joint end, so as to facilitate the butt joint and fixation of the upper and lower segments, the steel pipe columns in the same segment are further fixed by a plurality of metal frames, the metal frame is welded by an L-shaped steel and has a whole mouth shape, the metal frame with the mouth shape can directly connect the four groups of steel pipe columns as a whole, so as to enhance the stability of the whole, and a connecting reinforcing rib is further fixed between the upper and lower metal frames; The channel steel frame is limited outside the corresponding steel pipe column by the limit channel steels at both ends, The side surface of the limit channel steel is fixed with a triangular fixing seat, the triangular fixing seat is fixedly connected with a support by a bolt, two groups of limit wheels are installed on the support, so that the limit wheels are tightly attached to the outside of the corresponding steel pipe column; so that the whole of the channel steel frame and the lifting cage obtains better stability, and the shaking of the lifting cage in the lifting process is reduced.
2. The construction safety shield hoist system of claim 1, wherein: The power mechanism includes two groups of motors and reduction mechanisms arranged in series, the motors and the reduction mechanisms are located at the top of the lifting cage and are fixedly arranged on the channel steel frame, the output end of the reduction mechanism is provided with a transmission gear, and the transmission gear is engaged with the vertical rack.
3. The construction safety shield hoist system of claim 1, wherein: The protective fixing support includes a front support and a rear support, the front support and the rear support are connected by a bolt, a positioning seat for connecting with the construction building is installed at the front end of the front support, and the rear end of the rear support is fixedly connected with the metal frame in the corresponding column segment by a bolt, so as to fix the column unit and the construction building.
4. The construction safety shield hoist system of claim 1, wherein ; The side surfaces of the bottom safety cage and the lifting cage are respectively provided with openable doors, and a maintenance hole is formed in the top of the lifting cage.