Supporting frame installed on rotary platform of tower type pouring equipment
By designing a support frame on the rotating platform of the tower casting equipment, the support stability of the lifting arm and counterweight arm is enhanced, and the tower body is heightened by using a jacking mechanism. This solves the stability problem of the tower casting equipment when being hoisted by a large concrete placing boom, ensuring the safety and continuity of construction.
Patent Information
- Application Number
- CN202520625434.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-04-03
- Publication Date
- 2026-02-03
- Estimated Expiration
- 2035-04-03
AI Technical Summary
The existing support frame of the tower pouring equipment is not stable enough when hoisting large concrete placing booms, which cannot meet the requirements of efficient and safe concrete pouring, especially posing safety risks during the process of increasing the height of the tower.
Design a support frame for installation on the slewing platform of a tower-type casting equipment, including a first frame and a second frame. By connecting diagonal braces, tie plates and track beams, the support stability of the lifting arm and counterweight arm is enhanced, and a lifting mechanism is provided to increase the height of the tower body and adjust the height of the lifting arm.
It improves the support stability of the lifting boom and counterweight boom, ensuring smooth operation of the tower crane during hoisting and material placement, reducing safety risks, and increases the height of the tower body through the jacking mechanism to meet the pouring requirements of different heights, ensuring the continuity and efficiency of construction.
Smart Images

Figure CN223866244U_ABST
Abstract
Description
TECHNICAL FIELD
[0001] The utility model relates to the field of mass concrete pouring construction equipment, in particular to a support frame installed on the rotary platform of tower pouring equipment. BACKGROUND
[0002] In large water conservancy and hydropower projects, in order to meet the requirements of flood season, basically in a dry season, both the foundation pit excavation and the bottom mass concrete pouring should be completed, the concrete pouring lasts for a short time and has high strength. The construction period is quite tight, and generally tower belt machines, top belt machines, mobile feeders and other equipment are used for lifting and pouring.
[0003] The tower belt machine is a combination of a tower crane and a feeder or a feeder pipe, and the pouring position, angle and length of the feeder belt or the feeder pipe are changed by the tower crane. The total length of the feeder belt reaches 100m, and is used to deliver concrete to the pouring position, so higher requirements are put forward for the lifting capacity and stability of the tower crane. For a general tower crane, such as the anti-collision novel tower crane disclosed in CN218754710U, a support frame needs to be arranged on the rotary table and connected with the lifting arm and the counterweight arm through a pull rod. However, for the tower belt machine, the length of the feeder is large and the weight is heavy, so higher requirements are put forward for the stability of the tower body. Therefore, the support frame on the rotary table needs to be optimized. At the same time, with the pouring of concrete, the pouring working surface is continuously raised, and the lifting arm of the tower belt machine also needs to be raised synchronously. Therefore, a support frame installed on the rotary platform of the tower pouring equipment is proposed. SUMMARY
[0004] The technical problem to be solved by the utility model is to provide a support frame installed on the rotary platform of the tower pouring equipment, to improve the support stability of the lifting arm and the counterweight arm, and to cooperate with the jacking mechanism to raise the tower body of the tower belt machine.
[0005] To solve the above technical problems, the utility model adopts the technical scheme of a support frame installed on the rotary platform of the tower pouring equipment, comprising a first frame body and a second frame body, the second frame body is provided with two groups of connecting inclined rods on the top, the upper ends of the two groups of connecting inclined rods are connected with a first pull rod plate, the first frame body is provided with two groups of second pull rod plates on the top, the second pull rod plates are connected with the first pull rod plate through a top connecting rod, two groups of track beams are arranged between the first frame body and the second frame body, the outer sides of the two groups of track beams are provided with mounting frames, the mounting frames are used for mounting jacking mechanisms, and the mounting frames are located above the tower body of the tower belt machine.
[0006] In the preferred scheme, the mounting frames are connected with the second frame body through a plurality of connecting rods.
[0007] In the preferred scheme, the adjacent connecting rods are connected in the shape of an "eight".
[0008] In a preferred solution, the first frame body and the mounting frame are connected by a diagonal pull rod.
[0009] In a preferred solution, the mounting frame is internally provided with a clearance groove, and the track beam is arranged in the clearance groove.
[0010] In a preferred solution, the mounting frame is provided with a plurality of mounting holes for fixing the jacking mechanism.
[0011] In a preferred solution, the first frame body and the second frame body each include two groups of vertical rods, and a plurality of connecting cross rods are arranged between the vertical rods.
[0012] In a preferred solution, diagonal connecting rods are arranged between adjacent connecting cross rods.
[0013] In a preferred solution, the first pull rod plate and the second pull rod plate are each provided with a pin hole for connecting with the pull rod of the tower belt conveyor.
[0014] In a preferred solution, the lower end of the first frame body and the second frame body is provided with a pin ear plate for hinging with a mounting seat on the rotary platform.
[0015] The support frame provided by the utility model is installed on the rotary platform of a tower pouring equipment, and has the following beneficial effects:
[0016] 1. The first frame body and the second frame body are arranged, the first pull rod plate is connected with the second pull rod plate at the top of the second frame body by two groups of connecting diagonal rods, and the second pull rod plate at the top of the first frame body is connected with the first pull rod plate by a top connecting rod, so that the load transmitted by the hoisting arm and the counterweight arm of the tower belt conveyor can be effectively dispersed, the support stability of the hoisting arm and the counterweight arm is improved, the operation of the tower belt conveyor is more stable and safe during hoisting and material distribution, and the safety risk caused by unstable support is reduced.
[0017] 2. The mounting frame arranged outside the two groups of track beams is specially used for mounting the jacking mechanism, and the mounting frame is arranged above the tower body of the tower belt conveyor, thereby providing a convenient condition for the heightening of the tower body of the tower belt conveyor. After the heightening of the tower section is completed, the jacking mechanism is downwardly jacked and supported at the top of the newly added tower section, then the locking of the rotary platform is released, the jacking mechanism is continuously elongated, the whole rotary platform is lifted and locked on the tower section which is heightened, the height adjustment of the hoisting arm is completed, the tower belt conveyor can continuously meet the pouring requirements of different heights, and the continuity and efficiency of construction are ensured.
[0018] 3、The mounting frame is connected with the second frame body through a plurality of connecting rods, and adjacent connecting rods are connected in an "eight" shape, which enhances the connection strength and stability between the mounting frame and the second frame body, and makes the whole support frame structure more firm and reliable. Meanwhile, the first frame body and the mounting frame are connected through the inclined rods, which further improves the structural strength and anti-deformation capacity of the whole support frame, and ensures stable operation in complex construction environment.
[0019] 4、The inside of the mounting frame is provided with an avoiding groove, and the track beam is arranged in the avoiding groove, which can not affect the movement of the hoisting trolley on the track beam. BRIEF DESCRIPTION OF DRAWINGS
[0020] The utility model will be further described below in combination with the drawings and embodiments:
[0021] Fig. 1 It is the front view of the utility model;
[0022] Fig. 2 It is the left view of the utility model;
[0023] Fig. 3 It is the structural schematic view of the second frame body of the utility model;
[0024] In the drawing: first frame body 1, second frame body 2, connecting inclined rod 3, first pull rod plate 4, second pull rod plate 5, top connecting rod 6, track beam 7, mounting frame 8, connecting rod 9, inclined rod 10, avoiding groove 801, mounting hole 802, vertical rod 11, connecting cross rod 12, oblique connecting rod 13, pin hole 14, through pin lug plate 15. DETAILED DESCRIPTION
[0025] The embodiments of the utility model will be described in detail below, the examples of the embodiments are shown in the drawings, the embodiments described below by referring to the drawings are exemplary, and are intended to explain the utility model, and can not be understood as the limitation of the utility model.
[0026] Embodiment 1:
[0027] As shown in Figs. 1-3 A support frame mounted on the rotary platform of tower pouring equipment includes first frame body 1 and second frame body 2, the height of first frame body 1 and second frame body 2 is consistent, two groups of connecting inclined rods 3 are arranged on the top of second frame body 2, the upper end of two groups of connecting inclined rods 3 is connected with first pull rod plate 4, and the lower end is connected with the two sides of second frame body 2; two groups of second pull rod plates 5 are arranged on the top of first frame body 1, and second pull rod plates 5 are connected with first pull rod plate 4 through top connecting rod 6, specifically, two groups of top connecting rod 6 are arranged, the upper end is hinged with first pull rod plate 4, and the lower end is connected with corresponding second pull rod plate 5.
[0028] Two sets of track beams 7 are provided between the first frame 1 and the second frame 2. The track beams 7 are used to install the lifting trolley.
[0029] Both sets of track beams 7 are equipped with mounting frames 8 on their outer sides. The mounting frames 8 are used to install the jacking mechanism. The mounting frames 8 are located above the tower body of the tower conveyor. The jacking mechanism is a jacking hydraulic cylinder or a jacking electric cylinder, etc.
[0030] Both the first tie rod plate 5 and the second tie rod plate 4 are provided with pin holes 14 for connecting with the tower belt conveyor tie rod.
[0031] Preferably, the mounting bracket 8 is provided with a plurality of mounting holes 802 for fixing the lifting mechanism. Specifically, the tail end of the lifting mechanism is provided with a connecting ear plate, which is connected by a plug-in hydraulic cylinder or a pin. Multiple sets of mounting holes 802 are provided, allowing the lifting mechanism to be installed in mounting holes 802 at different heights, thus adjusting the installation height of the lifting mechanism.
[0032] Preferred, such as Fig. 2 and 3 As shown, both the first frame 1 and the second frame 2 include two sets of vertical rods 11, with several connecting horizontal rods 12 between the vertical rods 11, and diagonal connecting rods 13 between adjacent connecting horizontal rods 12.
[0033] The lower ends of the first frame 1 and the second frame 2 are provided with through-pin ear plates 15 for hinged connection with the mounting base on the slewing platform. After the first frame 1 and the second frame are hoisted onto the slewing platform of the tower belt conveyor, the through-pin ear plates 15 are connected to the mounting base by pins for easy installation.
[0034] In practical use, the first tie rod plate 4 is connected to the lifting arm via a tie rod, and the second tie rod plate 5 is connected to the counterweight arm via a tie rod. This design can effectively distribute the load transmitted from the lifting arm and counterweight arm of the tower belt conveyor, improve the support stability of the lifting arm and counterweight arm, ensure that the tower belt conveyor operates more smoothly and safely during hoisting and material placement, and reduce the safety risks caused by unstable support.
[0035] When it is necessary to increase the height of the tower, the increased tower section is first hoisted to the top of the tower section using a crane trolley set on the track beam 7. The two tower sections are then connected, and a jacking operation is carried out. The slewing platform, the boom, and the counterweight boom are simultaneously lifted upwards. Specifically, after the tower section is increased in height, the jacking mechanism pushes it downwards, supporting the top of the newly added tower section. Then, the locking of the slewing platform is released, and the jacking mechanism continues to extend, raising the entire slewing platform and locking it onto the increased tower section. This completes the adjustment of the boom height, enabling the tower conveyor to continuously meet the pouring requirements at different heights, ensuring the continuity and efficiency of construction.
[0036] Example 2:
[0037] Unlike Embodiment 1, the mounting frame 8 is connected to the second frame 2 via several connecting rods 9, specifically, adjacent connecting rods 9 are connected in a figure-eight pattern. This connection method enhances the connection strength and stability between the mounting frame 8 and the second frame 2, making the entire support frame structure more robust and reliable. Simultaneously, the first frame 1 and the mounting frame 8 are connected by diagonal braces 10, further improving the overall structural strength and deformation resistance of the support frame, ensuring stable operation even in complex construction environments.
[0038] Example 3:
[0039] Unlike Example 1, such as Fig. 2 As shown, the mounting frame 8 has an inner clearance groove 801, and the track beam 7 is disposed in the clearance groove 801.
[0040] The mounting frame 8 has an inner clearance groove 801, and the track beam 7 is set in the clearance groove 801, so as not to affect the movement of the crane trolley on the track beam 7.
[0041] The working principle of this utility model is as follows:
[0042] The first tie rod plate 5 and the second tie rod plate 4 are respectively connected to the lifting arm and the counterweight arm through tie rods. The first tie rod plate 5 and the second tie rod plate 4 are respectively set at the top of the connecting diagonal bar 3 at the top of the second frame 2 and the top of the first frame 1, effectively dispersing the load transmitted from the lifting arm and the counterweight arm of the tower belt conveyor, and improving the support stability of the lifting arm and the counterweight arm.
[0043] When it is necessary to add a tower section, the added tower section is hoisted to the top of the tower section using a crane trolley set on the track beam 7. The two tower sections are then connected, and a jacking operation is performed. The jacking mechanism pushes downwards, supporting the top of the newly added tower section. Then, the locking of the slewing platform is released, and the jacking mechanism continues to extend, raising the entire slewing platform and locking it onto the added tower section. This completes the adjustment of the boom height, enabling the tower conveyor to continuously meet the pouring requirements at different heights, ensuring the continuity and efficiency of construction.
[0044] The above embodiments are merely preferred technical solutions of this utility model and should not be considered as limitations on this utility model. The embodiments and features described in this application can be arbitrarily combined without conflict. The protection scope of this utility model should be defined as the technical solution described in the claims, including equivalent substitutions of the technical features described in the claims. That is, equivalent substitutions and improvements within this scope are also within the protection scope of this utility model.
Claims
1. A support frame installed on the rotating platform of a tower-type casting equipment, characterized in that, The system includes a first frame (1) and a second frame (2). The second frame (2) has two sets of connecting diagonal rods (3) on its top. The upper ends of the two sets of connecting diagonal rods (3) are connected to the first tie rod plate (4). The first frame (1) has two sets of second tie rod plates (5) on its top. The second tie rod plates (5) are connected to the first tie rod plate (4) through the top connecting rod (6). There are two sets of track beams (7) between the first frame (1) and the second frame (2). There are mounting frames (8) on the outer side of the two sets of track beams (7). The mounting frames (8) are used to install the lifting mechanism. The mounting frames (8) are located above the tower body of the tower conveyor.
2. The support frame installed on the rotating platform of a tower-type casting equipment according to claim 1, characterized in that, The mounting frame (8) is connected to the second frame (2) via several connecting rods (9).
3. The support frame installed on the rotating platform of a tower-type casting equipment according to claim 2, characterized in that, The adjacent connecting rods (9) are connected in a figure-eight shape.
4. The support frame installed on the rotating platform of a tower-type casting equipment according to claim 1, characterized in that, The first frame ((1)) and the mounting frame (8) are connected by a tie rod (10).
5. A support frame installed on the rotating platform of a tower-type casting equipment according to claim 1, characterized in that, The mounting bracket (8) has an inner clearance groove (801), and the track beam (7) is set in the clearance groove (801).
6. The support frame installed on the rotating platform of a tower-type casting equipment according to claim 1, characterized in that, The mounting bracket (8) is provided with several mounting holes (802) for fixing the lifting mechanism.
7. A support frame installed on the rotating platform of a tower-type casting equipment according to claim 1, characterized in that, The first frame (1) and the second frame (2) both include two sets of vertical rods (11), and several connecting horizontal rods (12) are provided between the vertical rods (11).
8. A support frame installed on the rotating platform of a tower-type casting equipment according to claim 7, characterized in that, An oblique connecting rod (13) is provided between adjacent connecting crossbars (12).
9. A support frame installed on the rotating platform of a tower-type casting equipment according to claim 1, characterized in that, Both the first tie rod plate (4) and the second tie rod plate (5) are provided with pin holes (14) for connecting with the tower belt conveyor tie rod.
10. A support frame installed on the rotating platform of a tower-type casting equipment according to claim 1, characterized in that, The lower ends of the first frame (1) and the second frame (2) are provided with through-hole ear plates (15) for hinged connection with the mounting base on the rotary platform.
Citation Information
Patent Citations
Novel anti-collision tower crane
CN218754710U