Leveling support for modular building in-place decoration
By combining ground anchor fixing components and adjustment components, and using components such as fixing bolts and steel plates, rapid leveling of modular buildings is achieved, solving the problems of cumbersome leveling procedures and low construction efficiency in existing technologies, thereby improving construction efficiency and reducing costs.
Patent Information
- Application Number
- CN202423269481.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-12-30
- Publication Date
- 2026-02-13
- Estimated Expiration
- 2034-12-30
AI Technical Summary
The existing modular building leveling process is cumbersome, wastes a lot of manpower, has low construction efficiency, and makes it difficult to quickly and conveniently adjust the support elevation of building modules.
The system employs ground anchor fixing components, adjustment components, and top support components, including fixing bolts, steel plates, leveling bolts, and support square tubes. Leveling is achieved quickly by turning the adjusting nut with a wrench, ensuring that the building module is level.
It enables quick and convenient adjustment of support elevation, simplifies the operation process, improves construction efficiency, and reduces production and usage costs.
Smart Images

Figure CN223907674U_ABST
Abstract
Description
TECHNICAL FIELD
[0001] The embodiment of the utility model belongs to the technical field of fabricated building, more particularly, relate to a kind of adjustable leveling support for modular building landing decoration. BACKGROUND
[0002] Modular building is mainly composed of support, wallboard, roof and floor, which has flexible installation mode and fast assembly speed, and modular building is widely used in construction site, field, disaster area and other places due to its low cost, mobility and reusability.
[0003] After modular building is transported to assembly site, it is seated on the ground, and since the installation site is uneven, it is necessary to level the bottom of the building module with several pads after the building module is landed. Since the weight of the building module produces a large pressure on the ground and the pads after the building module is landed, the building module may be offset and inclined, so it is necessary to repeatedly check the elevation of the support, and if the elevations of the supports are inconsistent, it is necessary to repeatedly measure the elevations of the supports, and the building module is lifted and inserted into several pads to keep the building module level. This leveling method wastes a lot of labor, thereby affecting the construction efficiency of the building module decoration.
[0004] Therefore, at present, it is urgent to provide a leveling support for modular building landing decoration, which does not need to lift the building module, can quickly and conveniently adjust the elevation of the support, restores the level of the building module, and overcomes the problems of complicated leveling process, waste of a lot of labor and low construction efficiency in the prior art. SUMMARY
[0005] In view of the problems of complicated leveling process, waste of a lot of labor and low construction efficiency of the building module in the prior art, the utility model provides a leveling support for modular building landing decoration to solve such problems.
[0006] In order to achieve the above-mentioned purpose, the utility model provides a leveling support for modular building landing decoration, which comprises a ground anchor fixing assembly comprising a first steel plate arranged at a corresponding position of the ground and a fixing bolt for anchoring the first steel plate to the ground; an adjusting assembly for leveling operation, comprising: a leveling bolt fixedly arranged at the top of the first steel plate, an adjusting nut threadedly connected with the leveling bolt, and a second steel plate penetrating through the leveling bolt and contacting the top of the adjusting nut; and a top support assembly comprising a support square tube fixedly arranged vertically at the center of the second steel plate, and a third steel plate fixedly arranged at the top of the support square tube.
[0007] Further, a connecting beam is fixedly connected between the two groups of support square tubes of adjacent supports, and the top of the connecting beam is at the same height as the third steel plate.
[0008] Further, the fixing bolt is punched into the ground or is embedded into the ground synchronously when the concrete floor is poured, and the upper end of the rod is located on the ground.
[0009] Further, a fixing nut is threadedly connected to the upper end of the fixing bolt, and the fixing nut is used to press and fix the first steel plate.
[0010] Further, the leveling bolt is provided with four groups, and the four groups are fixed to the top of the first steel plate by welding.
[0011] Further, the leveling bolt is a coarse thread bolt.
[0012] Further, the second steel plate is provided with second through holes corresponding to the leveling bolts, and the second steel plate is arranged to pass through the leveling bolts and contact the top of the adjusting nut through the second through holes.
[0013] Further, a limiting nut is threadedly connected to the leveling bolt and is located on the top of the second steel plate, and the second steel plate is pressed and fixed on the top of the adjusting nut.
[0014] Overall, compared with the prior art, the above technical scheme of the utility model can achieve the following beneficial effects:
[0015] (1) The leveling support of the utility model can be leveled by twisting the adjusting nut with a wrench, and the building module does not need to be lifted, so that the support elevation adjustment work can be quickly and conveniently performed, and the leveling efficiency is high.
[0016] (2) The leveling support of the utility model is provided with steel plates, square tubes and bolts, and the overall structure of the support is simple, the components are firm and durable, the support can be quickly installed and disassembled, and the support can be repeatedly used, so that the production cost and use cost are greatly saved. BRIEF DESCRIPTION OF DRAWINGS
[0017] Figure 1 The utility model discloses an adjustable leveling support for modular building positioning decoration.
[0018] Figure 2 The utility model discloses an adjustable leveling support for modular building positioning decoration.
[0019] In all the drawings, the same reference signs represent the same technical features, and specifically, 1 is a fixing bolt, 2 is a first steel plate, 3 is a fixing nut, 4 is a leveling bolt, 5 is a second steel plate, 6 is an adjusting nut, 7 is a limiting nut, 8 is a supporting square tube, 9 is a third steel plate, and 10 is a connecting beam. DETAILED DESCRIPTION
[0020] To make the objectives, technical solutions, and advantages of this utility model clearer, the present utility model will be further described in detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only for explaining the present utility model and are not intended to limit the present utility model. Furthermore, the technical features involved in the various embodiments of the present utility model described below can be combined with each other as long as they do not conflict with each other.
[0021] like Figures 1-2 As shown, this utility model provides an adjustable leveling support for modular building placement and decoration, including a ground anchor fixing component, an adjustment component, and a top support component. The ground anchor fixing component includes a first steel plate 2 located at a corresponding position on the ground and a fixing bolt 1 anchoring the first steel plate 2 to the ground. The adjustment component includes a leveling bolt 4 fixed to the top of the first steel plate 2, an adjusting nut 6 threadedly connected to the leveling bolt 4, and a second steel plate 5 passing through the leveling bolt 4 and contacting the top of the adjusting nut 6. The top support component includes a support square tube 8 vertically fixed at the center of the second steel plate 5 and a third steel plate 9 fixed to the top of the support square tube 8. After initial leveling to allow the building module to be placed, the elevation of the third steel plate 9 can be checked daily. If inconsistencies in elevation occur, a wrench can be used to turn the adjusting nut 6 for secondary leveling. This method eliminates the need to lift the building module, enabling quick and convenient elevation adjustment of the support, with simple operation and high leveling efficiency.
[0022] like Figure 1 As shown, the ground anchor fixing assembly is used to fix and level the support to the ground, increasing the tensile strength and stability of the support. It is set at the corresponding position on the ground according to the installation of the building module, and includes a fixing bolt 1, a first steel plate 2 and a fixing nut 3. The fixing bolt 1 is an expansion bolt driven into the ground, or an anchor bolt that is buried in the ground simultaneously when the concrete ground is poured, with its upper end on the ground. The first steel plate 2 has multiple first through holes, through which the first steel plate 2 passes through the fixing bolt 1 and contacts the ground, thereby increasing the support area of the support to the ground and making the support more stable, so that the building module can be placed smoothly. Preferably, there are four sets of first through holes, located at the four corners of the first steel plate 2. The fixing nut 3 is threaded to the upper end of the fixing bolt 1 and presses the top of the first steel plate 2 to firmly fix the first steel plate 2 to the ground.
[0023] like Figure 2As shown, the adjusting assembly is used for leveling operation, and the top of the support is kept at the same level, which comprises leveling bolts 4, a second steel plate 5, an adjusting nut 6 and a limiting nut 7. The bottom of the leveling bolt 4 is fixed on the top of the first steel plate 2, and three or more groups of the leveling bolts 4 are arranged; preferably, four groups of the leveling bolts 4 are arranged, which are fixed on the top of the first steel plate 2 at four corners by welding and are staggered with the first through holes; further, the leveling bolts 4 are coarse thread bolts, which have large thread diameter and pitch and have excellent bearing performance, especially in the occasion requiring high bearing tension and shear force, and can effectively bear the weight of the building module, so that the support is durable; the adjusting nut 6 is threadedly connected with the leveling bolt 4, is located at the bottom of the second steel plate 5 and holds up the second steel plate 5; the second steel plate 5 is provided with second through holes corresponding to the leveling bolts 4, the second steel plate 5 passes through the leveling bolts 4 and is in contact with the top of the adjusting nut 6 through the second through holes; the limiting nut 7 is threadedly connected with the leveling bolt 4, is located at the top of the second steel plate 5, presses and fixes the second steel plate 5 on the top of the adjusting nut 6 and prevents the second steel plate 5 from vibrating up and down.
[0024] Preferably, the second steel plate 5 is further provided with a level, when the adjusting nut 6 is twisted by using a wrench for breakthrough operation, the leveling operation can be quickly and intuitively completed by observing the level.
[0025] The top support assembly is used for stably placing the building module, which comprises a support square tube 8 and a third steel plate 9, the support square tube 8 is fixedly arranged at the center of the second steel plate 5 by welding, and the top center of the third steel plate 9 is fixedly connected with the top of the support square tube 8.
[0026] Further, the adjacent supports are connected as a whole through a connecting beam 10, so that the support is more stable, the contact area with the bottom of the building module is increased, and the building module is placed more stably; the connecting beam 10 is located between two adjacent supports, and the two ends of the connecting beam 10 are fixedly connected with the side edges of the two adjacent support square tubes 8, and the top of the connecting beam 10 is at the same height as the third steel plate 5.
[0027] When the support of the utility model carries out leveling operation, the following steps are included:
[0028] S100: making a leveling support, welding the third steel plate 9 on the top of the support square tube 8 as a building module landing force surface, welding the second steel plate 5 at the bottom of the support square tube 8, opening holes at four corners of the first steel plate 2 as mounting expansion bolt reserved holes, and welding the leveling bolts 4 at four corners of the top of the first steel plate 2; welding the second steel plate 5 at the bottom of the support square tube 8, opening holes at four corners of the second steel plate 5 to pass through the leveling bolts 4, and installing the limiting nut 7 and the adjusting nut 6 on the top and the bottom of the second steel plate 5 respectively;
[0029] S200: the leveling support is placed on the ground, the fixing bolt 1 is used for fixing connection with the ground, the level is used for leveling the third steel plate 9 for the first time, if the elevation is inconsistent, the adjusting nut 6 is twisted by using a wrench, the elevation is consistent, after completion, the limiting nut 7 is used for limiting locking;
[0030] S300: the decoration building module is positioned, during decoration, the level is used for checking the elevation of the third steel plate 9 every day, if the elevation of the third steel plate 9 is inconsistent, the adjusting nut 6 is twisted by using a wrench, and the third steel plate 9 is leveled for the second time.
[0031] When the support of the utility model is leveled, a plurality of leveling supports are arranged at the end and the middle of the building module, so that the building module is stable after being positioned and does not deviate; when the support square tube 8 is made, the length of the support square tube 8 is ensured to be the same, so that the building module is uniformly stressed after being positioned; when the first steel plate 2 and the second steel plate 5 are made, the hole position is noticed to ensure that the steel plate is uniformly stressed.
[0032] The leveling support of the utility model can be leveled by twisting the adjusting nut 6 by using a wrench, does not need to lift the building module, can quickly and conveniently adjust the height of the support, is simple to operate and has high leveling efficiency.
[0033] The leveling support of the utility model is made of steel plates, square tubes and bolts, and has simple overall structure, firm and durable components, can be quickly installed and disassembled, is repeatedly used, and greatly saves production and use costs.
[0034] It is easily understood by those skilled in the art that the above description is only a preferred embodiment of the utility model, and is not used for limiting the utility model, and any modification, equivalent replacement and improvement within the spirit and principle of the utility model should be included in the protection scope of the utility model.
Claims
1. An adjustable leveling support for modular building setting out fit-out, characterized in that, The utility model relates to a kind of ground anchor fixing assembly, adjusting assembly and top support assembly, including: Ground anchor fixing assembly, including the first steel plate (2) being arranged at corresponding place of ground, the fixing bolt (1) for anchoring the first steel plate (2) to ground; Adjusting assembly for leveling operation, including: leveling bolt (4) being fixedly arranged at the top of first steel plate (2), adjusting nut (6) being threadedly connected with leveling bolt (4), second steel plate (5) passing through leveling bolt (4) and being in contact with the top of adjusting nut (6); And top support assembly, including support square tube (8) being vertically fixedly arranged at the center of second steel plate (5), and third steel plate (9) being fixedly arranged at the top of support square tube (8).
2. An adjustable leveling support for modular building sitework, according to claim 1, wherein, Connecting beam (10) is fixedly connected between two groups of support square tube (8) of adjacent support, and the top of connecting beam (10) is at the same height with third steel plate (9).
3. An adjustable leveling support for modular building sitework finishing according to any one of claims 1-2, wherein, The fixing bolt (1) is punched into the bottom of ground using expansion bolt, or is buried in the bottom of ground using anchor bolt when pouring concrete ground, and the upper end of stem is located on ground surface;First through hole is formed on the first steel plate (2), and the first steel plate (2) is contacted with ground through the first through hole.
4. An adjustable leveling support for modular building sitework construction in accordance with claim 3, wherein, Fixed nut (3) is threadedly connected on the upper end of stem of fixing bolt (1), and the top of first steel plate (2) is pressed and fixed by fixed nut (3).
5. An adjustable leveling support for modular building sitework finishing according to any one of claims 1-2, wherein, Leveling bolt (4) is provided with four groups, and is fixed to the top of four corners of first steel plate (2) by welding.
6. An adjustable leveling support for modular building sitework finishing according to any one of claims 1-2, wherein, Leveling bolt (4) is coarse thread bolt.
7. An adjustable leveling support for modular building sitework finishing according to any one of claims 1-2, wherein, Second through hole corresponding to leveling bolt (4) is formed on the second steel plate (5), and the second steel plate (5) is contacted with the top of adjusting nut (6) by the second through hole.
8. An adjustable leveling support for modular building sitework finishing according to any one of claims 1-2, wherein, Limiting nut (7) is further threadedly connected on the leveling bolt (4), and the top of second steel plate (5) is pressed and fixed on the top of adjusting nut (6).