Concrete pouring cylinder structure for secondary load bearing wall grouting construction

By designing a concrete pouring cylinder with a base, automatic feeding structure, and pointed pouring nozzle, the problem of top pouring in secondary structure construction was solved, achieving seamless pouring, avoiding honeycombing and delamination, and improving construction quality.

CN224032194UActive Publication Date: 2026-03-24CHINA MCC5 GROUP CORP LTD
View PDF 0 Cites 0 Cited by

Patent Information

Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-03-26
Publication Date
2026-03-24

AI Technical Summary

Technical Problem

The existing grouting cylinder is too large, which makes it impossible to pour properly when it is near the top during secondary structure construction, and easily leads to quality problems such as honeycomb and delamination.

Method used

A concrete pouring cylinder comprising a base, an automatic feeding structure, and a pouring structure was designed. It employs a bendable conveying pipe and a pointed pouring nozzle, achieving seamless pouring through automatic feeding and precise nozzle insertion into the slot.

Benefits of technology

This effectively avoids problems such as honeycombing and delamination, ensuring that the concrete reaches the design elevation smoothly and improving construction quality.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN224032194U_ABST
    Figure CN224032194U_ABST
Patent Text Reader

Abstract

The utility model discloses a concrete pouring cylinder structure for secondary bearing wall grouting construction, which comprises a base, an automatic feeding structure and a pouring structure, the automatic feeding structure is arranged on the base, the pouring structure is arranged above the automatic feeding structure, and the automatic feeding structure is arranged on the base. The automatic feeding structure comprises a trough, a fixing seat, a feeding barrel, a motor, a rotating shaft and a pushing shifting piece, the trough is fixedly arranged above the base, the fixing seat is fixedly arranged on the inner wall of the trough, the feeding barrel penetrates through the fixing seat to be fixedly arranged, and the motor is fixedly arranged on the base at the bottom of the trough. The utility model belongs to the technical field of concrete pouring equipment, particularly relates to a concrete pouring barrel structure for secondary bearing wall grouting construction, and effectively solves the quality problems that most of pouring barrels are large in size, and when the pouring barrels are close to the top, due to narrow space, the top cannot be fully poured to form honeycombs and faults, and the like.
Need to check novelty before this filing date? Find Prior Art

Description

TECHNICAL FIELD

[0001] The utility model belongs to concrete pouring equipment technical field, specifically point to a kind of secondary load-bearing wall grouting construction with concrete pouring cylinder structure. BACKGROUND

[0002] It is known that secondary structure construction is usually carried out after the completion of the main structure. After the deepening of the secondary structure, a large part of the structural column is arranged at the bottom of the plate or beam. After the wall is built, the structural column is sealed to the top of the mold plate, leaving a dustpan opening, but it is basically close to the top plate, causing the concrete pouring to become a difficult problem, which cannot be normally poured to the design elevation, increasing the construction difficulty and quality risk.

[0003] However, the existing pouring cylinder is mostly large in size. When it is close to the top, the space is narrow, causing the top to be unable to be fully filled and forming quality problems such as honeycomb and fault INVENTION CONTENTS

[0004] In view of the above situation, in order to overcome the defects of the prior art, the utility model provides a concrete pouring cylinder structure for secondary load-bearing wall grouting construction, which effectively solves the problem of the large size of the pouring cylinder, the narrow space near the top, and the quality problems such as honeycomb and fault caused by the inability to fully fill the top.

[0005] The technical scheme adopted by the utility model is as follows: the utility model provides a concrete pouring cylinder structure for secondary load-bearing wall grouting construction, which comprises a base, an automatic feeding structure and a pouring structure. The automatic feeding structure is arranged on the base, and the pouring structure is arranged above the automatic feeding structure. The automatic feeding structure comprises a chute, a fixed seat, a feeding cylinder, a motor, a rotating shaft and a push piece. The chute is fixedly arranged above the base. The fixed seat is fixedly arranged on the inner wall of the chute. The feeding cylinder is fixedly arranged through the fixed seat. The motor is fixedly arranged on the base at the bottom of the chute. One end of the rotating shaft is inserted into the feeding cylinder through the base, and the other end is fixedly arranged on the output shaft of the motor. The push piece is spirally wrapped on the outer wall of the rotating shaft.

[0006] Preferably, the pouring structure comprises a connecting head one, a feeding cylinder, a connecting head two, a conveying pipe and a pouring nozzle. The connecting head one is threadedly fixed on the top of the feeding cylinder. The feeding cylinder is fixedly arranged above the connecting head one. The connecting head two is threadedly fixed on the top of the feeding cylinder. The conveying pipe is fixedly arranged above the connecting head two. The pouring nozzle is fixedly arranged at the front end of the conveying pipe.

[0007] In order to better realize the effect of seamless pouring, the pouring nozzle is in the shape of a sharp nozzle.

[0008] In order to achieve the purpose of suction pouring faster, the feeding cylinder is vertically inserted into the chute.

[0009] Further, the conveying pipe adopts a bendable flexible pipe and is internally provided with flexible spiral ribs.

[0010] To realize the conveying effect, the pushing piece is closely arranged between the rotating shaft and the inner wall of the feeding cylinder.

[0011] The beneficial effects achieved by the concrete pouring cylinder structure for secondary load-bearing wall grouting construction according to the present application are as follows: the concrete pouring cylinder structure for secondary load-bearing wall grouting construction according to the present application uses a conveying pipe to extend the feeding path, sets a pouring nozzle at the front end of the conveying pipe, inserts the pouring nozzle into the slot in the bottom plate, realizes full-penetration pouring, and avoids the problems of honeycomb and fault. BRIEF DESCRIPTION OF DRAWINGS

[0012] Figure 1 Fig. 1 is a schematic diagram of the overall structure of the concrete pouring cylinder structure for secondary load-bearing wall grouting construction according to the present application;

[0013] Figure 2 Fig. 2 is a schematic diagram of the structure of the concrete pouring cylinder structure for secondary load-bearing wall grouting construction according to the present application from another perspective;

[0014] Figure 3 Fig. 3 is a schematic diagram of the cross-sectional structure of the concrete pouring cylinder structure for secondary load-bearing wall grouting construction according to the present application;

[0015] Figure 4 Fig. 4 is a schematic diagram of another cross-sectional structure of the concrete pouring cylinder structure for secondary load-bearing wall grouting construction according to the present application.

[0016] 1, base, 2, automatic feeding structure, 3, pouring structure, 4, chute, 5, fixed seat, 6, feeding cylinder, 7, motor, 8, rotating shaft, 9, pushing piece, 10, connecting head one, 11, feeding cylinder, 12, connecting head two, 13, conveying pipe, 14, pouring nozzle.

[0017] The accompanying drawings are used to provide a further understanding of the present application, and constitute a part of the specification, and are used to explain the present application together with embodiments of the present application, and do not constitute a limitation on the present application. DETAILED DESCRIPTION

[0018] The technical solutions in the embodiments of the present application will be clearly and completely described below with reference to the drawings in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, rather than all the embodiments of the present application; based on the embodiments in the present application, all other embodiments obtained by those skilled in the art without creative labor fall within the scope of protection of the present application.

[0019] As Figure 1 ,Figure 2 、 Figure 3 and Figure 4 As shown in the utility model discloses a kind of secondary load-bearing wall grouting construction with concrete pouring cylinder structure, including pedestal 1, automatic feeding structure 2 and pouring structure 3, automatic feeding structure 2 is located on pedestal 1, pouring structure 3 is located on the top of automatic feeding structure 2, automatic feeding structure 2 includes chute 4, fixed seat 5, feeding cylinder 6, motor 7, shaft 8 and push piece 9, chute 4 is fixedly arranged above pedestal 1, fixed seat 5 is fixedly arranged on the inner wall of chute 4, feeding cylinder 6 is fixedly arranged through fixed seat 5, feeding cylinder 6 is vertically inserted into chute 4 and is arranged, motor 7 is fixedly arranged on the bottom base 1 of chute 4, one end of shaft 8 is inserted into feeding cylinder 6 and the other end is fixedly arranged on the output shaft of motor 7, and push piece 9 is spirally wrapped on the outer wall of shaft 8, and push piece 9 is closely arranged between shaft 8 and the inner wall of feeding cylinder 6.

[0020] As shown in Figure 1 、 Figure 3 and Figure 4 Pouring structure 3 includes connector one 10, material conveying cylinder 11, connector two 12, conveying pipe 13 and pouring nozzle 14, connector one 10 is threadedly fixed on the top of feeding cylinder 6, material conveying cylinder 11 is fixedly arranged above connector one 10, connector two 12 is threadedly fixed on the top of material conveying cylinder 11, conveying pipe 13 is fixedly arranged above connector two 12, conveying pipe 13 is a bendable flexible pipe and is internally provided with flexible spiral ribs, and pouring nozzle 14 is fixedly arranged at the front end of conveying pipe 13, and pouring nozzle 14 is in the shape of a sharp nozzle.

[0021] Specific use, when secondary pouring, first formwork, after formwork is completed, groove is opened on the top edge of the top, then concrete material is added to chute 4, motor 7 is controlled to drive shaft 8 to rotate, so that shaft 8 drives push piece 9 to rotate in feeding cylinder 6, so that push piece 9 rotates and pushes the concrete material in chute 4 upwards, and the concrete material is discharged from pouring nozzle 14 through material conveying cylinder 11 and conveying pipe 13, at this time, pouring nozzle 14 is inserted into the top groove, at this time, the concrete flows into the support form from the groove, and after the support form is filled, the concrete rises to the top, without fault or honeycomb hole, improving pouring quality, after pouring is completed, the equipment is cleaned, and the above is the use process of the entire secondary load-bearing wall grouting construction with concrete pouring cylinder structure.

[0022] It is to be noted that, in the present document, relational terms such as first and second and the like can be used solely to distinguish one entity or action from another entity or action without necessarily requiring or implying any actual such relationship or order between such entities or actions. Moreover, the terms "comprises", "comprising", or any other variation thereof, are intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but can include other elements not expressly listed or inherent to such process, method, article, or apparatus.

[0023] While the embodiments of the present application have been illustrated and described, it will be understood by those skilled in the art that various changes, modifications, substitutions, and alterations can be made therein without departing from the spirit and scope of the application, which is defined by the following claims and their equivalents.

[0024] The above description of the present application and its embodiments has been described, which is not restrictive, and the embodiments shown in the drawings are only one of the embodiments of the present application, and the actual structure is not limited thereto. In general, if a person skilled in the art is inspired by it, without departing from the creative purpose of the present application, without creative design, similar structure and embodiments of the technical scheme should belong to the protection scope of the present application.

Claims

1. A concrete pouring tube structure for grouting construction of a secondary load-bearing wall, characterized by: The application relates to an automatic feeding and pouring device, which comprises a base, an automatic feeding structure and a pouring structure.

2. The concrete pouring tube structure for secondary load-bearing wall grouting construction according to claim 1, characterized in that: The pouring structure comprises a connecting head one, a feeding cylinder, a connecting head two, a conveying pipe and a pouring nozzle.

3. The concrete pouring tube structure for secondary load-bearing wall grouting construction according to claim 2, characterized in that: The pouring nozzle is in the shape of a pointed nozzle.

4. The concrete pouring tube structure for secondary load-bearing wall grouting construction according to claim 3, characterized in that: The feeding cylinder is vertically inserted into the groove.

5. The concrete pouring tube structure for secondary load-bearing wall grouting construction according to claim 4, characterized in that: The conveying pipe is made of a bendable flexible pipe and internally provided with flexible spiral ribs.

6. The concrete pouring tube structure for secondary load-bearing wall grouting construction according to claim 5, characterized in that: The pushing piece is closely arranged between the rotating shaft and the inner wall of the feeding cylinder.